DURATION: 47 WEEKS
PERT-CPM
Clearing
and
Grubbing
5 Electrical 44/47
5/47 13
Mobilization
and Finishing
Temporary Steel and
Form Concrete Backfill and Masonry
Facilities Excavation Works Carpentry Works Painting
Works Works Compaction Works
1 2 3 7 8 9 10 11 14 15
3/47 8/47 16/47 19/47 24/47 30/47 36/47 44/47 47/47
44/47
PREPARED BY: CHECKED AND REVIEWED BY: RECOMMENDING APPROVAL: APPROVED BY:
GENECA BACLADO MA. GLORIA G. SORRERA MELAGROS E. DELOS REYES WILFREDO G. AGUILAR
President of QBS OIC - Chief, Construction Assistant District Engineer District Engineer