Cottonwood

 Dr  Jordan  Rd


Interim  Traffic  Signal
Cost  Estimate

Unit Qty Unit  Cost Total


TRAFFIC  SIGNAL  MAST  ARM  (50') EA 1 19000 19000
TRAFFIC  SIGNAL  MAST  ARM  (65') EA 1 22000 22000
TRAFFIC  SIGNAL  MAST  ARM  (70') EA 1 25000 25000
TRAFFIC  SIGNAL  FACE  (5  SECTION  DOGHOUSE  WITH  BACKPLATE) EA 3 1200 3600
TRAFFIC  SIGNAL  FACE  (5  SECTION  VERTICAL  WITH  BACKPLATE) EA 4 1000 4000
TRAFFIC  SIGNAL  FACE  (3  SECTION  WITH  BACKPLATE) EA 6 800 4800
TRAFFIC  SIGNAL  FACE  (3  SECTIONS) EA 4 700 2800
PEDESTRIAN  SIGNAL EA 2 575 1150
PEDESTRIAN  PUSHBUTTON  (W/SIGNS) EA 2 700 1400
PULLBOX  (17X30X18) EA 3 700 2100
QUADRAPOLE  LOOPS  (6X40) EA 6 3000 18000
WATERVALVE  PULLBOX EA 4 400 1600
2"  CONDUIT LF 180 12 2160
3"  CONDUIT LF 1260 15 18900
LUMINAIRES  (LED) EA 3 1500 4500
RESET  GTT  DETECTOR EA 1 800 800
GTT  DETECTOR  (722)(FURNISH  &  INSTALL) EA 1 4500 4500
LANE  CONTROL  SIGNS EA 5 75 375
INTERNALLY  ILLUMINATED  STREET  NAME  SIGN EA 3 2500 7500
FIBER  OPTIC  TERMINATION  (12  STRAND)(W/TERMINATIONS  AND  PATCH  PANEL) LS 1 2500 2500
222  LOOP  DETECTOR  AMPLIFIERS EA 3 250 750
WIRING LS 1 10000 10000
TRAFFIC  CONTROL LS 1 10000 10000
REMOVE  EXISTING  TRAFFIC  SIGNAL LS 1 3000 3000
REMOVE  SIGNAL  POLE  FOUNDATIONS EA 2 200 400
REMOVE  PEDESTAL  POLE  FOUNDATION EA 1 100 100
15%  CONTINGENCY 25640
PROJECT  TOTAL $196,575

LANTZ  ASSOCIATES
June  2014