Page 1/3
DESCRIPTION
Project: Festival Plaza (Dubai II Big Box
Client: AFGRE
Retail)
Job No: 4615 Date: 18th Feb 2019
Venue: BBR Site Office Time: 10:00 AM
VALUE
ID KPI'S NOTES
Previous 1-week Current week
Quality Compliance
1 NCRs raised (Consultant) To Date 12 6
2 NCRs closed (Consultant) To Date 5 5
VALUE NOTES
ID KPI’S
Previous 1-week Current week
3 SORs Raised to Date 4 2
4 SORs Closed to Date 3 2
5 Inspections of Work Passed (approved) 93
6 Inspections of Work Failed (rejected) 77
7 Number of Internal Toolbox Talks - -
8 Number of 3rd party Toolbox talks - -
Page 2/5
Date 18/02/2019
Festival Plaza (Dubai II Big Box Retail)
QA/QC Weekly Meeting Minutes No. 08
NCR: BSBG noted and tabled the pending NCRs which are open either due to no proposed
corrective action given or the corrective actions have been agreed with BSBG but the
implementation at site is still incomplete. Refer to NCR register.
SOR: BSBG noted that a total of 21 Nos. of SOR are open since September 2018 up until December
2018. Most of the SORs were responded by AFC with corrective action and were returned by BSBG
with noted acceptance. From thereafter, no further responses were made on records. Refer to
attached SOR register. BSBG noted that the escalation from SOR to NCR is mandatory, due to failure
to respond and close the related SORs as agreed in the last meeting.
Page 3/5
Date 18/02/2019
Festival Plaza (Dubai II Big Box Retail)
QA/QC Weekly Meeting Minutes No. 08
BSBG noted that below issues which are again prevalent during the site walk.
12. Secondary steel member for MEP supports commenced without approved shop
drawing, MIR for steel members, Calculations etc.
13. Reinforcement steel stacking in Zone 5
Parallel to above item 2.1, BSBG noticed that target dates tabled below by AFC are getting revised
and extended on similar account in respect of the first meeting. The target dates proposed were
missed subsequently hence are revised and extended by AFC whose new target dates are given
below heretofore. BSBG remarked that delay of rectification and response is unacceptable and
must be sorted out immediately pursuant to the contractual obligations.
The site walk was intended to assist and provide the site team proactive measures to avert
any recurrent issues thus diminishing the issuance of further NCRs and SORs of persistent
nature but will not be effective unless otherwise their involvement is fully materialized. AFC
have noted that internal instructions were given, and all PM’s are now required to attend
the site walks from next week onwards.
8.0 AOB
Intention is that future meetings shall discuss site wide quality matters and critical NCR.
Page 5/5
Date 18/02/2019
Festival Plaza (Dubai II Big Box Retail)
QA/QC Weekly Meeting Minutes No. 08
Note: These MOM is a formal record of the meeting. Any dissent must be confirmed within 24 hours from
the date and time of issue.
To: The Project Manager, Contractor: AFC Report: 04 DATE OF INSPECTION: 17 February 2019
Inspection Team: Please refer the attached list for all attendees
Note: The Quality Joint walk has been conducted on project in the presence of involved
Inspection Area: As indicated
stakeholders mentioned in attendees’ list
Name Company
With reference to our today’s site Quality joint inspection, we observed the following deficiencies mentioned below, we require contractor Julius
BSBG
to comply with relevant project specification, Hence the construction director is required to take immediate action and submit the closeout Khuram
AFGRE-HSE-02 Rev 0
CJ detail and restraint post rebar
2 Zone 3 and
For external wall not as per IF SOR
4-, GF
drawings
Zone 4-
3 Concrete honeycombs SOR
GF
AFGRE-HSE-02 Rev 0
Incomplete soffit insulation prior Zone 3 –
4 ONR
painting B
ONR
AFGRE-HSE-02 Rev 0
Improper plaster termination for
6 Zone 1 - GF ONR
MEP wall penetrations
AFGRE-HSE-02 Rev 0
MEP conduits wall cut outs
without meshwork for different Zone 1 –
8 SOR
substrate during plaster GF
preparation
AFGRE-HSE-02 Rev 0
10 No lateral restraint for blockwork Zone 4 - GF NCR
AFGRE-HSE-02 Rev 0
Missed out steel columns,
Zone 1 –
12 restraint ties provision on the
ONR
block work not found GF
AFGRE-HSE-02 Rev 0
Lateral ties not provided and half-
14 lap stretcher not achieved on Zone 3 - GF SOR
blockwork
AFGRE-HSE-02 Rev 0
Missing bolts for steel
Zone 1 –
16 connections
ONR
Level 2
AFGRE-HSE-02 Rev 0
Secondary Steel for MEP
supports installation without
Zone 1 –
18 relevant MIR and WIR approval.
NCR
Level 1
AFGRE-HSE-02 Rev 0
Manual Mixing without measuring
20 tools for correct constituent Zone 4 - GF SOR
proportion for blockwork mortar
AFGRE-HSE-02 Rev 0