LEMBAR ISIAN

1 KEGIATAN
PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN
LOKASI : RT 006
DESA : DESA LATTA
TAHUN ANGGARAN : 2019
2 PELAKSANA
DIBUAT : J NITALESSY
JABATAN : KAUR PERENCANAAN
DISETUJUI : L.H. SOPAMENA, S.STP, MT
JABATAN : PENJABAT KEPALA DESA
NIP : 19820126200112 1 004
DIVERIFIKASI : V PATTY
JABATAN : SEKERTARIS DESA
ALUR BAHAN DAN UPAH

HARGA PPN PPh 22 PPh 21


No. KEBUTUHAN UPAH/BAHAN SAT
DASAR 10% 1.50% 2.50%
1 2 3 4 5 6 7
A UPAH
1 Mandor HOK 191,100.00 4,900.00
2 Kepala Tukang HOK 166,725.00 4,275.00
3 Tukang Batu HOK 141,375.00 3,625.00
4 Tukang Kayu HOK 141,375.00 3,625.00
5 Tukang Besi HOK 141,375.00 3,625.00
6 Tukang Cat HOK 141,375.00 3,625.00
7 Tukang Listrik HOK 141,375.00 3,625.00
8 Pekerja HOK 73,125.00 1,875.00
8 Upah Pembersihan Awal HOK 731,250.00 18,750.00
9 Upah Pembersihan Akhir HOK 487,500.00 12,500.00

B BAHAN
1 Kayu Klas I M3 7,000,000.00 700,000.00 105,000.00
2 Kayu 15 x 15-4M M' 100,800.00 10,080.00 2,362.50
3 Alat Bantu Pancang Set 100,000.00 10,000.00
4 Kayu 15 x 15-750 M M3 100,800.00 10,080.00 2,362.50
5 Kayu 20 x 20-1000 cm M3 280,000.00 28,000.00 4,200.00
6 Kayu Klas II M3 2,800,000.00 280,000.00 42,000.00
7 Papan Kayu Kls I M3 7,000,000.00 700,000.00 105,000.00
8 Papan Kayu Kls III M3 1,750,000.00 175,000.00 26,250.00
9 Batu Kerikil Pecah ( 3 / 2 cm ) M3 235,000.00 23,500.00 3,525.00
9 Pasir Pasang M3 200,000.00 20,000.00 3,000.00
10 Pasir Urug M3 140,000.00 14,000.00 2,100.00
11 Pasir Beton Kg 127.27 12.73 1.91
12 Batu Krikil (Kg) Kg 195.83 19.58 2.94
13 Batu Kali M3 178,000.00 17,800.00 2,670.00
14 Batako Bh 2,500.00 250.00 37.50
15 Semen PC (Zak) Sak 65,000.00 6,500.00 975.00
16 Semen PC (Kg) Kg 1,300.00 130.00 19.50
17 Sement Warna Kg 1,800.00 180.00 27.00
18 Air Liter 500.00 7.50
19 Besi Dia 16 mm Standart Staff 246,480.00 24,648.00 3,697.20
20 Besi Dia 12 mm Standart Staff 138,528.00 13,852.80 2,077.92
21 Besi Dia 10 mm Standart Staff 96,252.00 9,625.20 1,443.78
22 Besi Dia 6 mm Standart Staff 61,620.00 6,162.00 924.30
HARGA PPN PPh 22 PPh 21
No. KEBUTUHAN UPAH/BAHAN SAT
DASAR 10% 1.50% 2.50%
1 2 3 4 5 6 7
23 Dolken Kayu Galam Batang 20,000.00 2,000.00 300.00
24 Besi Strip Kg 5,000.00 500.00 75.00
25 Minyak Bakesting Liter 5,000.00 500.00 75.00
26 Paku / Skrup Genteng Kg 22,500.00 2,250.00 337.50
27 Paku Campuran Kg 19,000.00 1,900.00 285.00
28 Play Wood 3 mm uk. 120 x 240 cm Lbr 126,000.00 12,600.00 1,890.00
29 Cat Meni Besi Kg 30,000.00 3,000.00 450.00
30 Cat Kayu Kg 57,000.00 5,700.00 855.00
31 Plamir Kg 16,000.00 1,600.00 240.00
32 Politur Liter 25,000.00 2,500.00 375.00
33 Menie Kayu Kg 30,000.00 3,000.00 450.00
34 Dumpul Kayu Kg 15,000.00 1,500.00 225.00
35 Politur Kg 10,000.00 1,000.00 150.00
36 Politur Jadi Kg 25,000.00 2,500.00 375.00
37 Amplas Kg 25,000.00 2,500.00 375.00
38 Gloteks Kg 10,000.00 1,000.00 150.00
39 MCB 60 AMP Bh 210,000.00 21,000.00 3,150.00
40 Kabel NYM 3 x 2.5 mm M 15,000.00 1,500.00 225.00
41 Pipa PVC dia. 3" M' 22,000.00 2,200.00 330.00
42 Pipa PVC dia. 2" M' 12,000.00 1,200.00 180.00
43 Kran Air 3/4 Bh 35,000.00 3,500.00 525.00
44 Kran Air 1/2 Bh 35,000.00 3,500.00 525.00
45 Seal Tape Set 8,000.00 800.00 120.00
46 Floordrain (metal) Set 37,000.00 3,700.00 555.00
47 Wastafel lengkap Bh 544,000.00 54,400.00 8,160.00
48 Paving Block Bh 15,000.00 1,500.00 225.00
49 Sekring Bh 70,000.00 7,000.00 1,050.00
50 Kabel NYY 3x2,5 M' 15,000.00 1,500.00 225.00
51 Benang Roll 5,000.00 500.00 75.00
52 Titik Lampu Titik 75,000.00 7,500.00 1,125.00
53 Lem Kayu Kg 7,500.00 750.00 112.50
54 Pipa PVC Conduit M' 3,750.00 375.00 56.25
55 Lampu TL 20 Watt Bh 78,000.00 7,800.00 1,170.00
56 Lampu pijar philips putih 18 watt Bh 47,500.00 4,750.00 712.50
57 Lampu pijar philips putih 23 watt Bh 60,000.00 6,000.00 900.00
58 Lampu PL 11 Watt Bh 78,000.00 7,800.00 1,170.00
59 Saklar tunggal Bh 18,000.00 1,800.00 270.00
60 Saklar ganda Bh 25,000.00 2,500.00 375.00
61 Stop kontak Bh 23,000.00 2,300.00 345.00
62 Kabel NYY 3 Phase M' 15,000.00 1,500.00 225.00
63 Fiting Tempel Bh 15,000.00 1,500.00 225.00
64 T Dooz Bh 6,500.00 650.00 97.50
65 Isolator Bh 15,000.00 1,500.00 225.00
66 Lasdop Bh 5,000.00 500.00 75.00
67 Pipa Gip Medium A 2 Inci M' 95,833.33 9,583.33 1,437.50
68 Perlengkapan Pipa Galvanis 2 Inci Bh 50,000.00 5,000.00 750.00
69 Pipa Galvanis Medium A 1 1/2 Inci M' 77,500.00 7,750.00 1,162.50
70 Perlengkapan Pipa Galvanis 1 1/2 Inci Bh 30,000.00 3,000.00 450.00
71 Mangkok Listrik Bh 50,000.00 5,000.00 750.00
72 L.Bow Bh 2,500.00 250.00 37.50
73 Klem Pipa Bh 1,000.00 100.00 15.00
BAHAN DAN UPAH

ONGKOS ANGKUT ONGKOS PIKUL


HARGA SATUAN
8 9 10

- - 196,000.00
- - 171,000.00
- - 145,000.00
- - 145,000.00
- - 145,000.00
- - 145,000.00
- - 145,000.00
- - 75,000.00
- - 750,000.00
- - 500,000.00

75,000.00 75,000.00 7,955,000.00


1,687.50 1,687.50 116,700.00
110,000.00
1,687.50 1,687.50 116,700.00
3,000.00 3,000.00 318,200.00
19,250.00 3,141,300.00
75,000.00 75,000.00 7,955,000.00
75,000.00 75,000.00 2,101,300.00
75,000.00 100,000.00 437,100.00
75,000.00 100,000.00 398,000.00
75,000.00 100,000.00 331,100.00
64.55 90.91 300.00
56.40 83.33 400.00
75,000.00 100,000.00 373,500.00
200.00 3,000.00
1,500.00 2,000.00 76,000.00
30.00 40.00 1,600.00
2,100.00
600.00
1,000.00 1,000.00 276,900.00
1,000.00 1,000.00 156,500.00
1,000.00 1,000.00 109,400.00
1,000.00 1,000.00 70,800.00
ONGKOS ANGKUT ONGKOS PIKUL
HARGA SATUAN
8 9 10
22,300.00
5,600.00
5,600.00
25,100.00
21,200.00
140,500.00
33,500.00
63,600.00
17,900.00
27,900.00
33,500.00
16,800.00
11,200.00
27,900.00
27,900.00
11,200.00
234,200.00
16,800.00
24,600.00
13,400.00
39,100.00
39,100.00
9,000.00
41,300.00
606,600.00
16,800.00
78,100.00
16,800.00
5,600.00
83,700.00
8,400.00
4,200.00
87,000.00
53,000.00
66,900.00
87,000.00
20,100.00
27,900.00
25,700.00
16,800.00
16,800.00
7,300.00
16,800.00
5,600.00
20,000.00 126,900.00
55,800.00
18,000.00 104,500.00
33,500.00
55,800.00
2,800.00
1,200.00
REKAPITULASI

PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN


LOKASI : RT 006
DESA : DESA LATTA
TAHUN ANGGARAN : 2019

No. URAIAN PEKERJAAN

A PEKERJAAN PERSIAPAN

B REHAB JALAN SETAPAK DAN PENERANGAN JALAN

C PEKERJAAN PENERANGAN JALAN

D ALAT

E HONOR

F PEKERJAAN AKHIR

NILAI KONSTRUKSI
JUMLAH NILAI KONSTRUKSI
DIBULATKAN

TERBILANG : Dua Puluh Tiga Juta Delapan Ratus Enam Puluh Lima Ribu Rupiah

DISETUJUI OLEH DIVERIFIKASI OLEH


PENJABAT KEPALA DESA SEKERTARIS DESA

L.H. SOPAMENA, S.STP, MT V PATTY


NIP .19820126200112 1 004
REKAPITULASI

JUMLAH HARGA
(Rp.)

1,750,000.00

5,555,591.66

14,229,493.74

880,000.00

1,450,000.00

23,865,085.40
23,865,085.40
23,865,000.00

a Juta Delapan Ratus Enam Puluh Lima Ribu Rupiah

DIBUAT OLEH
KAUR PERENCANAAN

J NITALESSY
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN


LOKASI : RT 006
DESA : DESA LATTA
TAHUN ANGGARAN : 2019

NO. JENIS PEKERJAAN SATUAN VOLUME

A PEKERJAAN PERSIAPAN
1 Pembersihan Awal Ls 1.00
2 Papan Nama Kegiatan Ls 1.00
3 Biaya Perencanaan Ls 1.00

B REHAB JALAN SETAPAK DAN PENERANGAN JALAN


1 Plesteran M2 11.09
2 Rabat Beton M3 3.52

C PEKERJAAN PENERANGAN JALAN


I PEMASANGAN TIANG LAMPU JALAN
1 Galian Pondasi Umpak M3 0.54
2 Pondasi Umpak Beton K-100 M3 0.54
3 Pemasangan Tiang Lampu PIPA GIP dia. 1.50" Medium A Staff 15.00
4 Pengecatan Tiang Lampu Jalan m2 15.00

II PEMASANGAN LAMPU DAN ACSESORIS


1 LAMPU BH 15.00
2 SAKLAR BH 15.00
4 KABEL NYY M' 75.00

JUMLAH C =
D ALAT
1 Skop Bh 2.00
2 Benang Tukang Tukal 5.00
3 Gerobak Dorong Bh 1.00
4 Martil Bh 2.00
5 Ember Cor Bh 4.00

E HONOR
1 Insentif TPK Ls -

F PEMBERSIHAN AKHIR
1 Pemasangan Prasasti Ls 1.00
2 Pembersihan Akhir Ls 1.00
4 Administrasi + Dokumentasi Ls 1.00
ANGGARAN BIAYA (RAB)

HARGA JUMLAH HARGA


SATUAN
(Rp.) (Rp.)

750,000.00 750,000.00
250,000.00 250,000.00
750,000.00 750,000.00
Jumlah 1,750,000.00

69,291.00 768,298.61
1,360,181.00 4,787,293.05
Jumlah 5,555,591.66

61,150.00 33,021.00
1,360,181.00 734,497.74
561,808.00 8,427,120.00
31,307.00 469,605.00
Jumlah 9,664,243.74

119,950.00 1,799,250.00
64,150.00 962,250.00
24,050.00 1,803,750.00
Jumlah 4,565,250.00
JUMLAH C = I + II 14,229,493.74

85,000.00 170,000.00
10,000.00 50,000.00
500,000.00 500,000.00
50,000.00 100,000.00
15,000.00 60,000.00
Jumlah 880,000.00

650,000.00 -
Jumlah -

450,000.00 450,000.00
500,000.00 500,000.00
500,000.00 500,000.00
Jumlah 1,450,000.00
RINCIAN ANGGARAN BIAYA

PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN


LOKASI : RT 006
DESA : DESA LATTA
TAHUN ANGGARAN : 2019

HARGA
NO. URAIAN SATUAN (Rp.)

A UPAH
1 Mandor OH 196,000.00
2 Kepala Tukang OH 171,000.00
3 Tukang Batu OH 145,000.00
4 Tukang Kayu OH 145,000.00
6 Tukang Listrik OH 145,000.00
5 Pekerja OH 75,000.00
6 Upah Pembersihan Awal OH 750,000.00
7 Upah Pembersihan Akhir OH 500,000.00
T
B BAHAN
2 Batu Kerikil Pecah ( 3 / 2 cm ) M3 437,100.00
3 Batu Krikil (Kg) Kg 400.00
4 Pasir Pasang M3 398,000.00
5 Pasir Beton Kg 300.00
6 Pasir Urug M3 331,100.00
7 Batu Kali M3 373,500.00
8 Semen PC (Kg) Kg 1,600.00
9 Air Kg 600.00
10 Cat Kayu Kg 63,600.00
11 Menie Kayu Kg 33,500.00
13 Kayu Klas II M3 3,141,300.00
17 Kabel NYY 3x2,5 M' 16,800.00
18 Lampu pijar philips putih 23 watt Bh 66,900.00
19 Saklar tunggal Bh 20,100.00
20 Saklar ganda Bh 27,900.00
21 Stop kontak Bh 25,700.00
22 Fiting Tempel Bh 16,800.00
23 Pipa Gip Medium A 2 Inci m' 126,900.00
T
C ALAT
1 Skop Bh 85,000.00
2 Benang Tukang Tukal 10,000.00
3 Gerobak Dorong Bh 500,000.00
4 Martil Bh 50,000.00
5 Ember Cor Bh 15,000.00
TO
D BIAYA UMUM
1 Papan Nama Proyek Bh 250,000.00
2 Prasasti Bh 450,000.00
3 Insentif TPK Ls 650,000.00
4 Administrasi + Dokumentasi Ls 500,000.00
5 Gambar kerja Ls 750,000.00
TO
GRAND
RINCIAN ANGGARAN BIAYA

JUMLAH
VOLUME (Rp.)

0.60 117,600.00
0.60 102,600.00
3.80 551,000.00
1.10 159,500.00
11.30 1,638,500.00
12.70 952,500.00
1.00 750,000.00
1.00 500,000.00
TOTAL I 4,771,700.00
- -
- -
4,055.50 1,622,200.00
0.30 119,400.00
3,527.80 1,058,340.00
- -
- -
1,071.90 1,715,040.00
811.90 487,140.00
3.90 248,040.00
3.00 100,500.00
- -
75.00 1,260,000.00
15.00 1,003,500.00
- -
15.00 418,500.00
- -
15.00 252,000.00
63.00 7,994,700.00
TOTAL II 16,279,360.00
- -
2.00 170,000.00
5.00 50,000.00
1.00 500,000.00
2.00 100,000.00
4.00 60,000.00
TOTAL III 880,000.00
- -
1.00 250,000.00
1.00 450,000.00
- -
1.00 500,000.00
1.00 750,000.00
TOTAL IV 1,950,000.00
GRAND TOTAL 23,881,060.00
ANALISA HARGA SATUAN-SNI 2016

HARGA SATUAN
No. Uraian Kegiatan
(Rp.)

A.2.3.1.1. Penggalian 1M³ Tanah biasa sedalam 1 m


0.750 OH Pekerja 75,000.00
0.025 OH Mandor 196,000.00
A.2.3.1.9. Pengurungan kembali 1 M³ galian tanah
0.500 OH Pekerja 75,000.00
0.050 OH Mandor 196,000.00
A.2.3.1.11. Pengurungan 1M³ dengan pasir urug
0.300 OH Pekerja 75,000.00
0.010 OH Mandor 196,000.00
1.200 M3 Pasir urug 331,100.00
A.3.2.1.9. Pemasangan 1M³ batu kosong ( anstamping )
0.780 OH Pekerja 75,000.00
0.390 OH Tukang batu 145,000.00
0.039 OH Kepala tukang 171,000.00
0.039 OH Mandor 196,000.00
1.200 M3 Batu Kali 373,500.00
0.432 M3 Pasir urug 331,100.00
A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 4 PP
1.500 OH Pekerja 75,000.00
0.750 OH Tukang batu 145,000.00
0.075 OH Kepala tukang 171,000.00
0.075 OH Mandor 196,000.00
1.200 M3 Batu Kali 373,500.00
163.000 Kg Semen PC 1,600.00
0.520 M3 Pasir pasang 398,000.00
Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100)
1.650 OH Pekerja 75,000.00
0.275 OH Tukang batu 145,000.00
0.028 OH Kepala tukang 171,000.00
0.083 OH Mandor 196,000.00
247.000 Kg Semen PC 1,600.00
869.000 Kg Pasir Pasang 300.00
999.00 Kg Batu Kerikil 400.00
200.000 Liter Air 600.00
A.4.4.2.4. Pemasangan 1 m2 plesteran 1 SP : 4 PP, tebal 15 mm
0.300 OH Pekerja 75,000.00
0.150 OH Tukang batu 145,000.00
0.015 OH Kepala tukang 171,000.00
0.015 OH Mandor 196,000.00
6.240 Kg Semen PC 1,600.00
0.024 M3 Pasir pasang 398,000.00
Pemasangan 1 M' pipa Galvanis Medium A Ø 2"
0.081 OH Pekerja 75,000.00
0.135 OH Tukang Batu 145,000.00
0.014 OH Kepala Tukang 171,000.00
0.004 OH Mandor 196,000.00
4.200 Staff Pipa Gip Medium A 2 Inci 126,900.00
Pengecetan bidang Besi Baru ( 1 lapisan cat dasar, 2 lapisan cat penutup)
0.070 OH Pekerja 75,000.00
0.009 OH Tukang Batu 145,000.00
0.006 OH Kepala Tukang 171,000.00
0.003 OH Mandor 196,000.00
0.200 Kg Cat Menie Besi 33,500.00
0.260 Kg Cat Besi 63,600.00
HARGA SATUAN
No. Uraian Kegiatan
(Rp.)

PASANG LAMPU PIJAR PHILIPS 23 WATT


0.250 Ls Tukang Listrik 145,000.00
1.000 Bh Fiting Tempel 16,800.00
1.000 Bh Lampu pijar philips putih 23 watt 66,900.00
PASANG STOP KONTAK
0.250 Ls Tukang Listrik 145,000.00
1.000 Bh Stop kontak 25,700.00
PASANG SAKLAR TUNGGAL
0.250 Ls Tukang Listrik 145,000.00
1.000 Bh Saklar tunggal 20,100.00
PASANG SAKLAR GANDA
0.250 Ls Tukang Listrik 145,000.00
1.000 Bh Saklar ganda 27,900.00
PASANG VITTING
0.250 Ls Tukang Listrik 145,000.00
1.000 Bh Fiting Tempel 16,800.00
PASANG KABEL NYY
0.050 Ls Tukang Listrik 145,000.00
1.000 M Kabel NYY 3x2,5 16,800.00
PERALATAN DAN LAIN-LAIN
1.000 Bh Pakuel 90,000.00
1.000 Bh Skop 85,000.00
1.000 Tukal Benang Tukang 10,000.00
1.000 Bh Gerobak Dorong 500,000.00
1.000 Bh Martil 50,000.00
1.000 M' Selang 15,000.00
1.000 Bh Ember Cor 15,000.00
1.000 M' Gergaji 50,000.00

1.000 Bh Papan Nama Proyek 250,000.00


1.000 Bh Prasasti 450,000.00
1.000 Ls Insentif Pekerja 650,000.00
1.000 Ls Biaya Pmbersihan Awal 750,000.00
1.000 Ls Biaya Pembersihan Akhir 500,000.00
1.000 Ls Administrasi + Dokumentasi 500,000.00
1.000 Ls Biaya Perencanaan 750,000.00
HARGA SATUAN-SNI 2016

JUMLAH
(Rp.)

61,150.00
56,250.00
4,900.00
47,300.00
37,500.00
9,800.00
421,780.00
22,500.00
1,960.00
397,320.00
720,598.20
58,500.00
56,550.00
6,669.00
7,644.00
448,200.00
143,035.20
1,164,735.00
112,500.00
108,750.00
12,825.00
14,700.00
448,200.00
260,800.00
206,960.00
1,360,181.00
123,750.00
39,875.00
4,788.00
16,268.00
395,200.00
260,700.00
399,600.00
120,000.00
69,291.00
22,500.00
21,750.00
2,565.00
2,940.00
9,984.00
9,552.00
561,808.00
6,075.00
19,575.00
2,394.00
784.00
532,980.00
31,307.00
5,250.00
1,305.00
1,026.00
490.00
6,700.00
16,536.00
JUMLAH
(Rp.)

119,950.00
36,250.00
16,800.00
66,900.00
61,950.00
36,250.00
25,700.00
56,350.00
36,250.00
20,100.00
64,150.00
36,250.00
27,900.00
53,050.00
36,250.00
16,800.00
24,050.00
7,250.00
16,800.00

90,000.00
85,000.00
10,000.00
500,000.00
50,000.00
15,000.00
15,000.00
50,000.00

250,000.00
450,000.00
650,000.00
750,000.00
500,000.00
500,000.00
750,000.00
DAFTAR UPAH DAN HARGA BAHAN

PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN


LOKASI : RT 006
DESA : DESA LATTA
TAHUN ANGGARAN : 2019

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A UPAH
1 Mandor OH 196,000.00
2 Kepala Tukang OH 171,000.00
3 Tukang Batu OH 145,000.00
4 Tukang Kayu OH 145,000.00
5 Tukang Besi OH 145,000.00
6 Tukang Cat OH 145,000.00
7 Tukang Listrik OH 145,000.00
8 Pekerja OH 75,000.00
8 Upah Pembersihan Awal Ls 750,000.00
9 Upah Pembersihan Akhir Ls 500,000.00
B BAHAN
1 Kayu Klas I M3 7,955,000.00
2 Kayu Klas II M3 3,141,300.00
3 Papan Kayu Kls I M3 7,955,000.00
4 Papan Kayu Kls III M3 2,101,300.00
5 Pasir Urug M3 331,100.00
6 Batu Kerikil Pecah ( 3 / 2 cm ) M3 437,100.00
7 Pasir Pasang M3 398,000.00
8 Batu Kali M3 373,500.00
9 Pasir Beton Kg 300.00
10 Batu Krikil (Kg) Kg 400.00
11 Semen PC (Zak) Sak 76,000.00
12 Semen PC (Kg) Kg 1,600.00
13 Cat Meni Besi Kg 33,500.00
14 Cat Kayu Kg 63,600.00
15 Plamir Kg 17,900.00
16 Politur Kg 27,900.00
17 Menie Kayu Kg 33,500.00
18 Dumpul Kayu Kg 16,800.00
19 Air Kg 600.00
20 Sekring Bh 78,100.00
21 Kabel NYY 3x2,5 M' 16,800.00
22 Benang Roll 5,600.00
23 Titik Lampu Titik 83,700.00
24 Lem Kayu Kg 8,400.00
25 Pipa PVC Conduit M' 4,200.00
26 Lampu TL 20 Watt Bh 87,000.00
27 Lampu pijar philips putih 18 watt Bh 53,000.00
28 Lampu pijar philips putih 23 watt Bh 66,900.00
29 Lampu PL 11 Watt Bh 87,000.00
30 Saklar tunggal Bh 20,100.00
31 Saklar ganda Bh 27,900.00
32 Stop kontak Bh 25,700.00
33 Kabel NYY 3 Phase M' 16,800.00
34 Fiting Tempel Bh 16,800.00
35 Pipa Gip Medium A 2 Inci m' 126,900.00
36 Perlengkapan Pipa Galvanis 2 Inci m' 55,800.00
37 Pipa Galvanis Medium A 1 1/2 Inci m' 104,500.00
38 Perlengkapan Pipa Galvanis 1 1/2 Inci m' 33,500.00

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
7 Ember Cor Bh 15,000.00
8 Gergaji Bh 50,000.00
D BIAYA UMUM
1 Papan Nama Proyek Bh 250,000.00
2 Prasasti Bh 450,000.00
3 Biaya Pembersihan Awal Ls 750,000.00
4 Biaya Pembersihan Akhir Ls 500,000.00
3 Insentif TPK Ls 650,000.00
4 Administrasi + Dokumentasi Ls 500,000.00
5 Gambar kerja Ls 750,000.00
PERHITUNGAN VOLUME PEKERJAAN JALAN RABAT
PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN
LOKASI : RT 006
DESA : DESA LATTA

No. Lokasi / Lebar Perhitungan Dimensi Luas


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (M) ( M2 )

PANJANG Jalan Setapak


1 Anak Tangga RT 006
n = 22 BH
P = 1.2 M
l = 0.45 M
t = 0.24 M
6 Jalan Rabat
P = 32 m
L = 1.2 m
t = 0.07 m
A RABAT BETON K-100
1 anak Tangga
N L T p p x l x t X N
0.07 22 0.45 0.07 1.2 1.2 X 0.45 X 0.07 X 22 0.8316
0.45

Jumlah Anak Tangga

2 Jalan Rabat

0.07 1.20 0.07 32.00 1.20 x 0.07 x 32.00 0.084


1.20

Total
B Plesteran Anak Tangga
bagian T x l x x bh
i 1 0.24 x 2.10 x x 22
ii 2 0.00 x 0.00 x x 0
iii 3 0.00 x 0.00 x x 0

Total Plesteran
ME PEKERJAAN JALAN RABAT

Volume
( M3 )

0.832

2.69

3.520

11.088
0
0

11.088
PERHITUNGAN VOLUME PEKERJAAN LAM
PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN
LOKASI : RT 006
DESA : DESA LATTA

No. Lokasi / Lebar


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah

LAMPU JALAN
1 TITIK LAMPU
n = 15 BH
T = 4 M
2 PONDASI UMPAK
n = 15 BH
P = 0.3 M
l = 0.3 M
t = 0.4 M
3 ACSESORIS
n = 15 BH
Cok =
Kabel =
Lampu =

01. GALIAN TANAH

Galian Tanah Untuk Pondasi Jalan Setapak

N L T p
15 0.3 0.40 0.30

06. PONDASI TIANG LAMPU

Pondasi Umpak Beton K-100


N L T p
15 0.30 0.40 0.30

0.4

0.30

06. TIANG LAMPU

TIANG LAMPU
N L T
15 1.00 4.00

1.00
06. PENGECATAN TIANG LAMPU

PENGECATAN
N D T p
15 0.25 4.00 0.0

0.25
JAAN LAMPU JALAN

Perhitungan Dimensi Luas Volume


(M) ( M2 ) ( M3 )

p x l x t X N
0.3 X 0.3 X 0.4 X 15.0 0.54

Total Galian Tanah 0.54

p x l x t X N
0.3 X 0.3 X 0.4 X 15.0 0.54

Pondasi Umpak Beton K-100 0.54

x t X N
X 4 X 15 60

TIANG LAMPU 60
15.00 STAFF
l x t X N
0.25 X 4 X 15 15

PENGECATAN 15
15.00 m2
REKAPITULASI

PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN


LOKASI : RT 006
DESA : DESA LATTA
TAHUN ANGGARAN : 2019

No. Jenis Pekerjaan

A PEKERJAAN PERSIAPAN

### ALAT

D BIAYA UMUM

E PEKERJAAN AKHIR

NILAI KONSTRUKSI
JUMLAH NILAI KONSTRUKSI
DIBULATKAN

TERBILANG : Empat Juta Empat Ratus Delapan Puluh Ribu Rupiah

DISETUJUI OLEH DIVERIFIKASI OLEH


PENJABAT KEPALA DESA SEKERTARIS DESA

PENJABAT KEPALA DESA V PATTY


NIP .19820126200112 1 004

DIPERIKSA OLEH
TA ID KOTA AMBON

JOHANIS D.S. PATTIAPON, ST


REKAPITULASI

Jumlah Harga
(Rp.)

1,500,000.00

880,000.00

650,000.00

1,450,000.00

4,480,000.00
4,480,000.00
4,480,000.00

mpat Ratus Delapan Puluh Ribu Rupiah

DIBUAT OLEH
KAUR PERENCANAAN

J NITALESSY

JOHANIS D.S. PATTIAPON, ST


RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN


LOKASI : RT 006
DESA : DESA LATTA
TAHUN ANGGARAN : 2019

NO. JENIS PEKERJAAN TEM SATUAN

A PEKERJAAN PERSIAPAN
1 Pembersihan Awal BR-20 Ls
2 Biaya Perencanaan BR-13 Ls

B REHAB JALAN SETAPAK DAN PENERANGAN JALAN


1 Plesteran A.4.4.2.4. M'
2 Rabat Beton A.4.1.1.1 M'

C ALAT
2 Skop BR-2 Bh
3 Benang Tukang BR-3 Tukal
4 Gerobak Dorong BR-4 Bh
5 Martil BR-5 Bh
7 Ember Cor BR-7 Bh

D BIAYA UMUM
3 Insentif Pekerja BR-11 Ls

E PEMBERSIHAN AKHIR
1 Pemasangan Prasasti BR-10 Ls
2 Pembersihan Akhir BR-21 Ls
4 Administrasi + Dokumentasi BR-12 Ls
NGGARAN BIAYA (RAB)

HARGA JUMLAH HARGA


VOLUME SATUAN
(Rp.) (Rp.)

1.00 750,000.00 750,000.00


1.00 750,000.00 750,000.00
Jumlah 1,500,000.00

11.09 69,291.00 768,298.61


3.52 1,360,181.00 4,787,293.05
Jumlah 5,555,591.66

2.00 85,000.00 170,000.00


5.00 10,000.00 50,000.00
1.00 500,000.00 500,000.00
2.00 50,000.00 100,000.00
4.00 15,000.00 60,000.00
Jumlah 880,000.00

1.00 650,000.00 650,000.00


Jumlah 650,000.00

1.00 450,000.00 450,000.00


1.00 500,000.00 500,000.00
1.00 500,000.00 500,000.00
Jumlah 1,450,000.00
PERHITUNGAN VOLUME PEKERJAAN
### : ###
### : ###
### : ###

04. Beton Bertulang

Beton Bertulang Utk Kolom

4O 12
0.15 0.15 0.15 3.60 0.15 x
` 8 - 15

Kolom 15/15
0.15

Beton Bertulang Utk Sloof

4O 12
0.15 0.20 - 0.15 x
0.20 O 8 - 20

0.15 Sloof 15/20

Beton Bertulang Utk Balok

4O 12
0.20 0.15 0.20 - 0.15 x
O 8 - 20

Balok 15/20
0.15 `

Beton Bertulang Utk Plat Conopi


Beton Canopi diatas Jen
0.00 0.10 9.00 0.00 x
0.1

Beton Bertulang Utk Plat Conopi


Beton Canopi diatas Jen
0.80 0.10 9.00 0.80 x
0.1

0.8
Beton Bertulang Utk Plat Septik

0.1 1.80 0.10 - 1.80 x

1.8
Beton Bertulang Utk Plat Lantai

0.08 2.50 0.08 4.50 2.50 x

2.5
05. RABAT BETON TUMBUK

Rabat Beton Tumbuk Utk Entrans

0.05 1.50 0.05 4.00

1.50

Rabat Beton Tumbuk Utk Lantai

0.05 8.50 0.05 12.00

8.50

Rabat Beton Tumbuk Selasar

0.05 1.00 0.05 35.00


1

PEKERJAAN PLESTERAN & LANTAI

01. Plesteran Dinding Sumbu Tegak/Datar ad. 1:5

0 - 0 x
0.00
Total Luasan Kos

0.0
VOLUME PEKERJAAN

0.15 0.02 0.08

Jumlah Tiang 25 0.5625 2.03

Total Beton Kolom 2.025

0.20 0.03 0

Total Beton Sloof 0.000

0.20 0.03 -

Total Beton Balok 0.000

Beton Canopi diatas Jendela


0.10 0.00 -

Jumlah Conopi 1 -

Beton Canopi diatas Jendela


0.10 0.08 0.72

Jumlah Conopi 1 0.72


0.10 Plat Septik 0.18 -

0.08 0.20 0.90


1.50 x 0.05 0.075 0.30

8.50 x 0.05 0.425 5.10

1.00 x 0.05 0.05 1.75

Total Beton Tumbuk 7.150

0.0 0.00

Total Luasan Kosen 0.00

Total 0.00
Total Muka Belakang 2 0.00
PERHITUNGAN VOLUME PE
#REF! : ###
#REF! : ###
#REF! : ###

Pembesiaan
No. Lokasi /
Sketsa / Gambar Bengkokan Panjang
Urut STA
Atas Bawah Besi

01 Pembesian Kolom

0.03 0.03 0.03 0.03 3.70


3.70

4 O 12 0.03 0.03 0.48


0.12 O 8 - 10

0.12

Pembesian Sloof

0.03 0.03 0.03 0.03 -0.05


-0.05

4 O 12 0.03 0.03 0.58


0.17
O 8 - 15

0.12

Pembesian Balok

0.03 0.03 0.03 0.03 -0.05


-0.05

4 O 12 0.03 0.03 0.58


0.17
O 8 - 15

0.12

02. Pembesian Plat Septik

0.03 0.03 0.03 0.03 0.00


0.00

0.03 0.03 0.03 0.03 1.80


1.80
Pembesiaan
No. Lokasi /
Sketsa / Gambar Bengkokan Panjang
Urut STA
Atas Bawah Besi

03. Pembesian Plat Conopi di atas jendela

0.03 0.03 0.03 0.03 9.00


9.00

0.03 0.03 0.03 0.03 0.80


0.80

Pembesian Plat Lantai

0.03 0.03 0.03 0.03 4.50


4.50

0.03 0.03 0.03 0.03 2.50


2.50
N VOLUME PEKERJAAN

Pembesiaan Panjang Jumlah Total


Jarak Panjang Bangunan Total
Total Total Stap Jumlah Volume
Panjang Besi Lebar Panjang Batang (M) ( Staf )

3.76 4.00 15.04 1.4 25.00 34

0.54 0.10 3.32 33 17.928 1.6 25.00 41

0.01 4.00 0.04 0 1.00 0

0.64 0.15 (0.05) (0) -0.213 (0) 1.00 (0)

0.01 4.00 0.04 0 1.00 0

0.64 0.15 (0.05) (0) -0.213 (0) 1.00 (0)

0.06 0.1 1.80 18 1.08 0 0.00 -

1.86 0.1 - - 0.00 0 0.00 -


Pembesiaan Panjang Jumlah Total
Jarak Panjang Bangunan Total
Total Total Stap Jumlah Volume
Panjang Besi Lebar Panjang Batang (M) ( Staf )

9.06 0.1 0.80 8 72.48 7 1.00 7

0.86 0.1 9.00 90 77.40 7 1.00 7

4.56 0.1 2.00 20 91.20 8 1.00 8

2.56 0.1 4.00 40 102.40 9 1.00 9

Besi dia. 12 59
Besi dia. 8 47
Kota : AMBON
Kecamatan : BAGUALA BACK UP TALUD
Desa : DESA LATTA RT 010 / RW 003

I. PEKERJAAN PERSIAPAN

I.1. Pemasangan Bouwplank+Pengukuran


Keliling = 10 x 2.0 = 20.00 M'

II. PEKERJAAN TANAH

II.1. Galian Tanah


Panjang = 50 M

Luas Profil I : (1 x 1 ) = 1.00 M2


Volume Galian I : (50 x 1 ) = 50.00 M3
Profil Galian I
(Rata-rata) 1.00 M

1.00 M'

III. PEKERJAAN BATU KALI

III.1. Pasangan Dinding Batu Kali 1 : 5


Panjang = 50 M
b
0.35
0.2
Luas Pasangan I (T1) : ((0.35 + 0.8)/2) x 1.25 = 0.72 M2
c T1 1.25 M Luas Pasangan I (T2) : ((0.35 + )/2) x 1.25 = 0.72 M2
T2 1.25 M Luas Pasangan Rata2 : (Luas I + Luas II)/2 0.7188 M2
0.20 Luas Pasangan II : 1x1= 1.00 M2
0.2 Vol. Pasangan : ( 1 + 0.71875 ) x 50 = 85.94 M3
1.00 M

0.8
1.00 M

III.2. Plesteran Batu Kali 1 : 5 Panjang a : 0.2


Panjang 50 M Panjang b : 0.35
Panjang C1 : √ (1.25)^2 + (0.8)^2 = 1 M1
Panjang c 2 : √ (1.25)^2 + (0.8)^2 = 1 M1
Panjang c Rata-Rata ( 1.48 + 1.48 )/2 = 1.48 M1
Panjang d : 0.2 = 0.20 M1
Panjang e : 0.2 = 0.20 M1
Luas Plesteran : (a + b + c + d + e) x 50 = 122 M2
Jenis Prasarana : Talud
Ukuran :-
Volume : 1 Unit (P = 11 M')

Volume 20.00 M'

Vol. Gal. Total = 50.00 M3

Volume Pas. Tot. 85.94 M3

V. Plesteran = 121.50 M2
Kota : AMBON
Kecamatan : BAGUALA BACK UP TALUD
Desa : DESA LATTA RT 010 / RW 003

I. PEKERJAAN PERSIAPAN

I.1. Pemasangan Bouwplank+Pengukuran


Keliling = 10 x 2.0 = 20.00 M'

II. PEKERJAAN TANAH

II.1. Galian Tanah


Panjang = 7 M

Luas Profil I : (0.5 x 0.5 ) = 0.25 M2


Volume Galian I : (7 x 0.25 ) = 1.75 M3
Profil Galian I
(Rata-rata) 0.50 M

0.50 M'

III. PEKERJAAN BATU KALI

III.1. Pasangan Dinding Batu Kali 1 : 5


Panjang = 7 M
b
0.3
0.2
Luas Pasangan I (T1) : ((0.3 + 0.4)/2) x 2.5 = 0.88 M2
c T1 2.50 M Luas Pasangan I (T2) : ((0.3 + )/2) x 0.4 = 0.14 M2
T2 0.40 M Luas Pasangan Rata2 : (Luas I + Luas II)/2 0.5075 M2
0.00 Luas Pasangan II : 0.4 x 0.5 = 0.20 M2
0.1 Vol. Pasangan : ( 0.2 + 0.5075 ) x 7 = 4.95 M3
0.50 M

0.4
0.40 M

III.2. Plesteran Batu Kali 1 : 5 Panjang a : 0.2


Panjang 7 M Panjang b : 0.3
Panjang C1 : √ (2.5)^2 + (0.4)^2 = 3 M1
Panjang c 2 : √ (0.4)^2 + (0.4)^2 = 1 M1
Panjang c Rata-Rata ( 2.53 + 0.57 )/2 = 1.55 M1
Panjang d : 0= 0.00 M1
Panjang e : 0.1 = 0.10 M1
Luas Plesteran : (a + b + c + d + e) x 7 = 15 M2
Jenis Prasarana : Talud
Ukuran :-
Volume : 1 Unit (P = 11 M')

Volume 20.00 M'

Vol. Gal. Total = 1.75 M3

Volume Pas. Tot. 4.95 M3

V. Plesteran = 15.05 M2
PERHITUNGAN VOLUME PEKERJAAN
### : ###
### : ###
### : ###

No. Lokasi / Lebar Perhitun


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (

01. GALIAN TANAH

Galian Tanah Untuk Pondasi

0.25
0.15 0.25 15.60 0.15 x

0.15

02. URUGAN TANAH 1/4

03. URUGAN PASIR UNTUK TANGGA 1

Urugan Pasir Bawa Lantai 0.60 0.05 4.80

0.05
0.60

03. URUGAN PASIR UNTUK TANGGA 2

Urugan Pasir Bawa Lantai 0.60 0.05 6.00

0.05
0.60

03. URUGAN PASIR UNTUK TANGGA 3

Urugan Pasir Bawa Lantai 0.60 0.05 4.80

0.05
0.60

06. PASANGAN BATU

1 Pasangan Batu Kali Pondasi Tangga 1

0.15 0.24 4.80


0.24
0.15
2 Pasangan Batu Kali Pondasi Tangga 2

0.15 0.21 6.00


0.21

0.15
2 Pasangan Batu Kali Pondasi Tangga 3

0.15 0.24 4.80


0.24

0.15

09. RABAT BETON TUMBUK

Rabat Beton Tumbuk Lantai

0.07 1.20 0.07 168.00


1.20

09. RABAT BETON ANAK TANGGA

Rabat Beton Tumbuk Lantai

0.07 0.60 0.07 15.60


0.60

10. PLESTERAN ANAK TANGGA

Plesteran Pondasi
0.60

0.25 0.25 0.25 15.60 0.25 +


0.25
VOLUME PEKERJAAN

Perhitungan Dimensi Luas Volume


(M) ( M2 ) ( M3 )

0.3 0.04 0.59

Total Galian Tanah 1 0.59

Total Urugan Tanah 1/4 0.146

0.60 x 0.05 0.03 0.14

0.60 x 0.05 0.03 0.18

0.60 x 0.05 0.03 0.14

Total Urugan Tanah 0.468

0.15 x 0.24 0.036 0.17


0.15 x 0.21 0.0315 0.19

0.15 x 0.24 0.036 0.17

Total Pasangan 0.535

1.20 x 0.07 0.084 14.11

0.60 x 0.07 0.042 0.66

Total Beton Tumbuk 14.767

0.25 + 0.60 = 1.10 9.36

Total 9.36
PERHITUNGAN VOLUME PEKERJAAN
### : ###
### : ###
### : ###

No. Lokasi / Lebar Perhitun


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah

01. GALIAN TANAH

Galian Tanah Untuk Pondasi Saluran

0.4
0.30 0.40 109.00 0.30 x

0.30

02. URUGAN TANAH


02. INSTALASI PIPA

1 PIPA Ø 2 " 109.00 18.17

03. PEMASANGAN METERAN

1 Jumlah KK pengguna Air 0 25


VOLUME PEKERJAAN

Perhitungan Dimensi Luas Volume


(M) ( M2 ) ( M3 )

0.4 0.12 13.08

Total Galian Tanah 13.08

Total Urugan Tanah 1/4 Galian 3.2700

Staff

Buah
LEMBAR ISIAN
1 KEGIATAN
PEKERJAAN : PEMBANGUNAN DRAINASE TYPE I
LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018
2 PELAKSANA
DIBUAT : JACOB N BUNGAA
JABATAN : KAUR PERENCANAAN
DISETUJUI : IMELDA A. TAHALELE, S.STP
JABATAN : PEJABAT KEPALA DESA
NIP : 19800706 1991 2 001
REKAPITULASI

PEKERJAAN : PEMBANGUNAN DRAINASE TYPE I


LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018

Jumlah Harga
No. Jenis Pekerjaan
(Rp.)

I PEKERJAAN PERSIAPAN/UMUM 4,520,0

II PEMBANGUNAN DRAINASE TYPE I 25,372,9


A PEKERJAAN TANAH 4,067,8
B PASANGAN DAN PLESTERAN 21,305,0

NILAI KONSTRUKSI 29,892,9


JUMLAH NILAI KONSTRUKSI 29,892,9
DIBULATKAN 29,892,0

TERBILANG : Dua Puluh Sembilan Juta Delapan Ratus Sembilan Puluh Dua Ribu Rupiah

DISETUJUI OLEH DIBUAT OLEH


PEJABAT KEPALA DESA KAUR PERENCANAAN

IMELDA A. TAHALELE, S.STP JACOB N BUNGAA


NIP .19800706 1991 2 001
REKAPITULASI

Jumlah Harga
(Rp.)

4,520,000.00

25,372,906.28
4,067,836.88
21,305,069.40

29,892,906.28
29,892,906.28
29,892,000.00

an Juta Delapan Ratus Sembilan Puluh Dua Ribu Rupiah

DIBUAT OLEH
KAUR PERENCANAAN

JACOB N BUNGAA
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN DRAINASE TYPE I


LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018

NO. JENIS PEKERJAAN TEM SATUAN

I PEKERJAAN PERSIAPAN/UMUM
A OPERASIONAL
1 Papan Nama Proyek BR-9 Ls
2 Prasasti BR-10 Ls
3 Insentif Pekerja BR-11 Ls
4 Administrasi + Dokumentasi selama proyek berjalan BR-12 Ls
5 Asbuilt drawing BR-13 Ls
A ALAT
1 Pakuel BR-1 Bh
2 Skop BR-2 Bh
3 Benang Tukang BR-3 Tukal
4 Gerobak Dorong BR-4 Bh
5 Martil BR-5 Bh
6 Selang BR-6 M'
7 Ember Cor BR-7 Bh
8 Gergaji BR-8 M'

II PEMBANGUNAN DRAINASE TYPE I


A PEKERJAAN TANAH
1 Galian Tanah A.2.3.1.1. M3
2 Urugan Kembali Galian A.2.3.1.9. M3
3 Urugan Pasir A.2.3.1.11 M3

B PASANGAN DAN PLESTERAN


1 Pasangan Batu A.3.2.1.2 M2
2 Rabat Beton A.A.4.1.4 M'
3 Pesteran A.4.4.2.4. M2
NGGARAN BIAYA (RAB)

HARGA JUMLAH HARGA


VOLUME SATUAN
(Rp.) (Rp.)

1.00 150,000.00 150,000.00


1.00 500,000.00 500,000.00
1.00 650,000.00 650,000.00
1.00 1,000,000.00 1,000,000.00
1.00 1,000,000.00 1,000,000.00

1.00 90,000.00 90,000.00


2.00 85,000.00 170,000.00
5.00 10,000.00 50,000.00
1.00 500,000.00 500,000.00
2.00 50,000.00 100,000.00
10.00 15,000.00 150,000.00
4.00 15,000.00 60,000.00
2.00 50,000.00 100,000.00
Total Jumlah I 4,520,000.00

24.57 60,625.00 1,489,556.25


6.14 46,250.00 284,090.63
1.08 2,124,250.00 2,294,190.00
Jumlah 4,067,836.88

10.53 776,125.00 8,172,596.25


10.00 765,339.02 7,653,390.15
91.80 59,685.00 5,479,083.00
Jumlah 21,305,069.40
Total Jumlah II 25,372,906.28
RINCIAN ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN DRAINASE TYPE I


LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018

HARGA
NO. URAIAN SATUAN
(Rp.)

A UPAH
1 Mandor OH 175,000.00
2 Kepala Tukang OH 150,000.00
3 Tukang Batu OH 125,000.00
4 Tukang Kayu OH 125,000.00
5 Tukang Besi OH 125,000.00
6 Tukang Cat OH 125,000.00
7 Tukang Listrik OH 125,000.00
8 Pekerja OH 75,000.00

B BAHAN
1 Pasir Urug M3 1,750,000.00
2 Batu Kerikil Pecah ( 3 / 2 cm ) M3 175,000.00
3 Batu Krikil (Kg) Kg 145.83
3 Pasir Beton Kg 159.09
4 Pasir Pasang M3 175,000.00
5 Batu Kali M3 175,000.00
6 Semen PC (Zak) Sak 75,000.00
7 Semen PC (Kg) Kg 1,500.00
8 Pipa PVC dia. 2" M' 12,000.00

C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
7 Ember Cor Bh 15,000.00
8 Gergaji Bh 50,000.00

D OPERASIONAL DAN BIAYA LAIN-LAIN


1 Papan Nama Proyek Bh 150,000.00
2 Prasasti Bh 500,000.00
3 Insentif Pekerja Ls 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00
5 As Buildrawing Ls 1,000,000.00
N ANGGARAN BIAYA

JUMLAH
VOLUME
(Rp.)

3.70 647,311.88
2.37 355,012.50
13.77 1,721,250.00
9.90 1,237,187.50
- -
- -
- -
77.16 5,786,831.25
TOTAL I 9,747,593.13
- -
1.30 2,268,000.00
- -
10,270.00 1,497,708.33
8,930.00 1,420,681.82
7.68 1,343,790.00
12.64 2,211,300.00
- -
4,589.22 6,883,833.00
- -
TOTAL II 15,625,313.15
- -
1.00 90,000.00
2.00 170,000.00
5.00 50,000.00
1.00 500,000.00
2.00 100,000.00
10.00 150,000.00
4.00 60,000.00
2.00 100,000.00
TOTAL III 1,220,000.00
- -
1.00 150,000.00
1.00 500,000.00
1.00 650,000.00
1.00 1,000,000.00
1.00 1,000,000.00
TOTAL IV 3,300,000.00
GRAND TOTAL 29,892,906.28
ANALISA HARGA SATUAN

HARGA SATUAN
No. Uraian Kegiatan
(Rp.)

A.2.3.1.1. Penggalian 1M³ Tanah biasa sedalam 1 m


0.750 OH Pekerja 75,000.00
0.025 OH Mandor 175,000.00
A.2.3.1.9. Pengurungan kembali 1 M³ galian tanah
0.500 OH Pekerja 75,000.00
0.050 OH Mandor 175,000.00
A.2.3.1.11. Pengurungan 1M³ dengan pasir urug
0.300 OH Pekerja 75,000.00
0.010 OH Mandor 175,000.00
1.200 M3 Pasir urug 1,750,000.00
A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 4 PP
1.500 OH Pekerja 75,000.00
0.750 OH Tukang batu 125,000.00
0.075 OH Kepala tukang 150,000.00
0.075 OH Mandor 175,000.00
1.200 M3 Batu Kali 175,000.00
163.000 Kg Semen PC 1,500.00
0.520 M3 Pasir pasang 175,000.00
A.A.4.1.4 Pembuatan 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slum
1.200 OH Pekerja 75,000.00
0.200 OH Tukang batu 125,000.00
0.020 OH Kepala tukang 150,000.00
0.060 OH Mandor 175,000.00
230.000 Kg Semen PC 1,500.00
893.000 Kg Pasir Pasang 159.09
1,027.00 Kg Batu Kerikil 145.83
A.4.4.2.4. Pemasangan 1 m2 plesteran 1 SP : 4 PP, tebal 15 mm
0.300 OH Pekerja 75,000.00
0.150 OH Tukang batu 125,000.00
0.015 OH Kepala tukang 150,000.00
0.015 OH Mandor 175,000.00
6.240 Kg Semen PC 1,500.00
0.024 M3 Pasir pasang 175,000.00

PERALATAN DAN LAIN-LAIN


1.000 Bh Pakuel 90,000.00
1.000 Bh Skop 85,000.00
1.000 Tukal Benang Tukang 10,000.00
1.000 Bh Gerobak Dorong 500,000.00
1.000 Bh Martil 50,000.00
1.000 M' Selang 15,000.00
1.000 Bh Ember Cor 15,000.00
1.000 M' Gergaji 50,000.00

1.000 Bh Papan Nama Proyek 150,000.00


1.000 Bh Prasasti 500,000.00
1.000 Ls Insentif Pekerja 650,000.00
1.000 Ls Administrasi + Dokumentasi 1,000,000.00
1.000 Ls As Buildrawing 1,000,000.00
LISA HARGA SATUAN

JUMLAH
(Rp.)

60,625.00
56,250.00
4,375.00
46,250.00
37,500.00
8,750.00
2,124,250.00
22,500.00
1,750.00
2,100,000.00
776,125.00
112,500.00
93,750.00
11,250.00
13,125.00
210,000.00
244,500.00
91,000.00
765,339.02
90,000.00
25,000.00
3,000.00
10,500.00
345,000.00
142,068.18
149,770.83
59,685.00
22,500.00
18,750.00
2,250.00
2,625.00
9,360.00
4,200.00

90,000.00
85,000.00
10,000.00
500,000.00
50,000.00
15,000.00
15,000.00
50,000.00

150,000.00
500,000.00
650,000.00
1,000,000.00
1,000,000.00
DAFTAR UPAH DAN HARGA BAHAN

PEKERJAAN : PEMBANGUNAN DRAINASE TYPE I


LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A UPAH
1 Mandor OH 175,000.00
2 Kepala Tukang OH 150,000.00
3 Tukang Batu OH 125,000.00
4 Tukang Kayu OH 125,000.00
5 Tukang Besi OH 125,000.00
6 Tukang Cat OH 125,000.00
7 Tukang Listrik OH 125,000.00
8 Pekerja OH 75,000.00

B BAHAN
1 Kayu Klas I M3 6,500,000.00
2 Kayu Klas II M3 3,500,000.00
3 Papan Kayu Kls I M3 6,500,000.00
4 Papan Kayu Kls III M3 1,750,000.00
5 Pasir Urug M3 1,750,000.00
6 Batu Kerikil Pecah ( 3 / 2 cm ) M3 175,000.00
7 Pasir Pasang M3 175,000.00
8 Batu Kali M3 175,000.00
9 Pasir Beton Kg 159.09
10 Batu Krikil (Kg) Kg 145.83
11 Semen PC (Zak) Sak 75,000.00
12 Semen PC (Kg) Kg 1,500.00
13 Pipa PVC dia. 2" M' 12,000.00
C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
Ember Cor Bh 15,000.00
Gergaji Bh 50,000.00
D OPERASIONAL DAN BIAYA LAIN-LAIN
1 Papan Nama Proyek Bh 150,000.00
2 Prasasti Bh 500,000.00
3 Insentif Pekerja Ls 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00
5 As Buildrawing Ls 1,000,000.00
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : PEMBANGUNAN DRAINASE TYPE I
LOKASI : RT 009
DESA : NEGERI LAMA

No. Lokasi / Lebar Perhitun


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (

PANJANG SALURAN
= 54 M

01. GALIAN TANAH

Galian Tanah Untuk Pondasi Saluran

0.65
0.70 0.65 54.00 0.70 x

0.70

02. URUGAN TANAH 1/4

03. URUGAN PASIR

Urugan Pasir Bawa Lantai 0.25 0.08 54.00

0.08
0.25

06. PASANGAN BATU

Pasangan Batu Kali Utk Saluran

0.15 0.65 54.00


0.65

0.15

08. PLESTERAN

09. RABAT BETON TUMBUK

Rabat Beton Tumbuk Utk Saluran

0.07 0.40 0.07 54.00


0.40
10. PLESTERAN

Plesteran Saluran

0.15 0.15 1.7 54.00 1.7 x

0.50 0.5

0.40
VOLUME PEKERJAAN

Perhitungan Dimensi Luas Volume


(M) ( M2 ) ( M3 )

0.7 0.46 24.57

Total Galian Tanah 24.57

Total Urugan Tanah 1/4 6.1425

0.25 x 0.08 0.02 1.08

0.15 x 0.65 0.0975 5.27

Total Pasangan 2 10.530

0.40 x 0.07 0.028 1.51

Total Beton Tumbuk 1.512


54.0 91.80

Total 91.80
LEMBAR ISIAN
1 KEGIATAN
PEKERJAAN : PEMBANGUNAN DRAINASE TYPE II
LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018
2 PELAKSANA
DIBUAT : JACOB N BUNGAA
JABATAN : KAUR PERENCANAAN
DISETUJUI : IMELDA A. TAHALELE, S.STP
JABATAN : PEJABAT KEPALA DESA
NIP : 19800706 1991 2 001
REKAPITULASI

PEKERJAAN : PEMBANGUNAN DRAINASE TYPE II


LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018

Jumlah Harga
No. Jenis Pekerjaan
(Rp.)

I PEKERJAAN PERSIAPAN/UMUM 4,520,0

II PEMBANGUNAN DRAINASE TYPE II 24,001,3


A PEKERJAAN TANAH 3,391,8
B PASANGAN DAN PLESTERAN 20,609,4

NILAI KONSTRUKSI 28,521,3


JUMLAH NILAI KONSTRUKSI 28,521,3
DIBULATKAN 28,521,0

TERBILANG : Dua Puluh Delapan Juta Lima Ratus Dua Puluh Satu Ribu Rupiah

DISETUJUI OLEH DIBUAT OLEH


PEJABAT KEPALA DESA KAUR PERENCANAAN

IMELDA A. TAHALELE, S.STP JACOB N BUNGAA


NIP .19800706 1991 2 001
REKAPITULASI

Jumlah Harga
(Rp.)

4,520,000.00

24,001,303.46
3,391,892.44
20,609,411.03

28,521,303.46
28,521,303.46
28,521,000.00

n Juta Lima Ratus Dua Puluh Satu Ribu Rupiah

DIBUAT OLEH
KAUR PERENCANAAN

JACOB N BUNGAA
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN DRAINASE TYPE II


LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018

NO. JENIS PEKERJAAN TEM SATUAN

I PEKERJAAN PERSIAPAN/UMUM
A OPERASIONAL
1 Papan Nama Proyek BR-9 Ls
2 Prasasti BR-10 Ls
3 Insentif Pekerja BR-11 Ls
4 Administrasi + Dokumentasi selama proyek berjalan BR-12 Ls
5 Asbuilt drawing BR-13 Ls
A ALAT
1 Pakuel BR-1 Bh
2 Skop BR-2 Bh
3 Benang Tukang BR-3 Tukal
4 Gerobak Dorong BR-4 Bh
5 Martil BR-5 Bh
6 Selang BR-6 M'
7 Ember Cor BR-7 Bh
8 Gergaji BR-8 M'

II PEMBANGUNAN DRAINASE TYPE II


A PEKERJAAN TANAH
1 Galian Tanah A.2.3.1.1. M3
2 Urugan Kembali Galian A.2.3.1.9. M3
3 Urugan Pasir A.2.3.1.11 M3

B PASANGAN DAN PLESTERAN


1 Pasangan Batu A.3.2.1.2 M2
2 Rabat Beton A.A.4.1.4 M'
3 Pesteran A.4.4.2.4. M2
NGGARAN BIAYA (RAB)

HARGA JUMLAH HARGA


VOLUME SATUAN
(Rp.) (Rp.)

1.00 150,000.00 150,000.00


1.00 500,000.00 500,000.00
1.00 650,000.00 650,000.00
1.00 1,000,000.00 1,000,000.00
1.00 1,000,000.00 1,000,000.00

1.00 90,000.00 90,000.00


2.00 85,000.00 170,000.00
5.00 10,000.00 50,000.00
1.00 500,000.00 500,000.00
2.00 50,000.00 100,000.00
10.00 15,000.00 150,000.00
4.00 15,000.00 60,000.00
2.00 50,000.00 100,000.00
Total Jumlah I 4,520,000.00

17.33 60,625.00 1,050,328.13


4.33 46,250.00 200,320.31
1.01 2,124,250.00 2,141,244.00
Jumlah 3,391,892.44

10.40 776,125.00 8,067,819.38


10.00 765,339.02 7,653,390.15
81.90 59,685.00 4,888,201.50
Jumlah 20,609,411.03
Total Jumlah II 24,001,303.46
RINCIAN ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN DRAINASE TYPE II


LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018

HARGA
NO. URAIAN SATUAN
(Rp.)

A UPAH
1 Mandor OH 175,000.00
2 Kepala Tukang OH 150,000.00
3 Tukang Batu OH 125,000.00
4 Tukang Kayu OH 125,000.00
5 Tukang Besi OH 125,000.00
6 Tukang Cat OH 125,000.00
7 Tukang Listrik OH 125,000.00
8 Pekerja OH 75,000.00

B BAHAN
1 Pasir Urug M3 1,750,000.00
2 Batu Kerikil Pecah ( 3 / 2 cm ) M3 175,000.00
3 Batu Krikil (Kg) Kg 145.83
3 Pasir Beton Kg 159.09
4 Pasir Pasang M3 175,000.00
5 Batu Kali M3 175,000.00
6 Semen PC (Zak) Sak 75,000.00
7 Semen PC (Kg) Kg 1,500.00
8 Pipa PVC dia. 2" M' 12,000.00

C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
7 Ember Cor Bh 15,000.00
8 Gergaji Bh 50,000.00

D OPERASIONAL DAN BIAYA LAIN-LAIN


1 Papan Nama Proyek Bh 150,000.00
2 Prasasti Bh 500,000.00
3 Insentif Pekerja Ls 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00
5 As Buildrawing Ls 1,000,000.00
N ANGGARAN BIAYA

JUMLAH
VOLUME
(Rp.)

3.27 571,881.19
2.21 331,218.75
12.29 1,535,625.00
9.80 1,224,531.25
- -
- -
- -
67.62 5,071,820.63
TOTAL I 8,735,076.81
- -
1.21 2,116,800.00
- -
10,270.00 1,497,708.33
8,930.00 1,420,681.82
7.37 1,289,925.00
12.47 2,182,950.00
- -
4,505.44 6,758,161.50
- -
TOTAL II 15,266,226.65
- -
1.00 90,000.00
2.00 170,000.00
5.00 50,000.00
1.00 500,000.00
2.00 100,000.00
10.00 150,000.00
4.00 60,000.00
2.00 100,000.00
TOTAL III 1,220,000.00
- -
1.00 150,000.00
1.00 500,000.00
1.00 650,000.00
1.00 1,000,000.00
1.00 1,000,000.00
TOTAL IV 3,300,000.00
GRAND TOTAL 28,521,303.46
ANALISA HARGA SATUAN

HARGA SATUAN
No. Uraian Kegiatan
(Rp.)

A.2.3.1.1. Penggalian 1M³ Tanah biasa sedalam 1 m


0.750 OH Pekerja 75,000.00
0.025 OH Mandor 175,000.00
A.2.3.1.9. Pengurungan kembali 1 M³ galian tanah
0.500 OH Pekerja 75,000.00
0.050 OH Mandor 175,000.00
A.2.3.1.11. Pengurungan 1M³ dengan pasir urug
0.300 OH Pekerja 75,000.00
0.010 OH Mandor 175,000.00
1.200 M3 Pasir urug 1,750,000.00
A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 4 PP
1.500 OH Pekerja 75,000.00
0.750 OH Tukang batu 125,000.00
0.075 OH Kepala tukang 150,000.00
0.075 OH Mandor 175,000.00
1.200 M3 Batu Kali 175,000.00
163.000 Kg Semen PC 1,500.00
0.520 M3 Pasir pasang 175,000.00
A.A.4.1.4 Pembuatan 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slum
1.200 OH Pekerja 75,000.00
0.200 OH Tukang batu 125,000.00
0.020 OH Kepala tukang 150,000.00
0.060 OH Mandor 175,000.00
230.000 Kg Semen PC 1,500.00
893.000 Kg Pasir Pasang 159.09
1,027.00 Kg Batu Kerikil 145.83
A.4.4.2.4. Pemasangan 1 m2 plesteran 1 SP : 4 PP, tebal 15 mm
0.300 OH Pekerja 75,000.00
0.150 OH Tukang batu 125,000.00
0.015 OH Kepala tukang 150,000.00
0.015 OH Mandor 175,000.00
6.240 Kg Semen PC 1,500.00
0.024 M3 Pasir pasang 175,000.00

PERALATAN DAN LAIN-LAIN


1.000 Bh Pakuel 90,000.00
1.000 Bh Skop 85,000.00
1.000 Tukal Benang Tukang 10,000.00
1.000 Bh Gerobak Dorong 500,000.00
1.000 Bh Martil 50,000.00
1.000 M' Selang 15,000.00
1.000 Bh Ember Cor 15,000.00
1.000 M' Gergaji 50,000.00

1.000 Bh Papan Nama Proyek 150,000.00


1.000 Bh Prasasti 500,000.00
1.000 Ls Insentif Pekerja 650,000.00
1.000 Ls Administrasi + Dokumentasi 1,000,000.00
1.000 Ls As Buildrawing 1,000,000.00
LISA HARGA SATUAN

JUMLAH
(Rp.)

60,625.00
56,250.00
4,375.00
46,250.00
37,500.00
8,750.00
2,124,250.00
22,500.00
1,750.00
2,100,000.00
776,125.00
112,500.00
93,750.00
11,250.00
13,125.00
210,000.00
244,500.00
91,000.00
765,339.02
90,000.00
25,000.00
3,000.00
10,500.00
345,000.00
142,068.18
149,770.83
59,685.00
22,500.00
18,750.00
2,250.00
2,625.00
9,360.00
4,200.00

90,000.00
85,000.00
10,000.00
500,000.00
50,000.00
15,000.00
15,000.00
50,000.00

150,000.00
500,000.00
650,000.00
1,000,000.00
1,000,000.00
DAFTAR UPAH DAN HARGA BAHAN

PEKERJAAN : PEMBANGUNAN DRAINASE TYPE II


LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A UPAH
1 Mandor OH 175,000.00
2 Kepala Tukang OH 150,000.00
3 Tukang Batu OH 125,000.00
4 Tukang Kayu OH 125,000.00
5 Tukang Besi OH 125,000.00
6 Tukang Cat OH 125,000.00
7 Tukang Listrik OH 125,000.00
8 Pekerja OH 75,000.00

B BAHAN
1 Kayu Klas I M3 6,500,000.00
2 Kayu Klas II M3 3,500,000.00
3 Papan Kayu Kls I M3 6,500,000.00
4 Papan Kayu Kls III M3 1,750,000.00
5 Pasir Urug M3 1,750,000.00
6 Batu Kerikil Pecah ( 3 / 2 cm ) M3 175,000.00
7 Pasir Pasang M3 175,000.00
8 Batu Kali M3 175,000.00
9 Pasir Beton Kg 159.09
10 Batu Krikil (Kg) Kg 145.83
11 Semen PC (Zak) Sak 75,000.00
12 Semen PC (Kg) Kg 1,500.00
13 Pipa PVC dia. 2" M' 12,000.00
C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
Ember Cor Bh 15,000.00
Gergaji Bh 50,000.00
D OPERASIONAL DAN BIAYA LAIN-LAIN
1 Papan Nama Proyek Bh 150,000.00
2 Prasasti Bh 500,000.00
3 Insentif Pekerja Ls 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00
5 As Buildrawing Ls 1,000,000.00
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : PEMBANGUNAN DRAINASE TYPE II
LOKASI : RT 009
DESA : NEGERI LAMA

No. Lokasi / Lebar Perhitun


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (

PANJANG SALURAN
= 63 M

01. GALIAN TANAH

Galian Tanah Untuk Pondasi Saluran

0.55
0.50 0.55 63.00 0.50 x

0.50

02. URUGAN TANAH 1/4

03. URUGAN PASIR

Urugan Pasir Bawa Lantai 0.20 0.08 63.00

0.08
0.20

06. PASANGAN BATU

Pasangan Batu Kali Utk Saluran

0.15 0.55 63.00


0.55

0.15

08. PLESTERAN

09. RABAT BETON TUMBUK

Rabat Beton Tumbuk Utk Saluran

0.07 0.20 0.07 63.00


0.20
10. PLESTERAN

Plesteran Saluran

0.15 0.15 1.3 63.00 1.3 x

0.40 0.4

0.20
VOLUME PEKERJAAN

Perhitungan Dimensi Luas Volume


(M) ( M2 ) ( M3 )

0.6 0.28 17.33

Total Galian Tanah 17.33

Total Urugan Tanah 1/4 4.33125

0.20 x 0.08 0.016 1.01

0.15 x 0.55 0.0825 5.20

Total Pasangan 2 10.395

0.20 x 0.07 0.014 0.88

Total Beton Tumbuk 0.882


63.0 81.90

Total 81.90
PERHITUNGAN VOLUME PEKERJA
#REF! : ###
#REF! : ###
#REF! : ###

No. Lebar
Lokasi / STA Sketsa / Gambar Tinggi Panjang
Urut Atas Bawah

PAGAR Panjang Sumbu Tegak


= 5 + 1.5 + 7 + 2 + 5 + 7 +
1.5 + 2 + 0 + 0 + 0 + +
= 31 M

Panjang Sumbu Datar


= 2 + 12 + 2 + 2 + 3.8 + 4.2 +
4 + 2 + 0 + 0 + + +
= 32 M

Total Panjang sumbu ( Tegak + Datar )

= 31 + 32
= 63 M / 3 = 21

01. GALIAN TANAH

Galian Tanah Untuk Pondasi

0.6 0.55 63.00

0.55

0.60

02. URUGAN TANAH 1/4

03. URUGAN PASIR

Urugan Pasir Bawa Pondasi 0.60 0.05 63.00

0.05
0.60

04. TRIMBIRISAN BATU KALI

0.60 0.10 63.00


0.10

0.60
05. PASANGAN BATU

Pasangan Batu Kali Utk Pondasi Pagar

0.25 0.25 0.40 0.55 63.00

0.55

0.4

06. BETON BERTULANG

Beton Bertulang Utk Kolom

4O 12
0.15 0.15 0.15 1.70
` 8 - 15

Kolom 15/15
0.15
Beton Bertulang Utk Sloof

4O 12
0.15 0.20 61.00
0.20 O 8 - 20

0.15 Sloof 15/20

Beton Bertulang Utk Balok

4O 12
0.20 0.15 0.20 61.00
O 8 - 20

Balok 15/20
0.15 `

07. PASANGAN BATU BATA

Pasangan Batu Bata

61.0 1.7

1.7

61
0.1

8. PLESTERAN
Plesteran Sumbu Tegak/Datar

1.7 61.00
1.70

61
VOLUME PEKERJAAN

Perhitungan Dimensi Luas Volume


(M) ( M2 ) ( M3 )

0.55 x 0.6 0.33 20.79

Total Urugan Tanah 1/4 5.1975

0.60 x 0.05 0.03 1.89

Total Urugan Pasir 1.890

0.60 x 0.10 0.06 3.78


( 0.25 + 0.40 ) 0.55 0.17875 11.26
x
2

Total Pasangan 11.261

0.15 x 0.15 0.02 0.04

Jumlah Tiang 21 0.4725 0.80

0.15 x 0.20 0.03 1.83


Pintu 2.00

Total Beton Sloof 1.830

0.15 x 0.20 0.03 1.83

Total Beton Balok 1.830

61.0 x 1.7 103.70

Kolom Beton
0.15 x 0.15 x 21 0.47

Total Pasangan 103.23 10.32275


1.7 x 61.0 103.70

Total 103.70
Total Muka Belakang 2 207.40
TAKE OF SHEET
#REF! : ###
#REF! : ###
#REF! : ###

Pembesiaan
No. Lokasi /
Sketsa / Gambar Bengkokan Panjang
Urut STA
Atas Bawah Besi

01. Pembesian Kolom

0.03 0.03 0.03 0.03 1.70


1.70

4 O 12 0.03 0.03 0.48


0.12 O 8 - 10

0.12

02. Pembesian Sloof

0.03 0.03 0.03 0.03 61.00


61.00

4 O 12 0.03 0.03 0.58


0.17
O 8 - 15

0.12

03. Pembesian Balok

0.03 0.03 0.03 0.03 61.00


61.00

4 O 12 0.03 0.03 0.58


0.17
O 8 - 15

0.12

04. Pintu Pagar 1 Set


E OF SHEET
Pekerjaan :: Pembesian Pagar

Pembesiaan Panjang Jumlah Total


Jarak Panjang Bangunan Total
Total Total Stap Jumlah Volume
Panjang Besi Lebar Panjang Batang (M) ( Staf )

1.76 4.00 7.04 0.6 21.00 13

0.54 0.10 1.70 17 9.180 0.8 21.00 18

61.06 4.00 244.24 22 1.00 22

0.64 0.15 61.00 407 260.267 24 1.00 24

61.06 4.00 244.24 22 1.00 22

0.64 0.15 61.00 407 260.267 24 1.00 24

Besi dia. 10 58
Besi dia. 8 65
PERHITUNGAN VOLUME PEKERJAAN
### : ###
### : ###
### : ###

No. Lokasi / Lebar Perhitun


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (

01. GALIAN TANAH

Galian Tanah Untuk Septik

2.3 1.65 1.80 1.65 x

1.65

2.30

02. URUGAN TANAH 1/4

03. URUGAN PASIR

Urugan Pasir Bawa Lantai 2.30 0.05 1.80

0.05
2.30

04. BETON BERTULANG

Beton Bertulang Utk Plat Penutup

0.60 0.11 0.60 0.60 x


0.11

0.6

Beton Bertulang Utk Plat Septik

0.1 2.30 0.10 1.80 2.30 x

2.30

05. PASANGAN BATU BATA

Pasangan Batu Bata


8.2 1.5 8.2 x

1.5

8.2
0.1
06. BETON

Beton Bertulang ad. 1:2:3

0.10 2.30 0.10 1.80

2.30

07. PLESTERAN

Plesteran Sumbu Tegak/Datar

1.5 8.20 1.5 x


1.50

8.2
VOLUME PEKERJAAN

Perhitungan Dimensi Luas Volume


(M) ( M2 ) ( M3 )

2.3 3.80 6.83

Total Galian Tanah 6.831

Total Urugan Tanah 1/4 1.708

2.30 x 0.05 0.115 0.207

Total Urugan Pasir 0.207

0.11 0.07 0.04

Jumlah Conopi 1 0.04

0.10 Plat Septik 0.23 0.41


1.5 12.30

Total Pasangan 12.30 1.23


2.30 x 0.10 0.23 0.41

Total Beton Tumbuk 0.41

8.2 12.30
PERHITUNGAN VOLU
#REF! : ###
#REF! : ###
#REF! : ###

Pembesiaan
No. Lokasi /
Sketsa / Gambar Bengkokan Panjang
Urut STA
Atas Bawah Besi

01. Pembesian Plat Septik

0.03 0.03 0.03 0.03 2.40


2.40

0.03 0.03 0.03 0.03 1.80


1.80

02. Pembesian Plat Penutup Septik

0.03 0.03 0.64


0.07 0.5 0.07
0.03 0.03

0.03 0.03 0.64


0.07 0.5 0.07
0.03 0.03

Ukuran Batu Gomblo


0.14 x 0.40 = 0.056
12.30
220
UNGAN VOLUME PEKERJAAN

Pembesiaan Panjang Jumlah Total


Jarak Panjang Bangunan Total
Total Total Stap Jumlah Volume
Panjang Besi Lebar Panjang Batang (M) ( Staf )

2.46 0.1 1.80 18 44.28 4 1.00 4

1.86 0.1 2.40 24 44.64 4 1.00 4

0.70 0.1 0.60 6 4.20 0 1.00 0.4

0.70 0.1 0.60 6 4.20 0 1.00 0.4

Besi dia. 10 9
PERHITUNGAN VOLUME PEKERJAAN
### : ###
### : ###
### : ###

No. Lokasi / Lebar Perhitun


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (

RUMAH Panjang Sumbu Tegak


= 7 + 7.5 + 1.5 + 1.5 + 7.5 + 7 +
0.5 + 0.5 + + + + +
= 33 M

Panjang Sumbu Datar


= 19 + 4 + 7.5 + 7.5 + 4 + 0.5 +
0.5 + + + + + +
= 43 M

Total Panjang sumbu ( Tegak + Datar )

= 33 + 43
= 76 M

PEKERJAAN TANAH

01. Galian Tanah

Galian Tanah Untuk Pondasi

0.8 0.8 76.00 0.80 x

0.80

0.80

02. Urugan Tanah 1/4

03. Urugan Pasir Bawa Pondasi 0.80 0.05 76.00

0.05
0.8

04. Urugan Pasir Bawa Lantai 8.50 0.05 12.00

0.05
8.5

Urugan Pasir Lantai Selasar 0.90 0.05 38.00

0.05
0.9

05. Urugan Tanah dibawah Lantai


Urugan Tanah di bawa Lantai

0.10 8.50 0.10 12.00

8.5

Urugan Tanah di bawa Selasar

0.08 0.90 0.08 38.00

0.9

PEKERJAAN PASANGAN & BETON

01. Timbrisan Batu Kali


0.90 0.15 76.00
0.15

0.90

02. Pas. Pondasi Batu Kali ad. 1:5


0.25
0.25 0.50 0.50 76.00 (

0.50

0.50

03. Pasangan Batu Bata ad. 1:5

Sumbu Tegak
Pasangan Batu Bata 1

7.0 3.32 7.0 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
1.32 x
Kosen Jendelah
7 0.58 x

0.1

Pasangan Batu Bata 2

8.0 3.32 8.0 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
1.32 x
Kosen Jendelah
8.0 0.58 x
0.1

Pasangan Batu Bata 3

1.5 3.32 1.5 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
0.72 x
Kosen Jendelah
1.5 0.58 x

0.1

Pasangan Batu Bata 4

1.5 3.32 1.5 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
1.32 x
Kosen Jendelah
1.5 0.58 x

0.1

Pasangan Batu Bata 5

8.0 3.32 8.0 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
0.72 x
Kosen Jendelah
8 0.58 x

0.1

Pasangan Batu Bata 6

0.0 3.32 0.0 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
0 0.58 x

0.1

Pasangan Batu Bata 7

0.5 3.32 0.5 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
0.5 0.58 x

0.1

Sumbu Datar
Pasangan Batu Bata 1

12.0 3.32 12.0 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
1.00 x
Kosen Jendelah
12 0.58 x
0.1

Pasangan Batu Bata 2

4.0 3.32 4.0 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
0.72 x
Kosen Jendelah
4 0.58 x

0.1

Pasangan Batu Bata 3

0.0 3.32 0.0 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.86 x
Kosen Jendelah
0 0.58 x

0.1

Pasangan Batu Bata 4

4.0 3.32 4.0 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
4 0.58 x

0.1

Pasangan Batu Bata 5

0.0 3.32 0.0 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
0 0.58 x

0.1

Pasangan Batu Bata 6

0.5 3.32 0.5 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
0.5 0.58 x

0.1

Pasangan Batu Bata 7

0.5 3.32 0.5 x

Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
0.5 0.58 x

0.1

Bak Kecil

1.20 0.5 1.2 x


0.5

0.1
1.20

Dinding Kloset

0.9 0.2 0.9 x


0.2
0.1
0.90

04. Beton Bertulang

Beton Bertulang Utk Kolom

4O 12
0.15 0.15 0.15 3.60 0.15 x
` 8 - 15

Kolom 15/15
0.15

Beton Bertulang Utk Sloof

4O 12
0.15 0.20 76.00 0.15 x
0.20 O 8 - 20

0.15 Sloof 15/20


Beton Bertulang Utk Balok

4O 12
0.20 0.15 0.20 76.00 0.15 x
O 8 - 20

Balok 15/20
0.15 `

Beton Bertulang Utk Plat Conopi


Beton Canopi diatas Jen
0.00 0.10 9.00 0.00 x
0.1

Beton Bertulang Utk Plat Conopi


Beton Canopi diatas Jen
0.80 0.10 9.00 0.80 x
0.1

0.8
Beton Bertulang Utk Plat Septik

0.1 1.80 0.10 - 1.80 x

1.8
Beton Bertulang Utk Plat Lantai

0.08 2.50 0.08 4.50 2.50 x

2.5
05. RABAT BETON TUMBUK

Rabat Beton Tumbuk Utk Entrans

0.05 1.50 0.05 4.00

1.50

Rabat Beton Tumbuk Utk Lantai

0.05 8.50 0.05 12.00

8.50

Rabat Beton Tumbuk Selasar

0.05 1.00 0.05 35.00


1

PEKERJAAN PLESTERAN & LANTAI

01. Plesteran Dinding Sumbu Tegak/Datar ad. 1:5

3.32 47.50 3.32 x


3.32
Total Luasan Kos

47.5

02. Plesteran Dinding Sumbu Tegak/Datar ad. 1:2

Bak KM

0.5 1.20 1.20 x

0.5

1.20

Kloset

0.3 0.60 0.60 x

0.30

0.60

03. Pemasangan Lantai Keramik 40 x 40

Lantai Keramik Entrans


1.50 1.50 12.00 12.00 x

12

Lantai Keramik Ruang Dapur

7.00 7.00 0.00 0.00 x

0
Total Keramik Warn
Lantai Keramik Ruang 1

7.00 7.00 8.00 8.00 x

8.0

Lantai Keramik Ruang 2

6.00 6.00 4.00 4.00 x

4.0

Lantai Keramik Ruang 3

7.00 7.00 0.00 0.00 x

0.0

Lantai Keramik Ruang 4

7.00 7.00 0.00 0.00 x

Lantai Keramik Ruang 5

4.00 4.00 0.00 0.00 x

0.00 Total Keramik Putih


04. Pemasangan Lantai Keramik 40 x 40 Batu Alam

Dinding Keramik Batu Alam 1

0.60 0.60 22.00 22.00 x

22

Dinding Keramik Batu Alam 2

0.60 0.60 7.00 7.00 x

Dinding Keramik Batu Alam 3

0.57 0.57 0.00 0.00 x

0
Total Keramik Cora
05. Pemasangan Lantai WC/KM Keramik 20 x 20 Anti Slip

Lantai Keramik KM
1.00 1.50 1.50 x

1.00 1 1.00 1.50 1.50 x

1.5 1.5

0.7 0.70 0.90 0.70 x

0.9 Total Keramik P

06. Pemasangan Lantai Dinding Keramik 20 x 25

Dinding Lapis Keramik Bak

Luas Alas
0.5 0.50 3.60 0.60 x
Luas Dinding
0.60 x

3.60

Dinding Lapis Wc

Luas Alas
1.25 1.25 6.00 1.25 x
Total Keramik Warn
PEKERJAAN KAYU DAN ATAP

01. Kuda-Kuda Kayu Kls I & Gording

Kuda-Kuda Kecil Kayu Klas I Kayu 6 / 12


C
E F

A G H B Balok Tarik
0 D 0 Kaki Kuda-kuda

0.00
Tiang Kuda-kuda
Dari Kuda-kuda ABC diketahui Skor DE + DF
<A = <B = 30 °
CD = 1/2 AC = 1/2 BC Skor EG + FH
AD = BD = 0
AC² = CD² + AD² Balok Pengunci
AC² = ( 1/2 AC² ) + ( 0 )² Balok Pengapit
AC² = 1/4 AC² + 0
4 AC² = AC² + 4 X 0
3 AC² = 0.00 `
AC² = 0.00 = 0
3 3
AC = Ѵ 0 = 0.0 Skor Angin
CD = 1/2 AC = 0.0
AD = EF = 0 Nok Gording
ED = DF = CD = 0.0 ( <C1 = <D2 = <E= 60° )
EG = FH = 1/2 CD = 0.0

Uraian Volume
0 x

02. Kayu 5 / 10

Gording

Uraian Volume
0 x

Kuda-Kuda Besar Kayu Klas I Kayu 6 / 12


C
E F

A G H B Balok Tarik
3.5 D 3.5 Kaki Kuda-kuda

7.00
Tiang Kuda-kuda
Dari Kuda-kuda ABC diketahui Skor DE + DF
<A = <B = 30 °
CD = 1/2 AC = 1/2 BC Skor EG + FH
AD = BD = 3.5
AC² = CD² + AD² Balok Pengunci
AC² = ( 1/2 AC² ) + ( 3.5 )² Balok Pengapit
AC² = 1/4 AC² + 12.25
4 AC² = AC² + 4 X 12.25
3 AC² = 49.00 `
AC² = 49.00 = 16.333
3
AC = Ѵ 16.333 = 4.0 4
CD = 1/2 AC = 2.0 Skor Angin
AD = EF = 3.5
ED = DF = CD = 2.0 ( <C1 = <D2 = <E= 60° ) Nok Gording
EG = FH = 1/2 CD = 1.0

C C
Uraian Volume
163 x
A
1.00 D D 1.5 B Kayu 5 / 10

<A = <B = 30 ° <A = <B = 30 ° Gording


CD = 1/2 AC = 1/2 BC CD = 1/2 BC = 1/2 BC

AD = BD = 1.00 AD = BD = 1.5
AC² = CD² + AD² BC² = CD² + AD²

AC² = ( 1/2 AC² ) + ( 1 BC² = ( 1/2 AC² ) + ( 1.5


AC² = 1/4 AC² + 1 BC² = 1/4 AC² + 2.25 Uraian Volume
4 AC² = AC² + 4 X 1 4 BC² = AC² + 4 X 2.25 471 x
3 AC² = 4.00 ` 3 BC² = 9.00 `
AC² = 4.00 = 1.3333 BC² = 9.00 = 3
3 3
AC = Ѵ 1.3333 = 1.2 BC² = Ѵ 3 = 1.7

Jadi Kuda-kud AC = 4.0 + 1.2


= 5.2 M

Jadi Kuda-kud BC = 4.0 + 1.7


= 5.8 M

03. PAPAN LISPLANK KAYU KLS 1

0.200 0.03 0.200 48 0.200 x

48
04. RANGKA PLAFON

Rangka Plafon Dalam


Ruang 1
8 x
7 x
3 4 5
1 8 x
7 x
7 / 0.6 = 12 Ruang 2
8 / 0.8 = 10 4 / 0.6 = 7 7 x
7 / 0.8 = 9 8 x
7 x
2 8 x
Ruang 3
1.5 x
3). 1.5 / 0.6 = 3 1.5 x
1.5 / 0.6 = 3 Ruang 4
4). 1.5 / 0.6 = 3 2 x
1.0 / 0.6 = 2 4 x
Ruang 5
1.5 x
1.5 x

Rangka Plafon Luar Ruang 1


9.5 x
2 0.8 x
Ruang 2
14 x
0.8 x
3 Ruang 3
1 9.5 x
0.8 x
Ruang 4
5 7 x
0.8 x
4 Ruang 5
8 x
1.5 x
0.11 Kehilangan Kayu 8 x
1.5 x

Volume
Volume

Uraian Volume
144 x
Uraian Volume
436 x
05. PLAFON TRIPLEKS

Plafon Dalam Ruang 1


Ruang 2
Ruang 3
Ruang 4
Ruang 5
Ruang 6
Entrans WC
WC / KM

Plafon Luar Samping Kiri


Belakang
Samping Kanan
Depan Ruang Gu
Entrance

06. KUSEN

Kosen Vetilasi Kayu 6 / 12

Ventilasi Ventilasi Type V


1.90 0.060 x
0.35
0.3
0.3

Jendela Jendela Type J1


4.20 Panjang Jendela
Telingga

1.52 0.060 x

0.58

Pintu Kabaya Pintu Type P1 J


5.64 Panjang Pintu
Telingga

2.16 0.060 x

1.32

Pintu Pintu Type P2 J


5.09 Panjang Pintu
Telingga

2.16 0.060 x

0.77

Pintu Pintu Type P3 J


5.04 Panjang Pintu
Telingga

2.16 0.060 x

0.72

07. PEKERJAAN PINTU & JENDELA

Pasang Kaca tebal Riben 3 mm

Jendela Type J1
0.38 1.40 0.38 x
1.4

0.38
Pasang Daun Pintu Panel Kayu

Pintu Type P1 J
1.20 2.10 1.20 x
2.1

1.2

Pintu Type P2 J
0.65 2.10 0.65 x
2.1

0.65

Pasang Daun Pintu Teak Wood

Pintu Type P3 J
0.60 2.10 0.60 x
2.1 Daun Muka Be

0.6
08. PEKERJAAN ATAP

Pasangan Seng Gelombang Bjls 0.25

1.5 x
1.5 x
1.5 x

( 7.5 +
( 7.5 +
( 6 +
( 6 +

0.025

Pasangan Seng Datar Bjls 0.25 = 9 +


4 +

= 25.00
VOLUME PEKERJAAN

Perhitungan Dimensi Luas Volume


(M) ( M2 ) ( M3 )

0.8 0.64 48.64

Total Galian Tanah 48.640

Total Urugan Tanah 1/4 12.16

0.80 x 0.05 0.04 3.04

8.50 x 0.05 0.425 5.10

0.90 x 0.05 0.045 1.71


Total Urugan Pasir 6.810
8.50 x 0.10 0.85 10.20

0.90 x 0.08 0.072 2.74

Total Urugan Tanah/Sirtu 12.936

0.90 x 0.15 0.135 10.26

0.25 + 0.50 ) 0.50 0.1875 14.25


x
2

3.3 23.24

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 23.24 2.324

3.3 26.56

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
Total Pasangan 26.56 2.656

3.3 4.98

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu
2.16 x 1 1.56
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 3.42 0.34248

3.3 4.98

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 4.98 0.498

3.3 26.56

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 26.56 2.656

3.3 0.00

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 0.00 0

3.3 1.66

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 1.66 0.166

3.3 39.84

Kosen Ventilasi
0.3 x 9 0.81
Kosen Pintu
2.16 x 1 2.16
Kosen Jendelah
1.52 x 6 5.29
Total Pasangan 31.58 3.15804

3.3 13.28

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 1 1.56
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 11.72 1.17248

3.3 0.00

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 0.00 0

3.3 13.28

Kosen Ventilasi
0.3 x 6 0.54
Kosen Pintu Kabaya
2.16 x 1 2.85
Kosen Jendelah
1.9 x 4 4.41

Total Pasangan 5.48 0.54808

3.3 0.00

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 0.00 0

3.3 1.66

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 1.66 0.166

3.3 1.66

Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00

Total Pasangan 1.66 0.166

0.5 x 1.0 0.60

Total Pasangan 1 0.60 0.060

0.2 0.18

Total Pasangan 1 0.18 0.018

0.15 0.02 0.08

Jumlah Tiang 25 0.5625 2.03

Total Beton Kolom 2.025

0.20 0.03 2.28


Total Beton Sloof 2.280

0.20 0.03 2.28

Total Beton Balok 2.280

Beton Canopi diatas Jendela


0.10 0.00 -

Jumlah Conopi 1 -

Beton Canopi diatas Jendela


0.10 0.08 0.72

Jumlah Conopi 1 0.72


0.10 Plat Septik 0.18 -

0.08 0.20 0.90


1.50 x 0.05 0.075 0.30

8.50 x 0.05 0.425 5.10

1.00 x 0.05 0.05 1.75

Total Beton Tumbuk 7.150

47.5 157.70

Total Luasan Kosen 19.17

Total 138.53
Total Muka Belakang 2 277.06

0.5 x 1.0 0.60

Total Muka Belakang 1 0.60

0.3 x 1 0.18

Total 2 WC 1 0.18

Total Plesteran ad. 1:2 0.78


1.5 18.00

7.0 0.00

Total Keramik Warna 40 x 40 Coklat 18.00

7.0 56.00

6.0 24.00

7.0 0.00

7.0 0.00

4.0 0.00

Total Keramik Putih Corak 40 x 40 80.00


0.60 13.20

0.60 4.20

0.57 0.00

Total Keramik Corak Alam 40 x 40 4.20

1.0 = 1.5 x 2 3.00

1.0 x 1.0 1.50

0.9 x 1 0.63

Total Keramik Polos 20 x 20 5.13

Luas Alas
0.6 = 0.36 0.36
Luas Dinding
0.6 x 3.6 = 1.296

Total 1 WC = 1.296 1.30

Luas Alas
6.0 = 7.5 7.50
Total Keramik Warna 20 x 25 Dinding 9.16
-

Balok Tarik = 0.0


Kaki Kuda-kuda
2 x 0.0 = 0.0

Tiang Kuda-kuda 0.0


Skor DE + DF
2 x 0.0 = 0.0
Skor EG + FH
2 x 0.0 = 0.0
Balok Pengunci = 0
Balok Pengapit
2 x 0.0 = 0.0

Total = 0.0

Buah Kuda-kuda = 0.0


Skor Angin
4 x 0.0 = 0.0 M
Nok Gording = 0

Total = 0 M

Uraian Volume
0.06 x 0.12 0.000

5 x 0 = 0
5 x 0 = 0

Total = 0 M

Uraian Volume
0.05 x 0.1 0

Balok Tarik = 7.0


Kaki Kuda-kuda = 5.2
= 5.8

Tiang Kuda-kuda 2.0


Skor DE + DF
2 x 2.0 = 4.0
Skor EG + FH
2 x 1.0 = 2.0
Balok Pengunci = 0.8
Balok Pengapit
2 x 3.5 = 7.0

Total = 33.9

Buah Kuda-kuda = 135.4


Skor Angin
6 x 3.0 = 18.0 M
Nok Gording = 10

Total = 163 M

Uraian Volume
0.06 x 0.12 1.177

8 x 21 = 168
6 x 9.5 = 57
6 x 9.5 = 57
9 x 21 = 189
Total = 471 M

Uraian Volume
0.05 x 0.1 2.355

48.00 9.6 0.288


Kayu 5/10 Kayu 5/7

4 = 32
4 = 28
9 = 72
7 = 49

4 = 28
4 = 32
4 = 28
5 = 40

3 = 4.5
3 = 4.5

5 = 10
4 = 16

3 = 4.5
3 = 4.5

3 = 28.5
15 = 12

3 = 42
24 = 19.2

3 = 28.5
17 = 13.6

3 = 21
11 = 8.8

2 = 16
5 = 7.5
2 = 16
9 = 13.5

5/10 = 143.5 + 0.11


5/7 = 0.11 + 436

Uraian Volume
0.05 x 0.1 0.71805
Uraian Volume
0.05 x 0.07 1.52712

7.0 x 8.0 1 56
6.5 x 4.0 26
0.0 x 0.0 0
0.0 x 0.0 0
0.0 x 0.0 0
0.0 x 0.0 0
Entrans WC 1.0 x 1.5 1.5
1.5 x 1.5 x 1.0 2.25

Samping Kiri 1.0 x 9.5 9.5


1.0 x 14.0 14
Samping Kanan 1.0 x 9.5 9.5
Depan Ruang Guru 2.0 x 4.0 8
2.0 x 9.0 18

Total Tripleks 144.75

Kayu 6 / 12

Ventilasi Type V1 Jumlah = 22


0.12 x 1.90 0.456 0.014
Jumlah 22 Bh 10.032 0.30

Jendela Type J1 Jumlah = 15


Panjang Jendelah = 4.20
4 x 0.041 = 0.164
Total = 4.36
0.12 x 4.36 1.008 0.031
Jumlah 15 Bh 15.12 0.47

Pintu Type P1 Jumlah = 2


Panjang Pintu = 5.64
2 x 0.041 = 0.082
Total = 5.72
0.12 x 5.72 1.3536 0.041
Jumlah 2 Bh 2.7072 0.08

Pintu Type P2 Jumlah = 1


Panjang Pintu = 5.09
2 x 0.041 = 0.082
Total = 5.17
0.12 x 5.17 1.22 0.037

Pintu Type P3 Jumlah = 2


Panjang Pintu = 5.04
2 x 0.041 = 0.082
Total = 5.12
0.12 x 5.12 1.21 0.0369
Jumlah 2 Bh 2.4192 0.0738

Total Kusen 31.50 0.97

Jendela Type J1 Jumlah = 15


1.40 0.53
Total Pintu 15 8.0

Pintu Type P1 Jumlah = 2


2.10 2.52
Total Pintu 2 5.04

Pintu Type P2 Jumlah = 1


2.10 1.37

Total Daun Panel 6.41

Pintu Type P3 Jumlah = 2


2.10 = 1.26 1.26
Daun Muka Belakang 2 2.52

Total Pintu 2 5.04


9
9.0 13.5
9.0 13.5
14.0 21

14.0 )x 3.5 x 1 75.25


14.0 )x 3.5 x 1 75.25
9.0 )x 3.5 x 1 52.5
9.0 )x 3.5 x 1 52.5

1.0 x 10 ) 10

Total Seng Gelombang 313.50

4.00 + 4.00 + 4 +
0 + 0

25.00
PERHITUNGAN VOLU
#REF! : ###
#REF! : ###
#REF! : ###

Pembesiaan
No. Lokasi /
Sketsa / Gambar Bengkokan Panjang
Urut STA
Atas Bawah Besi

01 Pembesian Kolom

0.03 0.03 0.03 0.03 3.70


3.70

4 O 12 0.03 0.03 0.48


0.12 O 8 - 10

0.12

Pembesian Sloof

0.03 0.03 0.03 0.03 75.95


75.95

4 O 12 0.03 0.03 0.58


0.17
O 8 - 15

0.12

Pembesian Balok

0.03 0.03 0.03 0.03 75.95


75.95

4 O 12 0.03 0.03 0.58


0.17
O 8 - 15

0.12

02. Pembesian Plat Septik

0.03 0.03 0.03 0.03 0.00


0.00

0.03 0.03 0.03 0.03 1.80


1.80
Pembesiaan
No. Lokasi /
Sketsa / Gambar Bengkokan Panjang
Urut STA
Atas Bawah Besi

03. Pembesian Plat Conopi di atas jendela

0.03 0.03 0.03 0.03 9.00


9.00

0.03 0.03 0.03 0.03 0.80


0.80

Pembesian Plat Lantai

0.03 0.03 0.03 0.03 4.50


4.50

0.03 0.03 0.03 0.03 2.50


2.50

04.

04.
1.86
3
Ukuran Tripleks
1.22 x 2.44 = 2.9768
0.61 0.8133
1.22 2.44

5.7377 3.27869 18.8


3.2787 2.86885 9.4
1.2295 0.61475 0.8
0.8197 0.61475 0.5
1.2295 0.61475 0.8

1.2295 3.27869 4.0312


0.6557 3.48361 2.2843
0.6557 5.7377 3.7624
0.6557 3.89344 2.5531
0.6557 2.86885 1.8812

44.746

18.812 2.9768 Luasan Tripleks


8.7342
0
0
0
0
0.5039
0.7558

3.1913
4.703
3.1913
2.6874
6.0468

48.626
11.345 Ukuran Seng Gelombang
11.345 1.83 x 0.81 = 1.4823
17.647 1.7 x 0.7 = 1.19

63.235
63.235
44.118
44.118

8.4034

263.45 lembar

21.008 10.5042 lembar


UNGAN VOLUME PEKERJAAN

Pembesiaan Panjang Jumlah Total


Jarak Panjang Bangunan Total
Total Total Stap Jumlah Volume
Panjang Besi Lebar Panjang Batang (M) ( Staf )

3.76 4.00 15.04 1.4 25.00 34

0.54 0.10 3.32 33 17.928 1.6 25.00 41

76.01 4.00 304.04 28 1.00 28

0.64 0.15 75.95 506 324.053 29 1.00 29

76.01 4.00 304.04 28 1.00 28

0.64 0.15 75.95 506 324.053 29 1.00 29

0.06 0.1 1.80 18 1.08 0 0.00 -

1.86 0.1 - - 0.00 0 0.00 -


Pembesiaan Panjang Jumlah Total
Jarak Panjang Bangunan Total
Total Total Stap Jumlah Volume
Panjang Besi Lebar Panjang Batang (M) ( Staf )

9.06 0.1 0.80 8 72.48 7 1.00 7

0.86 0.1 9.00 90 77.40 7 1.00 7

4.56 0.1 2.00 20 91.20 8 1.00 8

2.56 0.1 4.00 40 102.40 9 1.00 9

Besi dia. 12 114


Besi dia. 8 106
Besi dia. 12 89
Besi dia. 8 107
PERHITUNGAN VOLUME

#REF! : #REF!
#REF! : #REF!
#REF! : #REF!

No. URAIAN PEKERJAAN SATUAN

I. PEKERJAAN PENGGANTUNG, PENGUNCI & KACA

01. Kunci tanam 2x mengunci BH


02. Kunci BH
03. Engsel pintu nilon kuningan 4" PSG
04. Engsel jendela, ventilasi nilon kuningan 3" PSG
05. Grendel jendela, ventilasi kuningan kodok BH
06. Kait angin PSG
07. Baut, mur, beugel, angker dll. BH

II. PEKERJAAN INSTALASI LISTRIK

01. Titik cahaya lampu dan stop kontak TTK


02. Lampu hias ruang tamu BH
03. Lampu hias ruang keluarga BH
04. Lampu Philips SL 13 Watt BH
05. Lampu Philips TL 18 Watt BH
06. AC 1/2 PK merk mitsubishi komplit Unit
07. Stop kontak merk Broco BH
08. Saklar tunggal merk Broco BH
09. Saklar ganda merk Broco BH
10. Panel MCB 2 group Unit

III. PEKERJAAN INSTALASI AIR

01. Titik air bersih/ Instalasi air TTK


02. Kloset duduk poselin tipe concord BH
02. Kloset jongkok poselin tipe concord BH
03. Kran air vernekel BH
04. Kran air leher angsa BH
05. Wastafel porselin BH
06. Tempat cuci alluminium 2 bak BH
07. Floor dryn stanless steel BH
08. Saluran pembuangan kotoran, pipa PVC dia. 4" Staf
09. Saluran air kotor pipa PVC dia. 2" Staf

IV. PEKERJAAN PENGECATAN

01. Cat kayu dengan cat glotex M2


02. Menie teakoil M2
03. Cat plafon tripleks dengan Metrolite M2
04. Cat dinding luar dan dalam dengan Metrolite M2
05. Acian & Plamir dinding M2
VOLUME

2.00
3.00
7.00
15.00
15.00
30.00
25.00

14.00
0.00
0.00
6.00
8.00
0.00
2.00
2.00
4.00
1.00

3.00
0.00
2.00
3.00
0.00
1.00
0.00
0.00
3.00
3.00

41.10
313.50
144.75
277.06
277.06
TABEL BERAT BESI

NO DIA BERAT

1 25 #VALUE!

2 22 #VALUE!

3 19 #VALUE!

4 16 #VALUE!

5 12 #VALUE!

6 10 #VALUE!

7 8 #VALUE!

8 6 #VALUE!
LEMBAR ISIAN
1 KEGIATAN
PEKERJAAN : REHAB JALAN SETAPAK P=25M, L=1.2M
LOKASI : RT 003
DESA : DESA LATTA
TAHUN ANGGARAN : 2018
2 PELAKSANA
DIBUAT : J NITALESSY
JABATAN : TIM PELAKSANA KEGIATAN
DISETUJUI : L.H. SOPAMENA, S.STP, MT
JABATAN : PENJABAT KEPALA DESA
NIP : 19820126200112 1 004
DIVERIFIKASI : V PATTY
JABATAN : SEKERTARIS DESA
REKAPITULASI

PEKERJAAN : REHAB JALAN SETAPAK P=25M, L=1.2M


LOKASI : RT 003
DESA : DESA LATTA
TAHUN ANGGARAN : 2018

No. Jenis Pekerjaan

A PEKERJAAN PERSIAPAN

### REHAB JALAN SETAPAK P=25M, L=1.2M

C ALAT

D BIAYA UMUM

E PEMBERSIHAN AKHIR

NILAI KONSTRUKSI
JUMLAH NILAI KONSTRUKSI
DIBULATKAN

TERBILANG : #NAME?

DISETUJUI OLEH DIVERIFIKASI OLEH


PENJABAT KEPALA DESA SEKERTARIS DESA

PENJABAT KEPALA DESA V PATTY


NIP .19820126200112 1 004

DIPERIKSA OLEH
TA ID KOTA AMBON

JOHANIS D.S. PATTIAPON, ST


REKAPITULASI

Jumlah Harga
(Rp.)

1,900,000.00

1,881,207.05

#REF!

#REF!

#REF!

#REF!
#REF!
#REF!

DIBUAT OLEH
TIM PELAKSANA KEGIATAN

J NITALESSY

JOHANIS D.S. PATTIAPON, ST


RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : REHAB JALAN SETAPAK P=25M, L=1.2M


LOKASI : RT 003
DESA : DESA LATTA
TAHUN ANGGARAN : 2018

NO. JENIS PEKERJAAN TEM SATUAN

A PEKERJAAN PERSIAPAN
1 Pembersihan Awal BR-20 HOK
2 Papan Kegiatan BR-9 Ls
3 Gambar Kerja BR-13 Ls

B REHAB JALAN SETAPAK P=25M, L=1.2M


2 Rabat Beton A.A.4.1.4 M'

C ALAT
2 Skop BR-2 Bh
3 Benang Tukang BR-3 Tukal
4 Gerobak Dorong BR-4 Bh
5 Martil BR-5 Bh
7 Ember Cor BR-7 Bh

D HONOR
3 Insentif TPK BR-11 Ls

E PEMBERSIHAN AKHIR
1 Pemasangan Prasasti BR-10 Ls
2 Pembersihan Akhir BR-21 HOK
4 Administrasi + Dokumentasi BR-12 Ls
NGGARAN BIAYA (RAB)

HARGA JUMLAH HARGA


VOLUME SATUAN
(Rp.) (Rp.)

10.00 75,000.00 750,000.00


1.00 150,000.00 150,000.00
1.00 1,000,000.00 1,000,000.00
Jumlah 1,900,000.00

2.10 895,812.88 1,881,207.05


Jumlah 1,881,207.05
Total Jumlah II 1,881,207.05

2.00 85,000.00 170,000.00


5.00 10,000.00 50,000.00
1.00 500,000.00 500,000.00
2.00 50,000.00 100,000.00
4.00 15,000.00 60,000.00
Jumlah 880,000.00

1.00 650,000.00 650,000.00


Jumlah 650,000.00

1.00 450,000.00 450,000.00


10.00 500,000.00 5,000,000.00
1.00 500,000.00 500,000.00
Jumlah 5,950,000.00
RINCIAN ANGGARAN BIAYA

PEKERJAAN : REHAB JALAN SETAPAK P=25M, L=1.2M


LOKASI : RT 003
DESA : DESA LATTA
TAHUN ANGGARAN : 2018

HARGA JUMLAH
NO. URAIAN SATUAN VOLUME
(Rp.) (Rp.)

A UPAH
1 Mandor OH 190,000.00 0.13 23,940.00
2 Kepala Tukang OH 175,000.00 0.04 7,350.00
3 Tukang Batu OH 145,000.00 - -
4 Tukang Kayu OH 145,000.00 0.42 60,900.00
5 Tukang Besi OH 145,000.00 - -
6 Tukang Cat OH 145,000.00 - -
7 Tukang Listrik OH 145,000.00 - -
8 Pekerja OH 75,000.00 22.52 1,689,000.00
TOTAL I 1,781,190.00
B BAHAN - -
1 Pasir Urug M3 250,000.00 - -
2 Batu Kerikil Pecah ( 3 / 2 cm ) M3 250,000.00 - -
3 Batu Krikil (Kg) Kg 208.33 2,156.70 449,312.50
3 Pasir Beton Kg 227.27 1,875.30 426,204.55
4 Pasir Pasang M3 250,000.00 - -
5 Batu Kali M3 175,000.00 - -
6 Semen PC (Zak) Sak 75,000.00 - -
7 Semen PC (Kg) Kg 1,500.00 483.00 724,500.00
8 Pipa PVC dia. 2" M' 12,000.00 - -
TOTAL II 1,600,017.05
C ALAT - -
1 Pakuel Bh 90,000.00 - -
2 Skop Bh 85,000.00 2.00 170,000.00
3 Benang Tukang Tukal 10,000.00 5.00 50,000.00
4 Gerobak Dorong Bh 500,000.00 1.00 500,000.00
5 Martil Bh 50,000.00 2.00 100,000.00
6 Selang M' 15,000.00 - -
7 Ember Cor Bh 15,000.00 4.00 60,000.00
8 Gergaji Bh 50,000.00 - -
TOTAL III 880,000.00
D BIAYA UMUM - -
1 Papan Nama Proyek Bh 150,000.00 1.00 150,000.00
2 Prasasti Bh 500,000.00 1.00 500,000.00
3 Insentif Pekerja Ls 650,000.00 1.00 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00 1.00 1,000,000.00
5 Biaya Perencanaan Ls 1,000,000.00 1.00 1,000,000.00
TOTAL IV 3,300,000.00
GRAND TOTAL 7,561,207.05
ANALISA HARGA SATUAN

HARGA SATUAN
No. Uraian Kegiatan
(Rp.)

A.2.3.1.1. Penggalian 1M³ Tanah biasa sedalam 1 m


0.750 OH Pekerja 75,000.00
0.025 OH Mandor 190,000.00
A.2.3.1.9. Pengurungan kembali 1 M³ galian tanah
0.500 OH Pekerja 75,000.00
0.050 OH Mandor 190,000.00
A.2.3.1.11. Pengurungan 1M³ dengan pasir urug
0.300 OH Pekerja 75,000.00
0.010 OH Mandor 190,000.00
1.200 M3 Pasir urug 250,000.00
A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 4 PP
1.500 OH Pekerja 75,000.00
0.750 OH Tukang batu 145,000.00
0.075 OH Kepala tukang 175,000.00
0.075 OH Mandor 190,000.00
1.200 M3 Batu Kali 175,000.00
163.000 Kg Semen PC 1,500.00
0.520 M3 Pasir pasang 250,000.00
A.A.4.1.4 Pembuatan 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slum
1.200 OH Pekerja 75,000.00
0.200 OH Tukang batu 145,000.00
0.020 OH Kepala tukang 175,000.00
0.060 OH Mandor 190,000.00
230.000 Kg Semen PC 1,500.00
893.000 Kg Pasir Pasang 227.27
1,027.00 Kg Batu Kerikil 208.33
A.4.4.2.4. Pemasangan 1 m2 plesteran 1 SP : 4 PP, tebal 15 mm
0.300 OH Pekerja 75,000.00
0.150 OH Tukang batu 145,000.00
0.015 OH Kepala tukang 175,000.00
0.015 OH Mandor 190,000.00
6.240 Kg Semen PC 1,500.00
0.024 M3 Pasir pasang 250,000.00

PERALATAN DAN LAIN-LAIN


1.000 Bh Pakuel 90,000.00
1.000 Bh Skop 85,000.00
1.000 Tukal Benang Tukang 10,000.00
1.000 Bh Gerobak Dorong 500,000.00
1.000 Bh Martil 50,000.00
1.000 M' Selang 15,000.00
1.000 Bh Ember Cor 15,000.00
1.000 M' Gergaji 50,000.00

1.000 Bh Papan Nama Proyek 150,000.00


1.000 Bh Prasasti 500,000.00
1.000 Ls Insentif Pekerja 650,000.00
1.000 Ls Biaya Pmbersihan Awal 75,000.00
1.000 Ls Biaya Pembersihan Akhir 75,000.00
1.000 Ls Administrasi + Dokumentasi 1,000,000.00
1.000 Ls Biaya Perencanaan 1,000,000.00
LISA HARGA SATUAN

JUMLAH
(Rp.)

61,000.00
56,250.00
4,750.00
47,000.00
37,500.00
9,500.00
324,400.00
22,500.00
1,900.00
300,000.00
833,125.00
112,500.00
108,750.00
13,125.00
14,250.00
210,000.00
244,500.00
130,000.00
895,812.88
90,000.00
29,000.00
3,500.00
11,400.00
345,000.00
202,954.55
213,958.33
65,085.00
22,500.00
21,750.00
2,625.00
2,850.00
9,360.00
6,000.00

90,000.00
85,000.00
10,000.00
500,000.00
50,000.00
15,000.00
15,000.00
50,000.00

150,000.00
500,000.00
650,000.00
75,000.00
75,000.00
1,000,000.00
1,000,000.00
DAFTAR UPAH DAN HARGA BAHAN

PEKERJAAN : REHAB JALAN SETAPAK P=25M, L=1.2M


LOKASI : RT 003
DESA : DESA LATTA
TAHUN ANGGARAN : 2018

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A UPAH
1 Mandor OH 190,000.00
2 Kepala Tukang OH 175,000.00
3 Tukang Batu OH 145,000.00
4 Tukang Kayu OH 145,000.00
5 Tukang Besi OH 145,000.00
6 Tukang Cat OH 145,000.00
7 Tukang Listrik OH 145,000.00
8 Pekerja OH 75,000.00
9 Buruh Tidak Terlatih OH 85,000.00
B BAHAN
1 Kayu Klas I M3 6,500,000.00
2 Kayu Klas II M3 3,500,000.00
3 Papan Kayu Kls I M3 6,500,000.00
4 Papan Kayu Kls III M3 1,750,000.00
5 Pasir Urug M3 250,000.00
6 Batu Kerikil Pecah ( 3 / 2 cm ) M3 250,000.00
7 Pasir Pasang M3 250,000.00
8 Batu Kali M3 175,000.00
9 Pasir Beton Kg 227.27
10 Batu Krikil (Kg) Kg 208.33
11 Semen PC (Zak) Sak 75,000.00
12 Semen PC (Kg) Kg 1,500.00
13 Pipa PVC dia. 2" M' 12,000.00
C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
Ember Cor Bh 15,000.00
Gergaji Bh 50,000.00
D BIAYA UMUM
1 Papan Nama Proyek Bh 150,000.00
2 Prasasti Bh 500,000.00
3 Insentif Pekerja Ls 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00
5 Biaya Perencanaan Ls 1,000,000.00
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : REHAB JALAN SETAPAK P=25M, L=1.2M
LOKASI : RT 003
DESA : DESA LATTA

No. Lokasi / Lebar Perhitu


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah

PANJANG Jalan Setapak


3 Jalan Rabat
P = 25 m
L = 1.2 m
t = 0.07 m
09. RABAT BETON TUMBUK
A RABAT BETON
2 Jalan Rabat

0.07 1.20 0.07 25.00


1.20
VOLUME PEKERJAAN

Perhitungan Dimensi Luas Volume


(M) ( M2 ) ( M3 )

1.20 x 0.07 x 25.00 0.084 2.10

Total 2.100