Company: RAK JV
No. Process/Location Testing and Commissioning of Chilled Water Pumps
General Workplace Hazards
Designation: HSE Supervisor Designation: Construction Manager Designation: HSE Manager Designation: Project Manager
likely hood
likely hood
Risk Level
Risk Level
Severity
Severity
Accident / Action Officer
No Work Activity Hazard Health & Existing Risk Control (if Any) Additional Risk Control (Designation)
Persons at (Follow-up date)
Risk
T & C engineer will request to main HSE Officer to verify / ensure PTW is in place
contractor for PTW before one day. for the T&C activity prior to start.
Improper & RAK will follow the approved LOTO Proper LOTO shall be secured to avoid any
Incomplete procedure (M007-RAKHMS-PRO-00001) unauthorized operation
PTW T & C Engineer,
Document Proper signage will be provided regarding All the contractors and working team will be
1 Incomplete Operatives 3 3 9 3 1 3 Supervisor,
arrangements the testing and commissioning procedures informed and coordinate properly about ongoing
LOTO
and authorized personal only. testing and their hazards.
procedure
requirements PPEs will be given to all operatives Third party certification of LOTO in-charge
relevant to their job. engineer.
Start briefing prior to start the activity.
PPEs will be given to all operatives
relevant to their job. Housekeeping of area prior to start and while
Access ways shall be ensuring by leaving the work area. T & C Engineer,
2 Site Arrangement Slip and trip Operatives competent person that all access and 3 2 6 Designated team will be assigned for 3 1 3 Supervisor,
egress points are free from obstructions. housekeeping.
Material will be stacked properly at
designated place.
RAK approved Heat stress plan (M007-
Fatigue Glucose juice shall be given.
Heat stress RAK-HMS-PLN-00002) will be followed.
Close supervision
To involved Proper monitoring of temperature
T & C Engineer,
Heat stroke 12 Proper communication arrangements Supervisor,
3 Working in Summer personnel 4 3 4 1 4
Dehydration Breaks and rotations will be given to all
Training will be given to all workers on heat
involved workers
stress.
Easy access to cool water
Electrocution. Personal System under test has been correctly Only trained personnel shall conduct test.
Poor Lighting Injury installed and inspected. In House Training will be given to the workers.
Spillage of Finger Injury Ensure approved work permit is available Proper hand protection gloves shall be worn.
Testing and Water Hand Injury Electrical Engineer / Supervisor shall be T & C Engineer,
prior to beginning of any testing
4 Commissioning of 5 3 15 available on task 5 1 5 Supervisor,
48 Hrs. notice to CCC prior to the testing
Chilled Water Pumps LOTO procedure (M007-RAK-HMS-PRO-
and approval shall be obtained /
coordinated. 00001)shall be followed.
Calibrated equipment will be used Acquired permit to work from the contractor.
likely hood
likely hood
Risk Level
Risk Level
Severity
Severity
Accident / Action Officer
No Work Activity Hazard Health & Existing Risk Control (if Any) Additional Risk Control (Designation)
Persons at (Follow-up date)
Risk
Tools & equipment TPC to be available at In case of an emergency, Emergency Rescue
site. plan of main contractor will be followed.
Area shall be barricaded (Physical barrier) Fire Extinguisher shall be placed nearby at the
and Signs placed for unauthorized entry. area of the task activity.
Ensure availability of water spill kit Proper supervision of the testing activities shall
during testing of CHW Pumps. be implemented.
PPEs will be provided as per their job.
Main contractors approved heat stress
Task lights will be provided for illumination.
plan will be followed.
Proper Communication system shall be
Sufficient lighting will be provided by
provided.
main contractor.
Injuries such Muscle pain Task Briefing conducted to workers on Only competent personnel will be allowed
as Back Eye strain, ergonomics and manual handling safety Main contractors PTW will be followed
Strain, headache, Training related to manual handling RAK approved HSE plan will be followed T & C Engineer,
4 Manual Handling Bruised or fatigue Close supervision by site supervisor 3 3 9 Ensure housekeeping of all areas. 3 1 3 Supervisor,
broken toes or Stress Manual Handling Risks briefed to
feet. Minor injuries workforce by the task in charge before
Sharp edges commencement of work.
It may cause Hand injuries All equipment will be inspected prior to Task Briefing conducted to workers on
injuries such Property use. ergonomics and use of hand tools safely
T & C Engineer,
as Back damage Use of Personal Protective Equipment at Colour code will be followed of main contractor.
5 Hand Tools 3 2 6 3 1 3 Supervisor,
Strain, all times (hard hats, safety glasses, gloves, Training related to hand tools.
Defective Ear Protection, etc.)
hand tools
Fire Injury and Main contractor rescue plan will be Designated rescue team
First aid property followed. ER team posters will be displayed at site.
Dizziness damage Provision of sufficient and suitable fire Refresher trainings of ER team after 03
months T & C Engineer,
Emergency Heat stroke extinguishers at site
6 4 3 12 Good coordination and communication with 4 1 4 Supervisor,
arrangements Provision of first aid box, Stretcher,
eyewash at site CCC male nurse.
Designated fire wardens team
Designated first aider teams