DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATE

Project
Client
Location

Item Code WBS / BoQ Code Definition

10 DEMOLITIONS
Demolish existing slabs or concrete
DEMOLISH0001 1010
pavings,buildings,foundations,structures
Demolition of asphaltic paving road, up to 15 cm thick, by
DEMOLISH0002 1020
mechanical means.
Demolition of underground piping and/or channels by
DEMOLISH0003 1030
mechanical means.
Demolition of manholes and/or pits (any type) by mechanical
DEMOLISH0004 1040
means.
20 SITE PREPARATION
Clearing, stripping and grading of of natural land for specified
SITECLEAR0001 2010
average thickness
EXCV0001 2020 General excavation by mechanical means (Cut)
General filling with select fill material from excavation (Fill /
FILL0001 2010
Embankment)
30 PILING WORKS
Supply and installation of sheet piling system with plate
SHEETPILE0001 3010 thickness as per project standards,specifications or approved
drawings.
Supply and execution in situ concrete ø30 cm diameter bored
PILE0001 3020
piles
Supply and execution in situ concrete ø60 cm diameter bored
PILE0002 3030
piles
Supply and execution in situ concrete ø90 cm diameter bored
PILE0003 3040
piles
Supply and execution in situ concrete ø120 cm diameter
PILE0004 3050
bored piles
PILE0005 3060 Cut-off concrete piles head
PILETEST0001 3070 Execution of integrity test for piles.
Execution of load compression test on working piles (1,5
PILETEST0002 3080
working load)
PILETEST0003 3090 Execution of Preliminary compression test (2,5 working load)
40 EARTHWORKS
EXCV0002 4010 Structural deep excavation of soil for the depth 0.00-2.00 m
EXCV0003 4020 Structural deep excavation of soil for the depth 2.00-4.00 m
EXCV0004 4030 Hand excavation of soil
EXCV0005 4040 Pipe/Trench excavation of soil for the depth 0.00-2.00 m
EXCV0006 4050 Pipe/Trench excavation of soil for the depth 2.00-4.00 m
FILL0002 4060 Structural filling with back fill material from excavation.

FILL0003 4070 General filling with borrowed granular material. (Imported Fill)
Structural filling with borrowed granular material. (Imported
FILL0004 4080
Fill)
FILL0005 4090 Trench filling with back fill material from excavation.
Pipe/Trench bedding/padding with borrowed granular fill
FILL0006 4100
material (Imported Fill)
FILL0007 4110 Pipe/Trench bedding/padding with clean sand
FILL0008 4120 Filling inside of tank foundations with clean sand.
FILL0009 4130 Tank foundations filling with oil sand mixture.
50 CONCRETE WORKS
CONCRETE0001 5010 Supply and pouring of lean concrete
CONCRETE0002 5020 Supply and pouring of mass concrete
Supply and pouring of concrete for various and slab
CONCRETE0003 5030 foundations (sleepers, stairs, thickened slab foundation,tank
foundations)
Supply and pouring of concrete for footing type foundations
CONCRETE0004 5040 (columns,equipment and valve foundations, pipe
supports,lighting post,single footing)
Supply and pouring of conrete for slabs,beams,walls and
CONCRETE0005 5050
columns.
CONCRETE0006 5060 Supply and pouring of conrete for manholes and trenches.
60 FORMWORKS
Supply and erection of straight formwork for various and slab
FORMWORK0001 6010 foundations (sleepers, stairs, thickened slab foundation,tank
foundations)
Supply and erection of straight formwork for footing type
FORMWORK0002 6020 foundations (columns,equipment and valve foundations, pipe
supports,lighting post,single footing)
Supply and erection of straight formwork for slab and beams
FORMWORK0003 6030
and column
FORMWORK0004 6040 Supply and erection of straight formwork for walls
Supply and erection of straight formwork for manholes and
FORMWORK0005 6050
trenches
70 REBAR WORKS
Supply and installation of steel reinforcement for various and
REBAR0001 7010 slab foundations (sleepers, stairs, thickened slab
foundation,tank foundations)
Supply and installation of steel reinforcement for footing type
REBAR0002 7020 foundations (columns,equipment and valve foundations, pipe
supports,lighting post,single footing)
Supply and installation of steel reinforcement for slabs,beams
REBAR0003 7030
and walls and column
Supply and installation of steel reinforcement for manholes
REBAR0004 7040
and trenches
Supply and installation of steel fabric mesh reinforcement for
REBAR0005 7050
pavements and slabs.
80 STRUCTURAL STEEL WORKS
Supply and erection of fabricated,painted heavy structural
STEEL0001 8010
steel
Supply and erection of fabricated,painted medium structural
STEEL0002 8020
steel
Supply and erection of fabricated and painted light structural
STEEL0003 8030
steel
Supply and erection of fabricated,painted piperack structural
STEEL0004 8040
steel
GRAT0001 8050 Supply and erection of fabricated,galvanized steel gratings
GRAT0002 8060 Supply and erection of fabricated,galvanized steel gratings
GRAT0003 8070 Supply and erection of galvanized chequered plate
ANCHOR0001 8080 Supply and installation of fabricated,galvanized anchor bolts
Supply and installation of fabricated,galvanized embedded
EMBEDDED0001 8090
plates
Supply and installation of steel intumescent fireproofing and
FIREPROOFING0001 8100
proper primer.
90 PRECAST WORKS
PRECAST0001 9010 Supply and installation of precast concrete manholes
100 GROUTS
GROUT0001 10010 Supply and application of cementious non-shrink mortar.
GROUT0002 10020 Supply and application of cement base grouting mortar.
GROUT0003 10030 Supply and application of epoxy grouting mortar.
110 JOINTS
JOINT0001 11010 Supply and application of expansion joint sealing.
JOINT0002 11020 Supply and application of construction/cutting joint sealing.
120 FENCES & GATES
Supply and installation of fence SSD-1,barbered wire chainlink
FENCE0001 12010
fence
Supply and installation of fenceTYPE-IV,barbered wire
FENCE0002 12020
chainlink fence
130 WATERPROOFING & COATING
Supply and erection of geotextile membrane under buried
GEOTEXT0001 13010
elements
Supply and erection of HDPE membrane liner under tank
HDPE0001 13020
foundations
Supply and erection of polyethylene sheet membrane under
POLYETH0001 13030
concrete pavements.
Supply and application of bituminous waterproofing emulsion
COATING0001 13040
for concrete surfaces
Supply and application of bituminous waterproofing emulsion
COATING0002 13050
for concrete surfaces
PVCWATERSTOP0001 13060 Supply and application of pvc waterstop.
140 PAVINGS & ROADS
Supply and execution of concrete in paving,reinforced with
PAVING0001 14010
single/double mesh.(Light Duty)
Supply and execution of concrete in paving,reinforced with
PAVING0002 14020
single/double mesh.(Heavy Duty)
ROAD0001 14030 Supply and execution of asphalt wearing course.
ROAD0002 14040 Supply and execution of asphalt binder course.
Supply and execution of subbase material for roads with
ROAD0003 14050
material according with project standards and specifications.

Supply and execution of base material for roads with material


ROAD0004 14060
according with project standards and specifications.
ROAD0005 14070 Supply and application of tack coat in asphalt roads.
ROAD0006 14080 Supply and application of prime coat in asphalt roads.
Supply and complete installation of metallic safety guardrail in
ROAD0007 14090
sides of roads.
Supply and complete installation of concrete barrier type "New
ROAD0008 14100
Jersey" or similar in sides of roads.
ROAD0009 14110 Supply and erection of signposting in ways.
KERB0001 14120 Supply and erection of signposting in ways.
150 U/G WORKS
PVCPIPE0001 15010 Supply and installation uPVC pipe Ø50 mm
PVCPIPE0002 15020 Supply and installation uPVC pipe Ø75 mm
PVCPIPE0003 15030 Supply and installation uPVC pipe Ø90 mm
PVCPIPE0004 15040 Supply and installation uPVC pipe Ø110 mm
PVCPIPE0005 15050 Supply and installation uPVC pipe Ø125 mm
PVCPIPE0006 15060 Supply and installation uPVC pipe Ø140 mm
PVCPIPE0007 15070 Supply and installation uPVC pipe Ø160 mm
PVCPIPE0008 15080 Supply and installation uPVC pipe Ø180 mm
PVCPIPE0009 15090 Supply and installation uPVC pipe Ø200 mm
PVCPIPE0010 15100 Supply and installation uPVC pipe Ø250 mm
PVCPIPE0011 15110 Supply and installation uPVC pipe Ø300 mm
PVCPIPE0012 15120 Supply and installation uPVC pipe Ø350 mm
PVCPIPE0013 15130 Supply and installation uPVC pipe Ø400 mm
PVCPIPE0014 15140 Supply and installation uPVC pipe Ø450 mm
PVCPIPE0015 15150 Supply and installation uPVC pipe Ø500 mm
PVCPIPE0016 15160 Supply and installation uPVC pipe Ø550 mm
PVCPIPE0017 15170 Supply and installation uPVC pipe Ø600 mm
PVCPIPE0018 15180 Supply and installation uPVC pipe Ø650 mm
PVCPIPE0019 15190 Supply and installation uPVC pipe Ø700 mm
PVCPIPE0020 15200 Supply and installation uPVC pipe Ø750 mm
PVCPIPE0021 15210 Supply and installation uPVC pipe Ø800 mm
PVCPIPE0022 15220 Supply and installation uPVC pipe Ø850 mm
PVCPIPE0023 15230 Supply and installation uPVC pipe Ø900 mm
PVCPIPE0024 15240 Supply and installation uPVC pipe Ø950 mm
HDPEPIPE0001 15250 Supply and installation HDPE pipe Ø75 mm
HDPEPIPE0002 15260 Supply and installation HDPE pipe Ø90 mm
HDPEPIPE0003 15270 Supply and installation HDPE pipe Ø100 mm
HDPEPIPE0004 15280 Supply and installation HDPE pipe Ø110 mm
HDPEPIPE0005 15290 Supply and installation HDPE pipe Ø125 mm
HDPEPIPE0006 15300 Supply and installation HDPE pipe Ø140 mm
HDPEPIPE0007 15310 Supply and installation HDPE pipe Ø160 mm
HDPEPIPE0008 15320 Supply and installation HDPE pipe Ø180 mm
HDPEPIPE0009 15330 Supply and installation HDPE pipe Ø200 mm
HDPEPIPE0010 15340 Supply and installation HDPE pipe Ø250 mm
HDPEPIPE0011 15350 Supply and installation HDPE pipe Ø300 mm
HDPEPIPE0012 15360 Supply and installation HDPE pipe Ø350 mm
HDPEPIPE0013 15370 Supply and installation HDPE pipe Ø400 mm
HDPEPIPE0014 15380 Supply and installation HDPE pipe Ø450 mm
HDPEPIPE0015 15390 Supply and installation HDPE pipe Ø500 mm
HDPEPIPE0016 15400 Supply and installation HDPE pipe Ø600 mm
HDPEPIPE0017 15410 Supply and installation HDPE pipe Ø700 mm
HDPEPIPE0018 15420 Supply and installation HDPE pipe Ø800 mm
HDPEPIPE0019 15430 Supply and installation HDPE pipe Ø900 mm
HDPEPIPE0020 15440 Supply and installation HDPE pipe Ø1000 mm
HDPEPIPE0021 15450 Supply and installation HDPE pipe Ø1100 mm
HDPEPIPE0022 15460 Supply and installation HDPE pipe Ø1200 mm
HDPEPIPE0023 15470 Supply and installation HDPE pipe Ø1300 mm
HDPEPIPE0024 15480 Supply and installation HDPE pipe Ø1400 mm
HDPEPIPE0025 15490 Supply and installation HDPE pipe Ø1500 mm
HDPEPIPE0026 15500 Supply and installation HDPE pipe Ø1600 mm
GRPPIPE0001 15510 Supply and installation GRP pipe Ø50 mm
GRPPIPE0002 15520 Supply and installation GRP pipe Ø75 mm
GRPPIPE0003 15530 Supply and installation GRP pipe Ø100 mm
GRPPIPE0004 15540 Supply and installation GRP pipe Ø150 mm
GRPPIPE0005 15550 Supply and installation GRP pipe Ø200 mm
GRPPIPE0006 15560 Supply and installation GRP pipe Ø250 mm
GRPPIPE0007 15570 Supply and installation GRP pipe Ø300 mm
GRPPIPE0008 15580 Supply and installation GRP pipe Ø350 mm
GRPPIPE0009 15590 Supply and installation GRP pipe Ø400 mm
GRPPIPE0010 15600 Supply and installation GRP pipe Ø450 mm
GRPPIPE0011 15610 Supply and installation GRP pipe Ø500 mm
GRPPIPE0012 15620 Supply and installation GRP pipe Ø550 mm
GRPPIPE0013 15630 Supply and installation GRP pipe Ø600 mm
GRPPIPE0014 15640 Supply and installation GRP pipe Ø650 mm
GRPPIPE0015 15650 Supply and installation GRP pipe Ø700 mm
GRPPIPE0016 15660 Supply and installation GRP pipe Ø750 mm
GRPPIPE0017 15670 Supply and installation GRP pipe Ø800 mm
GRPPIPE0018 15680 Supply and installation GRP pipe Ø850 mm
GRPPIPE0019 15690 Supply and installation GRP pipe Ø900 mm
Supply and installation of warning tape for underground
WARNINGTAPE0001 15700
systems.
160 MASONARY WORKS
Supply and installation of hollow concrete block including all
MASONARY0001 16010 associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of lightweight concrete block including
MASONARY0002 16020 all associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of solid block brick including all
MASONARY0003 16030 associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of pre-cast concrete lintels including
MASONARY0004 16040 all associated work, as specified under the Technical
Specification and applicable standards.
170 PLASTERING WORKS
Supply and application of cement plaster for external and
PLASTER0001 17010 internal surfaces including all associated work, as specified
under the Technical Specification and applicable standards.

Supply and application of gypsum plaster for wall and ceiling


PLASTER0002 17020 including all associated work, as specified under the Technical
Specification and applicable standards.
Supply and application of arcylic based ready mixed plaster
PLASTER0003 17040 including all associated work, as specified under the Technical
Specification and applicable standards.
180 PAINTING & ACID RESISTANT COATING
Supply and application of painting for external surfaces
PAINTING0001 18010 including all associated work, as specified under the Technical
Specification and applicable standards.

Supply and application of painting for internal surfaces walls


PAINTING0002 18020 and ceilings including all associated work, as specified under
the Technical Specification and applicable standards.
Supply and application of dust proof painting for cement
PAINTING0003 18030 floors including all associated work, as specified under the
Technical Specification and applicable standards.
Supply and application of acid resistant coating/epoxy screed
5mm minimum for floors including all associated work, as
PAINTING0004 18040
specified under the Technical Specification and applicable
standards.
190 FLOORING & TILING
Supply and application of rigid finished floors(ceramic)
FLOORTILE0001 19010 including all associated work, as specified under the Technical
Specification and applicable standards.

Supply and application of rigid finished floors(terazzo/marble)


FLOORTILE0002 19020 including all associated work, as specified under the Technical
Specification and applicable standards.

Supply and application of flexible finished


floors(uPVC/Vinyl/Carpet/Heavy Duty Vinyl) including all
FLOORTILE0003 19030
associated work, as specified under the Technical
Specification and applicable standards.
Supply and application of rigid finished
walls(ceramic/terazzo/marble) including all associated work,
FLOORTILE0004 19050
as specified under the Technical Specification and applicable
standards.
200 ROOFING & INSULATION
Supply and application of water-proof membrane for roofs
bituminous multi coats including all associated work, as
ROOF0001 20010
specified under the Technical Specification and applicable
standards.
Supply and application of rigid thermal insulation for roofs
ROOF0002 20020 including all associated work, as specified under the Technical
Specification and applicable standards.
Supply and application of light weight concrete screed
average th. 70mm for roofs including all associated work, as
ROOF0003 20030
specified under the Technical Specification and applicable
standards.
Supply and application of roof insulation with Thermal
insulation rockwool 40 mm + finish coatincluding all
ROOF0004 20040
associated work, as specified under the Technical
Specification and applicable standards.
Supply and application of roof insulation with ytong multipor
ROOF0005 20050 including all associated work, as specified under the Technical
Specification and applicable standards.
210 WINDOWS & DOORS & PARTITION WALLS
Supply and installation of timber door hollow core including all
DOOR0001 21010 associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of timber door solid including all
DOOR0002 21020 associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of internal hollow metal door single
DOOR0003 21030 leaf including all associated work, as specified under the
Technical Specification and applicable standards.

Supply and installation of internal hollow metal door double


DOOR0004 21040 leaf including all associated work, as specified under the
Technical Specification and applicable standards.
Supply and installation of roll-up shutter motorised door
DOOR0005 21050 including all associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of fire resistant 30 minutes including
DOOR0006 21060 all associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of fire resistant 60 minutes including
DOOR0007 21070 all associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of aluminium doors with panel
DOOR0008 21080 including all associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of External Hollow metal door double
leaf (Insulated) (Gas-Tight)including all associated work, as
DOOR0009 21090
specified under the Technical Specification and applicable
standards.
Supply and installation of Internal Hollow metal door double
leaf (Insulated) (Gas-Tight)including all associated work, as
DOOR0010 21100
specified under the Technical Specification and applicable
standards.
Supply and installation of gypsum board partition wall with
PARTITIONWALL0001 21110 panel including all associated work, as specified under the
Technical Specification and applicable standards.
Supply and installation of steel frame gas tight window
WINDOW0001 21120 including all associated work, as specified under the Technical
Specification and applicable standards.
220 CLADDING
Supply and installation of panel aluminium pre-finished (wall
CLAD0001 22010 single skin panel) including all associated work, as specified
under the Technical Specification and applicable standards.

Supply and installation of pre-formed panel aluminium pre-


finished (wall sandwich panel)including all associated work, as
CLAD0002 22020
specified under the Technical Specification and applicable
standards.

Supply and installation of Panel aluminium pre-finished (roof


CLAD0003 22030 single skin panel) including all associated work, as specified
under the Technical Specification and applicable standards.

Supply and installation of Pre-formed panel aluminium pre-


finished (roof sandwich panel) including all associated work,
CLAD0004 22040
as specified under the Technical Specification and applicable
standards.
Supply and installation of Pre-formed panel galvanized steel
sheet prefinished ( wall sandwich panel ) including all
CLAD0005 22050
associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of Panel galvanized steel sheet
prefinished ( roof single skin panel ) including all associated
CLAD0006 22060
work, as specified under the Technical Specification and
applicable standards.
Supply and installation of Pre-formed panel galvanized steel
sheet prefinished ( roof sandwich panel ) including all
CLAD0007 22070
associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of Suspended ceiling mineral fiber
CLAD0008 22080 Armstrong or similar including all associated work, as specified
under the Technical Specification and applicable standards.

Supply and installation of raised modular floor fire resistant


CLAD0009 22090 including all associated work, as specified under the Technical
Specification and applicable standards.
Supply and installation of Thermally Insulated Cladding panel
with Polyester powder coated finish including all associated
CLAD0010 22100
work, as specified under the Technical Specification and
applicable standards.
Supply and installation of Thermally Insulated Roof panel with
Polyester powder coated finish including all associated work,
CLAD0011 22110
as specified under the Technical Specification and applicable
standards.
) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS
(IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar

Drawings ID : 001-GA-001 001-GA-001 001-GA-001


WBS, Section, Area, etc. :

SECTION 1 - SECTION 3 -
Project Specific SUBSTATION TANKER
Standard / Class, Specification / 1, SECTION 2 - WEIGHBRIDG
Unit
Grade, Type, Property Employer's SUBSTATION 2 GATEHOUSE E AND
Requirements AND MCC LOGISTIC
BUILDINGS BUILDING

ea



Select Fill or Backfill

please specify.

C30/37concrete; S420
m
Rebar
C30/37concrete; S420
m
Rebar
C30/37concrete; S420
m
Rebar
C30/37concrete; S420
m
Rebar
C30/37concrete; S420
ea
Rebar
ea
ea

ea

m³ 7588.426666667




Select Fill or Backfill
m³ 5295.898666667
please specify.


Select Fill or Backfill

please specify.



m³ C16/20 237.498
m³ C30/37

m³ 1672.74

m³ 2313.531

m² 1374.16

m² 8672.80
m² 2777.28

ton S420

ton S420 167.274

ton S420 323.20503

ton S420

ton S420
ton

ton S275JR

ton 11.025

ton
m² 595.58


ton

ton



m
m

m² 5697.52

m² 3435.09

m² 15 cm THK

m² 20 cm THK
m² 5 cm
m² 8 cm

m³ 15 cm THK

m³ 15 cm THK


m

m

m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m

Water Based Paint-



External

Water Based Paint-



Internal

W=0,9 m H=2,1m

(8);W=1m H=2m (4)

W=0,9 m H=2,1m

(8);W=1m H=2m (4)

W=0,9 m H=2,1m

(8);W=1m H=2m (4)

W=0,9 m H=2,1m

(8);W=1m H=2m (4)
W=0,9 m H=2,1m

(8);W=1m H=2m (4)

W=0,9 m H=2,1m

(8);W=1m H=2m (4)

W=0,9 m H=2,1m

(8);W=1m H=2m (4)

W=0,9 m H=2,1m

(8);W=1m H=2m (4)

W=0,9 m H=2,1m

(8);W=1m H=2m (4)

W=0,9 m H=2,1m

(8);W=1m H=2m (4)

(th=7,5 cm : 1
m² Frame / Double
Board )

W=0,9 m H=2,1m

(8);W=1m H=2m (4)

m² 38/154;0,5 mm

0,4mm base sheet,0,5


m² mm top sheet,60 mm
polyurethane

0,4mm base sheet,0,5


m² mm top sheet,60 mm
polyurethane

0,4mm base sheet,0,5


m² mm top sheet,60 mm
polyurethane

0,4mm base sheet,0,5


m² mm top sheet,60 mm
polyurethane

0,4mm base sheet,0,5


m² mm top sheet,60 mm
polyurethane

0,4mm base sheet,0,5


m² mm top sheet,60 mm
polyurethane
600 x 600 ; Single

Board

600x600x38 mm, PVC



Vinyl

0,4mm base sheet,0,5


m² mm top sheet,60 mm
polyurethane

0,4mm base sheet,0,5


m² mm top sheet,60 mm
polyurethane
001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001

SECTION 9
-INLET
SECTION 4 - PUMPING
SECTION 6 - SECTION 7 SECTION 8
TANKER SECTION 5 STATION
ADMINISTRATION -LABORATORY - CHEMICAL
OFFLOADIN - CAR PARK WET WELL,
BUILDING BUILDING BUILDING
G BAYS DRYWELL
AND COARSE
SCREEN

3678.714667 215.2266667
3293.958667 191.8266667

84.468 4.84

248 14

68.8 6

683.56 36.80

344.00 35.00
0.00 0.00

24.8 1.4

10.32 0.9
986.58 14.7

2.863200421 0.249697711

2.1096875 0.183984375

2.752 0.24

844.68 48.4

1429.64 89.8
001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001

SECTION 10 SECTION 13 SECTION 14


SECTION 11
- FINE - -FLASH SECTION 15 SECTION 16
- SECTION 12
SCREENS, DISSOLVED MIXER, - SBR FEED -SBR
EQUALISATI - API
GRIT AIR FLOCCULAT TANK AND SINGLE
ON TANK SEPARATOR
REMOVAL, FLOATATIO OR AND SBR FEED STAGE AND
AND API UNIT
GRIT N UNIT PRIMARY PUMP WAS PUMP
FEED PUMP
CLASSIFIER (DAF) CLARIFIER
001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001

SECTION 19
- REACTION
TANK AND
SECTION 17
NEUTRALISA SECTION 23
- SBR SECTION 20 SECTION 22
TION TANK, - CLEAN
EFFLUENT SECTION 18 - CHLORINE SECTION 21- -
LAMELLA WATER
STORAGE -ADVANCED CONTACT DUAL MEDIA GRANULAR
CLARIFIER SUMP, GAC
TANK AND OXIDATION TANK AND FILTER ACTIVATED
AND AND DMF
REACTION PROCESS FILTER (DMF) CARBON
LAMELLA BACKWASH
TANK FEED FEED PUMP FILTER
CLARIFIER PUMPS
PUMP
INERT
SLUDGE
PUMP

784.7623333
555.5063333

30.1

178.184

25.988

188.64

44.32
213.08

17.8184

3.78012
25.28064

7.6

0.332930281

0.2453125

0.18

568.52

310.96
001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001

SECTION 27
SECTION 24 -
SECTION 25 SECTION 26
- BLENDING EMERGENC SECTION 28 SECTION 29 SECTION 30
- PLANT - PLANT
TANK AND Y LAGOON - OIL - INERT - INERT
DRAIN DRAIN
DEEP WELL AND FLOW RECOVERY SLUDGE SLUDGE
PUMPING PUMPING
INJECTION RETURN SYSTEM TREATMENT TREATMENT
STATION 1 STATION 2
PUMPS PUMPING
STATION

1122.206
452.282

50.368

590.704

42.62

252.26

152.18
242.48

59.0704

6.12448
51.0741

1.150607053

0.490625

0.49

2663.68

508.9
001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001

SECTION 33 SECTION 34
SECTION 36
SECTION 31 SECTION 32 - ODOUR - ODOUR SECTION 35 SECTION 37
-ORGANO
-BIO -BIO CONTROL CONTROL - FOAM -SODA ASH
SULPHIDES
SLUDGE SLUDGE UNIT 1 UNIT 2 DOSING DOSING
DOSING
TREATMENT TREATMENT (LIQUID (SLUDGE SYSTEM SYSTEM
SYSTEM
STREAM) STREAM)

2511.354 3280.68
1471.766 2083.63

103.402 130.05

880.09 852.60

71.816 275.60

502.38 659.36

168.68 520.00
517.44 1456.00

88.009 85.26

10.43976 40.404
139.86 1638

0.7182 0

1.301890573 5.753035264

0.6378125 2.453125

0.772 5

3494.82 1300.48

1135.2 1990.8
001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001

SECTION 38 SECTION 39 SECTION 40 SECTION 41 SECTION 42 SECTION 43 SECTION 44


- HCL - LIME - NaOCL -SMBS - Fe2(SO4)3 - POLYMER - UREA
DOSING DOSING DOSING DOSING DOSING DOSING DOSING
SYSTEM SYSTEM SYSTEM SYSTEM SYSTEM SYSTEM SYSTEM
001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001 001-GA-001

SECTION 50
SECTION 45 SECTION 48
SECTION 47 SECTION 49 - POWDER
- SECTION 46 - SECTION 51
- CATIONIC - DE- ACTIVATED
PHOSPHORI - GLUCOSE COAGULANT( - CHEMICAL
COAGULANT EMULSIFIE CARBON
C ACID DOSING FeCl3) DOSING
DOSING R DOSING (PAC)
DOSING SYSTEM DOSING LINES
SYSTEM SYSTEM DOSING
SYSTEM SYSTEM
SYSTEM
001-GA-001 001-GA-001 001-GA-001

SECTION 54
SECTION 53
SECTION 52 - SCADA
- EXTERNAL
- PROCESS SYSTEM AND
WORKS AND
PIPEWORK ASSOCIATED
SERVICES
WORKS

13212
11123

289

1800

2011.5

5480.00

6480.00
855.00

180.00

263.25
2890.00

7387.50
Page 81

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
10 DEMOLITIONS
DEMOLISH0001 1010 Demolish existing slabs or concrete All work required for the demolition, demolition equipment,
pavings,buildings,foundations,structures auxiliary requirements (scaffolding, etc.), cutting and removal
of rebars from reinforced concrete, loading and transporting
of debris to an authorized exterior dump site

DEMOLISH0002 1020 Demolition of asphaltic paving road, up to All work required for the demolition, demolition equipment,
15 cm thick, by mechanical means. auxiliary requirements (scaffolding, etc.), cutting and removal
of rebars from reinforced concrete, loading and transporting
of debris to an authorized exterior dump site

DEMOLISH0003 1030 Demolition of underground piping and/or All work required for the demolition, demolition equipment,
channels by mechanical means. auxiliary requirements (scaffolding, etc.), cutting and removal
of rebars from reinforced concrete, loading and transporting
of debris to an authorized exterior dump site

DEMOLISH0004 1040 Demolition of manholes and/or pits (any All work required for the demolition, demolition equipment,
type) by mechanical means. auxiliary requirements (scaffolding, etc.), cutting and removal
of rebars from reinforced concrete, loading and transporting
of debris to an authorized exterior dump site

20 SITE PREPARATION
SITECLEAR0001 2010 Clearing, stripping and grading of of natural Removal of natural and organic soil, trees, plants, bushes,
land for specified average thickness grass, roots. The vegetation, including roots tree stumps, shall
be removed completely Includes the transport of machinery to
and within the job site, positioning time for machinery,
cleaning, ripping, excavation of the surface grade,
intermediate storage, removal and transport of all materials
from the cleaned area to an authorized external dump area
(including trees, stumps, plants,and all types of undesirable
material) safety requirements and dumping fees.
Page 82

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
EXCV0001 2020 General excavation by mechanical means. Excavation required for leaving a working area to a specific
(Cut) level and to flatten, compact and prepare the site on a specific
conditions. The excavation is performed in rock and it is
required the use of hydraulic hammer. Includes positioning
time for machinery, cutting and ripping and excavating.

FILL0001 2010 General filling with select fill material from Backfilling for large open areas to create a work platform in
excavation.(Fill/Embankment) required level, compact and prepare the site on a specific
condition. In detail, general backfilling are performed on open
areas where backfilling equipment can operate at the same
level as the grading with temporary ramps if
necessary.Transportation of material,stockpiling and spreading
is included. The material shall be selected material from
excavations complying with specifications.If excaveted
material is suitable for backfilling ,no material price is
inclueded.If crusher is necessary to grade and screen
materials on site in terms of specification compliant, the
crusher price shall be included in material price, otherwise it
shall not.

30 PILING WORKS
SHEETPILE0001 3010 Supply and installation of sheet piling The price includes material supply, layout works and plotting,
system with plate thickness as per project installation, Removal, truck load and transport out of property
standards,specifications or approved limits, tools, auxiliary means, specialized machinery and, in
drawings. general all required material and labor for the correct
completion of all work. Supply, prefabrication, erection and
removal of auxiliary steel structure is included.

PILE0001 3020 Supply and execution in situ concrete The price includes machinery movement within the work site,
ø30 cm diameter boring piles. fuel, water, maintenance of machinery and cleaning, re-
exchanges steel casing and/or bentonite sludge or any other
thixotropic sludge, piling execution,supply and puring of
concrete, supply and installation of rebar.
Page 83

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PILE0002 3030 Supply and execution in situ concrete The price includes machinery movement within the work site,
ø60 cm diameter boring piles. fuel, water, maintenance of machinery and cleaning, re-
exchanges steel casing and/or bentonite sludge or any other
thixotropic sludge, piling execution,supply and puring of
concrete, supply and installation of rebar
PILE0003 3040 Supply and execution in situ concrete The price includes machinery movement within the work site,
ø90 cm diameter boring piles. fuel, water, maintenance of machinery and cleaning, re-
exchanges steel casing and/or bentonite sludge or any other
thixotropic sludge, piling execution,supply and puring of
concrete, supply and installation of rebar.
PILE0004 3050 Supply and execution in situ concrete The price includes machinery movement within the work site,
ø120 cm diameter boring piles. fuel, water, maintenance of machinery and cleaning, re-
exchanges steel casing and/or bentonite sludge or any other
thixotropic sludge, piling execution,supply and puring of
concrete, supply and installation of rebar.
PILE0005 3060 Cut-off concrete piles head The price includes the cutting off pile heads,load and
transport of debris to an authorized exterior dump site,
dumping fees, auxiliary means and, in general, all required
materials and labor for the correct completion of the required
unit.
PILETEST0001 3070 Execution of integrity test for piles. The price includes supply and installation of test set-up,
equipment,manpower and consumable.

PILETEST0002 3080 Execution of load compression test on The price includes supply and installation of test set-up,
working piles (1,5 working load) equipment,manpower and consumable.

PILETEST0003 3090 Execution of Preliminary compression test The price includes supply and installation of test set-up,
(2,5 working load) equipment,manpower and consumable.The material of test
specimen piles shall be provided by TEKFEN. Execution in situ
concrete test boring piles shall be carried by others.

40 EARTHWORKS
Page 84

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
EXCV0002 4010 Structural deep excavation of soil for the Structural deep excavations for foundations, catch basins,
depth 0.00-2.00 m pits, tie beams, etc., performed below the elevation of the
finishing grade with the machine shall be located outside of
the area to be excavated.Rock excavation refers to the
excavation executed with hydraulic hammer.

EXCV0003 4020 Structural deep excavation of soil for the Structural deep excavations for foundations, catch basins,
depth 2.00-4.00 m pits, tie beams, etc., performed below the elevation of the
finishing grade with the machine shall be located outside of
the area to be excavated.Rock excavation refers to the
excavation executed with hydraulic hammer.

EXCV0004 4030 Hand excavation of soil Structural deep excavations for foundations, catch basins,
pits, tie beams, etc., performed below the elevation of the
finishing grade with hand shall be located outside of the area
to be excavated.

EXCV0005 4040 Pipe/Trench excavation of soil for the depth Structural deep excavations for trecnhes,cable channels
0.00-2.00 m performed below the elevation of the finishing grade with
hand shall be located outside of the area to be excavated.Up
to 2.00 m
Page 85

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
EXCV0006 4050 Pipe/Trench excavation of soil for the depth Structural deep excavations for trecnhes,cable channels
2.00-4.00 m performed below the elevation of the finishing grade with
hand shall be located outside of the area to be excavated.Up
to 4.00 m

FILL0002 4060 Structural filling with select fill material Backfilling for limited areas such as foundations,pits etc to
from excavation. create a work platform in required level, compact and prepare
the site on a specific condition. In detail, general backfilling
are performed on limited areas where backfilling equipment
can operate at the same level as the grading with temporary
ramps if necessary.Transportation of material,stockpiling and
spreading is included.The material shall be selected material
from excavations complying with specifications.If crusher is
necessary to grade and screen materials on site in terms of
specification compliant, the crusher price shall be included in
material price, otherwise it shall not.

FILL0003 4070 General filling with borrowed granular Filling for large open areas to create a work platform in
material. (Imported Fill) required level, compact and prepare the site on a specific
condition. In detail, general backfilling are performed on open
areas where backfilling equipment can operate at the same
level as the grading with temporary ramps if necessary.
Supply of material,transportation of material,stockpiling and
spreading is included. The material shall be imported from
borrowed pits near the site.
Page 86

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
FILL0004 4080 Structural filling with borrowed granular Filling for limited areas such as foundations,pits etc to create
material. (Imported Fill) a work platform in required level, compact and prepare the
site on a specific condition. In detail, general backfilling are
performed on limited areas where backfilling equipment can
operate at the same level as the grading with temporary
ramps if necessary. Supply of material,transportation of
material,stockpiling and spreading is included. The material
shall be imported from borrowed pits close t o the site
complying with the specifications.

FILL0005 4090 Trench filling with select fill material from Backfilling for trenches to create a work platform in required
excavation. level, compact and prepare the site on a specific condition. In
detail, general backfilling are performed along trenches where
backfilling equipment can operate at the same level as the
grading with temporary ramps if necessary.Transportation of
material,stockpiling and spreading is included.The material
shall be selected material from excavations complying with
specifications.If crusher is necessary to grade and screen
materials on site in terms of specification compliant, the
crusher price shall be included in material price, otherwise it
shall not.
FILL0006 4100 Pipe/Trench bedding/padding with Filling with borrowed granular fill material for bedding/
borrowed granular fill material (Imported padding use around and under buried pipes.Supply of
Fill) material, transportation of material,stockpiling and spreading
is included.The material shall be imported from borrowed pits
close to the site complying with the specifications.

FILL0007 4110 Pipe/Trench bedding/padding with clean Filling with clean sand material for bedding/ padding use
sand around and under buried pipes.Supply of material,
transportation of material,stockpiling and spreading is
included.The material shall be imported from borrowed pits
close to the site complying with the specifications.
Page 87

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
FILL0008 4120 Filling inside of tank foundations with clean Filling with inside of tank foundations with clean sand.Supply
sand. of material, transportation of material,stockpiling and
spreading is included.The material shall be imported from
borrowed pits close to the site complying with the
specifications.
FILL0009 4120 Tank foundations filling with oil sand Supply of material, transportation of material,stockpiling and
mixture. spreading is included.The material shall be imported from
borrowed pits close to the site complying with the
specifications.

50 CONCRETE WORKS
CONCRETE0001 5010 Supply and pouring of lean concrete Supply and pouring of lean concrete 5<=th<= 10cm
.Concrete grade and content shall comply with the
specifications.

CONCRETE0002 5020 Supply and pouring of mass concrete Supply and pouring of mass concrete for the foundation that
has volume greater than 500 m3 and poured in a lumped.
Concrete grade and content shall comply with the
specifications.

CONCRETE0003 5030 Supply and pouring of concrete for various Supply and pouring of concrete for various and slab
and slab foundations (sleepers, stairs, foundations foundations. Concrete grade and content shall
thickened slab foundation,tank comply with the specifications.
foundations)
Page 88

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
CONCRETE0004 5040 Supply and pouring of concrete for footing Supply and pouring of concrete for any kind foundations.
type foundations (columns,equipment and Concrete grade and content shall comply with the
valve foundations, pipe supports,lighting specifications.
post,single footing)

CONCRETE0005 5050 Supply and pouring of conrete for Supply and pouring of concrete for elevated
slabs,beams,walls. slabs,beams,walls. Concrete grade and content shall comply
with the specifications.

CONCRETE0006 5060 Supply and pouring of conrete for Supply and pouring of concrete for manholes,trenches,valve
manholes and trenches. pits. Concrete grade and content shall comply with the
specifications.

60 FORMWORKS
FORMWORK0001 6010 Supply and erection of straight formwork Piping and equipment supports, sleepers, paving thickened
for various and slab foundations (sleepers, slab footings, pedestal for stairs and non-elevated pedestal for
stairs, thickened slab foundation,tank turbines shall be considered in this class. Including all aspects
foundations) of prefabrication of the required material, supply, layout works
and plotting, installation, shoring, bracing, removal of
formwork, cleaning and preparation of surface formwork for
subsequent work, manpower, material costs.
Page 89

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
FORMWORK0002 6020 Supply and erection of straight formwork Columns, pedestals less than 1 meter high (measured from
for footing type foundations the upper side of the foot) shall be considered in this
(columns,equipment and valve foundations, class.Including all aspects of prefabrication of the required
pipe supports,lighting post,single footing) material, supply, layout works and plotting, installation,
shoring, bracing, removal of formwork, cleaning and
preparation of surface formwork for subsequent work,
manpower, any material costs.
FORMWORK0003 6030 Supply and erection of straight formwork Elevated slabs and beams for building shall be considered in
for slab and beams. this class. Including all aspects of prefabrication of the
required material, supply, layout works and plotting,
installation, shoring, bracing, removal of formwork, cleaning
and preparation of surface formwork for subsequent work,
manpower, any material costs.
FORMWORK0004 6040 Supply and erection of straight formwork Basement, retaining and shear walls shall be considered in
for walls this class. Including all aspects of prefabrication of the
required material, supply, layout works and plotting,
installation, shoring, bracing, removal of formwork, cleaning
and preparation of surface formwork for subsequent work,
manpower, any material costs.
FORMWORK0005 6050 Supply and erection of straight formwork Basement, retainin and shear walls shall be considered in this
for manholes and trenches class. Including all aspects of prefabrication of the required
material, supply, layout works and plotting, installation,
shoring, bracing, removal of formwork, cleaning and
preparation of surface formwork for subsequent work,
manpower, any material costs.
70 REBAR WORKS
REBAR0001 7010 Supply and installation of steel Includes material supply, intermediate storage and transport,
reinforcement for various and slab labor costs (cutting and bending), installation, manpower,
foundations (sleepers, stairs, thickened slab tools, machinery and, in general, all required materials and
foundation,tank foundations) labor for the correct completion of all work. Steel
reinforcement grade and content shall comply with the
specifications.
Page 90

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
REBAR0002 7020 Supply and installation of steel Includes material supply, intermediate storage and transport,
reinforcement for footing type foundations labor costs (cutting and bending), installation, manpower,
(columns,equipment and valve foundations, tools, machinery and, in general, all required materials and
pipe supports,lighting post,single footing) labor for the correct completion of all work. Steel
reinforcement grade and content shall comply with the
specifications.
REBAR0003 7030 Supply and installation of steel Includes material supply, intermediate storage and transport,
reinforcement for slabs,beams and walls labor costs (cutting and bending), installation, manpower,
tools, machinery and, in general, all required materials and
labor for the correct completion of all work. Steel
reinforcement grade and content shall comply with the
specifications.
REBAR0004 7040 Supply and installation of steel Includes material supply, intermediate storage and transport,
reinforcement for manholes and trenches labor costs (cutting and bending), installation, manpower,
tools, machinery and, in general, all required materials and
labor for the correct completion of all work. Steel
reinforcement grade and content shall comply with the
specifications.
REBAR0005 7050 Supply and installation of steel fabric mesh Includes material supply, intermediate storage and transport,
reinforcement for pavements and slabs. labor costs (cutting and bending), installation, manpower,
tools, machinery and, in general, all required materials and
labor for the correct completion of all work. Steel
reinforcement grade and content shall comply with the
specifications.
80 STRUCTURAL STEEL WORKS
STEEL0001 8010 Supply and erection of fabricated,painted Includes material supply, intermediate storage and transport,
heavy structural steel labor costs, installation, manpower, tools, machinery and, in
general, all required materials and labor for the correct
completion of all work. The steel
frames,columns,beams,bracings greater than 250 kg shall be
considered in this class.(i.e.workshops,steel structure
buildings,) Steel grade and content shall comply with the
specifications.
Page 91

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
STEEL0002 8020 Supply and erection of fabricated,painted Includes material supply, intermediate storage and transport,
medium structural steel labor costs, installation, manpower, tools, machinery and, in
general, all required materials and labor for the correct
completion of all work. The steel
frames,columns,beams,bracings between 50 kg and 250 kg
shall be considered in this class.(i.e. platform ,skids) Steel
grade and content shall comply with the specifications.

STEEL0003 8030 Supply and erection of fabricated and Includes material supply, intermediate storage and transport,
painted light structural steel labor costs, installation, manpower, tools, machinery and, in
general, all required materials and labor for the correct
completion of all work. The steel
frames,columns,beams,bracings below 50 kg shall be
considered in this class.(i.e.shelters ,stairs) Steel grade and
content shall comply with the specifications.
STEEL0004 8040 Supply and erection of fabricated,painted Includes material supply, intermediate storage and transport,
piperack structural steel labor costs, installation, manpower, tools, machinery and, in
general, all required materials and labor for the correct
completion of all work. The steel
frames,columns,beams,bracings used in the piperack
construction shall be considered in this class. Steel grade and
content shall comply with the specifications.
GRAT0001 8050 Supply and erection of Including material supply, surface treatment (blasting +
fabricated,galvanized steel gratings priming if required / hot dip galvanizing), finishing surface
paint, special pieces, accessories, general repair
(priming/galvanizing, paint, damages, welding, etc.) and, in
general, all required materials and labor for the correct
completion of all work. Loads on the platform 250-300 kg/m2,
shall be considered in this class. Steel grade and content shall
comply with the specifications.
Page 92

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
GRAT0002 8060 Supply and erection of Including material supply, surface treatment (blasting +
fabricated,galvanized steel gratings priming if required / hot dip galvanizing), finishing surface
paint, special pieces, accessories, general repair
(priming/galvanizing, paint, damages, welding, etc.) and, in
general, all required materials and labor for the correct
completion of all work. Loads on the platform 750 kg/m2 shall
be considered in this class. Steel grade and content shall
comply with the specifications.
GRAT0003 8070 Supply and erection of galvanized Including material supply, surface treatment (blasting +
chequered plate priming if required / hot dip galvanizing), finishing surface
paint, special pieces, accessories, general repair
(priming/galvanizing, paint, damages, welding, etc.) and, in
general, all required materials and labor for the correct
completion of all work. Steel grade and content shall comply
with the specifications.
ANCHOR0001 8080 Supply and installation of The unit price includes fabrication, supply, installation, all
fabricated,galvanized anchor bolts related accessories (i.e. sleeves, nuts, washers, etc.), accurate
surveying, supply and installation of all templates (except for
turbines), drillings (screw and machine type included),
temporary supports, protections, labeling and any other
requirement, regardless of nature, necessary for the correct
complete installation of the required unit.Steel grade and
content shall comply with the specifications.
EMBEDDED0001 8090 Supply and installation of The unit price includes fabrication, supply, installation and any
fabricated,galvanized embedded plates other requirement, regardless of nature, necessary for the
correct complete installation of the required unit.Steel grade
and content shall comply with the specifications.
FIREPROOFING0001 8100 Supply and installation of steel intumescent The unit price includes fabrication, supply, installation of 5 cm
fireproofing and proper primer. < th <10 cm fire proofing concrete coating, supply and
installation of mesh reinforcement and hooks,mastic sealing
between the concrete layer edge and the metal structure,
according to the specifications.
90 PRECAST WORKS
Page 93

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PRECAST0001 9010 Supply and installation of precast concrete Includes material supply in workshop, works layout and
manholes plotting, formwork, concrete works, vibrating, curing, removal
of formwork, storage, protection, custody and, in general, all
required materials and labor for the correct completion of all
work.
It is also included the load, transport and unload in the final
position of the element.Embedded items are excluded. The
quantity of rebar shall be included in rebar items.

100 GROUTS
GROUT0001 10010 Supply and application of cementious non- The unit price includes supply, application, preparation,
shrink mortar. supports, pouring mediums, and any other requirement,
regardless of nature, necessary for the correct installation of
the required unit.
GROUT0002 10020 Supply and application of cement base The unit price includes supply, application, preparation,
grouting mortar. supports, pouring mediums, and any other requirement,
regardless of nature, necessary for the correct installation of
the required unit.
GROUT0003 10030 Supply and application of epoxy grouting The unit price includes supply, application, preparation,
mortar. supports, pouring mediums, and any other requirement,
regardless of nature, necessary for the correct installation of
the required unit.
110 JOINTS
JOINT0001 11010 Supply and application of expansion joint The unit price includes layout works and plotting, material
sealing. supply, installation of material following manufacturer
recommendations, manpower, surface preparation, , tools,
machinery, auxiliary means and, in general, all required
materials and labor for the correct completion of all work.
JOINT0002 11020 Supply and application of The unit price includes layout works and plotting, material
construction/cutting joint sealing. supply, installation of material following manufacturer
recommendations, manpower, surface preparation, , tools,
machinery, auxiliary means and, in general, all required
materials and labor for the correct completion of all work.
Page 94

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
120 FENCES & GATES
FENCE0001 12010 Supply and installation of fence SSD- The price includes material supply, clamps, accessories,
1,barbered wire chainlink fence earthing, tools, auxiliary means, machinery and, in general, all
required material and labor for the correct completion of all
work. Excavation, backfilling and filling, concrete pouring shall
be excluded. These items shall be considred in relevant line
items.SSD-1 is a type of fence used in ARAMCO projects.

FENCE0002 12020 Supply and installation of fenceTYPE- The price includes material supply, clamps, accessories,
IV,barbered wire chainlink fence earthing, tools, auxiliary means, machinery and, in general, all
required material and labor for the correct completion of all
work. Excavation, backfilling and filling, concrete pouring shall
be excluded. These items shall be considred in relevant line
items.TYPE-IV is a type of fence used in ARAMCO projects.

130 WATERPROOFING & COATING


GEOTEXT0001 13010 Supply and erection of geotextile The unit price includes material supply, manpower, grip,
membrane under buried elements overlaps, any additional widening, cuttings and cropping,
tools, machinery, auxiliary means, and, in general, all required
materials and labor for the correct completion of all work.

HDPE0001 13020 Supply and erection of HDPE membrane The unit price includes material supply of sitable material
liner under tank foundations according with project standars, specifications and drawings,
manpower, overlaps, any additional widening, cuttings and
cropping, tools, machinery, auxiliary means, and, in general,
all required materials and labor for the correct completion of
all work.
POLYETH0001 13030 Supply and erection of polyethylene sheet The unit price includes material supply of suitable material
membrane under concrete pavements. according with project standars, specifications and drawings,
manpower, overlaps, any additional widening, cuttings and
cropping, tools, machinery, auxiliary means, and, in general,
all required materials and labor for the correct completion of
all work.
Page 95

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
COATING0001 13040 Supply and application of bituminous Complete system of concrete surface treatments required for
waterproofing emulsion for concrete concrete protection, as required by project specifications. For
surfaces concrete below ground or above ground. The unit price
includes material supply of sitable material according with
project standars, specifications and drawings, application or
installation according with manufacturer recommendations,
manpower, overlaps, any additional widening, cuttings and
cropping, tools, machinery, auxiliary means, and, in general,
all required materials and labor for the correct completion of
all work.
COATING0002 13050 Supply and application of bituminous Complete system of concrete surface treatments required for
waterproofing emulsion for concrete concrete protection, as required by project specifications. For
surfaces concrete below ground or above ground. The unit price
includes material supply of sitable material according with
project standars, specifications and drawings, application or
installation according with manufacturer recommendations,
manpower, overlaps, any additional widening, cuttings and
cropping, tools, machinery, auxiliary means, and, in general,
all required materials and labor for the correct completion of
all work.
PVCWATERSTOP0001 13060 Supply and application of pvc waterstop. The unit price includes material supply of suitable material
according with project standars, specifications and drawings,
manpower, overlaps, any additional widening, cuttings and
cropping, tools, machinery, auxiliary means, and, in general,
all required materials and labor for the correct completion of
all work.
140 PAVINGS & ROADS
Page 96

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PAVING0001 14010 Supply and execution of concrete in The unit price includes material supply, mesh supply &
paving,reinforced with single/double mesh. installation, concrete pouring by any mean, spreading,
(Light Duty) vibrating, leveling, curing, slope forming, floating, troweling
according with project standards, specifications or approved
drawings, tools, auxiliary means, machinery, and, in general,
all required materials and labor for the correct completion of
all work. formworks shall be excluded. These items shall be
considered in relevant line items.

PAVING0002 14020 Supply and execution of concrete in The unit price includes material supply, mesh supply &
paving,reinforced with single/double mesh. installation, concrete pouring by any mean, spreading,
(Heavy Duty) vibrating, leveling, curing, slope forming, floating, troweling
according with project standards, specifications or approved
drawings, tools, auxiliary means, machinery, and, in general,
all required materials and labor for the correct completion of
all work. formworks shall be excluded. These items shall be
considered in relevant line items.

ROAD0001 14030 Supply and execution of asphalt wearing The unit price includes the material supply, spreading by any
course. means, compaction, forming and sealing joints, tools, auxiliary
means, machinery,according with project standards,
specifications or approved drawings and, in general, all
required materials and labor for the correct completion of all
work. Thickness shall be indicated in BoQ items.

ROAD0002 14040 Supply and execution of asphalt binder The unit price includes the material supply, spreading by any
course. means, compaction, forming and sealing joints, tools, auxiliary
means, machinery,according with project standards,
specifications or approved drawings and, in general, all
required materials and labor for the correct completion of all
work. Thickness shall be indicated in BoQ items.
Page 97

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
ROAD0003 14050 Supply and execution of subbase material The unit price includes material supply with characteristics
for roads with material according with according project requirements and specifications for each
project standards and specifications. kind of material, transportation, intermediate storage,
preparation of area to be backfilled (scarifying and re-
compacting), spreading, irrigation, compaction, grading,
machinery, auxiliary means and, in general, all required
materials and labor for the correct completion of all work.

ROAD0004 14060 Supply and execution of base material for The unit price includes material supply with characteristics
roads with material accoridng with project according project requirements and specifications for each
standards and specifications. kind of material, transportation, intermediate storage,
preparation of area to be backfilled (scarifying and re-
compacting), spreading, irrigation, compaction, grading,
machinery, auxiliary means and, in general, all required
materials and labor for the correct completion of all work.

ROAD0005 14070 Supply and application of tack coat in The unit price includes material supply, installation, surface
asphalt roads. treatment, tools, auxiliary means, machinery and, in general,
all required materials and labor for the correct completion of
all work.

ROAD0006 14080 Supply and application of prime coat in The unit price includes material supply, installation, surface
asphalt roads. treatment, tools, auxiliary means, machinery and, in general,
all required materials and labor for the correct completion of
all work.
Page 98

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
ROAD0007 14090 Supply and complete installation of metallic The unit price includes material supply (materials shall be
safety guardrail in sides of roads. according with project standards, specifications and drawings
and anchoring according with manufacturer
recommendations, painting as per specification and
installation of any required reflecting fittings. ), Excavation,
refining, backfilling, loading and transporting to an authorized
dumping area, dumping fees, compaction, complete
foundation shall be excluded. These items shall be considered
in relevant line items.
ROAD0008 14100 Supply and complete installation of The unit price includes material supply (materials shall be
concrete barrier type "New Jersey" or according with project standards, specifications and drawings
similar in sides of roads. and anchoring according with manufacturer
recommendations, painting as per specification and
installation of any required reflecting fittings.)
ROAD0009 14110 Supply and erection of signposting in The unit price includes material supply (materials shall be
ways. according with project standards, specifications and drawings
and anchoring according with manufacturer
recommendations, painting as per specification and
installation of any required reflecting fittings. ), Excavation,
refining, backfilling, loading and transporting to an authorized
dumping area, dumping fees, compaction, complete
foundation shall be excluded. These items shall be considered
in relevant line items.
KERB0001 14120 Supply and installation of kerbs The unit price includes material supply materials and
installation in accordance with project standards,
specifications and drawings.
150 U/G WORKS
Page 99

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PVCPIPE0001 15010 Supply and installation uPVC pipe Ø50 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0002 15020 Supply and installation uPVC pipe Ø75 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0003 15030 Supply and installation uPVC pipe Ø90 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0004 15040 Supply and installation uPVC pipe Ø110 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 100

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PVCPIPE0005 15050 Supply and installation uPVC pipe Ø125 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0006 15060 Supply and installation uPVC pipe Ø140 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0007 15070 Supply and installation uPVC pipe Ø160 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0008 15080 Supply and installation uPVC pipe Ø180 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 101

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PVCPIPE0009 15090 Supply and installation uPVC pipe Ø200 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0010 15100 Supply and installation uPVC pipe Ø250 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0011 15110 Supply and installation uPVC pipe Ø300 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0012 15120 Supply and installation uPVC pipe Ø350 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 102

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PVCPIPE0013 15130 Supply and installation uPVC pipe Ø400 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0014 15140 Supply and installation uPVC pipe Ø450 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0015 15150 Supply and installation uPVC pipe Ø500 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0016 15160 Supply and installation uPVC pipe Ø550 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 103

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PVCPIPE0017 15170 Supply and installation uPVC pipe Ø600 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0018 15180 Supply and installation uPVC pipe Ø650 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0019 15190 Supply and installation uPVC pipe Ø700 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0020 15200 Supply and installation uPVC pipe Ø750 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 104

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PVCPIPE0021 15210 Supply and installation uPVC pipe Ø800 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0022 15220 Supply and installation uPVC pipe Ø850 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0023 15230 Supply and installation uPVC pipe Ø900 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
PVCPIPE0024 15240 Supply and installation uPVC pipe Ø950 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 105

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
HDPEPIPE0001 15250 Supply and installation HDPE pipe Ø75 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0002 15260 Supply and installation HDPE pipe Ø90 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0003 15270 Supply and installation HDPE pipe Ø100 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0004 15280 Supply and installation HDPE pipe Ø110 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 106

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
HDPEPIPE0005 15290 Supply and installation HDPE pipe Ø125 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0006 15300 Supply and installation HDPE pipe Ø140 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0007 15310 Supply and installation HDPE pipe Ø160 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0008 15320 Supply and installation HDPE pipe Ø180 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 107

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
HDPEPIPE0009 15330 Supply and installation HDPE pipe Ø200 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0010 15340 Supply and installation HDPE pipe Ø250 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0011 15350 Supply and installation HDPE pipe Ø300 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0012 15360 Supply and installation HDPE pipe Ø350 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 108

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
HDPEPIPE0013 15370 Supply and installation HDPE pipe Ø400 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0014 15380 Supply and installation HDPE pipe Ø450 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0015 15390 Supply and installation HDPE pipe Ø500 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0016 15400 Supply and installation HDPE pipe Ø600 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 109

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
HDPEPIPE0017 15410 Supply and installation HDPE pipe Ø700 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0018 15420 Supply and installation HDPE pipe Ø800 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0019 15430 Supply and installation HDPE pipe Ø900 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0020 15440 Supply and installation HDPE pipe Ø1000 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 110

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
HDPEPIPE0021 15450 Supply and installation HDPE pipe Ø1100 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0022 15460 Supply and installation HDPE pipe Ø1200 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0023 15470 Supply and installation HDPE pipe Ø1300 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0024 15480 Supply and installation HDPE pipe Ø1400 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 111

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
HDPEPIPE0025 15490 Supply and installation HDPE pipe Ø1500 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
HDPEPIPE0026 15500 Supply and installation HDPE pipe Ø1600 This unit price includes the material supply,spacers, special
mm pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0001 15510 Supply and installation GRP pipe Ø50 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0002 15520 Supply and installation GRP pipe Ø75 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 112

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
GRPPIPE0003 15530 Supply and installation GRP pipe Ø100 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0004 15540 Supply and installation GRP pipe Ø150 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0005 15550 Supply and installation GRP pipe Ø200 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0006 15560 Supply and installation GRP pipe Ø250 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 113

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
GRPPIPE0007 15570 Supply and installation GRP pipe Ø300 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0008 15580 Supply and installation GRP pipe Ø350 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0009 15590 Supply and installation GRP pipe Ø400 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0010 15600 Supply and installation GRP pipe Ø450 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 114

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
GRPPIPE0011 15610 Supply and installation GRP pipe Ø500 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0012 15620 Supply and installation GRP pipe Ø550 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0013 15630 Supply and installation GRP pipe Ø600 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0014 15640 Supply and installation GRP pipe Ø650 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 115

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
GRPPIPE0015 15650 Supply and installation GRP pipe Ø700 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0016 15660 Supply and installation GRP pipe Ø750 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0017 15670 Supply and installation GRP pipe Ø800 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
GRPPIPE0018 15680 Supply and installation GRP pipe Ø850 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
Page 116

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
GRPPIPE0019 15690 Supply and installation GRP pipe Ø900 mm This unit price includes the material supply,spacers, special
pieces, accessories and piping fittings, joints (elastic joints
could be glued or not), supply and installation of cable pulling
guides,lubricants, tools, auxiliary means, machinery and, in
general, all required materials and labor for the correct
completion of all work. Excavation,backfilling and filling shall
be excluded. These items shall be considered in relevant line
items.
WARNINGTAPE0001 15700 Supply and installation of warning tape for The unit price includes the material supply, installation,
underground systems. overlaps, tools, auxiliary means, and, in general, all required
materials and labor for the correct completion of all work.

160 MASONARY WORKS


MASONARY0001 16010 Supply and installation of hollow concrete The unit price includes the material supply, installation,
block including all associated work, as overlaps, tools, auxiliary means, and, in general, all required
specified under the Technical Specification materials and labor for the correct completion of all work.
and applicable standards.
MASONARY0002 16020 Supply and installation of lightweight The unit price includes the material supply, installation,
concrete block including all associated overlaps, tools, auxiliary means, and, in general, all required
work, as specified under the Technical materials and labor for the correct completion of all work.
Specification and applicable standards.
MASONARY0003 16030 Supply and installation of solid block brick The unit price includes the material supply, installation,
including all associated work, as specified overlaps, tools, auxiliary means, and, in general, all required
under the Technical Specification and materials and labor for the correct completion of all work.
applicable standards.
MASONARY0004 16040 Supply and installation of pre-cast concrete The unit price includes the material supply, installation,
lintels including all associated work, as overlaps, tools, auxiliary means, and, in general, all required
specified under the Technical Specification materials and labor for the correct completion of all work.
and applicable standards.
170 PLASTERING WORKS
Page 117

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PLASTER0001 17010 Supply and application of cement plaster The unit price includes the material supply, installation,
for external and internal surfaces including overlaps, tools, auxiliary means, and, in general, all required
all associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
PLASTER0002 17020 Supply and application of gypsum plaster The unit price includes the material supply, installation,
for wall and ceiling including all associated overlaps, tools, auxiliary means, and, in general, all required
work, as specified under the Technical materials and labor for the correct completion of all work.
Specification and applicable standards.

PLASTER0003 17030 Supply and application of arcylic based The unit price includes the material supply, installation,
ready mixed plaster including all associated overlaps, tools, auxiliary means, and, in general, all required
work, as specified under the Technical materials and labor for the correct completion of all work.
Specification and applicable standards.

180 PAINTING & ACID RESISTANT


COATING
PAINTING0001 18010 Supply and application of painting for The unit price includes the material supply, installation,
external surfaces including all associated overlaps, tools, auxiliary means, and, in general, all required
work, as specified under the Technical materials and labor for the correct completion of all work.
Specification and applicable standards.
PAINTING0002 18020 Supply and application of painting for The unit price includes the material supply, installation,
internal surfaces walls and ceilings overlaps, tools, auxiliary means, and, in general, all required
including all associated work, as specified materials and labor for the correct completion of all work.
under the Technical Specification and
applicable standards.
PAINTING0003 18030 Supply and application of dust proof The unit price includes the material supply, installation,
painting for cement floors including all overlaps, tools, auxiliary means, and, in general, all required
associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
Page 118

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
PAINTING0004 18040 Supply and application of acid resistant The unit price includes the material supply, installation,
coating/epoxy screed 5mm minimum for overlaps, tools, auxiliary means, and, in general, all required
floors including all associated work, as materials and labor for the correct completion of all work.
specified under the Technical Specification
and applicable standards.
190 FLOORING & TILING
FLOORTILE0001 19010 Supply and application of rigid finished The unit price includes the material supply, installation,
floors(ceramic) including all associated overlaps, tools, auxiliary means, and, in general, all required
work, as specified under the Technical materials and labor for the correct completion of all work.
Specification and applicable standards.
FLOORTILE0002 19010 Supply and application of rigid finished The unit price includes the material supply, installation,
floors(terazzo/marble) including all overlaps, tools, auxiliary means, and, in general, all required
associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
FLOORTILE0003 19020 Supply and application of flexible finished The unit price includes the material supply, installation,
floors(uPVC/Vinyl/Carpet/Heavy Duty Vinyl) overlaps, tools, auxiliary means, and, in general, all required
including all associated work, as specified materials and labor for the correct completion of all work.
under the Technical Specification and
applicable standards.
FLOORTILE0004 19040 Supply and application of rigid finished The unit price includes the material supply, installation,
walls(ceramic/terazzo/marble) including all overlaps, tools, auxiliary means, and, in general, all required
associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
200 ROOFING & INSULATION
ROOF0001 20010 Supply and application of water-proof The unit price includes the material supply, installation,
membrane for roofs bituminous multi coats overlaps, tools, auxiliary means, and, in general, all required
including all associated work, as specified materials and labor for the correct completion of all work.
under the Technical Specification and
applicable standards.
Page 119

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
ROOF0002 20020 Supply and application of rigid thermal The unit price includes the material supply, installation,
insulation for roofs including all associated overlaps, tools, auxiliary means, and, in general, all required
work, as specified under the Technical materials and labor for the correct completion of all work.
Specification and applicable standards.

ROOF0003 20030 Supply and application of light weight The unit price includes the material supply, installation,
concrete screed average th. 70mm for overlaps, tools, auxiliary means, and, in general, all required
roofs including all associated work, as materials and labor for the correct completion of all work.
specified under the Technical Specification
and applicable standards.
ROOF0004 20050 Supply and application of roof insulation The unit price includes the material supply, installation,
with bituminous primer including all overlaps, tools, auxiliary means, and, in general, all required
associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
ROOF0005 20060 Supply and application of roof insulation The unit price includes the material supply, installation,
with ytong multipor mm including all overlaps, tools, auxiliary means, and, in general, all required
associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
210 WINDOWS & DOORS & PARTITION
WALLS
DOOR0001 21010 Supply and installation of timber door The unit price includes the material supply, installation,
hollow core including all associated work, overlaps, tools, auxiliary means, and, in general, all required
as specified under the Technical materials and labor for the correct completion of all work.
Specification and applicable standards.
DOOR0002 21020 Supply and installation of timber door solid The unit price includes the material supply, installation,
including all associated work, as specified overlaps, tools, auxiliary means, and, in general, all required
under the Technical Specification and materials and labor for the correct completion of all work.
applicable standards.
Page 120

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
DOOR0003 21030 Supply and installation of internal hollow The unit price includes the material supply, installation,
metal door single leaf including all overlaps, tools, auxiliary means, and, in general, all required
associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
DOOR0004 21040 Supply and installation of internal hollow The unit price includes the material supply, installation,
metal door double leaf including all overlaps, tools, auxiliary means, and, in general, all required
associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
DOOR0005 21050 Supply and installation of roll-up shutter The unit price includes the material supply, installation,
motorised door including all associated overlaps, tools, auxiliary means, and, in general, all required
work, as specified under the Technical materials and labor for the correct completion of all work.
Specification and applicable standards.
DOOR0006 21060 Supply and installation of fire resistant 30 The unit price includes the material supply, installation,
minutes including all associated work, as overlaps, tools, auxiliary means, and, in general, all required
specified under the Technical Specification materials and labor for the correct completion of all work.
and applicable standards.
DOOR0007 21070 Supply and installation of fire resistant 60 The unit price includes the material supply, installation,
minutes including all associated work, as overlaps, tools, auxiliary means, and, in general, all required
specified under the Technical Specification materials and labor for the correct completion of all work.
and applicable standards.
DOOR0008 21080 Supply and installation of aluminium doors The unit price includes the material supply, installation,
with panel including all associated work, as overlaps, tools, auxiliary means, and, in general, all required
specified under the Technical Specification materials and labor for the correct completion of all work.
and applicable standards.
PARTITIONWALL0001 21090 Supply and installation of gypsum board The unit price includes the material supply, installation,
partition wall with panel including all overlaps, tools, auxiliary means, and, in general, all required
associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
Page 121

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
WINDOW0001 21100 Supply and installation of steel frame gas The unit price includes the material supply, installation,
tight window including all associated work, overlaps, tools, auxiliary means, and, in general, all required
as specified under the Technical materials and labor for the correct completion of all work.
Specification and applicable standards.
220 CLADDING
CLAD0001 22010 Supply and installation of panel aluminium The unit price includes the material supply, installation,
pre-finished (wall single skin panel) overlaps, tools, auxiliary means, and, in general, all required
including all associated work, as specified materials and labor for the correct completion of all work.
under the Technical Specification and
applicable standards.
CLAD0002 22020 Supply and installation of pre-formed panel The unit price includes the material supply, installation,
aluminium pre-finished (wall sandwich overlaps, tools, auxiliary means, and, in general, all required
panel)including all associated work, as materials and labor for the correct completion of all work.
specified under the Technical Specification
and applicable standards.
CLAD0003 22030 Supply and installation of Panel aluminium The unit price includes the material supply, installation,
pre-finished (roof single skin panel) overlaps, tools, auxiliary means, and, in general, all required
including all associated work, as specified materials and labor for the correct completion of all work.
under the Technical Specification and
applicable standards.
CLAD0004 22040 Supply and installation of Pre-formed panel The unit price includes the material supply, installation,
aluminium pre-finished (roof sandwich overlaps, tools, auxiliary means, and, in general, all required
panel) including all associated work, as materials and labor for the correct completion of all work.
specified under the Technical Specification
and applicable standards.
CLAD0005 22050 Supply and installation of Pre-formed panel The unit price includes the material supply, installation,
galvanized steel sheet prefinished ( wall overlaps, tools, auxiliary means, and, in general, all required
sandwich panel ) including all associated materials and labor for the correct completion of all work.
work, as specified under the Technical
Specification and applicable standards.
Page 122

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
CLAD0006 22060 Supply and installation of Panel galvanized The unit price includes the material supply, installation,
steel sheet prefinished ( roof single skin overlaps, tools, auxiliary means, and, in general, all required
panel ) including all associated work, as materials and labor for the correct completion of all work.
specified under the Technical Specification
and applicable standards.

CLAD0007 22070 Supply and installation of Pre-formed panel The unit price includes the material supply, installation,
galvanized steel sheet prefinished ( roof overlaps, tools, auxiliary means, and, in general, all required
sandwich panel ) including all associated materials and labor for the correct completion of all work.
work, as specified under the Technical
Specification and applicable standards.

CLAD0008 22080 Supply and installation of Suspended ceiling The unit price includes the material supply, installation,
mineral fiber Armstrong or similar including overlaps, tools, auxiliary means, and, in general, all required
all associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
CLAD0009 22090 Supply and installation of raised modular The unit price includes the material supply, installation,
floor 600x600mm fire resistant including all overlaps, tools, auxiliary means, and, in general, all required
associated work, as specified under the materials and labor for the correct completion of all work.
Technical Specification and applicable
standards.
CLAD0010 22100 Supply and installation of Thermally The unit price includes the material supply, installation,
Insulated Cladding panel with Polyester overlaps, tools, auxiliary means, and, in general, all required
powder coated finish including all materials and labor for the correct completion of all work.
associated work, as specified under the
Technical Specification and applicable
standards.
Page 123

Project DESIGN, BUILD, OPERATE AND MAINTAIN (DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TR
Client
Location
WBS / BoQ
Item Code Definition Description / Price Content
Code
CLAD0011 22110 Supply and installation of Thermally The unit price includes the material supply, installation,
Insulated Roof panel with Polyester powder overlaps, tools, auxiliary means, and, in general, all required
coated finish including all associated work, materials and labor for the correct completion of all work.
as specified under the Technical
Specification and applicable standards.
Page 124

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure

Volume of concrete in each


concrete element, as measured
on approved drawings. m³

Surface of asphalt roads , as


measured on approved
drawings. m²

Length of pipes/channels, as
measured on approved
drawings. m

Number of pits,manholes, as
measured on approved
drawings. ea

Surface will be measured as


defined on reference drawings.


Page 125

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
Volume for excavation shall be
measured in its natural state
as is stated on approved

reference plans and
topographic profiles.

The filling volume shall be


measured as stated on
approved reference drawings
and, when required, using
topographic profiles.

Surface will be measured as


defined on reference drawings.

The measurement of “in-situ”


piles shall be as specified on
approved m
Page 126

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The measurement of “in-situ”
piles shall be as specified on
approved m

The measurement of “in-situ”


piles shall be as specified on
approved m

The measurement of “in-situ”


piles shall be as specified on
approved m

The measurement of “in-situ”


piles shall be as specified on
approved ea

The measurement of “in-situ”


piles shall be as specified on ea
approved
The measurement of “in-situ”
piles shall be as specified on ea
approved
The measurement of “in-situ”
piles shall be as specified on
approved ea
Page 127

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
Excavated volume will be
measured in its natural state
considering the elevations as

shown on approved reference
plans and topographical
profiles.
Excavated volume will be
measured in its natural state
considering the elevations as

shown on approved reference
plans and topographical
profiles.
Excavated volume will be
measured in its natural state
considering the elevations as

shown on approved reference
plans and topographical
profiles.
Excavated volume will be Up to 150 : s=10 cm
measured in its natural state >=151 to 300 s=15 cm
considering the elevations as >=301 to 500 s=20 cm
shown on approved reference >=501 to 900 s=30 cm
plans and topographical >=901 to 1600 s=45
profiles. cm
m³ >=1601 to 2400 s=60
cm
>=2401 s=90 cm
s=Additional width
allowance for each side
of conduit
Page 128

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
Excavated volume will be Up to 150 : s=10 cm
measured in its natural state >=151 to 300 s=15 cm
considering the elevations as >=301 to 500 s=20 cm
shown on approved reference >=501 to 900 s=30 cm
plans and topographical >=901 to 1600 s=45
profiles. cm
m³ >=1601 to 2400 s=60
cm
>=2401 s=90 cm
s=Additional width
allowance for each side
of conduit
The filling volume shall be
measured as stated on
approved reference drawings
and, when required, using
topographic profiles.

The filling volume shall be


measured as stated on
approved reference drawings
and, when required, using
topographic profiles. m³
Page 129

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The filling volume shall be
measured as stated on
approved reference drawings
and, when required, using
topographic profiles.

The filling volume shall be


measured as stated on
approved reference drawings
and, when required, using
topographic profiles.

The filling volume shall be


measured as stated on
approved reference drawings

and, when required, using
topographic profiles.

The filling volume shall be


measured as stated on
approved reference drawings m³
and, when required, using
topographic profiles.
Page 130

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The filling volume shall be
measured as stated on
approved reference drawings m³
and, when required, using
topographic profiles.
The filling volume shall be
measured as stated on
approved reference drawings m³
and, when required, using
topographic profiles.

The unit shall be measured as


stated on approved drawings
and it shall be measured

assigning the same surface as
the foundation that is
supported.
The unit shall be measured as
stated on approved drawings
and it shall be measured

assigning the same surface as
the foundation that is
supported.
The unit shall be measured as
stated on approved drawings
and it shall be measured

assigning the same surface as
the foundation that is
supported.
Page 131

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings
and it shall be measured

assigning the same surface as
the foundation that is
supported.
The unit shall be measured as
stated on approved drawings
and it shall be measured

assigning the same surface as
the foundation that is
supported.
The unit shall be measured as
stated on approved drawings
and it shall be measured

assigning the same surface as
the foundation that is
supported.

The unit shall be measured as


stated on approved drawings,
measuring the formwork in
contact with concrete.

Page 132

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings,
measuring the formwork in
contact with concrete. m²

The unit shall be measured as


stated on approved drawings,
measuring the formwork in

contact with concrete.

The unit shall be measured as


stated on approved drawings,
measuring the formwork in

contact with concrete.

The unit shall be measured as


stated on approved drawings,

measuring the formwork in
contact with concrete.

The unit shall be measured as


stated on approved drawings.
Overlaps not indicated on
ton
drawings shall not be
measured
Page 133

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.
Overlaps not indicated on
ton
drawings shall not be
measured

The unit shall be measured as


stated on approved drawings.
Overlaps not indicated on
ton
drawings shall not be
measured

The unit shall be measured as


stated on approved drawings.
Overlaps not indicated on
ton
drawings shall not be
measured

The unit shall be measured as


stated on approved drawings.
Overlaps not indicated on
ton
drawings shall not be
measured

The unit shall be measured as


stated on approved drawings.

ton
Page 134

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.

ton

The unit shall be measured as


stated on approved drawings.

ton

The unit shall be measured as


stated on approved drawings.

ton

The unit shall be measured as


stated on approved drawings.


Page 135

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

ton

The unit shall be measured as


stated on approved drawings.
ton

The unit shall be measured as


stated on approved drawings.

Page 136

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.
m

The unit shall be measured as


stated on approved drawings.
m
Page 137

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as



stated on approved drawings.

The unit shall be the area of


the surface to be waterproofed

as specified on approved
drawings.

The unit shall be measured as


specified on approved
drawings, considering only the m²
concrete surface in horizontal
projection to be protected.
Page 138

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be the area of
the protected concrete as
specified on approved
drawings.

The unit shall be the area of


the protected concrete as
specified on approved
drawings.

The unit shall be the area of


the protected concrete as
specified on approved
m
drawings.
Page 139

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.


Page 140

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The filling volume shall be
measured as specified on
approved drawings.

The filling volume shall be


measured as specified on
approved drawings.

The unit shall be measured as


specified on approved
drawings. m²

The unit shall be measured as


specified on approved
drawings. m²
Page 141

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured
along the axis as specified on
approved drawings.

The unit shall be measured


along the axis as specified on
approved drawings. m

The unit shall be measured


along the axis as specified on
approved drawings.

The unit shall be measured


along the axis as specified on m
approved drawings.
Page 142

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 143

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 144

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 145

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 146

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 147

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 148

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 149

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 150

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 151

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 152

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 153

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 154

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 155

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 156

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 157

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 158

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured as


the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.
Page 159

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
the length of piping correctly
installed, theoretical
measurement in approved
drawings considering the axes m
of the pipe.

The unit shall be measured


with the trench length
indicated on drawings m
measured along the trench
axis.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

Page 160

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

Page 161

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

Page 162

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

Page 163

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

Page 164

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

Page 165

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

The unit shall be measured as


stated on approved drawings.

Page 166

(DBOM) CONTRACT FOR INTEGRATED INDUSTRIAL WASTEWATER TREATMENT WORKS (IIWWTW) PHASE I (CP798)
ASHGHAL PWA
Doha,Qatar
Unit of
Measurement Sketch NOTES
measure
The unit shall be measured as
stated on approved drawings.