Sei sulla pagina 1di 18

1. BF Corporation vs. CA parties may avail of the relief under that clause.

“Reasonableness” is
a relative term and the question of whether the time within which an
Same; Same; A contract may be encompassed in several instruments act has to be done is reasonable depends on attendant
even though every instrument is not signed by the parties, since it is circumstances. This Court finds that under the circumstances
sufficient if the unsigned instruments are clearly identified or referred obtaining in this case, a one-month period from the time the parties
to and made part of the signed instrument or instruments.— held a conference on July 12, 1993 until private respondent SPI
Petitioner’s contention that there was no arbitration clause because notified petitioner that it was invoking the arbitration clause, is a
the contract incorporating said provision is part of a “hodgepodge” reasonable time. Indeed, petitioner may not be faulted for resorting to
document, is therefore untenable. A contract need not be contained in the court to claim what was due it under the contract. However, we
a single writing. It may be collected from several different writings find its denial of the existence of the arbitration clause as an attempt
which do not conflict with each other and which, when connected, to cover up its misstep in hurriedly filing the complaint before the
show the parties, subject matter, terms and consideration, as in lower court.
contracts entered into by correspondence. A contract may be
encompassed in several instruments even though every instrument is Same; Republic Act 876; The potentials of arbitration as one of the
not signed by the parties, since it is sufficient if the unsigned alternative dispute resolution methods that are now rightfully vaunted
instruments are clearly identified or referred to and made part of the as “the wave of the future” in international relations, is recognized
signed instrument or instruments. Similarly, a written agreement of worldwide.—It should be noted that in this jurisdiction, arbitration has
which there are two copies, one signed by each of the parties, is been held valid and constitutional. Even before the approval on June
binding on both to the same extent as though there had been only one 19, 1953 of Republic Act No. 876, this Court has countenanced the
copy of the agreement and both had signed it. settlement of disputes through arbitration. Republic Act No. 876 was
adopted to supplement the New Civil Code’s provisions on arbitration.
Same; Same; The subscription of the principal agreement effectively Its potentials as one of the alternative dispute resolution methods that
covers the other documents incorporated by reference therein.—The are now rightfully vaunted as “the wave of the future” in international
flaw in petitioner’s contentions therefore lies in its having segmented relations, are recognized worldwide. To brush aside a contractual
the various components of the whole contract between the parties into agreement calling for arbitration in case of disagreement between the
several parts. This notwithstanding, petitioner ironically admits the parties would therefore be a step backward.
execution of the Articles of Agreement. Notably, too, the lower court
found that the said Articles of Agreement “also provides that the 2. ABS-CBN Broadcasting Corporation vs. World Interactive
‘Contract Documents’ therein listed ‘shall be deemed an integral part Network Systems (WINS) Japan Co., Ltd.
of this Agreement,’ and one of the said documents is the ‘Conditions
of Contract’ which contains the Arbitration Clause.’ ” It is this Articles Courts; Jurisdictions; Arbitration; Alternative Dispute Resolution; RA
of Agreement that was duly signed by Rufo B. Colayco, president of 876 itself mandates that it is the Court of First Instance, now the RTC,
private respondent SPI, and Bayani F. Fernando, president of which has jurisdiction over questions relating to arbitration, such as a
petitioner corporation. The same agreement was duly subscribed petition to vacate an arbitral award.—RA 876 itself mandates that it is
before notary public Nilberto R. Briones. In other words, the the Court of First Instance, now the RTC, which has jurisdiction over
subscription of the principal agreement effectively covered the other questions relating to arbitration, such as a petition to vacate an arbitral
documents incorporated by reference therein. award.

Same; Same; Words and Phrases; “Reasonableness” is a relative Same; Same; Same; Same; As RA 876 did not expressly provide for
term and the question of whether the time within which an act has to errors of fact and/or law and grave abuse of discretion (proper
be done is reasonable depends on attendant circumstances.—The grounds for a petition for review under Rule 43 and a petition for
arbitration clause provides for a “reasonable time” within which the certiorari under Rule 65, respectively) as grounds for maintaining a
petition to vacate an arbitral award in the RTC, it necessarily follows Employees Union-Olalia v. Court of Appeals, 443 SCRA 286 (2004).
that a party may not avail of the latter remedy on the grounds of errors These cases held that the proper remedy from the adverse decision of
of fact and/or law or grave abuse of discretion to overturn an arbitral a voluntary arbitrator, if errors of fact and/or law are raised, is a
award.—The law itself clearly provides that the RTC must issue an petition for review under Rule 43 of the Rules of Court. Thus,
order vacating an arbitral award only “in any one of the . . . cases” petitioner’s contention that it may avail of a petition for review under
enumerated therein. Under the legal maxim in statutory construction Rule 43 under the circumstances of this case is correct.
expressio unius est exclusio alterius, the explicit mention of one thing
in a statute means the elimination of others not specifically mentioned. Same; Same; Same; Same; Any agreement stipulating that “the
As RA 876 did not expressly provide for errors of fact and/or law and decision of the arbitrator shall be final and unappealable” and “that no
grave abuse of discretion (proper grounds for a petition for review further judicial recourse if either party disagrees with the whole or any
under Rule 43 and a petition for certiorari under Rule 65, respectively) part of the arbitrator’s award may be availed of” cannot be held to
as grounds for maintaining a petition to vacate an arbitral award in the preclude in proper cases the power of judicial review which is inherent
RTC, it necessarily follows that a party may not avail of the latter in courts.—As may be gleaned from the above stated provision, it is
remedy on the grounds of errors of fact and/or law or grave abuse of well within the power and jurisdiction of the Court to inquire whether
discretion to overturn an arbitral award. any instrumentality of the Government, such as a voluntary arbitrator,
has gravely abused its discretion in the exercise of its functions and
Same; Same; Same; Same; Adamson v. Court of Appeals (232 SCRA prerogatives. Any agreement stipulating that “the decision of the
602) gave ample warning that a petition to vacate filed in the RTC arbitrator shall be final and unappealable” and “that no further judicial
which is not based on the grounds enumerated in Section 24 of RA recourse if either party disagrees with the whole or any part of the
876 should be dismissed.—Adamson v. Court of Appeals, 232 SCRA arbitrator’s award may be availed of” cannot be held to preclude in
602 (1994), gave ample warning that a petition to vacate filed in the proper cases the power of judicial review which is inherent in courts.
RTC which is not based on the grounds enumerated in We will not hesitate to review a voluntary arbitrator’s award where
Section 24 of RA 876 should be dismissed. In that case, the trial court there is a showing of grave abuse of authority or discretion and such
vacated the arbitral award seemingly based on grounds included in is properly raised in a petition for certiorari and there is no appeal, nor
Section 24 of RA 876 but a closer reading thereof revealed otherwise. any plain, speedy remedy in the course of law.
On appeal, the CA reversed the decision of the trial court and affirmed
the arbitral award. 3. Real Bank, Inc. vs. Samsung Mabuhay Corporation

Same; Same; Same; Same; The Court held that a voluntary arbitrator Actions; Mediation; Mediation is part of pre-trial and failure of the
is properly classified as a “quasi-judicial instrumentality” and is, thus, plaintiff to appear thereat merits sanction on the part of the absent
within the ambit of Section 9(3) of the Judiciary Reorganization Act, as party.—In Senarlo v. Judge Paderanga, 617 SCRA 247 (2010), this
amended.—In Luzon Development Bank v. Association of Luzon Court accentuated that mediation is part of pre-trial and failure of the
Development Bank Employees, 249 SCRA 162 (1965), the Court held plaintiff to appear thereat merits sanction on the part of the absent
that a voluntary arbitrator is properly classified as a “quasi-judicial party. This court held: A.M. No. 01-10-5- SC-PHILJA dated 16
instrumentality” and is, thus, within the ambit of Section 9 (3) of the October 2001, otherwise known as the Second Revised Guidelines for
Judiciary Reorganization Act, as amended. Same; Same; Same; the Implementation of Mediation Proceedings and Section 5, Rule 18
of the Rules of Court grant judges the discretion to dismiss an action
Same; The proper remedy from the adverse decision of a voluntary for failure of the plaintiff to appear at mediation proceedings.
arbitrator, if errors of fact and/or law are raised, is a petition for review
under Rule 43 of the Rules of Court.—This rule was cited in Sevilla 4. LM Power Engineering Corporation vs. Capitol Industrial
Trading Company v. Semana, 428 SCRA 239 (2004), Manila Midtown Construction Groups, Inc.
Hotel v. Borromeo, 438 SCRA 653 (2004), and Nippon Paint
Alternative Dispute Resolution; Arbitration; Courts; Jurisdiction; The Submission to CIAC Jurisdiction.—An arbitration clause in a
inclusion of an arbitration clause in a contract does not ipso facto construction contract or a submission to arbitration of a construction
divest the courts of jurisdiction to pass upon the findings of arbitral dispute shall be deemed an agreement to submit an existing or future
bodies, because the awards are still judicially reviewable under controversy to CIAC jurisdiction, notwithstanding the reference to a
certain conditions.—We side with respondent. Essentially, the dispute different arbitration institution or arbitral body in such contract or
arose from the parties’ incongruent positions on whether certain submission. When a contract contains a clause for the submission of
provisions of their Agreement could be applied to the facts. The a future controversy to arbitration, it is not necessary for the parties to
instant case involves technical discrepancies that are better left to an enter into a submission agreement before the claimant may invoke
arbitral body that has expertise in those areas. In any event, the the jurisdiction of CIAC.” The foregoing amendments in the Rules
inclusion of an arbitration clause in a contract does not ipso facto were formalized by CIAC Resolution Nos. 2-91 and 3-93.
divest the courts of jurisdiction to pass upon the findings of arbitral
bodies, because the awards are still judicially reviewable under 5. Rizal Commercial Banking Corporation vs. Magwin Marketing
certain conditions. Corporation

Same; Same; Same; Being an inexpensive, speedy and amicable Same; Same; Alternative Dispute Resolution; Compromise
method of settling disputes, arbitration—along with mediation, Agreements; The proper course of action that should have been taken
conciliation and negotiation—is encouraged by the Supreme Court; by the court a quo, upon manifestation of the parties of their
Arbitration is regarded as the “wave of the future” in international civil willingness to discuss a settlement, is to suspend the proceedings and
and commercial disputes; Consistent with the policy of encouraging allow them reasonable time to come to terms; While the rules allow
alternative dispute resolution methods, courts should liberally the trial court to suspend its proceedings consistent with the policy to
construe arbitration clauses.—Being an inexpensive, speedy and encourage the use of alternative mechanisms of dispute resolution,
amicable method of settling disputes, arbitration—along with the grant to the parties of only 15 days to conclude a deal is, to say
mediation, conciliation and negotiation— is encouraged by the the least, a passive and paltry attempt of the court a quo in its task of
Supreme Court. Aside from unclogging judicial dockets, arbitration persuading litigants to agree upon a reasonable concession.—As also
also hastens the resolution of disputes, especially of the commercial explained therein, the proper course of action that should have been
kind. It is thus regarded as the “wave of the future” in international civil taken by the court a quo, upon manifestation of the parties of their
and commercial disputes. Brushing aside a contractual agreement willingness to discuss a settlement, was to suspend the proceedings
calling for arbitration between the parties would be a step backward. and allow them reasonable time to come to terms (a) If willingness to
Consistent with the above-mentioned policy of encouraging alternative discuss a possible compromise is expressed by one or both parties;
dispute resolution methods, courts should liberally construe arbitration or (b) If it appears that one of the parties, before the commencement
clauses. Provided such clause is susceptible of an interpretation that of the action or proceeding, offered to discuss a possible compromise
covers the asserted dispute, an order to arbitrate should be granted. but the other party refused the offer, pursuant to Art. 2030 of the Civil
Any doubt should be resolved in favor of arbitration. Code. If despite efforts exerted by the trial court and the parties the
negotiations still fail, only then should the action continue as if no
Same; Same; Same; Construction Industry Arbitration Commission suspension had taken place. Ostensibly, while the rules allow the trial
(CIAC); Recourse to the CIAC may now be availed of whenever a court to suspend its proceedings consistent with the policy to
contract “contains a clause for the submission of a future controversy encourage the use of alternative mechanisms of dispute resolution, in
to arbitration.—On the other hand, Section 1 of Article III of the new the instant case, the trial court only gave the parties fifteen (15) days
Rules of Procedure Governing Construction Arbitration has dispensed to conclude a deal. This was, to say the least, a passive and paltry
with this requirement and recourse to the CIAC may now be availed attempt of the court a quo in its task of persuading litigants to agree
ofwhenever a contract “contains a clause for the submission of a upon a reasonable concession. Hence, if only to inspire confidence in
future controversy to arbitration,” in this wise: “SECTION 1. the pursuit of a middle ground between petitioner and respondents,
we must not interpret the trial court’s Orders as dismissing the action the spirit of the CIAC rules, whose policy and objective is to “provide a
on its own motion because the parties, specifically petitioner, were fair and expeditious settlement of construction disputes through a
anxious to litigate their case as exhibited in their several nonjudicial process which ensures harmonious and friendly relations
manifestations and motions. between or among the parties.”

6. Rizalina Positos vs. Jacob Chua Same; Same; Same; Same; Aware of the objective of voluntary
arbitration in the labor field, in the construction industry, and in any
Same; Conciliation Proceedings; Non-compliance with conciliation other area for that matter, the Court will not assist one or the other or
requirement under the Local Government Code (Republic Act No. even both parties in any effort to subvert or defeat that objective for
7160) affects the sufficiency of a party’s cause of action and renders their private purposes; The Court will not permit the parties to
the complaint susceptible to dismissal on the ground of prematurity.— relitigate before it the issues of facts previously presented and argued
As reflected above, respondent’s complaint was dismissed for failure before the Arbitral Tribunal, save only where a clear showing is made
to comply with the conciliation process. Non-compliance affected the that, in reaching its factual conclusions, the Arbitral Tribunal
sufficiency of his cause of action and rendered the complaint committed an error so egregious and hurtful to one party as to
susceptible, as in fact it resulted to dismissal on the ground of constitute a grave abuse of discretion resulting in lack or loss of
prematurity. jurisdiction.—It is worthy to stress our ruling in Hi-
Precision Steel Center, Inc. v. Lim Kim Steel Builders, Inc., 228 SCRA
7. Uniwide Sales Realty and Resources Corporation vs. Titan- 397 (1993), which was reiterated in David v. Construction Industry
Ikeda Construction and Development Corporation and Arbitration Commission, 435 SCRA 654 (2004), that: x x x
Executive Order No. 1008 created an arbitration facility to which the
Same; Same; Same; Same; As an arbitration body, the Construction construction industry in the Philippines can have recourse. The
Industry Arbitration Commission (CIAC) can only resolve issues Executive Order was enacted to encourage the early and expeditious
brought before it by the parties through the Terms of Reference (TOR) settlement of disputes in the construction industry, a public policy the
which functions similarly as a pre-trial brief.— Arbitration has been implementation of which is necessary and important for the realization
defined as “an arrangement for taking and abiding by the judgment of of national development goals. Aware of the objective of voluntary
selected persons in some disputed matter, instead of carrying it to arbitration in the labor field, in the construction industry, and in any
established tribunals of justice, and is intended to avoid the other area for that matter, the Court will not assist one or the other or
formalities, the delay, the expense and vexation of ordinary litigation.” even both parties in any effort to subvert or defeat that objective for
Voluntary arbitration, on the other hand, involves the reference of a their private purposes. The Court will not review the factual findings of
dispute to an impartial body, the members of which are chosen by the an arbitral tribunal upon the artful allegation that such body had
parties themselves, which parties freely consent in advance to abide “misapprehended facts” and will not pass upon issues which are, at
by the arbitral award issued after proceedings where both parties had bottom, issues of fact, no matter how cleverly disguised they might be
the opportunity to be heard. The basic objective is to provide a speedy as “legal questions.” The parties here had recourse to arbitration and
and inexpensive method of settling disputes by allowing the parties to chose the arbitrators themselves; they must have had confidence in
avoid the formalities, delay, expense and aggravation which such arbitrators. The Court will not, therefore, permit the parties to
commonly accompany ordinary litigation, especially litigation which relitigate before it the issues of facts previously presented and argued
goes through the entire hierarchy of courts. As an arbitration body, the before the Arbitral Tribunal, save only where a clear showing is made
CIAC can only resolve issues brought before it by the parties through that, in reaching its factual conclusions, the Arbitral Tribunal
the TOR which functions similarly as a pre-trial brief. Thus, if committed an error so egregious and hurtful to one party as to
Uniwide’s claim for liquidated damages was not raised as an issue in constitute a grave abuse of discretion resulting in lack or loss of
the TOR or in any modified or amended version of it, the CIAC cannot jurisdiction. Prototypical examples would be factual conclusions of the
make a ruling on it. The Rules of Court cannot be used to contravene Tribunal which resulted in deprivation of one or the other party of a fair
opportunity to present its position before the Arbitral Tribunal, and an judicial bodies that have acquired expertise are generally accorded
award obtained through fraud or the corruption of arbitrators. Any great respect and even finality, if they are supported by substantial
other, more relaxed rule would result in setting at naught the basic evidence. The Court, however, has consistently held that despite
objective of a voluntary arbitration and would reduce arbitration to a statutory provisions making the decisions of certain administrative
largely inutile institution. agencies “final,” it still takes cognizance of petitions showing want of
jurisdiction, grave abuse of discretion, violation of due process, denial
8. Philrock, Inc. vs. Construction Industry Arbitration of substantial justice or erroneous interpretation of the law. Voluntary
Commission arbitrators, by the nature of their functions, act in a quasi-judicial
capacity, such that their decisions are within the scope of judicial
Actions; Arbitration; Construction Industry Arbitration Commission review.
(CIAC); Jurisdiction; Section 4 of Executive Order (EO) 1008
expressly vests in the CIAC original and exclusive jurisdiction over 9. Agan, Jr. vs. Philippine International Air Terminals Co., Inc.
disputes arising from or connected with construction contracts entered
into by parties that have agreed to submit their dispute to voluntary Actions; Alternative Dispute Resolution; Arbitration; Where petitioners
arbitration.—Petitioner avers that the CIAC lost jurisdiction over the are not parties to a contract with an arbitration clause, they cannot be
arbitration case after both parties had withdrawn their consent to compelled to submit to arbitration proceedings; A speedy and decisive
arbitrate. The June 13, resolution of all the critical issues in the present controversy, including
1995 RTC Order remanding the case to the CIAC for arbitration was those raised by petitioners, cannot be made before an arbitral
allegedly an invalid mode of referring a case for arbitration. We tribunal.—It is established that petitioners in the present cases who
disagree. Section 4 of Executive Order 1008 expressly vests in the have presented legitimate interests in the resolution of the controversy
CIAC original and exclusive jurisdiction over disputes arising from or are not parties to the PIATCO Contracts. Accordingly, they cannot be
connected with construction contracts entered into by parties that bound by the arbitration clause provided for in the ARCA and hence,
have agreed to submit their dispute to voluntary arbitration. cannot be compelled to submit to arbitration proceedings. A speedy
and decisive resolution of all the critical issues in the present
Same; Same; Same; Same; The Supreme Court will not countenance controversy, including those raised by petitioners, cannot be made
the effort of any party to subvert or defeat the objective of voluntary before an arbitral tribunal. The object of arbitration is precisely to allow
arbitration for its own private motives.—As pointed out by the solicitor an expeditious determination of a dispute. This objective would not be
general, petitioner maneuvered to avoid the RTC’s final resolution of met if this Court were to allow the parties to settle the cases by
the dispute by arguing that the regular court also lost jurisdiction after arbitration as there are certain issues involving nonparties to the
the arbitral tribunal’s April 13, 1994 Order referring the case back to PIATCO Contracts which the arbitral tribunal will not be equipped to
the RTC. In so doing, petitioner conceded and estopped itself from resolve.
further questioning the jurisdiction of the CIAC. The Court will not
countenance the effort of any party to subvert or defeat the objective 10. Transfield Philippines, Inc. vs. Luzon Hydro Corporation
of voluntary arbitration for its own private motives. After submitting
itself to arbitration proceedings and actively participating therein, Same; Same; Same; Arbitration; The pendency of arbitral
petitioner is estopped from assailing the jurisdiction of the CIAC, proceedings does not foreclose resort to the courts for provisional
merely because the latter rendered an adverse decision. reliefs.—As a fundamental point, the pendency of arbitral proceedings
does not foreclose resort to the courts for provisional reliefs. The
Same; Same; Same; Judicial Review; Voluntary arbitrators, by the Rules of the ICC, which governs the parties’ arbitral dispute, allows
nature of their functions, act in quasi-judicial capacity, such that their the application of a party to a judicial authority for interim or
decisions are within the scope of judicial review.— We disagree with conservatory measures. Likewise, Section 14 of Republic Act (R.A.)
the solicitor general. As pointed out earlier, factual findings of quasi- No. 876 (The Arbitration Law) recognizes the rights of any party to
petition the court to take measures to safeguard and/or conserve any International Commercial Arbitration of the United Nations
matter which is the subject of the dispute in arbitration. In addition, Commission on International Trade Law (UNCITRAL) in the New York
R.A. 9285, otherwise known as the “Alternative Dispute Resolution Convention on June 21, 1985, the Philippines committed itself to be
Act of 2004,” allows the filing of provisional or interim measures with bound by the Model Law. We have even incorporated the Model Law
the regular courts whenever the arbitral tribunal has no power to act in Republic Act No. (RA) 9285, otherwise known as the Alternative
or to act effectively. Dispute Resolution Act of 2004 entitled An Act to Institutionalize the
Use of an Alternative Dispute Resolution System in the Philippines
11. Korea Technologies Co., Ltd. vs. Lerma and to Establish the Office for Alternative Dispute Resolution, and for
Other Purposes, promulgated on April 2, 2004. Secs. 19 and 20 of
Contracts; Arbitration; Conflict of Laws; While it is established in this Chapter 4 of the Model Law are the pertinent provisions.
jurisdiction is the rule that the law of the place where the contract is
made governs—lex loci contractus—Art. 2044 of the Civil Code Same; Same; Same; Same; Same; Statutory Construction; RA 9285
sanctions the validity of mutually agreed arbitral clause or the finality is a procedural law which has a retroactive effect.—While RA 9285
and binding effect of an arbitral award.— was passed only in 2004, it nonetheless applies in the instant case
Established in this jurisdiction is the rule that the law of the place since it is a procedural law which has a retroactive effect. Likewise,
where the contract is made governs. Lex loci contractus. The contract KOGIES filed its application for arbitration before the KCAB on July 1,
in this case was perfected here in the Philippines. Therefore, our laws 1998 and it is still pending because no arbitral award has yet been
ought to govern. Nonetheless, Art. 2044 of the Civil Code sanctions rendered. Thus, RA 9285 is applicable to the instant case. Well-
the validity of mutually agreed arbitral clause or the finality and settled is the rule that procedural laws are construed to be applicable
binding effect of an arbitral award. Art. 2044 provides, “Any stipulation to actions pending and undetermined at the time of their passage, and
that the arbitrators’ award or decision shall be final, is valid, without are deemed retroactive in that sense and to that extent. As a general
prejudice to Articles 2038, 2039 and rule, the retroactive application of procedural laws does not violate
2040.” (Emphasis supplied.) Arts. 2038, 2039, and 2040 abovecited any personal rights because no vested right has yet attached nor
refer to instances where a compromise or an arbitral award, as arisen from them.
applied to Art. 2044 pursuant to Art. 2043, may be voided, rescinded,
or annulled, but these would not denigrate the finality of the arbitral Same; Same; Same; Same; Same; Under Sec. 24 of R.A. 9285, the
award. Regional Trial Court does not have jurisdiction over disputes that are
properly the subject of arbitration pursuant to an arbitration clause,
Same; Same; Same; Model Law on International Commercial and mandates the referral to arbitration in such cases.—Under Sec.
Arbitration of the United Nations Commission on International Trade 24, the RTC does not have jurisdiction over disputes that are properly
Law (UNCITRAL Model Law); Alternative Dispute Resolution Act of the subject of arbitration pursuant to an arbitration clause, and
2004 (R.A. 9285); As signatory to the Arbitration Rules of the United mandates the referral to arbitration in such cases, thus: SEC. 24.
Nations Commission on International Trade Law (UN-CITRAL) Model Referral to Arbitration.—A court before which an action is brought in a
Law on International Commercial Arbitration of the UNCITRAL in the matter which is the subject matter of an arbitration agreement shall, if
New York Convention on 21 June 1985, the Phil-ippines committed at least one party so requests not later than the pre-trial conference,
itself to be bound by the Model Law; The Philip-pines has or upon the request of both parties thereafter, refer the parties to
incorporated the Model Law in Alternative Dispute Resolution Act of arbitration unless it finds that the arbitration agreement is null and
2004.—For domestic arbitration proceedings, we have particular void, inoperative or incapable of being performed.
agencies to arbitrate disputes arising from contractual relations. In
case a foreign arbitral body is chosen by the parties, the arbitration Same; Same; Same; Same; Same; Judicial Review; Even if foreign
rules of our domestic arbitration bodies would not be applied. As arbitral awards are mutually stipulated by the parties in the arbitration
signatory to the Arbitration Rules of the UNCITRAL Model Law on clause to be final and binding, the same are not immediately
enforceable or cannot be implemented immediately— they must still arbitral awards, while final and binding, do not oust courts of
be confirmed by the Regional Trial Court.—Foreign arbitral awards jurisdiction since these arbitral awards are not absolute and without
while mutually stipulated by the parties in the arbitration clause to be exceptions as they are still judicially reviewable. Chapter 7 of RA 9285
final and binding are not immediately enforceable or cannot be has made it clear that all arbitral awards, whether domestic or foreign,
implemented immediately. Sec. 35 of the are subject to judicial review on specific grounds provided for.
UNCITRAL Model Law stipulates the requirement for the arbitral
award to be recognized by a competent court for enforcement, which Same; Same; Same; Same; Same; Same; Grounds for judicial review
court under Sec. 36 of the UNCITRAL Model Law may refuse different in domestic and foreign arbitral awards—for foreign or
recognition or enforcement on the grounds provided for. RA 9285 international arbitral awards, the grounds for setting aside, rejecting or
incorporated these provisos to Secs. 42, 43, and 44 relative to Secs. vacating the award by the Regional Trial Court (RTC) are provided
47 and 48. under Art. 34(2) of the United Nations Commission on International
Trade Law (UNCITRAL) Model Law, while for final domestic arbitral
Same; Same; Same; Same; Same; Same; It is now clear that foreign awards, they may only be assailed before the RTC and vacated on
arbitral awards when confirmed by the Regional Trial Court are the grounds provided under Sec. 25 of RA 876.— The differences
deemed not as a judgment of a foreign court but as a Foreign arbitral between a final arbitral award from an international or foreign arbitral
award, and when confirmed, are enforced as final and executory tribunal and an award given by a local arbitral tribunal are the specific
decisions of our courts of law—the concept of a final and binding grounds or conditions that vest jurisdiction over our courts to review
arbitral award is similar to judgments or awards given by some quasi- the awards. For foreign or international arbitral awards which must
judicial bodies, like the National Labor Relations Commission and the first be confirmed by the RTC, the grounds for setting aside, rejecting
Mines Adjudication Board.—It is now clear that foreign arbitral awards or vacating the award by the RTC are provided under Art. 34(2) of the
when confirmed by the RTC are deemed not as a judgment of a UNCITRAL Model Law. For final domestic arbitral awards, which also
foreign court but as a foreign arbitral award, and when confirmed, are need confirmation by the RTC pursuant to Sec. 23 of RA 876 and
enforced as final and executory decisions of our courts of law. Thus, it shall be recognized as final and executory decisions of the RTC, they
can be gleaned that the concept of a final and binding arbitral award is may only be assailed before the RTC and vacated on the grounds
similar to judgments or awards given by some of our quasi-judicial provided under Sec. 25 of RA 876.
bodies, like the National Labor Relations Commission and Mines
Adjudication Board, whose final judgments are stipulated to be final Same; Same; Same; Same; Same; Same; An arbitration clause,
and binding, but not immediately executory in the sense that they may stipulating that the arbitral award is final and binding, does not oust
still be judicially reviewed, upon the instance of any party. Therefore, our courts of jurisdiction as the international arbitral award is still
the final foreign arbitral awards are similarly situated in that they need judicially reviewable under certain conditions provided for by the
first to be confirmed by the RTC. United Nations Commission on International Trade Law (UN-CITRAL)
Model Law on International Commercial Arbitration (ICA) as applied
Same; Same; Same; Same; Same; Same; While the Regional and incorporated in RA 9285.—Petitioner is correct in its contention
Trial Court (RTC) does not have jurisdiction over disputes governed that an arbitration clause, stipulating that the arbitral award is final and
by arbitration mutually agreed upon by the parties, still the foreign binding, does not oust our courts of jurisdiction as the international
arbitral award is subject to judicial review by the RTC which can set arbitral award, the award of which is not absolute and without
aside, reject, or vacate it.—While the RTC does not have jurisdiction exceptions, is still judicially reviewable under certain conditions
over disputes governed by arbitration mutually agreed upon by the provided for by the UNCITRAL Model Law on ICA as applied and
parties, still the foreign arbitral award is subject to judicial review by incorporated in RA 9285.
the RTC which can set aside, reject, or vacate it. In this sense, what
this Court held in Chung Fu Industries (Phils.), Inc., 206 SCRA 545 Same; Same; Rescission; Where an arbitration clause in a contract is
(1992), relied upon by KOGIES is applicable insofar as the foreign availing, neither of the parties can unilaterally treat the contract as
rescinded since whatever infractions or breaches by a party or has no power to act or to act effectively. It is thus beyond cavil that the
differences arising from the contract must be brought first and RTC has authority and jurisdiction to grant interim measures of
resolved by arbitration, and not through an extrajudicial rescission or protection.
judicial action.—What this Court held in University of the Philippines v.
De Los Angeles, 35 SCRA 102 (1970) and reiterated in succeeding 12. Koppel, Inc. vs. Makati Rotary Club Foundation, Inc.
cases, that the act of treating a contract as rescinded on account of
infractions by the other contracting party is valid albeit provisional as it Civil Law; Mines and Mining; Mining Act of 1995 (R.A. No. 7942);
can be judicially assailed, is not applicable to the instant case on Arbitrators; Panel of Arbitrators of the Mines and Geosciences Bureau
account of a valid stipulation on arbitration. Where an arbitration (PA-MGB); Jurisdiction; The Supreme Court pointed out to the
clause in a contract is availing, neither of the parties can unilaterally provisions of R.A. No. 7942, or the Mining Act of 1995, which granted
treat the contract as rescinded since whatever infractions or breaches the PA-MGB with exclusive original jurisdiction only over mining
by a party or differences arising from the contract must be brought disputes, i.e., disputes involving “rights to mining areas,” “mineral
first and resolved by arbitration, and not through an extrajudicial agreements or permits,” and “surface owners, occupants,
rescission or judicial action. claimholders or concessionaires” requiring the technical knowledge
and experience of mining authorities in order to be resolved.—
Same; Same; Court Personnel; Sheriffs; A sheriff is not technically Gonzales decided the issue in the negative. In holding that the PA-
competent to ascertain the actual status of the equipment and MGB was devoid of any jurisdiction to take cognizance of the
machineries as installed in the plant.—Whatever findings and complaint for arbitration, this Court pointed out to the provisions of
conclusions made by the RTC Branch Sheriff from the inspection R.A. No. 7942, or the Mining Act of 1995, which granted the PA-MGB
made on October 28, 1998, as ordered by the trial court on October with exclusive original jurisdiction only over mining disputes, i.e.,
19, 1998, is of no worth as said Sheriff is not technically competent to disputes involving “rights to mining areas,” “mineral agreements or
ascertain the actual status of the equipment and machineries as permits,” and “surface owners, occupants, claimholders or
installed in the plant. concessionaires” requiring the technical knowledge and experience of
mining authorities in order to be resolved. Accordingly, since the
Same; Same; Alternative Dispute Resolution Act of 2004 (R.A. 9285); complaint for arbitration in Gonzales did not raise mining disputes as
The pendency of an arbitral proceeding does not foreclose resort to contemplated under R.A. No. 7942 but only issues relating to the
the courts for provisional reliefs—the RTC has authority and validity of certain mining related agreements, this Court held that such
jurisdiction to grant interim measures of protection.—In the recent complaint could not be arbitrated before the PA-MGB. It is in this
2006 case of Transfield Philippines, Inc. v. Luzon Hydro Corporation, context that we made the pronouncement now in discussion:
490 SCRA 14 (2006), we were explicit that even “the pendency of an Arbitration before the Panel of Arbitrators is proper only when there is
arbitral proceeding does not foreclose resort to the courts for a disagreement between the parties as to some provisions of the
provisional reliefs.” We explicated this way: As a fundamental point, contract between them, which needs the interpretation and the
the pendency of arbitral proceedings does not foreclose resort to the application of that particular knowledge and expertise possessed by
courts for provisional reliefs. The Rules of the ICC, which governs the members of that Panel. It is not proper when one of the parties
parties’ arbitral dispute, allows the application of a party to a judicial repudiates the existence or validity of such contract or agreement on
authority for interim or conservatory measures. Likewise, Section 14 the ground of fraud or oppression as in this case. The validity of the
of Republic Act (R.A.) No. 876 (The Arbitration Law) recognizes the contract cannot be subject of arbitration proceedings. Allegations of
rights of any party to petition the court to take measures to safeguard fraud and duress in the execution of a contract are matters within the
and/or conserve any matter which is the subject of the dispute in jurisdiction of the ordinary courts of law. These questions are legal in
arbitration. In addition, R.A. 9285, otherwise known as the “Alternative nature and require the application and interpretation of laws and
Dispute Resolution Act of 2004,” allows the filing of provisional or jurisprudence which is necessarily a judicial function.
interim measures with the regular courts whenever the arbitral tribunal
Same; Doctrine of Separability; Under the doctrine of separability, an the agreement between the parties.— Petitioner claims that
arbitration agreement is considered as independent of the main respondents are guilty of forum-shopping for failing to disclose before
contract. Being a separate contract in itself, the arbitration agreement this Court that they had filed a Petition to Compel for Arbitration
may thus be invoked regardless of the possible nullity or invalidity of before the RTC of Makati City. However, it cannot be determined from
the main contract.—Under the doctrine of separability, an arbitration petitioner’s mere allegations in the Petition that the Petition to Compel
agreement is considered as independent of the main contract. Being a for Arbitration instituted by respondent Climax-Arimco, involves
separate contract in itself, the arbitration agreement may thus be related causes of action and the grant of the same or substantially the
invoked regardless of the possible nullity or invalidity of the main same reliefs as those involved in the instant case. Petitioner did not
contract. Once again instructive is Cargill, wherein this Court held attach copies of the Petition to Compel for Arbitration or any order or
that, as a further consequence of the doctrine of separability, even the resolution of the RTC of Makati City related to that case. Furthermore,
very party who repudiates the main contract may invoke its arbitration it can be gleaned from the nature of the two actions that the issues in
clause. the case before the RTC of Makati City and in the petition for certiorari
before the Court of Appeals are different. A petition for certiorari
Same; Arbitration; Mediation; “Mediation” and “Arbitration,” raises the issue of whether or not there was grave abuse of discretion,
Distinguished.—The JDR framework is based on the processes of while the Petition to Compel for Arbitration seeks the implementation
mediation, conciliation or early neutral evaluation which entails the of the arbitration clause in the agreement between the parties.
submission of a dispute before a “JDR judge” who shall merely
“facilitate settlement” between the parties in conflict or make a “non- Same; Same; Same; Mining Claims; Words and Phrases; A judicial
binding evaluation or assessment of the chances of each party’s question is a question that is proper for determination by the courts,
case.” Thus in JDR, the JDR judge lacks the authority to render a as opposed to a moot question or one properly decided by the
resolution of the dispute that is binding upon the parties in conflict. In executive or legislative branch while a mining dispute is a dispute
arbitration, on the other hand, the dispute is submitted to an involving (a) rights to mining areas, (b) mineral agreements, FTAAs,
arbitrator/s — a neutral third person or a group of thereof — who shall or permits, and (c) surface owners, occupants and
have the authority to render a resolution binding upon the parties. claimholders/concessionaires.—A judicial question is a question that
is proper for determination by the courts, as opposed to a moot
Same; Same; It is clear that under the law, the petitioner and the question or one properly decided by the executive or legislative
respondent should have been referred to arbitration pursuant to the branch. A judicial question is raised when the determination of the
arbitration clause of the 2005 Lease Contract.—It is clear that under question involves the exercise of a judicial function; that is, the
the law, the instant unlawful detainer action should have been stayed; question involves the determination of what the law is and what the
the petitioner and the respondent should have been referred to legal rights of the parties are with respect to the matter in controversy.
arbitration pursuant to the arbitration clause of the 2005 Lease On the other hand, a mining dispute is a dispute involving (a) rights to
Contract. The MeTC, however, did not do so in violation of the law — mining areas, (b) mineral agreements, FTAAs, or permits, and (c)
which violation was, in turn, affirmed by the RTC and Court of Appeals surface owners, occupants and claimholders/concessionaires. Under
on appeal. Republic Act No. 7942 (otherwise known as the Philippine Mining Act
of 1995), the Panel of Arbitrators has exclusive and original
13. Gonzales vs. Climax Mining Ltd. jurisdiction to hear and decide these mining disputes. The Court of
Appeals, in its questioned decision, correctly stated that the Panel’s
Actions; Alternative Dispute Resolution; Arbitration; Forum Shopping; jurisdiction is limited only to those mining disputes which raise
Pleadings and Practice; There is no forum shopping where one is a questions of fact or matters requiring the application of technological
petition for certiorari which raises the issue of whether or not there knowledge and experience.
was grave abuse of discretion while the other is a Petition to Compel
for Arbitration seeking the implementation of the arbitration clause in
Same; Same; Same; Same; The trend has been to make the constitutionality is exclusively within the jurisdiction of the courts to
adjudication of mining cases a purely administrative matter.—In resolve as this would clearly involve the exercise of judicial power.
Pearson v. Intermediate Appellate Court, this Court observed that the The Panel of Arbitrators does not have jurisdiction over such an issue
trend has been to make the adjudication of mining cases a purely since it does not involve the application of technical knowledge and
administrative matter. Decisions of the Supreme Court on mining expertise relating to mining. This the Panel of Arbitrators has even
disputes have recognized a distinction between (1) the primary conceded in its Orders dated 18 October 2001 and 25 June 2002. At
powers granted by pertinent provisions of law to the then this juncture, it is worthy of note that in a case, which was resolved
Secretary of Agriculture and Natural Resources (and the bureau only on 1 December 2004, this Court upheld the validity of the FTAA
directors) of an executive or administrative nature, such as granting of entered into by the Republic of the Philippines and WMC
license, permits, lease and contracts, or approving, rejecting, (Philippines), Inc. and constitutionality of Rep. Act No. 7942 and
reinstating or canceling applications, or deciding conflicting DENR Administrative Order 96-40. In fact, the Court took the case on
applications, and (2) controversies or disagreements of civil or an original petition, recognizing “the exceptional character of the
contractual nature between litigants which are questions of a judicial situation and the paramount public interest involved, as well as the
nature that may be adjudicated only by the courts of justice. This necessity for a ruling to put an end to the uncertainties plaguing the
distinction is carried on even in Rep. Act No. 7942. mining industry and the affected communities as a result of doubts
case upon the constitutionality and validity of the Mining Act, the
Same; Same; Same; Same; Contracts; The resolution of the validity subject FTAA and future FTAAs, and the need to avert a multiplicity of
or voidness of the contracts remains a legal or judicial question as it suits.”
requires the exercise of judicial function.—Whether the case involves
void or voidable contracts is still a judicial question. It may, in some Same; Same; Same; Same; Same; Arbitration before the Panel of
instances, involve questions of fact especially with regard to the Arbitrators is proper only when there is a disagreement between the
determination of the circumstances of the execution of the contracts. parties as to some provisions of the contract between them, which
But the resolution of the validity or voidness of the contracts remains a needs the interpretation and the application of that particular
legal or judicial question as it requires the exercise of judicial function. knowledge and expertise possessed by members of that Panel—it is
It requires the ascertainment of what laws are applicable to the not proper when one of the parties repudiates the existence or validity
dispute, the interpretation and application of those laws, and the of such contract or agreement on the ground of fraud or oppression.—
rendering of a judgment based thereon. Clearly, the dispute is not a Arbitration before the Panel of Arbitrators is proper only when there is
mining conflict. It is essentially judicial. The complaint was not merely a disagreement between the parties as to some provisions of the
for the determination of rights under the mining contracts since the contract between them, which needs the interpretation and the
very validity of those contracts is put in issue. application of that particular knowledge and expertise possessed by
members of that Panel. It is not proper when one of the parties
Same; Same; Same; Same; Same; The question of constitutionality is repudiates the existence or validity of such contract or agreement on
exclusively within the jurisdiction of the courts to resolve as this would the ground of fraud or oppression as in this case. The validity of the
clearly involve the exercise of judicial power and a Panel of Arbitrators contract cannot be subject of arbitration proceedings. Allegations of
does not have jurisdiction over such an issue since it does not involve fraud and duress in the execution of a contract are matters within the
the application of technical knowledge and expertise relating to jurisdiction of the ordinary courts of law. These questions are legal in
mining.—The Complaint is also not what is contemplated by Rep. Act nature and require the application and interpretation of laws and
No. 7942 when it says the dispute should involve FTAAs. The jurisprudence which is necessarily a judicial function.
Complaint is not exclusively within the jurisdiction of the Panel of
Arbitrators just because, or for as long as, the dispute involves an Same; Same; Same; Same; The question of validity of the contract
FTAA. The Complaint raised the issue of the constitutionality of the containing the agreement to submit to arbitration will affect the
FTAA, which is definitely a judicial question. The question of applicability of the arbitration clause itself—a party cannot rely on the
contract and claim rights or obligations under it and at the same time contract is invalid or did not come into existence, since the arbitration
impugn its existence or validity.—We agree that the case should not agreement shall be treated as a separate agreement independent of
be brought under the ambit of the Arbitration Law, but for a different the main contract. To reiterate a contrary ruling would suggest that a
reason. The question of validity of the contract containing the party’s mere repudiation of the main contract is sufficient to avoid
agreement to submit to arbitration will affect the applicability of the arbitration and that is exactly the situation that the separability
arbitration clause itself. A party cannot rely on the contract and claim doctrine sought to avoid. Thus, we find that even the party who has
rights or obligations under it and at the same time impugn its repudiated the main contract is not prevented from enforcing its
existence or validity. Indeed, litigants are enjoined from taking arbitration clause.
inconsistent positions. As previously discussed, the complaint should
have been filed before the regular courts as it involved issues which 15. Uy vs. Public Estates Authority
are judicial in nature.
Construction Industry; Alternative Dispute Resolution; Arbitration;
14. Cargill Philippines, Inc. vs. San Fernando Regala Trading, Inc. Construction Industry Arbitration Commission (CIAC); Appeals;
Appeals from judgment of the Construction Industry Arbitration
Arbitration; Alternative Dispute Resolution; Arbitration, as an Commission (CIAC) shall be taken to the Court of Appeals (CA) by
alternative mode of settling disputes, has long been recognized and filing a petition for review within fifteen (15) days from the receipt of
accepted in our jurisdiction.—Arbitration, as an alternative mode of the notice of award, judgment, final order or resolution, or from the
settling disputes, has long been recognized and accepted in our date of its last publication if publication is required by law for its
jurisdiction. R.A. No. 876 authorizes arbitration of domestic disputes. effectivity, or of the denial of petitioner’s motion for new trial or
Foreign arbitration, as a system of settling commercial disputes of an reconsideration.—Appeals from judgment of the CIAC shall be taken
international character, is likewise recognized. The enactment of R.A. to the CA by filing a petition for review within fifteen (15) days from the
No. 9285 on April 2, 2004 further institutionalized the use of receipt of the notice of award, judgment, final order or resolution, or
alternative dispute resolution systems, including arbitration, in the from the date of its last publication if publication is required by law for
settlement of disputes. its effectivity, or of the denial of petitioner’s motion for new trial or
reconsideration duly filed in accordance with the governing law of the
Same; Same; Contracts; Submission to arbitration is a contract and a court or agency a quo.
clause in a contract providing that all matters in dispute between the
parties shall be referred to arbitration is a contract.—A contract is 16. Shinryo (Philippines) Company, Inc. vs. RPN Incorporated
required for arbitration to take place and to be binding. Submission to
arbitration is a contract and a clause in a contract providing that all Appeals; Administrative Law; Alternative Dispute Resolution (ADR);
matters in dispute between the parties shall be referred to arbitration Construction Industry; It is settled that findings of fact of quasi-judicial
is a contract. The provision to submit to arbitration any dispute arising bodies, which have acquired expertise because their jurisdiction is
therefrom and the relationship of the parties is part of the contract and confined to specific matters, are generally accorded not only respect,
is itself a contract. but also finality, especially when affirmed by the Court of Appeals;
Factual findings of construction arbitrators are final and conclusive
Same; Same; Same; An arbitration agreement which forms part of the and not reviewable by this Court on appeal.— As reiterated by the
main contract shall not be regarded as invalid or nonexistent just Court in IBEX International, Inc. v. Government Service Insurance
because the main contract is invalid or did not come into existence, System, 603 SCRA 306 (2009), to wit: It is settled that findings of fact
since the arbitration agreement shall be treated as a separate of quasi-judicial bodies, which have acquired expertise because their
agreement independent of the main contract.—Applying the Gonzales jurisdiction is confined to specific matters, are generally accorded not
ruling, an arbitration agreement which forms part of the main contract only respect, but also finality, especially when affirmed by the Court of
shall not be regarded as invalid or non-existent just because the main Appeals. In particular, factual findings of construction arbitrators are
final and conclusive and not reviewable by this Court on appeal. This
rule, however, admits of certain exceptions. In Uniwide Sales Realty 17. Heunghwa Industry Co., Ltd. vs. DJ Builders Corp.
and Resources Corporation v. Titan-Ikeda Construction and
Development Corporation, 511 SCRA 335 (2006), we said: In David v. Courts; Certiorari; Administrative Law; Jurisdiction; Whether the
Construction Industry and Arbitration Commission, 435 SCRA 654 subject matter falls within the exclusive jurisdiction of a quasijudicial
(2004), we ruled that, as exceptions, factual findings of construction agency is a question of law.—As a general rule, a petition for certiorari
arbitrators may be reviewed by this Court when the petitioner proves before a higher court will not prosper unless the inferior court has
affirmatively that: (1) the award was procured by corruption, fraud or been given, through a motion for reconsideration, a chance to correct
other undue means; (2) there was evident partiality or corruption of the errors imputed to it. This rule, though, has certain exceptions: (1)
the arbitrators or any of them; (3) the arbitrators were guilty of when the issue raised is purely of law, (2) when public interest is
misconduct in refusing to hear evidence pertinent and material to the involved, or (3) in case of urgency. As a fourth exception, it has been
controversy; (4) one or more of the arbitrators were disqualified to act held that the filing of a motion for reconsideration before availment of
as such under Section nine of the remedy of certiorari is not a condition sine qua non when the
Republic Act No. 876 and willfully refrained from disclosing such questions raised are the same as those that have already been
disqualifications or of any other misbehavior by which the rights of any squarely argued and exhaustively passed upon by the lower court.
party have been materially prejudiced; or (5) the arbitrators exceeded The Court agrees with petitioner that the main issue of the petition for
their powers, or so imperfectly executed them, that a mutual, final and certiorari filed before the CA undoubtedly involved a question of
definite award upon the subject matter submitted to them was not jurisdiction as to which between the RTC and the CIAC had authority
made. Other recognized exceptions are as follows: (1) when there is a to hear the case. Whether the subject matter falls within the exclusive
very clear showing of grave abuse of discretion resulting in lack or jurisdiction of a quasi-judicial agency is a question of law. Thus, given
loss of jurisdiction as when a party was deprived of a fair opportunity the circumstances present in the case at bar, the non-filing of a
to present its position before the Arbitral Tribunal or when an award is motion for reconsideration by petitioner to the CIAC Order should
obtained through fraud or the corruption of arbitrators, (2) when the have been recognized as an exception to the rule.
findings of the Court of Appeals are contrary to those of the CIAC, and
(3) when a party is deprived of administrative due process. Alternative Dispute Resolution; Arbitration; Construction Industry
Arbitration Commission (CIAC); Jurisdiction; Executive Order 1008
Arbitration; Mathematical computations, the propriety of arbitral grants to the Construction Industry Arbitration Commission (CIAC)
awards, claims for “other costs” and “abandonment” are factual original and exclusive jurisdiction over disputes arising from, or
questions.—Again, these issues are purely factual and cannot be connected with, contracts entered into by parties involved in
properly addressed in this petition for review on certiorari. In Hanjin construction in the Philippines.—Executive Order 1008 grants to the
Heavy Industries and Construction Co., Ltd. v. Dynamic Planners and CIAC original and exclusive jurisdiction over disputes arising from, or
Construction Corp., 553 SCRA 541 (2008), it was emphasized that connected with, contracts entered into by parties involved in
mathematical computations, the propriety of arbitral awards, claims for construction in the Philippines. In the case at the bar, it is undeniable
“other costs” and “abandonment” are factual questions. Since the that the controversy involves a construction dispute as can be seen
discussions of the CIAC and the CA in their respective Decisions from the issues referred to the CIAC, to wit: 1. Manpower and
show that its factual findings are supported by substantial evidence, equipment standby time; 2. Unrecouped mobilization expenses; 3.
there is no reason why this Court should not accord finality to said Retention; 4. Discrepancy of billings; and 5. Price escalation for fuel
findings. Verily, to accede to petitioner’s request for a recalibration of and oil usage. x x x x
its evidence, which had been thoroughly studied by both the CIAC
and the CA would result in negating the objective of Executive Order Same; Same; Same; Same; There are two acts which may vest the
No. 1008, which created an arbitration body to ensure the prompt and Construction Industry Arbitration Commission (CIAC) with jurisdiction
efficient settlement of disputes in the construction industry. over a construction dispute—one is the presence of an arbitration
clause in a construction contract, and the other is the agreement by
the parties to submit the dispute to the Construction Industry 18. Tuna Processing, Inc. vs. Philippine Kingford, Inc.
Arbitration Commission (CIAC).—There are two acts which may vest
the CIAC with jurisdiction over a construction dispute. One is the Statutory Construction; Between a general law and a special law, the
presence of an arbitration clause in a construction contract, and the latter prevails.—In several cases, this Court had the occasion to
other is the agreement by the parties to submit the dispute to the discuss the nature and applicability of the Corporation Code of the
CIAC. The first act is applicable to the case at bar. The bare fact that Philippines, a general law, viz-a-viz other special laws. Thus, in
the parties incorporated an arbitration clause in their contract is Koruga v. Arcenas, Jr., 590 SCRA 49 (2009), this Court rejected the
sufficient to vest the CIAC with jurisdiction over any construction application of the Corporation Code and applied the New Central
controversy or claim between the parties. The rule is explicit that the Bank Act. It ratiocinated: Koruga’s invocation of the provisions of the
CIAC has jurisdiction notwithstanding any reference made to another Corporation Code is misplaced. In an earlier case with similar
arbitral body. It is well-settled that jurisdiction is conferred by law and antecedents, we ruled that: “The Corporation Code, however, is a
cannot be waived by agreement or acts of the parties. Thus, the general law applying to all types of corporations, while the New
contention of petitioner that it never authorized its lawyer to submit the Central Bank Act regulates specifically banks and other financial
case for arbitration must likewise fail. Petitioner argues that institutions, including the dissolution and liquidation thereof. As
notwithstanding the presence of an arbitration clause, there must be a between a general and special law, the latter shall prevail—generalia
subsequent consent by the parties to submit the case for arbitration. specialibus non derogant.” (Emphasis supplied) Further, in the recent
To stress, the CIAC was already vested with jurisdiction the moment case of Hacienda Luisita, Incorporated v. Presidential Agrarian
both parties agreed to incorporate an arbitration clause in the sub- Reform Council, 653 SCRA 154 (2011), this Court held: Without
contract agreement. Thus, a subsequent consent by the parties would doubt, the Corporation Code is the general law providing for the
be superfluous and unnecessary. formation, organization and regulation of private corporations. On the
other hand, RA 6657 is the special law on agrarian reform. As
Same; Same; Same; Same; Where the jurisdiction of Construction between a general and special law, the latter shall prevail—generalia
Industry Arbitration Commission (CIAC) is properly invoked by the specialibus non derogant. Following the same principle, the
filing of a Request for Arbitration in accordance with these Rules, the Alternative Dispute Resolution Act of 2004 shall apply in this case as
failure despite due notice which amounts to a refusal of the the Act, as its title—An Act to Institutionalize the Use of an Alternative
Respondent to arbitrate, shall not stay the proceedings Dispute Resolution System in the Philippines and to Establish the
notwithstanding the absence or lack of participation of the Office for
respondent.—Under the CIAC rules, even without the participation of Alternative Dispute Resolution, and for Other Purposes—would
petitioner in the proceedings, the CIAC was still required to proceed suggest, is a law especially enacted “to actively promote party
with the hearing of the construction dispute. Section 4.2 of the CIAC autonomy in the resolution of disputes or the freedom of the party to
rules provides: SECTION 4.2 Failure or refusal to arbitrate—Where make their own arrangements to resolve their disputes.” It specifically
the jurisdiction of CIAC is properly invoked by the filing of a Request provides exclusive grounds available to the party opposing an
for Arbitration in accordance with these Rules, the failure despite due application for recognition and enforcement of the arbitral award.
notice which amounts to a refusal of the Respondent to arbitrate, shall
not stay the proceedings notwithstanding the absence or lack of Same; Alternative Dispute Resolution; Alternative Dispute Resolution
participation of the Respondent. In such case, CIAC shall appoint the Act of 2004; Conflict of Laws; The Alternative Dispute Resolution Act
arbitrator/s in accordance with these Rules. Arbitration proceedings of 2004 complies with international obligations under the New York
shall continue, and the award shall be made after receiving the Convention and the Model Law.—Inasmuch as the Alternative Dispute
evidence of the Claimant. This Court finds that the CIAC simply Resolution Act of 2004, a municipal law, applies in the instant petition,
followed its rules when it proceeded with the hearing of the dispute we do not see the need to discuss compliance with international
notwithstanding that petitioner refused to participate therein. obligations under the New York Convention and the Model Law. After
all, both already form part of the law. In particular, the Alternative award deals with a difference not contemplated by or not falling within
Dispute Resolution Act of 2004 incorporated the New York the terms of the submission to arbitration, or it contains decisions on
Convention in the Act by specifically providing: SEC. 42. Application matters beyond the scope of the submission to arbitration, provided
of the New York Convention.—The New York Convention shall govern that, if the decisions on matters submitted to arbitration can be
the recognition and enforcement of arbitral awards covered by the separated from those not so submitted, that part of the award which
said Convention. xxx SEC. 45. Rejection of a Foreign Arbitral contains decisions on matters submitted to arbitration may be
Award.—A party to a foreign arbitration proceeding may oppose an recognized and enforced; or (d) The composition of the arbitral
application for recognition and enforcement of the arbitral award in authority or the arbitral procedure was not in accordance with the
accordance with the procedural rules to be promulgated by the agreement of the parties, or, failing such agreement, was not in
Supreme Court only on those grounds enumerated under Article V of accordance with the law of the country where the arbitration took
the New York Convention. Any other ground raised shall be place; or (e) The award has not yet become binding on the parties, or
disregarded by the regional trial court. It also expressly adopted the has been set aside or suspended by a competent authority of the
Model Law, to wit: Sec. 19. Adoption of the Model Law on country in which, or under the law of which, that award was made. 2.
International Commercial Arbitration. International commercial Recognition and enforcement of an arbitral award may also be
arbitration shall be governed by the Model Law on International refused if the competent authority in the country where recognition
Commercial Arbitration (the “Model Law”) adopted by the United and enforcement is sought finds that: (a) The subject matter of the
Nations Commission on International Trade Law on difference is not capable of settlement by arbitration under the law of
June 21, 1985 xxx.” that country; or (b) The recognition or enforcement of the award would
be contrary to the public policy of that country. Clearly, not one of
Alternative Dispute Resolution; Alternative Dispute Resolution Act of these exclusive grounds touched on the capacity to sue of the party
2004; Conflict of Laws; Sec. 45 of the Alternative Dispute Resolution seeking the recognition and enforcement of the award. Pertinent
Act of 2004 provides that the opposing party in an application for provisions of the Special Rules of Court on Alternative Dispute
recognition and enforcement of the arbitral award may raise only Resolution, which was promulgated by the Supreme Court, likewise
those grounds that were enumerated under Article V of the New York support this position. Rule 13.1 of the Special Rules provides that
Convention.—Does a foreign corporation not licensed to do business “[a]ny party to a foreign arbitration may petition the court to recognize
in the Philippines have legal capacity to sue under the provisions of and enforce a foreign arbitral award.” The contents of such petition
the Alternative Dispute Resolution Act of 2004? We answer in the are enumerated in Rule 13.5. Capacity to sue is not included.
affirmative. Sec. 45 of the Alternative Dispute Resolution Act of 2004 Oppositely, in the Rule on local arbitral awards or arbitrations in
provides that the opposing party in an application for recognition and instances where “the place of arbitration is in the Philippines,” it is
enforcement of the arbitral award may raise only those grounds that specifically required that a petition “to determine any question
were enumerated under Article V of the New York Convention, to wit: concerning the existence, validity and enforceability of such arbitration
Article V 1. Recognition and enforcement of the award may be agreement” available to the parties before the commencement of
refused, at the request of the party against whom it is invoked, only if arbitration and/or a petition for “judicial relief from the ruling of the
that party furnishes to the competent authority where the recognition arbitral tribunal on a preliminary question upholding or declining its
and enforcement is sought, proof that: (a) The parties to the jurisdiction” after arbitration has already commenced should state
agreement referred to in article II were, under the law applicable to “[t]he facts showing that the persons named as petitioner or
them, under some incapacity, or the said agreement is not valid under respondent have legal capacity to sue or be sued.”
the law to which the parties have subjected it or, failing any indication
thereon, under the law of the country where the award was made; or Same; Same; Same; When a party enters into a contract containing a
(b) The party against whom the award is invoked was not given foreign arbitration clause and in fact submits itself to arbitration, it
proper notice of the appointment of the arbitrator or of the arbitration becomes bound by the contract, by the arbitration and by the result of
proceedings or was otherwise unable to present his case; or (c) The arbitration, conceding thereby the capacity of the other party to enter
into the contract, participate in the arbitration and cause the concerned.—There is no need to consider respondent’s contention
implementation of the result.— Indeed, it is in the best interest of that petitioner TPI improperly raised a question of fact when it posited
justice that in the enforcement of a foreign arbitral award, we deny that its act of entering into a MOA should not be considered “doing
availment by the losing party of the rule that bars foreign corporations business” in the Philippines for the purpose of determining capacity to
not licensed to do business in the Philippines from maintaining a suit sue. We reiterate that the foreign corporation’s capacity to sue in the
in our courts. When a party enters into a contract containing a foreign Philippines is not material insofar as the recognition and enforcement
arbitration clause and, as in this case, in fact submits itself to of a foreign arbitral award is concerned.
arbitration, it becomes bound by the contract, by the arbitration and by
the result of arbitration, conceding thereby the capacity of the other 19. F.F. Cruz & Co., Inc. vs. HR Construction Corp.
party to enter into the contract, participate in the arbitration and cause
the implementation of the result. Although not on all fours with the Construction Contracts; Construction Industry Arbitration Commission
instant case, also worthy to consider is the wisdom of then Associate (CIAC); Jurisdiction; Arbitration; Appeals; Executive Order (E.O.) No.
Justice Flerida Ruth P. Romero in her Dissenting Opinion in Asset 1008 vests upon the Construction Industry Arbitration Commission
Privatization Trust v. Court of Appeals, 300 SCRA 579 (1998), to wit: (CIAC) original and exclusive jurisdiction over disputes arising from, or
xxx Arbitration, as an alternative mode of settlement, is gaining connected with, contracts entered into by parties involved in
adherents in legal and judicial circles here and abroad. If its tested construction in the Philippines; The arbitral award of Construction
mechanism can simply be ignored by an aggrieved party, one who, it Industry Arbitration Commission (CIAC) shall be final and
must be stressed, voluntarily and actively participated in the inappealable except on questions of law which shall be appealable to
arbitration proceedings from the very beginning, it will destroy the very the Supreme Court.—Executive Order (E.O.) No. 1008 vests upon the
essence of mutuality inherent in consensual contracts. CIAC original and exclusive
Jurisdiction over disputes arising from, or connected with, contracts
Same; Same; Same; On the matter of capacity to sue, a foreign entered into by parties involved in construction in the Philippines.
arbitral award should be respected not because it is favored over Under Section 19 of E.O. No. 1008, the arbitral award of CIAC “shall
domestic laws and procedures, but because Republic Act No. 9285 be final and inappealable except on questions of law which shall be
has certainly erased any conflict of law question.—Clearly, on the appealable to the Supreme Court.” In Hi-Precision Steel Center, Inc.
matter of capacity to sue, a foreign arbitral award should be respected v. Lim Kim Steel Builders, Inc., 228 SCRA 397 (1993), we explained
not because it is favored over domestic laws and procedures, but raison d’ etre for the rule on finality of the CIAC’s arbitral award in this
because Republic Act No. 9285 has certainly erased any conflict of wise: Voluntary arbitration involves the reference of a dispute to an
law question. Finally, even assuming, only for the sake of argument, impartial body, the members of which are chosen by the parties
that the court a quo correctly observed that the Model Law, not the themselves, which parties freely consent in advance to abide by the
New York Convention, governs the subject arbitral award, petitioner arbitral award issued after proceedings where both parties had the
may still seek recognition and enforcement of the award in Philippine opportunity to be heard. The basic objective is to provide a speedy
court, since the Model Law prescribes substantially identical exclusive and inexpensive method of settling disputes by allowing the parties to
grounds for refusing recognition or enforcement. Premises avoid the formalities, delay, expense and aggravation which
considered, petitioner TPI, although not licensed to do business in the commonly accompany ordinary litigation, especially litigation which
Philippines, may seek recognition and enforcement of the foreign goes through the entire hierarchy of courts. Executive Order No. 1008
arbitral award in accordance with the provisions of the Alternative created an arbitration facility to which the construction industry in the
Dispute Resolution Act of 2004. Philippines can have recourse. The Executive Order was enacted to
encourage the early and expeditious settlement of disputes in the
Same; Same; Same; Foreign Corporations; The foreign corporation’s construction industry, a public policy the implementation of which is
capacity to sue in the Philippines is not material insofar as the necessary and important for the realization of national development
recognition and enforcement of a foreign arbitral award is goals. Aware of the objective of voluntary arbitration in the labor field,
in the construction industry, and in any other area for that matter, the that rules and regulations issued by administrative bodies to interpret
Court will not assist one or the other or even both parties in any effort the law which they are entrusted to enforce, have the force of law, and
to subvert or defeat that objective for their private purposes. The are entitled to great respect. Such rules and regulations partake of the
Court will not review the factual findings of an arbitral tribunal upon nature of a statute and are just as binding as if they have been written
the artful allegation that such body had “misapprehended the facts” in the statute itself. In the instant case, the Court finds no cogent
and will not pass upon issues which are, at bottom, issues of fact, no reason to depart from this rule.
matter how cleverly disguised they might be as “legal questions.” The
parties here had recourse to arbitration and chose the arbitrators Same; Same; Conciliation; Constitutional Law; Under the third
themselves; they must have had confidence in such arbitrators. x x x. paragraph, Section 3, Article XIII, of the Constitution, “[t]he State shall
promote the principle of shared responsibility between workers and
20. Estate of Nelson R. Dulay vs. Aboitiz Jebsen Maritime, Inc. employers and the preferential use of voluntary modes in settling
disputes, including conciliation, and shall enforce their mutual
Labor Law; Arbitration; It is settled that when the parties have validly compliance therewith to foster industrial peace.”—No less than the
agreed on a procedure for resolving grievances and to submit a Philippine Constitution provides, under the third paragraph, Section 3,
dispute to voluntary arbitration then that procedure should be strictly Article XIII, thereof that “[t]he State shall promote the principle of
observed.—In any case, the Court agrees with petitioner’s contention shared responsibility between workers and employers and the
that the CBA is the law or contract between the parties. Article 13.1 of preferential use of voluntary modes in settling disputes, including
the CBA entered into by and between respondent GCI and AMOSUP, conciliation, and shall enforce their mutual compliance therewith to
the union to which petitioner belongs, provides as follows: The foster industrial peace.”
Company and the Union agree that in case of dispute or conflict in the
interpretation or application of any of the provisions of this Agreement, 21. Agbayani vs. Court of Appeals
or enforcement of Company policies, the same shall be settled
through negotiation, conciliation or voluntary arbitration. The Same; Arbitration; The compulsory process of arbitration is a pre-
Company and the Union further agree that they will use their best condition for the filing of the complaint in court.—The compulsory
endeavor to ensure that any dispute will be discussed, resolved and process of arbitration is a pre-condition for the filing of the complaint in
settled amicably by the parties hereof within ninety (90) days from the court. Where the complaint (a) did not state that it is one of excepted
date of filing of the dispute or conflict and in case of failure to settle cases, or (b) it did not allege prior availment of said conciliation
thereof any of the parties retain their freedom to take appropriate process, or (c) did not have a certification that no conciliation had
action. (Emphasis supplied) From the foregoing, it is clear that the been reached by the parties, the case should be dismissed.
parties, in the first place, really intended to bring to conciliation or
voluntary arbitration any dispute or conflict in the interpretation or 23. RCBC Capital Corporation vs. Banco de Oro Unibank, Inc.
application of the provisions of their CBA. It is settled that when the
parties have validly agreed on a procedure for resolving grievances Alternative Dispute Resolution; A review brought to the Supreme
and to submit a dispute to voluntary arbitration then that procedure Court under the Special Alternative Dispute Resolution (ADR) Rules is
should be strictly observed. not a matter of right. Rule 19.36 of said Rules specified the conditions
for the exercise of this Court’s discretionary review of the Court of
Same; Same; Collective Bargaining Agreements; It is only in the Appeal’s decision.―At the outset, it must be stated that a review
absence of a collective bargaining agreement that parties may opt to brought to this Court under the Special ADR Rules is not a matter of
submit the dispute to either the National Labor Relations Commission right. Rule 19.36 of said Rules specified the conditions for the
(NLRC) or to voluntary arbitration.—It is only in the absence of a exercise of this Court’s discretionary review of the CA’s decision. Rule
collective bargaining agreement that parties may opt to submit the 19.36. Review discretionary.―A review by the Supreme Court is not a
dispute to either the NLRC or to voluntary arbitration. It is elementary matter of right, but of sound judicial discretion, which will be granted
only for serious and compelling reasons resulting in grave prejudice to interpretation when an arbitrator’s failure to disclose prior dealings is
the aggrieved party. The following, while neither controlling nor fully at issue.”
measuring the court’s discretion, indicate the serious and compelling,
and necessarily, restrictive nature of the grounds that will warrant the Same; Same; The plurality opinion written by Justice Black in
exercise of the Supreme Court’s discretionary powers, when the Court Commonwealth Coatings Corp. v. Continental Casualty Co., et al.,
of Appeals: a. Failed to apply the applicable standard or test for 393 U.S. 145 (1968), laid down the rule that the arbitrators must
judicial review prescribed in these Special ADR Rules in arriving at its disclose to the parties “any dealings that might create an impression
decision resulting in substantial prejudice to the aggrieved party; b. of possible bias,” and that underlying such standard is “the premise
Erred in upholding a final order or decision despite the lack of that any tribunal permitted by law to try cases and controversies not
jurisdiction of the court that rendered such final order or decision; c. only must be unbiased but also must avoid even the appearance of
Failed to apply any provision, principle, policy or rule contained in bias.”―The first case to delineate the standard of evident partiality in
these Special ADR Rules resulting in substantial prejudice to the arbitration proceedings was Commonwealth Coatings Corp. v.
aggrieved party; and d. Committed an error so egregious and harmful Continental Casualty Co., et al. decided by the US Supreme Court in
to a party as to amount to an undeniable excess of jurisdiction. The 1968. The Court therein addressed the issue of whether the
mere fact that the petitioner disagrees with the Court of Appeals’ requirement of impartiality applies to an arbitration proceeding. The
determination of questions of fact, of law or both questions of fact and plurality opinion written by Justice Black laid down the rule that the
law, shall not warrant the exercise of the Supreme Court’s arbitrators must disclose to the parties “any dealings that might create
discretionary power. The error imputed to the Court of Appeals must an impression of possible bias,” and that underlying such standard is
be grounded upon any of the above prescribed grounds for review or “the premise that any tribunal permitted by law to try cases and
be closely analogous thereto. A mere general allegation that the Court controversies not only must be unbiased but also must avoid even the
of Appeals has committed serious and substantial error or that it has appearance of bias.” In a separate concurring opinion, Justice White
acted with grave abuse of discretion resulting in substantial prejudice joined by Justice Marshall, remarked that “[t]he Court does not decide
to the petitioner without indicating with specificity the nature of such today that arbitrators are to be held to the standards of judicial
error or abuse of discretion and the serious prejudice suffered by the decorum of Article III judges, or indeed of any judges.” He opined that
petitioner on account thereof, shall constitute sufficient ground for the arbitrators should not automatically be disqualified from an arbitration
Supreme Court to dismiss outright the petition. (Emphasis supplied) proceeding because of a business relationship where both parties are
aware of the relationship in advance, or where the parties are
Same; Evident Partiality; Evident partiality in its common definition unaware of the circumstances but the relationship is trivial. However,
thus implies “the existence of signs and indications that must lead to in the event that the arbitrator has a “substantial interest” in the
an identification or inference” of partiality.―Evident partiality is not transaction at hand, such information must be disclosed.
defined in our arbitration laws. As one of the grounds for vacating an
arbitral award under the Federal Arbitration Act (FAA) in the United Same; Alternative dispute resolution methods or Alternative Dispute
States (US), the term “encompasses both an arbitrator’s explicit bias Resolution (ADRs)―like arbitration, mediation, negotiation and
toward one party and an arbitrator’s inferred bias when an arbitrator conciliation―are encouraged by this Court. By enabling parties to
fails to disclose relevant information to the parties.” Evident partiality resolve their disputes amicably, they provide solutions that are less
in its common definition thus implies “the existence of signs and time-consuming, less tedious, less confrontational, and more
indications that must lead to an identification or inference” of partiality. productive of goodwill and lasting relationship.―Alternative dispute
Despite the increasing adoption of arbitration in many jurisdictions, resolution methods or ADRs―like arbitration, mediation, negotiation
there seems to be no established standard for determining the and conciliation―are encouraged by this Court. By enabling parties to
existence of evident partiality. In the US, evident partiality “continues resolve their disputes amicably, they provide solutions that are less
to be the subject of somewhat conflicting and inconsistent judicial time-consuming, less tedious, less confrontational, and more
productive of goodwill and lasting relationship. Institutionalization of
ADR was envisioned as “an important means to achieve speedy and
impartial justice and declog court dockets.” The most important
feature of arbitration, and indeed, the key to its success, is the public’s
confidence and trust in the integrity of the process. For this reason,
the law authorizes vacating an arbitral award when there is evident
partiality in the arbitrators.

Potrebbero piacerti anche