PT.

INDOMINCO MANDIRI
PROJECT AND CONSTRUCTION DEPARTEMEN
Pekerjaan : POS CABIN FEEDER BREAKER PORTABLE
Lokasi : CRUSHER 3 PT. INDOMINCO MANDIRI
No. Kontrak :

MATERIAL
NO URAIAN PEKERJAAN VOL UNIT
Unit Price Unit Cost
I Pekerjaan Persiapan
1 Mobilisasi dan Demobilisasi 1.00 Ls 17,000,000.00 17,000,000.00

Sub Total
II Pekerjaan Rangka dan Dinding
1 Pek. Rangka bangunan utama pipa besi ¢ 2,5" matr. By IMM+Pengelasan 483.39 Kg 4,500.00 2,175,255.00
2 Pek. Rangka Lantai besi siku 50.50.4 + Pengelasan 48.00 Kg 18,500.00 888,000.00
3 Pek. Dinding plate besi t=1 mm + Pengelasan 165.85 Kg 18,500.00 3,068,225.00
4 Pekerjaan lantai plat kembang t = 3 mm + Pengelasan 147.19 Kg 19,000.00 2,796,610.00

Sub Total
III Pekerjaan Atap
1 Pek. Rangka atap pipa dia. 2,5" material by IMM 251.15 Kg 4,500.00 1,130,175.00
2 Pek. Gording besi hollow 40.40.2 + Pengelasan 77.26 Kg 35,000.00 2,704,100.00
3 Pek. Atap zincalum "Kencana Deck" t=0,35 mm warna biru 21.87 M2 170,000.00 3,717,900.00
4 Pek. Nok untuk jurai zincallum "Kencana Deck" t=0,35 mm warna biru 10.80 M1 65,000.00 702,000.00

Sub Total

1 / 17
PT. INDOMINCO MANDIRI
PROJECT AND CONSTRUCTION DEPARTEMEN
Pekerjaan : POS CABIN FEEDER BREAKER PORTABLE
Lokasi : CRUSHER 3 PT. INDOMINCO MANDIRI
No. Kontrak :

MATERIAL
NO URAIAN PEKERJAAN VOL UNIT
Unit Price Unit Cost
IV Pekerjaan Partisi & Plafond
1 Pekerjaan Plafond Plywood t=4mm rangka galvalum 40.40.2 6.25 M2 285,000.00 1,781,250.00
2 Pekerjaan List plafond Kayu meranti lebar = 50 mm 10.00 M1 12,500.00 125,000.00
Sub Total
V Pekerjaan Pintu dan Jendela
1 Pekerjaan Pintu P1 [ pipa Plate siku 50.50. 5 + Pengelasan, plate besi t = 2,5 mm, kaca 1.00 UNIT 7,500,000.00 7,500,000.00
polos t = 5mm, engsel bubut besi dia 1", list kaca kayu meranti 2 x 2 cm, kunci slot + level
handle " DORMA" door Closer TS77 "DORMA" sanblast + Pengecatan 1 x primer, 2x top
coat 240 micron + warna biru tua.

2 Pekerjaan Jendela J1 [ kusen besi siku 50.50.5 dan frame kaca besi siku 20x20.3, kaca 1.00 UNIT 2,500,000.00 2,500,000.00
polos t = 5mm
3 Pekerjaan Jendela J2 [ kusen besi siku 50.50.5 dan frame kaca besi siku 20x20.3, kaca 2.00 UNIT 2,750,000.00 5,500,000.00
polos t = 5mm
Sub Total
VI Pekerjaaan Kelistrikan
1 Kabel NYM 3X2.5agmm SUPREME 30.00 M1 14,500.00 435,000.00
2 Pekerjaan pemasangan AC 1/2 PK " PANASONIC" + Aksesories 1.00 Titik 150,000.00 150,000.00
3 Fitting Gantung Crome Masko + Led 14 Watt " PHILIPS " + Box galvanis 1.00 Titik 85,000.00 85,000.00
4 Pekerjaan Sakelar Ganda IB"MK" + galvanis Box 2.00 Titik 48,000.00 96,000.00

2 / 17
PT. INDOMINCO MANDIRI
PROJECT AND CONSTRUCTION DEPARTEMEN
Pekerjaan : POS CABIN FEEDER BREAKER PORTABLE
Lokasi : CRUSHER 3 PT. INDOMINCO MANDIRI
No. Kontrak :

MATERIAL
NO URAIAN PEKERJAAN VOL UNIT
Unit Price Unit Cost
5 Stop Kontak ' MK " + Box Galvanis 2.00 Titik 40,000.00 80,000.00
6 Pekerjaan Stop Kontak AC " MK " 1.00 BH 50,000.00 50,000.00
7 MCB 4A " SCHEIDER " 1.00 BH 48,000.00 48,000.00
8 MCB 6A " SCHEIDER " 1.00 BH 55,000.00 55,000.00
9 MCB 10A " SCHEIDER " 1.00 BH 80,000.00 80,000.00
10 MCB 16A " SCHEIDER " 2.00 BH 125,000.00 250,000.00
11 Pekerjaan Penarikan Kabel Power
Kabel Power 4 x 16 sqm NYFGBY 100.00 M1 75,000.00 7,500,000.00
galiaan tanah 3.84 M3 0.00 0.00
Pasir 1.92 M3 180,000.00 345,600.00
Urugan Tanah + Pemadatan 80.00 M1 5,000.00 400,000.00
Papan Penutup Kabel 0.50 M3 7,500,000.00 3,750,000.00

Sub Total
VII Pekerjaan Pengecatan
1 Pek. Brushing + Pengecatan 1 x Cat primer, 2 x Top Coat T = 240 Micron " Jotun Warna Biru 35.95 M2 45,000.00 1,617,750.00
Tua
2 Pek. Pengecatan Plafond 2 x Cat alkyd " AVIAN " warna putih 6.95 M2 22,000.00 152,900.00
Sub Total

3 / 17
PT. INDOMINCO MANDIRI
PROJECT AND CONSTRUCTION DEPARTEMEN
Pekerjaan : POS CABIN FEEDER BREAKER PORTABLE
Lokasi : CRUSHER 3 PT. INDOMINCO MANDIRI
No. Kontrak :

MATERIAL
NO URAIAN PEKERJAAN VOL UNIT
Unit Price Unit Cost
VIII Pekerjaan Emergency Shower
1 Pekerjaan pembuatan Lantai Konkrite Emergency Shower
- Wiremesh M6 1 Layer 2.25 M2 55,000.00 123,750.00
- Konkrite tebal 7 Cm K - 175 0.16 M3 1,250,000.00 200,000.00
2 Emeggency Shower and eye Face wash " HAWS" 8300-8309 1.00 Unit 6,500,000.00 6,500,000.00
3 Instalasi Air Bersih
- Pipa HDPE DN 32 mm DN 16 100.00 M1 110,000.00 11,000,000.00
- Gate Valve Sankyo SS 1" 1.00 Bh 150,000.00 150,000.00
- Clam Saddle DN 90 MM x 32 MM 1.00 Bh 450,000.00 450,000.00
- MTA DN 32 MM 2.00 Bh 450,000.00 900,000.00
- Pipa PVC AW 1/2" Maspion 4.00 Btg 35,000.00 140,000.00
- Copler HDPE DN 32 MM 2.00 Bh 550,000.00 1,100,000.00

Sub Total

A Total
B PPN 10%
C Grand Total

4 / 17
PT. INDOMINCO MANDIRI
PROJECT AND CONSTRUCTION DEPARTEMEN
Pekerjaan : POS CABIN FEEDER BREAKER PORTABLE
Lokasi : CRUSHER 3 PT. INDOMINCO MANDIRI
No. Kontrak :

MATERIAL
NO URAIAN PEKERJAAN VOL UNIT
Unit Price Unit Cost
D Pembulatan

5 / 17
PROJECT AND CONSTRUCTION DEPARTEMEN

LABOUR/ALAT TOTAL
Unit Price Unit Cost COST

0.00 0.00 17,000,000.00

17,000,000.00

6,500.00 3,142,035.00 5,317,290.00


6,500.00 312,000.00 1,200,000.00
6,500.00 1,078,025.00 4,146,250.00
6,500.00 956,735.00 3,753,345.00

14,416,885.00

6,500.00 1,632,475.00 2,762,650.00


18,000.00 1,390,680.00 4,094,780.00
25,000.00 546,750.00 4,264,650.00
18,000.00 194,400.00 896,400.00

12,018,480.00

6 / 17
PROJECT AND CONSTRUCTION DEPARTEMEN

LABOUR/ALAT TOTAL
Unit Price Unit Cost COST

45,000.00 281,250.00 2,062,500.00


1,000.00 10,000.00 135,000.00
2,197,500.00

450,000.00 450,000.00 7,950,000.00

150,000.00 150,000.00 2,650,000.00

175,000.00 350,000.00 5,850,000.00

16,450,000.00

35,000.00 1,050,000.00 1,485,000.00


250,000.00 250,000.00 400,000.00
15,000.00 15,000.00 100,000.00
15,000.00 30,000.00 126,000.00

7 / 17
PROJECT AND CONSTRUCTION DEPARTEMEN

LABOUR/ALAT TOTAL
Unit Price Unit Cost COST

50,000.00 100,000.00 180,000.00


50,000.00 50,000.00 100,000.00
15,000.00 15,000.00 63,000.00
15,000.00 15,000.00 70,000.00
15,000.00 15,000.00 95,000.00
20,000.00 40,000.00 290,000.00

8,000.00 800,000.00 8,300,000.00


100,000.00 384,000.00 384,000.00
45,000.00 86,400.00 432,000.00
5,000.00 400,000.00 800,000.00
150,000.00 75,000.00 3,825,000.00

16,650,000.00

24,000.00 862,800.00 2,480,550.00

12,500.00 86,875.00 239,775.00


2,720,325.00

8 / 17
PROJECT AND CONSTRUCTION DEPARTEMEN

LABOUR/ALAT TOTAL
Unit Price Unit Cost COST

15,000.00 33,750.00 157,500.00


300,000.00 48,000.00 248,000.00
850,000.00 850,000.00 7,350,000.00

35,000.00 3,500,000.00 14,500,000.00


20,000.00 20,000.00 170,000.00
100,000.00 100,000.00 550,000.00
100,000.00 200,000.00 1,100,000.00
15,000.00 60,000.00 200,000.00
100,000.00 200,000.00 1,300,000.00

25,575,500.00

107,028,690.00
10,702,869.00
117,731,559.00

9 / 17
PROJECT AND CONSTRUCTION DEPARTEMEN

LABOUR/ALAT TOTAL
Unit Price Unit Cost COST

117,732,000.00

10 / 17
SKEDUL PELAKSANAAN
PEKERJAAN : RELOKASI CABIN FEEDER BREAKER CPP3
SCHEDULE PELAKSANAAN : 60 ( Enam Puluh ) HARI KALENDER
LOCATION : Crusher 3 PT. Indominco Mandiri
PENAWAR : CV. BUANA PRIMA

BOBOT MINGGU KE -
NO URAIAN PEKERJAAN
(%) I II III IV

1 Pekerjaan Persiapan 15.8836 1.9854 1.9854 1.9854 1.9854

2 Pekerjaan Rangka dan Dinding 13.4701 6.7351 6.7351

3 Pekerjaan Atap 11.2292

4 Pekerjaan Partisi & Plafond 2.0532 2.0532

5 Pekerjaan Pintu dan Jendela 15.3697 7.6849

6 Pekerjaaan Kelistrikan 15.5566

7 Pekerjaan Pengecatan 2.5417


8 Pekerjaan Emergency Shower 23.8959 4.7792

TOTAL 100.000

RENCANA KEMAJUAN MINGGUAN 8.72 8.72 4.04 14.45


RENCANA KOMULATIF KEMAJUAN MINGGUAN 8.72 17.44 21.48 35.93
DEVIASI 0.00 0.00 0.00 0.00
AKTUAL MINGGUAN 0.00 0.00 0.00 0.00
KOMULATIF AKTUAL KEMAJUAN 0.00 0.00 0.00 0.00
JUMLAH TENAGA KERJA 6.00 6.00 6.00 6.00
BONTANG, 02 November 2015
ELAKSANAAN CV. BUANA PRIMA

Darnaningsih / Direktris
MINGGU KE -
REMARKS
V VI VII VIII

1.9854 1.9854 1.9854 1.9854 100.00%

5.6146 5.6146

50.00%
7.6849

7.7783 7.7783

1.2708 1.2708

0.00%
4.7792 4.7792 4.7792 4.7792
0.00%

27.84 20.16 8.04 8.04 %


63.77 83.93 91.96 100.00 %
0.00 0.00 0.00 0.00 %
0.00 0.00 0.00 0.00 %
0.00 0.00 0.00 0.00 %
6.00 6.00 6.00 6.00 ORANG
STRUKTUR PERUSAHAAN
CV. BERTIO INDAH

DIREKTUR
Drs. Jonny Sinaga

Site Manager
Drs. Jonny Sinaga

Tk. Kayu Tk. Batu

Pembantu Tukang Pembantu Tukang Pembantu Tukang Pembantu Tukang

Bontang, 24 Juni 2015


CV. Bertio Indah

Drs. Jonny Sinaga


Direktur
METODE PELAKSANAAN

- Pekerjaan Persiapan
Meliputi pekerjaan mobilisasi material ke lokasi proyek dan alat - alat kerja
- Pekerjaan Bouplank
melaksanakan pengukuran dan elevasi proyek yang akan dikerjakan
- Pekerjaan Galiaan
Galiaan Pondasi sesuai dengan gambar kerja
- Pekerjaan Pondasi
Pemasangan batu gunung untuk pondasi bangunan
- Pekerjaan Beton
Pekerjaan beton yang meliputi Pekerjaan Sloof, Kolom Ring Balk dan pembesiaannya
beserta pemasangan bagesting
- Pekerjaan Dinding
Pemasangan batu bata untuk dinding bangunaan yang meliputi plesteran dinding dan acian
dinding. Untuk pekerjaan ini harus dilaksanakan rapi sehingga pada waktu pengecatan
dinding tersebut nampak mulus dan rapi. Sebelum pekerjaan plesteran kanopi sudah selesai
dikerjakan.
- Pekerjaan Atap
Pekerjaan Meliputi Pemasangan rangka kuda - kuda, gording dan atap
- Pekerjaan Pintu dan Jendela
Pemasangan Pintu dan jendela harus diukur agar tampak rapi.
- Pekerjaan Kelistrikan
setelah pekerjaan rangka plafond dilaksanakan, maka dilanjutkan dengan pemasangan
instalasi listrik dan telepon
- Pekerjaan Sanita Air
pekerjaan yang meliputi Pemasangan saluran air kotor dan air bersih dan pekerjaan Septi Tank.
- Pekerjaan Bongkaran Bangunan Lama
Pekerjaan ini dilaksanakan bersamaan dengan pelaksanaan pekerjaan septi tank.
- Pekerjaan Pasang Lantai
Pekerjaan meliputi Pemasangan Keramik
- Pekerjaan Pengecatan
Pekerjaan Pengecatan bangunan
- Pekerjaan Finishing
Pekerjaan Perapiaan bagunan dan pembersihan Proyek.