~ Different Report ~

Duration
Old Original
Activity ID Activity Name New Original Duration
Duration
SYDE5100 Switchyard Earthing Calculation, Layout & Detail Submission & Approval 16 60
SYDE5110 132kV Control Building Earthing Layout Submission & Approval 16 60

SYDE5120 GIS Earthing Layout Submission & Approval 16 60


SYDE6060 33kV Control Building Earthing Layout & Details Submission & Approval 16 50

Dates
Activity ID Activity Name New Start Date Old Start Date
*Finish dates remain the same (02 May 2019)
SYDE5100 Switchyard Earthing Calculation, Layout & Detail Submission & Approval 9/Apr/19 4/Feb/19

SYDE5110 132kV Control Building Earthing Layout Submission & Approval 9/Apr/19 4/Feb/19

SYDE5120 GIS Earthing Layout Submission & Approval 9/Apr/19 4/Feb/19

SYDE6060 33kV Control Building Earthing Layout & Details Submission & Approval 9/Apr/19 4/Feb/19
~ Different Report ~

Activity Relationships Added/Deleted


The following Predecessor Activity Relationships have been added to the project
Predecessor
Activity ID Activity Name Relationship Lag Relationship Type Predecessor Activity Name
Activity Id

Switchyard Earthing Calculation, Layout & Detail Submission & Switchyard Lightning Protection Calculation, Layout & Sections
SYDE5100 128 Finish to Start SYDE5130
Approval Submission & Approval

33kV Control Building Earthing Layout & Details Submission &


SYDE6060 72 Finish to Start SYDE6030 33kV Control Building Support Layout Submission & Approval
Approval

Switchyard Lightning Protection Calculation, Layout & Sections Switchyard Earthing Calculation, Layout & Detail Submission &
SYDE5130 128 Finish to Start SYDE5100
Submission & Approval Approval

33kV Control Building Earthing Layout & Details Submission &


SYDE6030 33kV Control Building Support Layout Submission & Approval 72 Finish to Start SYDE6060
Approval

The following Predecessor Activity Relationships been deleted from the project
Predecessor
Activity ID Activity Name Relationship Lag Relationship Type Predecessor Activity Name
Activity Id

Switchyard Earthing Calculation, Layout & Detail Submission & Switchyard Lightning Protection Calculation, Layout & Sections
SYDE5100 96 Start to Start SYDE5130
Approval Submission & Approval

33kV Control Building Earthing Layout & Details Submission &


SYDE6060 280 Start to Start SYDE6030 33kV Control Building Support Layout Submission & Approval
Approval

Switchyard Lightning Protection Calculation, Layout & Sections Switchyard Earthing Calculation, Layout & Detail Submission &
SYDE5130 96 Start to Start SYDE5100
Submission & Approval Approval

33kV Control Building Earthing Layout & Details Submission &


SYDE6030 33kV Control Building Support Layout Submission & Approval 280 Start to Start SYDE6060
Approval