1
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Contents
EC-Declaration of conformity............................................................................................. 3
Delivery and Installation Requirements ............................................................................. 4
Fixing specifications& power values.................................................................................. 6
The most important designations according to the new concrete standard B 4710-1 ....... 7
Concrete strength classes ................................................................................................. 7
Conventional applications ................................................................................................. 8
Safety devices ................................................................................................................... 8
Supplementary help with the electronic controls ............................................................... 9
Practical use of the post-lifts............................................................................................ 11
Testing of lifts .................................................................................................................. 12
Disposal of the post lift .................................................................................................... 12
Technical details.............................................................................................................. 13
Dimension 2-Post-Lift ...................................................................................................... 14
Product description.......................................................................................................... 15
Foundation....................................................................................................................... 16
Floor fixing for lifts til 4 to................................................................................................. 17
Foundation work for lifts til 4 to........................................................................................ 18
Installation and initial operation....................................................................................... 19
Safety lock device (load nut failure) ................................................................................ 20
Load bearing nut testing ............................................................................................... 20
Description of the main board SGMX9 ............................................................................ 23
Preparation for the initial installation ......................................................................... 23
Notice of initialisation for EL lifts .................................................................................. 24
Faults and causes ........................................................................................................... 31
Emergency lowering ........................................................................................................ 33
Maintenance and service................................................................................................. 34
Maintenance Schedule .................................................................................................... 34
Lubrication system........................................................................................................... 35
Mechanical syncronisation device 409524 ...................................................................... 36
Ribbed drive belt.............................................................................................................. 37
Spindle guide................................................................................................................... 37
Pick up supports with attachable sleeve.......................................................................... 37
Manual arm lock override ................................................................................................ 38
Lifting plate with pin bushing ........................................................................................... 39
Control unit with push button ........................................................................................... 40
Electric diagram with push-button.................................................................................... 41
Electric diagram with push-buttons.................................................................................. 43
Sparepartdrawing ............................................................................................................ 44
Spare parts list H327 / H355 ........................................................................................... 48
Certificate ........................................................................................................................ 49
2
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
EC-Declaration of conformity
In the sense of the EC guidelines
We hereby declare that, on the basis of its design and constructions, as well as in the version brought
on to the market by us, the lifts armed with a cross conform to the relevant fundamental safety and health
requirements of the EC guidelines.
In the event of any alteration to the machine not agreed with us, the present declaration shall lose its
validity.
Relevant EC-guidelines:
EC-machine guideline (98/37/EG dated 22.07.98)
Electro-magnetic compatibility (89/336/EWG) in the version 91/263/EWG
in the version 92/31/EWG
TÜV CERTIFICATE-certification body of RWTÜV Anlagentechnik
notified to the EC-Commission under no.: 0044
applied harmonised standard: EN 60204 part 1
applied national standard and technical specification:
BGG 945
EN 1493
As the working means cannot be delivered ready for operation, the working means must be checked for
readiness for operation by an expert prior to initial commissioning. The company-trained fitters of the
CONSUL partners are experts.
__________________________________ _____________Betriebsleiter___________
*Date/signature of manufacturer Details of signature
Date: see delivery note
3
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
1. Delivery by haulier invoiced with normal freight charge: A forklift truck must be made available
at short notice. Weight of the lifts approx. 650 – 2700 kg, depending on lift type.
2. Delivery by truck with off - loading equipment invoiced with increase freight charge:
Unloading assistance must be provided at short notice. Weight of the lifts approx. 650 – 1000 kg,
depending on lift type
The surface of the floor must be flat and horizontal for all lifts. The foundation must conform to
the general guidelines for foundations (DIN 1054). For lifts installed outside, the foundation
must be frost-proof. When setting up on suspended floors, the floor must be certified by a
structural engineer. Lifts can be anchored with anchor bolts, chemical bolts or through bolts,
minimum strength 8.8 and washers – see also BGG 945 -.
6. Average time for installation (providing the conditions above are met):
4-Post-Lifts:
- without secondary lift approx. 7 hours working time
- with secondary lift approx. 9 hours working time
Short lifts approx. 2 hours working time
Scissor lifts approx. 9 hours working time
4
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
If the lift is set up by the operator himself, the attached assembly and operating instructions must
be observed. Subsequently the lift must be subjected to safety acceptance by a Consul customer
service section. This includes the following performances:
ۥElectrical functional check and trial run.
€‚according to BGG 945
€ƒexamination of the individual structural components.
€„Entry in the check list according to BGG 945-1.
€…Short instruction.
-If these points are not observed, the guarantee expires.-
In addition to the check prior to the initial commissioning of the lift by our customer service
section, the official regulations demand at least one safety inspection per year experts. Our
customer service section will be pleased to submit you a quotation for a maintenance contract.
9. Guarantee
On the basis of the fact that lifts must satisfy height safety requirements for the protection of the
persons working on them, we draw your attention to the fact that we must tie the guarantee
entitlement of the operator to the correctly performed safety acceptance and entry of this in the
check list. Always uses original spare parts. The use of any other parts invalidates the design
permit and all claims under warranty.
5
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
direction of travel
Important:
Quality of concrete
Min. thickness
see manufacturer
floor covering
Anchoring depth
Anchroing depth
all securtites
manufacturer
„slowly-acting”
unbreakable
dowels see
direction
of travel
without
Width in
B 4710-1
concrete
Length
in
Consul 1.25 H321 Shear connector 120 Nm 150 200 cm 15 cm C 20/25 12,5 400 V/ 50 Hz/
Hilti HVA/HAS M16x125 (6 Pcs.) cm cm 3x16 A
Consul 1.06 RM H345 shear connector 40 Nm 150 200 cm 15 cm C 20/25 12,5 400 V/ 50 Hz/
Hilti HVA/HAS-M12x110 (6 Pcs.) cm cm 3x16 A
Consul 2.30 Modula H264 Shear connector 80 Nm 120 100 cm 21 cm C 20/25 12,5 400 V/ 50 Hz/
Hilti HVA/HAS M16x125 (10 Pcs.) cm cm 3x16 A
Consul 2.30 Modula EL H300 shear connector 40 Nm 120 100 cm 21 cm C 20/25 11 cm 400 V/ 50 Hz/
Consul 2.35 Supra EL H339 Hilti HVA/HAS-M12x110 (12 Pcs.) cm 3x20 A
H400
Consul 2.35 Modula H265 see H264 80 Nm 120 100 cm 21 cm C 20/25 12,5 400 V/ 50 Hz/
cm cm 3x16 A
Consul 2.35 Modula EL H301 see H300 40 Nm 120 100 cm 21 cm C 20/25 11 cm 400 V/ 50 Hz/
cm 3x20 A
Consul 2.40 Modula EL H327 shear connector 80 Nm 120 100 cm 21 cm C 20/25 12,5 400 V/ 50 Hz/
H355 Hilti HVA/HAS-M16x125 (12 Pcs.) cm cm 3x20 A
Consul 2.60 2M H342 Shear connector 80 Nm 150 350 cm 15 cm C 20/25 10,5 400 V/ 50 Hz/
Multi XXL Hilti HVA/HAS-M12x110 (4 Pcs.) cm cm 3x20 A
Consul 2.60 EL H331 Shear connector 80 Nm 150 150 cm 21 cm C 20/25 12,5 400 V/ 50 Hz/
Multi XXL Hilti HVA/HAS-M16x125 (12 Pcs.) cm cm 3x25 A
Consul 3003 GA H325 as H342
Consul 2.40 Modula EL H327 shear connector 80 Nm 120 100 cm 21 cm C 20/25 12,5 400 V/ 50 Hz/
H355 Hilti HVA/HAS-M16x125 (12 Pcs.) cm cm 3x20 A
Consul 2.30 Modula H362 shear connector 80 Nm 120 100 cm 21 cm C 20/25 12,5 400 V/ 50 Hz/
Hilti HVA/HAS-M16x125 (10 Pcs.) cm cm 3x16 A
Consul 4.40 EK H305 shear connector 80 Nm 100 100 cm 18 cm C 20/25 12,5 400 V/ 50 Hz/
Consul 4.40 K-SN H371 Hilti HVA/HAS-M16x125 (16 Pcs.) cm cm 3x16 A
Consul 4.40 L H338
Consul 4.40 L-SN H372
Consul 4.40 BL H373
Consul 4.40 SN H 374
Consul 4.40 SN-AM H375
Consul 4.40 SN-AM H384
Consul 4.40 SN-DC Z073
Consul 4.40 DC Z 106
Consul 4.60 H349 shear connector 80 Nm 100 100 cm 18 cm C 20/25 12,5 400 V/ 50 Hz/
Consul 4.70 H350 Hilti HVA/HAS-M16x125 (16 Pcs.) cm cm 3x16 A
Consul 4.120 H151 shear connector 80 Nm 150 150 cm 18 cm C 20/25 12,5 400 V/ 50 Hz/
Hilti HVA/HAS-M16x125 (16 Pcs.) cm cm 3x16 A
Consul 0.25 KV H333 see H240 40 Nm 150 200 cm 15 cm C 20/25 11 cm 400 V/ 50 Hz/
Consul 0.25 KM H348 (8 Pcs.) cm 3x16 A
Consul 0.05 MH H257 see H240 (6 Pcs.) 40 Nm 150 100 cm 15 cm C 20/25 11 cm 400 V/ 50 Hz/
cm 3x16 A
Consul 0.35 H262 Shear connector 40 Nm 400 200 cm 18 cm C 20/25 11 cm 400 V/ 50 Hz/
Consul 0.35 S-AT H352 Hilti HVA/HAS-M12x110 (20 Pcs.) cm 3x16 A
Consul 0.35 SN H240
Consul 0.35 SN-AT H326
Consul 0.35 SN/AM H316
Consul 0.30 SDE H311 Shear connector 40 Nm 250 150 21 cm C 20/25 11 cm 400 V/ 50 Hz/
Consul 0.32 SDE H390 Hilti HVA/HAS-M12x110 (8 Pcs.) cm 3x16 A
The setting up of the lifts is only admissible and will only be carried out if the minimum requirement on the fundaments indicated are fulfilled at the place of setting up.
The bolt manufacturers’ instructions must be followed!
Subject to change without prior notice! Date: 19.03.2007
6
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
XC1
XC2 corrsosion released by carbonation
XC3
XC4
XC2 interiors with high air humidity, laundries, cattle sheds, indoor swimming pools, not
oppressive groundwater, water pressure height under 2 m
C3 water pressure height 2 to 10 m; seal concrete buildings (in former times: WU)
XF1 Rain and frost demand for curved (> 5 %) and vertical surfaces, all under-faces
with
frost
XF2 concrete with frost and rope means (salt) for curved ( < 5%) and horizontal
surfaces
XF3 rain and frost demand for horizontal surfaces; hydraulic engineerings
F4 concrete with frost and rope means (salt) for horizontal surfaces (in former times:
FTB)
7
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Conventional applications
Your Consul lift has been design-tested in its basic concept, it offers you maximum economic efficiency and
safety. It is up to you to make use of these advantages.
A prerequisite for this is correct operation, perfect maintenance and good care of the lift. Please read these
operating instructions carefully. They provide you with all necessary data and show how simple it is to keep
your lift ready for use at all times.
Your Consul lift is only designed to raise automobiles or vehicles whose total weight does not exceed the
lifts’s maximum permitted load capacity and whose specified support points are within the lift’s support area.
Safety devices
Your lift is equiped with several safety devices, to ensure workers safety, if the lift is used according to this
manual.
Please take care of this safety devices, when installing the lift and check them after any case of failure.
Only original parts are to be used for repair. If third parts equipment is used for repair, the CE certificate of
conformity will be avoided.
In accordance with the regulations regarding the operation of lifts, lift devices must be checked for their
operational safety by an expert at the latest after one year (LOLER).
In this respect please pay attention to ensuring that only company-trained experts, who have been instructed
in the function of lifts and who are in possession of a certificate from the manufacturing company, check
and accept your lift.
8
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
The operation of the controls using the PC communications software is only intended for service,
maintenance and repairs. Using this operation mode, safe working is not guaranteed. Operating in this
mode does not comply with the necessary demands of safe working practice! They are appropriate
precautions to be adhered to.
When altering the parameters using the PC communication software, it should be checked, by reselecting
and verifying the read data, whether the read data corresponds to the desired data.
The lift can then be put into operation and you should check whether the required limits are being adhered
to (test run).
You cannot infer the exact physical heights from the measured height values of the software. The readings
and the physical heights do not correspond when the lift is precisely levelled and the correct parameters for
the lift uploaded.
Beware:
All limits (upper and lower) and height differences are stored in N units (digital). The conversion into
physical units depends on the mechanical construction. The physical height is not defined by the controls as
it depends on the mechanical attachment of the potentiometer to the post. This offset is determined by the
system and must be allowed for when inputting the limits and parameters.
The controls simply assume that a reading of less than 3% from the end limit or more than 97% from the
end limit on the potentiometer indicates a sensor and they accept into the system all values greater than 3%
from the end and less than 97% from the end. As a routine maintenance measure (after one year at the
most) the operation of the D-channel must be checked.
For this the diagnostic function must be started. If the D-channel is defective then the controls must be
disabled or the control circuit board must be changed!
Beware:
When the D-channel is defective, the lift may appear to be working normally but its safe operation can no
longer be guaranteed!
9
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Attention!
Important instructions for assembling the 2-Post-Lift!
1. The assembly should be carried out by qualified staff in accordance with the construction and operating
instructions (otherwise the guarantee will be invalidated).
2. Check that all parts have been delivered before commencing assembly.
3. Final installation checks must be carried out according to VDE instruction 0100.
6. Ensure that the spindle hangs vertically. To do this lift a vehicle a short distance, loosen them re tighten
the hex- head screws at the top of the columns.
7. Check the locking mechanism of the swing arm, then ensure that the bolt is vertical and parallel to the
front of the column.
8. Only ever fill the lubrication system with original Consul Spindle Oil.
9. The lift is preprogrammed in the factory and must be adjusted to local conditions. Check that the foot
protection facility is at the correct height (compulsory stop and signal tone).
11. Check the gap between the steering frame and the tension band (correst and grease the back of the
tension band when necessary).
12. The self-securing swing arm screws only reach complete tightness after 24 hours (check for a gap of 1
to 2 mm between the screw head and the swing arm bearing)
14. Only lift using all 4 swinging arms and only at the lifting points permitted by the manufacturer.
www.consul-gmbh.de
10
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
According to the regulations for prevention of accidents, persons under the age of 18 are not permitted to
operate the lift without supervision.
The lift is designed only as a vehicle lift, it should not be used for other purposes.
See instruction on the lift column.
If there are any faults with the lift, turn off electricity, make safe, secure against unauthorised use and
contact the Consul Service Section.
Before lifting or lowering a vehicle check that nobody is in danger, that nothing is leaning against the vehicle
and no obstacles are underneath it.
Attention:
With some vehicles, higher lifting apparatus is necessary. As an necessary, a set (4) spacing bushes is
available. This ensures safe lifting of the vehicle.
When using a drive-on chassis, the chassis must be fully lowered before driving on to the lift.
The total vehicle weight must not exceed the authorised capacity and load dispatching.
In order to guarantee a safe lift of the vehicle it may only be lifted at all 4 lifting points as laid down
by the manufacturer. Check the safety of the lifting after having set up a little the vehicle.
Only original accessories may be used as load supporting devices (type tested parts), wooden blocks or
other devices for load lifting are not permitted. It is advidable that the vehicle should be driven on so that
the centre of gravity is between the lift columns (especially with the asymmetric swing arms).
Pay attention to the centre of gravity when working with heavy parts as it can cause the vehicle being raised
to fall. Only use the lift as intended: for lifting vehicles. Other, apparently practical uses are not among ist
intended purposes.
It is forbidden to use the lifts to raise heavy vehicle parts, eg, engines. The swing arms are fitted with
blocking devices which work automatically. These stop the swing arms moving after a short lifting distance
and release them again when lowered through 15 mm.
If the arms have to be swung to a greater height, eg, in order to place a vehicle on a bench, then a hand bolt
can be installed.
11
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Testing of lifts
The testing of lifts is to be carried out in accordance with the Trade Work Practice Agreements BGG945 and
the norms and regulations there in!
The quoted paragraphs are extracts: otherwise BGG945 is binding. The required tests are carried out by
Consul Construction Services according to the regulations. Please ask Consul Partners for thier reasonably
priced maintenance contracts.
The scrapping of the lift must be documented according to the country, in which this was installed.
Attention!
When loading/unloading, moving, installing, assembling or dimishing the lift all precautionary measures are
specified by rules for the prevention of accidents (safety helmets, gloves, shoes) are to be obeyed. These
rules are in accordance with the laws of the appropriate country.
12
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Technical details
Type: H327
Remark: with symmetric
swing arms
Width (mm): 3.300
Height (mm)ca.: 2555
Max. vehicle 2.390
width (mm):
Stroke 1.920
(mm):
Lifting height 2005
(mm):
Min. arm 85
clearance (mm):
Lifting time 45
(sec):
Net weight (kg): 550
13
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Dimension 2-Post-Lift
Consul 2.40 EL Multi XL (H327 / H355)
Accessory:
See catalogue!
Subject to change without prior notice!
14
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Product description
The lift basically consists of the main column and a slave column. In both columns are to be found the lifting
spindles and the lifting carriages with load bearing apparatus.
The motor turns the lifting spindle. On the spindles are nuts which are attached to the lifting carriage which,
according to the turning direction of the drive, moves up or down and thus performs the raising and lowering
operation. The lifting carriage is borne on maintenance free roller bearings within the column.
In each column is a motor driven belt which turns the spindles. The even running of the lifting carriages is
ensured via an electronic synchronizing governor. Any lack of synchronization in the lifting carriages (eg,
because of an uneven load, lack of lubrication, etc) is regulated by the synchronization control to within a
distance of approximately 10 cm. The advancing lifting carriage is briefly stopped until the slower carriage
reaches the same height. This check may be observed several times in the course of the lift.
The lift is operated by activating the control switch in the desired direction of travel. It is stopped by
releasing the switch or when the lift reaches one of the electronically programmed top and bottom limits. For
safety reasons, the downward movement can be programmed to automatically stop at a height of 200 mm
(between the floor and the underside of the lifting apparatus). The lift must be manually re-started and
descends to the bottom limit accompanied by an audible warning tone.
The control switch reverts automatically to the stop position when released and the movement of the lift is
stopped. In addition, the lift is equipped with a variety of both passive and active safety devices. For
example; the safety device for broken load nuts which transfers the load to a reserve safety nut in the event
of a worn main nut. At the same time, a mechanical locking system is engaged which only allows the lift to
be lowered until the safety devices are repaired. This prevents unsafe operation of the lift.
The arm lock of the 6 to lift stops the load arms moving after travelling upwards approx. 15 mm from the
lowered position. This is to prevent the lift pads slipping from the jacking points of the vehicle. Be aware of
the correct alignment of the toothed quadrant!
The swing arm lock of the 3-4 to lift stops the load arms moving after travelling upward a short distance
from the lowered position. This is to prevent the lifting apparatus slipping from the jacking points on the
vehicle being raised. Operating safety is paramount!
The heat sensors in the drive motors stop the lift in the event of overheating and only allow the lift to restart
after a cooling down period.
The Post-Lift can only be driven with symmetrical bearing arms.A maximum capacity of only 4.000 kg and
a maximum weight distribution of only 3:2 is allowed.
The swing arms are all the same length on the symmetrical 2-Post-Lift and the vehicle to be lifted is to be
place in the drive-on direction in the middle of the lifts.
With the asymmetrical design, the bearing arms of different lengths. The shorter arms are normally located
at the front of the vehicle. The vehicle to be lifted is positioned so that the front door hinges are close to the
lift columns allowing the doors to open. It is desirable that the vehicle’s engine is towards the short swing
arm (the centre of gravity of the vehicle as close as possible to the centre of the lift)! All 4 lifting pads are
positioned at the jacking points specified by the vehicle manufacturer!
15
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Foundation
The Consul Post-Lifts of the EL version is that of a „basefree“lift, therefore the floor fixing is critically
important. The entire loads (dead weight of lift and moving weight of vehicle) are transferred to the floor
through the anchor bolts.
Before installing the lift, it is necessary to ensure that the floor is adequate (see supplement anchoring for
lifts and BGG 945).
When installing the lift on a suspended floor, the floor’s suitability must be verified by a structural engineer,
or other competent person.
Only after checking the floor, can a decision be made about the appropriate fixing system.
The penetration depths of the anchors (anchors are not supplied) have to be followed (see instructions of
the anchor manufacturers). Otherwise the safety of the lift may be compromised.
The correct length (L) of the active part of the anchor bolt is obtained by adding the measurements „h“ +
thickness of the floorcover and height of the files and the height of the installation base. Drill size and the
thightening torque are in accordance to the bolt manufacturers instructions.
To achieve a perfect installation, the unbreakable concrete floor should be flat and level (min. C20/25, frost
proof) with the corresponding load capacity.
16
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
17
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Underground
unbreakable concrete
Permissible
²
sigma b=200KN/m
C20 /25, BST 500 M
Concrete floor > 2,0 cm
Important: Always follow the asssembly instructions and keep to the min. anchoring
depths specified by the dowel manufacturers!
In accordance with EN1493 there must be a safety margin of 500 mm minimum between the lift
columns and any other obstacle (wall, etc) and, similarly, between any load to be raised and another
obstacle.
Following renewed checking of the set-up situation, the baseplate is dowelled through the existing drilled
holes (the floor braces must lie on with their entire surface!). According to the chapter “Foundation”, 12
anchor bolts M12 are required. Other anchor bolts can also be used that have been appproved for the
concrete by the building supervisory authorities, resp. for this region. Dowels are not supplied.
The lift columns should be vertical. In no account should they lean inward.
A slight outward lean ( up to 10 mm ) is desirable. If necessary extra shims can be placed between the
column base plates and the floor for levelling purposes.
In the slave post there are the cables which are connected to the main post. These cables are taken under
the floor the the main post by means of a hollow pipe provided on site. An overhead conduit can also be
provided through which the cables can be fed. When installing the cables it is important to ensure that the
wires are not mixed up! Before commencing the electrical work carefully read and observe the instructions
regarding initial installation (follwing pages)! For further questions, Consul Service is available.
The electrical installation for the lift must be carried out by an electrical engineer and according to the
enclosed circuit diagram and the VDE regulations 0100. The lift should operate in accordance with the travel
direction symbols when the main drive switch is activated. If necessary, change the direction of turn by
swapping aroung the 2 phases.
Important:
Protective conductor checks must be carried out following initial installation,
after reparirs. After alterations to the instllation, as well as prescribed undert
the VDE regulations 0100!
With the lift down pull the angled sides of the locking bars out from the lift until approximately 40 mm
remain on the other side. Grease the take-up bolts thoroughly. Turn the angle of the lower locking bar
upwards and fix it along with the swivell arm. Turn the below of the upper locking bar into the drilled hole
with a pair of pliers after the swing arm has been fitted.
The lift has to be lubricated at the column according to the lubrication schedule (following pages).
Securing of the lift apparatus (eg, swing armes) against being disconnected:
Secure the eye bearing with a hexagonal safety screw on the take-up bolt so that there remains a gap of 1
to 2 mm between the eye and the screw head.
Attention: The self-securing screws only reach complete turning security after 24 hours.
The guide brackets for the flexible cover must be sufficiently spaced from the column so that the flexible
cover does not catch and get damaged. The guide brackets may need to be adjusted
The spindles must be oiled and the spindle oilers on the lifting carriage are to be filled with Consul Spindle
Oil using the observation holes on the columns (order no: 24960.3)
Should there be a noise from the flexible covers when the lift is in drive then multi-purpose grease can be
applied to the back of the cover.
19
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
By doing a test run, check or reprogramme the limits and safety stop. After examination of the
function of the lift by experts, the start-up can take place.
Fig. 2 and 3 show the position of the load bearing nut and respectively the safety nut with the angled safety
catch between the two nuts on the driving angles. The load carrying device are enclosed within the lifting
carriage and cannot be accessed from outside.
When running the lift in normal operation, there is a clearance between safety nut and carriage which allows
the safety nut to run unloaded.
If the thread of the load bearing nut is worn, the carriage falls on the safety nut and and activates the safety
lock which presses against the back wall of the column (see fig. 3).
If the lift is on the safety nut, it can be lowered. If the carriage is moved upwards again, the safety
lock catches on the bar on the back wall of the lift and stops the lift rising.
If the lift stops about 10 mm above the ground level, the supporting elements are defect.
To prevent load nut failure, the following check should be carried out periodically:
Load bearing nut testing
With safety nut „trapezoidal thread Tr 45x6”, available as special accessory (Ident-Nr.: 35416.7).
1. Remove the flexible cover so that the load nut can be seen in the carriage.
2. Using a bar, lift the carriage as and hold .
3. Fix the testing nut on the spindle, turn anti-clockwise until it touches the load nut
4. Lower the carriage
5. Measure the gap between the load nut and the testing nut with a gauge or vernier.
If the wear is over 1mm, the load nut must be replaced !
20
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Roller bearing
Load nut
Spindle guide
Carriage
Bar
Safety lock
Safety nut
Fig 2
Load nut
o.k.
Fig 3
Load nut destroyed
21
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Load nut
22
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
During the first installation of the lift, it is necessary to check the adjustment of the upper and lower
limits. If necessary, they have to be adjusted.
Safety stop:
When lowering the lift, the carriages stop at the programmed point. After pushing the down button agains,
the carriages continue to the lower limit. You can hear the auditible warning noise during this operation.
Attention!
During programming the lift, the automatic limits do not work. – danger of collision in the upper and lower
limits-. Take care of approx. 15 mm overrun.
Initial installation:
Due to different local requirements and individual wishes, the different limits must be programmed.
Standard adjustments:
The lower limit: Between the lowest point of the arm and the ground, there should be at least
10 mm of space.
The upper limit: Between the base plate and the lowest point of ther arm, there should be
A max. difference of 1900 mm.
Safety stop: There should be a minimum of 200 mm between the lowest point of the arm and
the ground.
Notice: The potentiometers are protected against mechanical breakage by means of a mechanical
end stop. It is possible, that the lower limit cannot be reached by using the motor. In this case,
the potentiometer has to be dismounted and the carriage should be lwoered by turning the pulley
on top of the lift. When reaching the lower limit of the carriage, turn the potentiometer clockwise
until you reach the mechanical end stop. After that, turn it back half a turn.
In the lower lifting carriage position the path transitter pinion when unlocked is turned clockwise (seen from
above) until it reaches the mechanical Stopp, then turned back half a turn. With light pressure it will then
return to the locked position and the M6 safety screw of the path transmitter mounting is again secured.
Make sure there is an undamaged spring wahser under the screw head.
23
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
*If you encounter any fault during these test modes, this fault will be stored on the EEPROM . The main board cannot be adjusted to normal
mode in this case. If normal drive mode is selected, and a fault occurs during test mode, both red and green LED’s blink. To ovecame this
situation, change defective parts or run test mode again.
Important notice:
If you encounter big differences in voltage or any other problems, it might happen that the
main board is shut down automatically for safety purpose. In this case the lift cannot be
operated. To make it work again, this can be done usually by turning the main switch on
and off again.
Post lift without cover
Main column
Slave column
Lifting screw
with threat
potentiometer
white white
brown brown
green green
The potentiometer connections P1 and P2 are not marked on the lift. The configuration of the components corresponds to this
drawing. The wiring of the potentiometer connections must be carried out according to the colour scheme of the prescribed plan.
Incorrect wiring damages the potentiometers
When fitting a new EEPROM or circuit board or in the event of any interruption to the control
sequence which cannot be dealt with, carrying out the following steps will help!
To activate EEPROM:
1. Main switch off
2. Place jumper in bridge position
3. Main switch on, diodes flash green / orange
4. Wait three seconds
5. Main switch off
6. Remove the jumper (place in non-bridge position)
7. Main switch on
8. Activate control via position 8 on the program switch and press confirmation switch lower / upper
9. Reinstall stop value and stop position (see above)
25
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Activation of the diagnostic function using the code switch position 8, and pressing the “enter” button.
On connecting, both LEDs will flash red / green and the buzzer will sound intermittently.
The control requires the button to be pressed for up.
Press the AUF (up) button. LED1 will show red. LED2 goes out. The safety circuit is checked. If this is all
correct, LED1 goes out – LED2 shows red and the electronic relays for upward travel are set in motion. The
lift goes up – both LEDs show red.
Press the AUF (up) button until the lift stops automatically. Release the button – both LEDs flash orange /
green.
Press the AB (down) button, LED1 shows orange – LED2 goes out. The safety circuit is checked. If this
contains no faults LED1 goes out- LED2 shows orange and the relays for downward travel are activated.
The lift travels downwards – both LEDs shows orange.
Press the AB (down) button until the lift stops automatically.
Release the button – both LEDs flash green.
Place the code switch in position 0 – press the enter button once – both LEDs show green – test
okay - activation of the PC circuit board successful.
If the test runs successfully, a corresponding entry is registered with EEPROM. The lift can only be used normally in
position “0” after the successful completion of this test.
If a fault occurs during the test the lift cannot be used in the position “0”. A rerun of the test is only possible after
cutting the mains voltage and repeating the above procedure.
Potentiometer Test
Malfunction Indication
Position 0: Normal operation
Both LEDs show green if no buttons are pressed.
If the Aufwärts (up) buttons are pressed both LEDs show red.
If the Abwarts (down) buttons are pressed both LEDs show orange.
26
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
PROBLEM: One or both LEDS flash orange and the alarm buzzer sounds
REASON: The lower stop contact of that particular pillar has been overridden.
SOLUTION: The lift must be relevelled. Further operation is not possible.
PROBLEM: Both LEDs flash alternately orange / red and the alarm sounds
REASON: The maximum allowed distortion between the pillars has been overridden
SOLUTION: The lift must be relevelled. Further operation is not possible.
PROBLEM: After switching on, the buzzer gives three short sounds
REASON: The internal real time clock is not correctly set
SOLUTION: The clock must be set using the PC – configuration software.
PROBLEM: Both LEDs flash orange / green alternately. During downward travel, both motors suddenly stop, although
both the LEDs show orange.
REASON: The stop position has been reached.
SOLUTION: Release the button and press again
PROBLEM: One of the motors cuts out during movement. The relevant LED shows green.
REASON: The control mechanism is re-establishing the even running of the pillars
SOLUTION: This behaviour is normal.
PROBLEM: One or both LEDs flash red and the alarm buzzer sounds
REASON: The upper stop contact of that particular pillar has been overridden.
SOLUTION: The lift must be relevelled. Further operation is not possible.
27
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Drive Modes
Position 4: To control the drive pillar directly
1. Turn the code switch to position 4 and press enter. (The LEDs go out briefly while the button is being pressed and
flash green upon release).
2. By pressing the “Hoch” (up) button, the pillar goes up. LED1 flashes red.
3. By pressing the “Runter” (down) button the pillar goes down. LED1 flashes orange.
1. Turn the code switch to position 5 and press enter. (The LEDs go out briefly while the button is being pressed and
flash green upon release.
2. By pressing the “Hoch” (up) button, the pillar goes up. LED2 flashes red.
3. By pressing the “Runter” (down) button the pillar goes down. LED2 flashes orange.
1. Run the motors with position 4 and position 5 to the required lower point.
2. Turn the code switch to position 1 and press enter. (The LEDs go out briefly during the pressing of the button and
show green on being released).
3. By pressing “enter” again the stops are programmed. The LEDs flash green alternately.
4. A further pressing of “enter” reconnects to point 2.
1. Run motors with position 4 and position 5 to the required upper connection point.
2. Turn the code switch to position 3 and press “enter”. (The LEDs go out briefly whilst the button is being pressed
and show green after release).
3. By pressing “enter” again the stops are programmed. The LEDs flash green alternately.
4. A further pressing of “enter” reconnects to point 2.
1. Run the motors with position 4 and 5 to the required stopping point.
2. Turn the code switch to position 6 and press “enter”. (The LEDs go out briefly whilst the button is being pressed
and show green after release).
3. By pressing enter again the stops are programmed. The LEDs flash green alternately.
4. A further pressing of “enter” reconnects to point 2.
28
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
REASON: The parameters could not be programmed into EEPROM so as to be secure against failure of the current.
SOLUTION: Repeat tuning. If the problem reoccurs, the control mechanism must be replaced. In this situation, press
the “enter” button to return to point 2.
1. Align the motors with position 4 and position 5 as required (height difference = 0).
2. Turn the code switch to position 2 and press “enter”. (The LEDs go out briefly whilst the button is being pressed
and show green after release).
3. By pressing “enter” again the stops are programmed. The LEDs flash green alternately.
4. A further pressing of “enter” reconnects to point 2.
1. Turn the code switch to position 7 and press “enter”. (The LEDs go out briefly while the button is being pressed).
LED flashes orange – the corresponding potentiometer is in the non-permitted zone 0-3%
LED flashes green – the corresponding potentiometer is in the permitted zone 3-97%
LED flashes red – the corresponding potentiometer is in the non-permitted zone 97-100%
1. Turn the code switch to position 8 and press “enter”. (The LEDs flash red / green and the buzzer sounds
intermittently after pressing the button).
2. Press the up button and hold pressed until the lift cuts out automatically.
3. LED1 shows red, LED2 is out. The relays for upward travel are activated. The lift cannot move.
4. LED1 is out, LED2 shows red, only the safety relay is activated, the lift cannot move.
5. LED1 and LED2 show red, the safety relay and the relays are activated for up. The lift must move upwards.
PROBLEM: After carrying out point 5, LED1 and LED2 flash red.
REASON: The lift has not moved although the safety relays and direction relays have switched on.
SOLUTION: Turn the control mechanism off and on. Repeat the test, check the wiring, and if necessary replace the
control mechanism.
29
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
10. LED1 is out, LED2 shows orange, only the safety relay is activated. The lift cannot travel.
11. LED1 and LED2 show orange, the safety relay and the relays are activated for down. The lift must travel
downwards.
PROBLEM: After carrying out point 11, LED1 and LED2 flash orange
REASON: The lift has not moved although the safety relays and direction relays have switched on.
SOLUTION: Turn the control mechanism off and on. Repeat the test, check the wiring, and if necessary replace the
control mechanism.
12. Both LEDs flash green. Release the down button, the test is complete, the control mechanism can be switched to
position 0 again.
NOTE: If the test under point 8 is not carried out completely then the lift can no
longer be used in position 0.
30
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Cause:
Lack of lubrication, worn lifting screw, loose v-belt
Remedy:
Lubrication of spindles.If spindle is defective, replace it.
Tighten v-Belt (replace it).
Remedy:
check supply current as well the fonction of the motor.
Check main switch, control circuits, fine-wire fuse
and thermal cut-out in motor winding and motor operation.
Check that the permitted lifting capacity of the lift has not been exceeded. Check the lubrication between
the load nuts and the spindle. Check the electric leads to the electric motor to see whether current is being
supplied in all 3 phases. Check the safety contacts and the drive belts.
Remedy:
Check safety devices, load bearing nut is probably worn and the safety lock is actived
shut down the lift, secure against unauthorised use and inform Consul Service Section
Remedy:
Check locking blocks, check springs between blocks and side of carriage,
check lock bars for perfect fit or no damage
Remedy:
(look “Preparation for the initial installation”)
Your Consul Service Section should be contacted in the event of any other faults.
Repairs of Consul lifts are only to be undertaken by authorised dealers.
Only original parts are to be used. If non-orignial parts are used all warranties and liabilities are invalid.
31
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
1. Proove mechanical syncronisation device if the slides were abgraded. Within the slides you can see
a hole and if you can see the lower edge they have to be replaced.
2. Pretense the hexagon socket with lapping torsional moment of 1,2 Nm – secure with counter nut.
Brake
The gap is
visible in case
of wear!
Then please
exchange!
32
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Emergency lowering
Important:
During the emergency lowering procedure the automatic end limits are switched off. It is possible to drive the lift into
the floor causing damage.
Notes:
The procedure described below for the emergency lowering of the lift may only be undertaken by authorised, trained
personnel. A second person should watch the procedure from outside the operating area to ensure the safety of the
operator and vehicle.
The emergency lowering procedure must be terminated immediately, if any danger should arise. Restarting the
emergency lowering procedure should begin again once the cause of the danger has been removed. It is only possible
to lower the lift once, making sure that the bad carrying parts do not touch the floor.
Emergency lowering using the motors can be necessary if the electronic controls fail. If other elements fail, then the lift
should be lowered manually (by turning the bolt on the large pulley).
The main switch must be on the „off“position.
The screws should be inserted into the two contactors and locked into position (as shown in the diagram) to enable
emergency lowering.
If the two sides are not synchronised then by locking only one contactor, the arms can be brought on the same level.
Extreme care must be taken and levelling should be done in small steps.
ABB contactor
Colour: black
Condor contactor
Colour: grey
33
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Thorough maintenance is essential if your lift is to have a long working lift and be constantly ready to give
good service.
The lift is equipped with a lubricator, which has a supporting effect on the lubrication of the spindle and the
nuts. In certain conditions (e.g. increased employment, low temperature, etc.) the spindle has to be lubed
separately. We recommend original Consul Spindle Oil. It is not allowed to use grease because the wick
may plug. At least once a month you should check that the oil provision is sufficient.
After installation and commissioning there may be some stretching of the power transmission elements,
depending on the type of lift. For example, stretching of the drive belt, chainds or calbes, consequential
adjustments, adjustments to the safety systems, etc. These changes do not constitue wear and tear of the
parts. They are routine aspects of running in and must form part of the customer’s maintenace and care.
With lack of care break downs can occur which are not occur which are not covered by the guarantee. In
this case, any costs airsing may have to be borne by the customer.
The swing arm joints must be greased when necessary and at least quarter yearly (oil underneath the safety
screws). Where lifts are exposed to the weather, the lubrication programm should be doubled (see the
lubrication instructions on the main column). The load bearing apparatus must always be kept in working
condition. The buffer points must be kept clean and greased-free. The spindles of the turntables must be
greased. They must not be able to unscrew themselves completely.
When the lift is used heavy-duty, please shorten the maintenance period!
34
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Lubrication system
Installation:
1. Remove the cove plate at the rear of the column.
2. Drive up the lift until approx. 440 mm (Floorlevel upto bottom edge of
location bolt for lifting arm), so that the carriage will stop between the
upper roller bearing and the safety lock device – the oil tank will be
visible in the maintenance opening.
Important!
Before carrying out any work at all on the lift, always disconnect it from
the mains electricity supply and ensure that no unauhjorised personnel
can use it.
3. Fill the oil container with oil (we recommend lubrication SAE 20). The
flat wick should be secured about 20-25 mm over the oil container with
a safety needle and fitted pointing downwards. Please check during
assembly!
4. Clamp the oil container to the carriage. Repeat this procedure on the
column. Then check the correct position of the oil container again!
5. Now replace the cover plates and connect the lift to the mains agains.
Check the oil at regular intervals. To do this, remove the cover plate and
raise the carriage so that the oil container is visible through the opening.
Disconnect the lift from the mains supply. Check the oil level and top up with
oil if necessary.
Cover plate
440
35
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Brake
36
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
When the motor cover is removed and the lift is without load then the big belt pulley
should be rotatable by hand (rough-running). Die properly tension of the belt is 220 – 240
Hz. During operation 195 - 220 Hz.
Spindle guide
After the mechanical synchronization device (on the motor holder plate)
is adjusted, the spindle guide has to be adjusted too.
For this the hose clamp at the spindle guide (position 4) must be
torque down.
After the adjustment of the hose clamp the spindle should rotate
on the top with a resisting torque of 20 Nm. Please check the torque,
after a test run, and if necessary repeat the procedure.
Attachable sleeve
with 35 mm
height
(Safety-pull-out limitation)
37
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Accessories
lever Order no.: 34990.2
Cover tape
Fasten the cover tape with the metal stripe and the guide bar
nuts again.
38
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Pin bushing
35 mm or
75 mm high
as alternative: 40602.5
(Safety-stretch limit)
39
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Item-No.: description:
01/2005
Subject to change without prior notice !
40
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
41
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
42
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
43
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Sparepartdrawing
45
15
43
31
55
56
44
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
40
37 5
39
30 4
38
18
29
7
7
20
39
26
45
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
24
8
25
17
15
10
16
1
loading nut
with
Spindle guide
57
20
17
2
16
38
46
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
47
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
48
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
Certificate
49
Operating and installation instructions
Consul 2.40 EL Multi XL Typ: H 327 / H 355
50