1 KEGIATAN
PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN
LOKASI : RT 006
DESA : DESA LATTA
TAHUN ANGGARAN : 2019
2 PELAKSANA
DIBUAT : J NITALESSY
JABATAN : KAUR PERENCANAAN
DISETUJUI : L.H. SOPAMENA, S.STP, MT
JABATAN : PENJABAT KEPALA DESA
NIP : 19820126200112 1 004
DIVERIFIKASI : V PATTY
JABATAN : SEKERTARIS DESA
ALUR BAHAN DAN UPAH
B BAHAN
1 Kayu Klas I M3 7,000,000.00 700,000.00 105,000.00
2 Kayu 15 x 15-4M M' 100,800.00 10,080.00 2,362.50
3 Alat Bantu Pancang Set 100,000.00 10,000.00
4 Kayu 15 x 15-750 M M3 100,800.00 10,080.00 2,362.50
5 Kayu 20 x 20-1000 cm M3 280,000.00 28,000.00 4,200.00
6 Kayu Klas II M3 2,800,000.00 280,000.00 42,000.00
7 Papan Kayu Kls I M3 7,000,000.00 700,000.00 105,000.00
8 Papan Kayu Kls III M3 1,750,000.00 175,000.00 26,250.00
9 Batu Kerikil Pecah ( 3 / 2 cm ) M3 235,000.00 23,500.00 3,525.00
9 Pasir Pasang M3 200,000.00 20,000.00 3,000.00
10 Pasir Urug M3 140,000.00 14,000.00 2,100.00
11 Pasir Beton Kg 127.27 12.73 1.91
12 Batu Krikil (Kg) Kg 195.83 19.58 2.94
13 Batu Kali M3 178,000.00 17,800.00 2,670.00
14 Batako Bh 2,500.00 250.00 37.50
15 Semen PC (Zak) Sak 65,000.00 6,500.00 975.00
16 Semen PC (Kg) Kg 1,300.00 130.00 19.50
17 Sement Warna Kg 1,800.00 180.00 27.00
18 Air Liter 500.00 7.50
19 Besi Dia 16 mm Standart Staff 246,480.00 24,648.00 3,697.20
20 Besi Dia 12 mm Standart Staff 138,528.00 13,852.80 2,077.92
21 Besi Dia 10 mm Standart Staff 96,252.00 9,625.20 1,443.78
22 Besi Dia 6 mm Standart Staff 61,620.00 6,162.00 924.30
HARGA PPN PPh 22 PPh 21
No. KEBUTUHAN UPAH/BAHAN SAT
DASAR 10% 1.50% 2.50%
1 2 3 4 5 6 7
23 Dolken Kayu Galam Batang 20,000.00 2,000.00 300.00
24 Besi Strip Kg 5,000.00 500.00 75.00
25 Minyak Bakesting Liter 5,000.00 500.00 75.00
26 Paku / Skrup Genteng Kg 22,500.00 2,250.00 337.50
27 Paku Campuran Kg 19,000.00 1,900.00 285.00
28 Play Wood 3 mm uk. 120 x 240 cm Lbr 126,000.00 12,600.00 1,890.00
29 Cat Meni Besi Kg 30,000.00 3,000.00 450.00
30 Cat Kayu Kg 57,000.00 5,700.00 855.00
31 Plamir Kg 16,000.00 1,600.00 240.00
32 Politur Liter 25,000.00 2,500.00 375.00
33 Menie Kayu Kg 30,000.00 3,000.00 450.00
34 Dumpul Kayu Kg 15,000.00 1,500.00 225.00
35 Politur Kg 10,000.00 1,000.00 150.00
36 Politur Jadi Kg 25,000.00 2,500.00 375.00
37 Amplas Kg 25,000.00 2,500.00 375.00
38 Gloteks Kg 10,000.00 1,000.00 150.00
39 MCB 60 AMP Bh 210,000.00 21,000.00 3,150.00
40 Kabel NYM 3 x 2.5 mm M 15,000.00 1,500.00 225.00
41 Pipa PVC dia. 3" M' 22,000.00 2,200.00 330.00
42 Pipa PVC dia. 2" M' 12,000.00 1,200.00 180.00
43 Kran Air 3/4 Bh 35,000.00 3,500.00 525.00
44 Kran Air 1/2 Bh 35,000.00 3,500.00 525.00
45 Seal Tape Set 8,000.00 800.00 120.00
46 Floordrain (metal) Set 37,000.00 3,700.00 555.00
47 Wastafel lengkap Bh 544,000.00 54,400.00 8,160.00
48 Paving Block Bh 15,000.00 1,500.00 225.00
49 Sekring Bh 70,000.00 7,000.00 1,050.00
50 Kabel NYY 3x2,5 M' 15,000.00 1,500.00 225.00
51 Benang Roll 5,000.00 500.00 75.00
52 Titik Lampu Titik 75,000.00 7,500.00 1,125.00
53 Lem Kayu Kg 7,500.00 750.00 112.50
54 Pipa PVC Conduit M' 3,750.00 375.00 56.25
55 Lampu TL 20 Watt Bh 78,000.00 7,800.00 1,170.00
56 Lampu pijar philips putih 18 watt Bh 47,500.00 4,750.00 712.50
57 Lampu pijar philips putih 23 watt Bh 60,000.00 6,000.00 900.00
58 Lampu PL 11 Watt Bh 78,000.00 7,800.00 1,170.00
59 Saklar tunggal Bh 18,000.00 1,800.00 270.00
60 Saklar ganda Bh 25,000.00 2,500.00 375.00
61 Stop kontak Bh 23,000.00 2,300.00 345.00
62 Kabel NYY 3 Phase M' 15,000.00 1,500.00 225.00
63 Fiting Tempel Bh 15,000.00 1,500.00 225.00
64 T Dooz Bh 6,500.00 650.00 97.50
65 Isolator Bh 15,000.00 1,500.00 225.00
66 Lasdop Bh 5,000.00 500.00 75.00
67 Pipa Gip Medium A 2 Inci M' 95,833.33 9,583.33 1,437.50
68 Perlengkapan Pipa Galvanis 2 Inci Bh 50,000.00 5,000.00 750.00
69 Pipa Galvanis Medium A 1 1/2 Inci M' 77,500.00 7,750.00 1,162.50
70 Perlengkapan Pipa Galvanis 1 1/2 Inci Bh 30,000.00 3,000.00 450.00
71 Mangkok Listrik Bh 50,000.00 5,000.00 750.00
72 L.Bow Bh 2,500.00 250.00 37.50
73 Klem Pipa Bh 1,000.00 100.00 15.00
BAHAN DAN UPAH
- - 196,000.00
- - 171,000.00
- - 145,000.00
- - 145,000.00
- - 145,000.00
- - 145,000.00
- - 145,000.00
- - 75,000.00
- - 750,000.00
- - 500,000.00
A PEKERJAAN PERSIAPAN
D ALAT
E HONOR
F PEKERJAAN AKHIR
NILAI KONSTRUKSI
JUMLAH NILAI KONSTRUKSI
DIBULATKAN
TERBILANG : Dua Puluh Tiga Juta Delapan Ratus Enam Puluh Lima Ribu Rupiah
JUMLAH HARGA
(Rp.)
1,750,000.00
5,555,591.66
14,229,493.74
880,000.00
1,450,000.00
23,865,085.40
23,865,085.40
23,865,000.00
DIBUAT OLEH
KAUR PERENCANAAN
J NITALESSY
RENCANA ANGGARAN BIAYA (RAB)
A PEKERJAAN PERSIAPAN
1 Pembersihan Awal Ls 1.00
2 Papan Nama Kegiatan Ls 1.00
3 Biaya Perencanaan Ls 1.00
JUMLAH C =
D ALAT
1 Skop Bh 2.00
2 Benang Tukang Tukal 5.00
3 Gerobak Dorong Bh 1.00
4 Martil Bh 2.00
5 Ember Cor Bh 4.00
E HONOR
1 Insentif TPK Ls -
F PEMBERSIHAN AKHIR
1 Pemasangan Prasasti Ls 1.00
2 Pembersihan Akhir Ls 1.00
4 Administrasi + Dokumentasi Ls 1.00
ANGGARAN BIAYA (RAB)
750,000.00 750,000.00
250,000.00 250,000.00
750,000.00 750,000.00
Jumlah 1,750,000.00
69,291.00 768,298.61
1,360,181.00 4,787,293.05
Jumlah 5,555,591.66
61,150.00 33,021.00
1,360,181.00 734,497.74
561,808.00 8,427,120.00
31,307.00 469,605.00
Jumlah 9,664,243.74
119,950.00 1,799,250.00
64,150.00 962,250.00
24,050.00 1,803,750.00
Jumlah 4,565,250.00
JUMLAH C = I + II 14,229,493.74
85,000.00 170,000.00
10,000.00 50,000.00
500,000.00 500,000.00
50,000.00 100,000.00
15,000.00 60,000.00
Jumlah 880,000.00
650,000.00 -
Jumlah -
450,000.00 450,000.00
500,000.00 500,000.00
500,000.00 500,000.00
Jumlah 1,450,000.00
RINCIAN ANGGARAN BIAYA
HARGA
NO. URAIAN SATUAN (Rp.)
A UPAH
1 Mandor OH 196,000.00
2 Kepala Tukang OH 171,000.00
3 Tukang Batu OH 145,000.00
4 Tukang Kayu OH 145,000.00
6 Tukang Listrik OH 145,000.00
5 Pekerja OH 75,000.00
6 Upah Pembersihan Awal OH 750,000.00
7 Upah Pembersihan Akhir OH 500,000.00
T
B BAHAN
2 Batu Kerikil Pecah ( 3 / 2 cm ) M3 437,100.00
3 Batu Krikil (Kg) Kg 400.00
4 Pasir Pasang M3 398,000.00
5 Pasir Beton Kg 300.00
6 Pasir Urug M3 331,100.00
7 Batu Kali M3 373,500.00
8 Semen PC (Kg) Kg 1,600.00
9 Air Kg 600.00
10 Cat Kayu Kg 63,600.00
11 Menie Kayu Kg 33,500.00
13 Kayu Klas II M3 3,141,300.00
17 Kabel NYY 3x2,5 M' 16,800.00
18 Lampu pijar philips putih 23 watt Bh 66,900.00
19 Saklar tunggal Bh 20,100.00
20 Saklar ganda Bh 27,900.00
21 Stop kontak Bh 25,700.00
22 Fiting Tempel Bh 16,800.00
23 Pipa Gip Medium A 2 Inci m' 126,900.00
T
C ALAT
1 Skop Bh 85,000.00
2 Benang Tukang Tukal 10,000.00
3 Gerobak Dorong Bh 500,000.00
4 Martil Bh 50,000.00
5 Ember Cor Bh 15,000.00
TO
D BIAYA UMUM
1 Papan Nama Proyek Bh 250,000.00
2 Prasasti Bh 450,000.00
3 Insentif TPK Ls 650,000.00
4 Administrasi + Dokumentasi Ls 500,000.00
5 Gambar kerja Ls 750,000.00
TO
GRAND
RINCIAN ANGGARAN BIAYA
JUMLAH
VOLUME (Rp.)
0.60 117,600.00
0.60 102,600.00
3.80 551,000.00
1.10 159,500.00
11.30 1,638,500.00
12.70 952,500.00
1.00 750,000.00
1.00 500,000.00
TOTAL I 4,771,700.00
- -
- -
4,055.50 1,622,200.00
0.30 119,400.00
3,527.80 1,058,340.00
- -
- -
1,071.90 1,715,040.00
811.90 487,140.00
3.90 248,040.00
3.00 100,500.00
- -
75.00 1,260,000.00
15.00 1,003,500.00
- -
15.00 418,500.00
- -
15.00 252,000.00
63.00 7,994,700.00
TOTAL II 16,279,360.00
- -
2.00 170,000.00
5.00 50,000.00
1.00 500,000.00
2.00 100,000.00
4.00 60,000.00
TOTAL III 880,000.00
- -
1.00 250,000.00
1.00 450,000.00
- -
1.00 500,000.00
1.00 750,000.00
TOTAL IV 1,950,000.00
GRAND TOTAL 23,881,060.00
ANALISA HARGA SATUAN-SNI 2016
HARGA SATUAN
No. Uraian Kegiatan
(Rp.)
JUMLAH
(Rp.)
61,150.00
56,250.00
4,900.00
47,300.00
37,500.00
9,800.00
421,780.00
22,500.00
1,960.00
397,320.00
720,598.20
58,500.00
56,550.00
6,669.00
7,644.00
448,200.00
143,035.20
1,164,735.00
112,500.00
108,750.00
12,825.00
14,700.00
448,200.00
260,800.00
206,960.00
1,360,181.00
123,750.00
39,875.00
4,788.00
16,268.00
395,200.00
260,700.00
399,600.00
120,000.00
69,291.00
22,500.00
21,750.00
2,565.00
2,940.00
9,984.00
9,552.00
561,808.00
6,075.00
19,575.00
2,394.00
784.00
532,980.00
31,307.00
5,250.00
1,305.00
1,026.00
490.00
6,700.00
16,536.00
JUMLAH
(Rp.)
119,950.00
36,250.00
16,800.00
66,900.00
61,950.00
36,250.00
25,700.00
56,350.00
36,250.00
20,100.00
64,150.00
36,250.00
27,900.00
53,050.00
36,250.00
16,800.00
24,050.00
7,250.00
16,800.00
90,000.00
85,000.00
10,000.00
500,000.00
50,000.00
15,000.00
15,000.00
50,000.00
250,000.00
450,000.00
650,000.00
750,000.00
500,000.00
500,000.00
750,000.00
DAFTAR UPAH DAN HARGA BAHAN
HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)
A UPAH
1 Mandor OH 196,000.00
2 Kepala Tukang OH 171,000.00
3 Tukang Batu OH 145,000.00
4 Tukang Kayu OH 145,000.00
5 Tukang Besi OH 145,000.00
6 Tukang Cat OH 145,000.00
7 Tukang Listrik OH 145,000.00
8 Pekerja OH 75,000.00
8 Upah Pembersihan Awal Ls 750,000.00
9 Upah Pembersihan Akhir Ls 500,000.00
B BAHAN
1 Kayu Klas I M3 7,955,000.00
2 Kayu Klas II M3 3,141,300.00
3 Papan Kayu Kls I M3 7,955,000.00
4 Papan Kayu Kls III M3 2,101,300.00
5 Pasir Urug M3 331,100.00
6 Batu Kerikil Pecah ( 3 / 2 cm ) M3 437,100.00
7 Pasir Pasang M3 398,000.00
8 Batu Kali M3 373,500.00
9 Pasir Beton Kg 300.00
10 Batu Krikil (Kg) Kg 400.00
11 Semen PC (Zak) Sak 76,000.00
12 Semen PC (Kg) Kg 1,600.00
13 Cat Meni Besi Kg 33,500.00
14 Cat Kayu Kg 63,600.00
15 Plamir Kg 17,900.00
16 Politur Kg 27,900.00
17 Menie Kayu Kg 33,500.00
18 Dumpul Kayu Kg 16,800.00
19 Air Kg 600.00
20 Sekring Bh 78,100.00
21 Kabel NYY 3x2,5 M' 16,800.00
22 Benang Roll 5,600.00
23 Titik Lampu Titik 83,700.00
24 Lem Kayu Kg 8,400.00
25 Pipa PVC Conduit M' 4,200.00
26 Lampu TL 20 Watt Bh 87,000.00
27 Lampu pijar philips putih 18 watt Bh 53,000.00
28 Lampu pijar philips putih 23 watt Bh 66,900.00
29 Lampu PL 11 Watt Bh 87,000.00
30 Saklar tunggal Bh 20,100.00
31 Saklar ganda Bh 27,900.00
32 Stop kontak Bh 25,700.00
33 Kabel NYY 3 Phase M' 16,800.00
34 Fiting Tempel Bh 16,800.00
35 Pipa Gip Medium A 2 Inci m' 126,900.00
36 Perlengkapan Pipa Galvanis 2 Inci m' 55,800.00
37 Pipa Galvanis Medium A 1 1/2 Inci m' 104,500.00
38 Perlengkapan Pipa Galvanis 1 1/2 Inci m' 33,500.00
HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)
C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
7 Ember Cor Bh 15,000.00
8 Gergaji Bh 50,000.00
D BIAYA UMUM
1 Papan Nama Proyek Bh 250,000.00
2 Prasasti Bh 450,000.00
3 Biaya Pembersihan Awal Ls 750,000.00
4 Biaya Pembersihan Akhir Ls 500,000.00
3 Insentif TPK Ls 650,000.00
4 Administrasi + Dokumentasi Ls 500,000.00
5 Gambar kerja Ls 750,000.00
PERHITUNGAN VOLUME PEKERJAAN JALAN RABAT
PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN
LOKASI : RT 006
DESA : DESA LATTA
2 Jalan Rabat
Total
B Plesteran Anak Tangga
bagian T x l x x bh
i 1 0.24 x 2.10 x x 22
ii 2 0.00 x 0.00 x x 0
iii 3 0.00 x 0.00 x x 0
Total Plesteran
ME PEKERJAAN JALAN RABAT
Volume
( M3 )
0.832
2.69
3.520
11.088
0
0
11.088
PERHITUNGAN VOLUME PEKERJAAN LAM
PEKERJAAN : REHAB JALAN SETAPAK DAN PENERANGAN JALAN
LOKASI : RT 006
DESA : DESA LATTA
LAMPU JALAN
1 TITIK LAMPU
n = 15 BH
T = 4 M
2 PONDASI UMPAK
n = 15 BH
P = 0.3 M
l = 0.3 M
t = 0.4 M
3 ACSESORIS
n = 15 BH
Cok =
Kabel =
Lampu =
N L T p
15 0.3 0.40 0.30
0.4
0.30
TIANG LAMPU
N L T
15 1.00 4.00
1.00
06. PENGECATAN TIANG LAMPU
PENGECATAN
N D T p
15 0.25 4.00 0.0
0.25
JAAN LAMPU JALAN
p x l x t X N
0.3 X 0.3 X 0.4 X 15.0 0.54
p x l x t X N
0.3 X 0.3 X 0.4 X 15.0 0.54
x t X N
X 4 X 15 60
TIANG LAMPU 60
15.00 STAFF
l x t X N
0.25 X 4 X 15 15
PENGECATAN 15
15.00 m2
REKAPITULASI
A PEKERJAAN PERSIAPAN
### ALAT
D BIAYA UMUM
E PEKERJAAN AKHIR
NILAI KONSTRUKSI
JUMLAH NILAI KONSTRUKSI
DIBULATKAN
DIPERIKSA OLEH
TA ID KOTA AMBON
Jumlah Harga
(Rp.)
1,500,000.00
880,000.00
650,000.00
1,450,000.00
4,480,000.00
4,480,000.00
4,480,000.00
DIBUAT OLEH
KAUR PERENCANAAN
J NITALESSY
A PEKERJAAN PERSIAPAN
1 Pembersihan Awal BR-20 Ls
2 Biaya Perencanaan BR-13 Ls
C ALAT
2 Skop BR-2 Bh
3 Benang Tukang BR-3 Tukal
4 Gerobak Dorong BR-4 Bh
5 Martil BR-5 Bh
7 Ember Cor BR-7 Bh
D BIAYA UMUM
3 Insentif Pekerja BR-11 Ls
E PEMBERSIHAN AKHIR
1 Pemasangan Prasasti BR-10 Ls
2 Pembersihan Akhir BR-21 Ls
4 Administrasi + Dokumentasi BR-12 Ls
NGGARAN BIAYA (RAB)
4O 12
0.15 0.15 0.15 3.60 0.15 x
` 8 - 15
Kolom 15/15
0.15
4O 12
0.15 0.20 - 0.15 x
0.20 O 8 - 20
4O 12
0.20 0.15 0.20 - 0.15 x
O 8 - 20
Balok 15/20
0.15 `
0.8
Beton Bertulang Utk Plat Septik
1.8
Beton Bertulang Utk Plat Lantai
2.5
05. RABAT BETON TUMBUK
1.50
8.50
0 - 0 x
0.00
Total Luasan Kos
0.0
VOLUME PEKERJAAN
0.20 0.03 0
0.20 0.03 -
Jumlah Conopi 1 -
0.0 0.00
Total 0.00
Total Muka Belakang 2 0.00
PERHITUNGAN VOLUME PE
#REF! : ###
#REF! : ###
#REF! : ###
Pembesiaan
No. Lokasi /
Sketsa / Gambar Bengkokan Panjang
Urut STA
Atas Bawah Besi
01 Pembesian Kolom
0.12
Pembesian Sloof
0.12
Pembesian Balok
0.12
Besi dia. 12 59
Besi dia. 8 47
Kota : AMBON
Kecamatan : BAGUALA BACK UP TALUD
Desa : DESA LATTA RT 010 / RW 003
I. PEKERJAAN PERSIAPAN
1.00 M'
0.8
1.00 M
V. Plesteran = 121.50 M2
Kota : AMBON
Kecamatan : BAGUALA BACK UP TALUD
Desa : DESA LATTA RT 010 / RW 003
I. PEKERJAAN PERSIAPAN
0.50 M'
0.4
0.40 M
V. Plesteran = 15.05 M2
PERHITUNGAN VOLUME PEKERJAAN
### : ###
### : ###
### : ###
0.25
0.15 0.25 15.60 0.15 x
0.15
0.05
0.60
0.05
0.60
0.05
0.60
0.15
2 Pasangan Batu Kali Pondasi Tangga 3
0.15
Plesteran Pondasi
0.60
Total 9.36
PERHITUNGAN VOLUME PEKERJAAN
### : ###
### : ###
### : ###
0.4
0.30 0.40 109.00 0.30 x
0.30
Staff
Buah
LEMBAR ISIAN
1 KEGIATAN
PEKERJAAN : PEMBANGUNAN DRAINASE TYPE I
LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018
2 PELAKSANA
DIBUAT : JACOB N BUNGAA
JABATAN : KAUR PERENCANAAN
DISETUJUI : IMELDA A. TAHALELE, S.STP
JABATAN : PEJABAT KEPALA DESA
NIP : 19800706 1991 2 001
REKAPITULASI
Jumlah Harga
No. Jenis Pekerjaan
(Rp.)
TERBILANG : Dua Puluh Sembilan Juta Delapan Ratus Sembilan Puluh Dua Ribu Rupiah
Jumlah Harga
(Rp.)
4,520,000.00
25,372,906.28
4,067,836.88
21,305,069.40
29,892,906.28
29,892,906.28
29,892,000.00
DIBUAT OLEH
KAUR PERENCANAAN
JACOB N BUNGAA
RENCANA ANGGARAN BIAYA (RAB)
I PEKERJAAN PERSIAPAN/UMUM
A OPERASIONAL
1 Papan Nama Proyek BR-9 Ls
2 Prasasti BR-10 Ls
3 Insentif Pekerja BR-11 Ls
4 Administrasi + Dokumentasi selama proyek berjalan BR-12 Ls
5 Asbuilt drawing BR-13 Ls
A ALAT
1 Pakuel BR-1 Bh
2 Skop BR-2 Bh
3 Benang Tukang BR-3 Tukal
4 Gerobak Dorong BR-4 Bh
5 Martil BR-5 Bh
6 Selang BR-6 M'
7 Ember Cor BR-7 Bh
8 Gergaji BR-8 M'
HARGA
NO. URAIAN SATUAN
(Rp.)
A UPAH
1 Mandor OH 175,000.00
2 Kepala Tukang OH 150,000.00
3 Tukang Batu OH 125,000.00
4 Tukang Kayu OH 125,000.00
5 Tukang Besi OH 125,000.00
6 Tukang Cat OH 125,000.00
7 Tukang Listrik OH 125,000.00
8 Pekerja OH 75,000.00
B BAHAN
1 Pasir Urug M3 1,750,000.00
2 Batu Kerikil Pecah ( 3 / 2 cm ) M3 175,000.00
3 Batu Krikil (Kg) Kg 145.83
3 Pasir Beton Kg 159.09
4 Pasir Pasang M3 175,000.00
5 Batu Kali M3 175,000.00
6 Semen PC (Zak) Sak 75,000.00
7 Semen PC (Kg) Kg 1,500.00
8 Pipa PVC dia. 2" M' 12,000.00
C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
7 Ember Cor Bh 15,000.00
8 Gergaji Bh 50,000.00
JUMLAH
VOLUME
(Rp.)
3.70 647,311.88
2.37 355,012.50
13.77 1,721,250.00
9.90 1,237,187.50
- -
- -
- -
77.16 5,786,831.25
TOTAL I 9,747,593.13
- -
1.30 2,268,000.00
- -
10,270.00 1,497,708.33
8,930.00 1,420,681.82
7.68 1,343,790.00
12.64 2,211,300.00
- -
4,589.22 6,883,833.00
- -
TOTAL II 15,625,313.15
- -
1.00 90,000.00
2.00 170,000.00
5.00 50,000.00
1.00 500,000.00
2.00 100,000.00
10.00 150,000.00
4.00 60,000.00
2.00 100,000.00
TOTAL III 1,220,000.00
- -
1.00 150,000.00
1.00 500,000.00
1.00 650,000.00
1.00 1,000,000.00
1.00 1,000,000.00
TOTAL IV 3,300,000.00
GRAND TOTAL 29,892,906.28
ANALISA HARGA SATUAN
HARGA SATUAN
No. Uraian Kegiatan
(Rp.)
JUMLAH
(Rp.)
60,625.00
56,250.00
4,375.00
46,250.00
37,500.00
8,750.00
2,124,250.00
22,500.00
1,750.00
2,100,000.00
776,125.00
112,500.00
93,750.00
11,250.00
13,125.00
210,000.00
244,500.00
91,000.00
765,339.02
90,000.00
25,000.00
3,000.00
10,500.00
345,000.00
142,068.18
149,770.83
59,685.00
22,500.00
18,750.00
2,250.00
2,625.00
9,360.00
4,200.00
90,000.00
85,000.00
10,000.00
500,000.00
50,000.00
15,000.00
15,000.00
50,000.00
150,000.00
500,000.00
650,000.00
1,000,000.00
1,000,000.00
DAFTAR UPAH DAN HARGA BAHAN
HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)
A UPAH
1 Mandor OH 175,000.00
2 Kepala Tukang OH 150,000.00
3 Tukang Batu OH 125,000.00
4 Tukang Kayu OH 125,000.00
5 Tukang Besi OH 125,000.00
6 Tukang Cat OH 125,000.00
7 Tukang Listrik OH 125,000.00
8 Pekerja OH 75,000.00
B BAHAN
1 Kayu Klas I M3 6,500,000.00
2 Kayu Klas II M3 3,500,000.00
3 Papan Kayu Kls I M3 6,500,000.00
4 Papan Kayu Kls III M3 1,750,000.00
5 Pasir Urug M3 1,750,000.00
6 Batu Kerikil Pecah ( 3 / 2 cm ) M3 175,000.00
7 Pasir Pasang M3 175,000.00
8 Batu Kali M3 175,000.00
9 Pasir Beton Kg 159.09
10 Batu Krikil (Kg) Kg 145.83
11 Semen PC (Zak) Sak 75,000.00
12 Semen PC (Kg) Kg 1,500.00
13 Pipa PVC dia. 2" M' 12,000.00
C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
Ember Cor Bh 15,000.00
Gergaji Bh 50,000.00
D OPERASIONAL DAN BIAYA LAIN-LAIN
1 Papan Nama Proyek Bh 150,000.00
2 Prasasti Bh 500,000.00
3 Insentif Pekerja Ls 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00
5 As Buildrawing Ls 1,000,000.00
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : PEMBANGUNAN DRAINASE TYPE I
LOKASI : RT 009
DESA : NEGERI LAMA
PANJANG SALURAN
= 54 M
0.65
0.70 0.65 54.00 0.70 x
0.70
0.08
0.25
0.15
08. PLESTERAN
Plesteran Saluran
0.50 0.5
0.40
VOLUME PEKERJAAN
Total 91.80
LEMBAR ISIAN
1 KEGIATAN
PEKERJAAN : PEMBANGUNAN DRAINASE TYPE II
LOKASI : RT 009
DESA : NEGERI LAMA
TAHUN ANGGARAN : 2018
2 PELAKSANA
DIBUAT : JACOB N BUNGAA
JABATAN : KAUR PERENCANAAN
DISETUJUI : IMELDA A. TAHALELE, S.STP
JABATAN : PEJABAT KEPALA DESA
NIP : 19800706 1991 2 001
REKAPITULASI
Jumlah Harga
No. Jenis Pekerjaan
(Rp.)
TERBILANG : Dua Puluh Delapan Juta Lima Ratus Dua Puluh Satu Ribu Rupiah
Jumlah Harga
(Rp.)
4,520,000.00
24,001,303.46
3,391,892.44
20,609,411.03
28,521,303.46
28,521,303.46
28,521,000.00
DIBUAT OLEH
KAUR PERENCANAAN
JACOB N BUNGAA
RENCANA ANGGARAN BIAYA (RAB)
I PEKERJAAN PERSIAPAN/UMUM
A OPERASIONAL
1 Papan Nama Proyek BR-9 Ls
2 Prasasti BR-10 Ls
3 Insentif Pekerja BR-11 Ls
4 Administrasi + Dokumentasi selama proyek berjalan BR-12 Ls
5 Asbuilt drawing BR-13 Ls
A ALAT
1 Pakuel BR-1 Bh
2 Skop BR-2 Bh
3 Benang Tukang BR-3 Tukal
4 Gerobak Dorong BR-4 Bh
5 Martil BR-5 Bh
6 Selang BR-6 M'
7 Ember Cor BR-7 Bh
8 Gergaji BR-8 M'
HARGA
NO. URAIAN SATUAN
(Rp.)
A UPAH
1 Mandor OH 175,000.00
2 Kepala Tukang OH 150,000.00
3 Tukang Batu OH 125,000.00
4 Tukang Kayu OH 125,000.00
5 Tukang Besi OH 125,000.00
6 Tukang Cat OH 125,000.00
7 Tukang Listrik OH 125,000.00
8 Pekerja OH 75,000.00
B BAHAN
1 Pasir Urug M3 1,750,000.00
2 Batu Kerikil Pecah ( 3 / 2 cm ) M3 175,000.00
3 Batu Krikil (Kg) Kg 145.83
3 Pasir Beton Kg 159.09
4 Pasir Pasang M3 175,000.00
5 Batu Kali M3 175,000.00
6 Semen PC (Zak) Sak 75,000.00
7 Semen PC (Kg) Kg 1,500.00
8 Pipa PVC dia. 2" M' 12,000.00
C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
7 Ember Cor Bh 15,000.00
8 Gergaji Bh 50,000.00
JUMLAH
VOLUME
(Rp.)
3.27 571,881.19
2.21 331,218.75
12.29 1,535,625.00
9.80 1,224,531.25
- -
- -
- -
67.62 5,071,820.63
TOTAL I 8,735,076.81
- -
1.21 2,116,800.00
- -
10,270.00 1,497,708.33
8,930.00 1,420,681.82
7.37 1,289,925.00
12.47 2,182,950.00
- -
4,505.44 6,758,161.50
- -
TOTAL II 15,266,226.65
- -
1.00 90,000.00
2.00 170,000.00
5.00 50,000.00
1.00 500,000.00
2.00 100,000.00
10.00 150,000.00
4.00 60,000.00
2.00 100,000.00
TOTAL III 1,220,000.00
- -
1.00 150,000.00
1.00 500,000.00
1.00 650,000.00
1.00 1,000,000.00
1.00 1,000,000.00
TOTAL IV 3,300,000.00
GRAND TOTAL 28,521,303.46
ANALISA HARGA SATUAN
HARGA SATUAN
No. Uraian Kegiatan
(Rp.)
JUMLAH
(Rp.)
60,625.00
56,250.00
4,375.00
46,250.00
37,500.00
8,750.00
2,124,250.00
22,500.00
1,750.00
2,100,000.00
776,125.00
112,500.00
93,750.00
11,250.00
13,125.00
210,000.00
244,500.00
91,000.00
765,339.02
90,000.00
25,000.00
3,000.00
10,500.00
345,000.00
142,068.18
149,770.83
59,685.00
22,500.00
18,750.00
2,250.00
2,625.00
9,360.00
4,200.00
90,000.00
85,000.00
10,000.00
500,000.00
50,000.00
15,000.00
15,000.00
50,000.00
150,000.00
500,000.00
650,000.00
1,000,000.00
1,000,000.00
DAFTAR UPAH DAN HARGA BAHAN
HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)
A UPAH
1 Mandor OH 175,000.00
2 Kepala Tukang OH 150,000.00
3 Tukang Batu OH 125,000.00
4 Tukang Kayu OH 125,000.00
5 Tukang Besi OH 125,000.00
6 Tukang Cat OH 125,000.00
7 Tukang Listrik OH 125,000.00
8 Pekerja OH 75,000.00
B BAHAN
1 Kayu Klas I M3 6,500,000.00
2 Kayu Klas II M3 3,500,000.00
3 Papan Kayu Kls I M3 6,500,000.00
4 Papan Kayu Kls III M3 1,750,000.00
5 Pasir Urug M3 1,750,000.00
6 Batu Kerikil Pecah ( 3 / 2 cm ) M3 175,000.00
7 Pasir Pasang M3 175,000.00
8 Batu Kali M3 175,000.00
9 Pasir Beton Kg 159.09
10 Batu Krikil (Kg) Kg 145.83
11 Semen PC (Zak) Sak 75,000.00
12 Semen PC (Kg) Kg 1,500.00
13 Pipa PVC dia. 2" M' 12,000.00
C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
Ember Cor Bh 15,000.00
Gergaji Bh 50,000.00
D OPERASIONAL DAN BIAYA LAIN-LAIN
1 Papan Nama Proyek Bh 150,000.00
2 Prasasti Bh 500,000.00
3 Insentif Pekerja Ls 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00
5 As Buildrawing Ls 1,000,000.00
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : PEMBANGUNAN DRAINASE TYPE II
LOKASI : RT 009
DESA : NEGERI LAMA
PANJANG SALURAN
= 63 M
0.55
0.50 0.55 63.00 0.50 x
0.50
0.08
0.20
0.15
08. PLESTERAN
Plesteran Saluran
0.40 0.4
0.20
VOLUME PEKERJAAN
Total 81.90
PERHITUNGAN VOLUME PEKERJA
#REF! : ###
#REF! : ###
#REF! : ###
No. Lebar
Lokasi / STA Sketsa / Gambar Tinggi Panjang
Urut Atas Bawah
= 31 + 32
= 63 M / 3 = 21
0.55
0.60
0.05
0.60
0.60
05. PASANGAN BATU
0.55
0.4
4O 12
0.15 0.15 0.15 1.70
` 8 - 15
Kolom 15/15
0.15
Beton Bertulang Utk Sloof
4O 12
0.15 0.20 61.00
0.20 O 8 - 20
4O 12
0.20 0.15 0.20 61.00
O 8 - 20
Balok 15/20
0.15 `
61.0 1.7
1.7
61
0.1
8. PLESTERAN
Plesteran Sumbu Tegak/Datar
1.7 61.00
1.70
61
VOLUME PEKERJAAN
Kolom Beton
0.15 x 0.15 x 21 0.47
Total 103.70
Total Muka Belakang 2 207.40
TAKE OF SHEET
#REF! : ###
#REF! : ###
#REF! : ###
Pembesiaan
No. Lokasi /
Sketsa / Gambar Bengkokan Panjang
Urut STA
Atas Bawah Besi
0.12
0.12
0.12
Besi dia. 10 58
Besi dia. 8 65
PERHITUNGAN VOLUME PEKERJAAN
### : ###
### : ###
### : ###
1.65
2.30
0.05
2.30
0.6
2.30
1.5
8.2
0.1
06. BETON
2.30
07. PLESTERAN
8.2
VOLUME PEKERJAAN
8.2 12.30
PERHITUNGAN VOLU
#REF! : ###
#REF! : ###
#REF! : ###
Pembesiaan
No. Lokasi /
Sketsa / Gambar Bengkokan Panjang
Urut STA
Atas Bawah Besi
Besi dia. 10 9
PERHITUNGAN VOLUME PEKERJAAN
### : ###
### : ###
### : ###
= 33 + 43
= 76 M
PEKERJAAN TANAH
0.80
0.80
0.05
0.8
0.05
8.5
0.05
0.9
8.5
0.9
0.90
0.50
0.50
Sumbu Tegak
Pasangan Batu Bata 1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
1.32 x
Kosen Jendelah
7 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
1.32 x
Kosen Jendelah
8.0 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
0.72 x
Kosen Jendelah
1.5 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
1.32 x
Kosen Jendelah
1.5 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
0.72 x
Kosen Jendelah
8 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
0 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
0.5 0.58 x
0.1
Sumbu Datar
Pasangan Batu Bata 1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu
1.00 x
Kosen Jendelah
12 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
0.72 x
Kosen Jendelah
4 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.86 x
Kosen Jendelah
0 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
4 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
0 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
0.5 0.58 x
0.1
Kosen Ventilasi
3.32 0.30 x
Kosen Pintu Kab
1.32 x
Kosen Jendelah
0.5 0.58 x
0.1
Bak Kecil
0.1
1.20
Dinding Kloset
4O 12
0.15 0.15 0.15 3.60 0.15 x
` 8 - 15
Kolom 15/15
0.15
4O 12
0.15 0.20 76.00 0.15 x
0.20 O 8 - 20
4O 12
0.20 0.15 0.20 76.00 0.15 x
O 8 - 20
Balok 15/20
0.15 `
0.8
Beton Bertulang Utk Plat Septik
1.8
Beton Bertulang Utk Plat Lantai
2.5
05. RABAT BETON TUMBUK
1.50
8.50
47.5
Bak KM
0.5
1.20
Kloset
0.30
0.60
12
0
Total Keramik Warn
Lantai Keramik Ruang 1
8.0
4.0
0.0
22
0
Total Keramik Cora
05. Pemasangan Lantai WC/KM Keramik 20 x 20 Anti Slip
Lantai Keramik KM
1.00 1.50 1.50 x
1.5 1.5
Luas Alas
0.5 0.50 3.60 0.60 x
Luas Dinding
0.60 x
3.60
Dinding Lapis Wc
Luas Alas
1.25 1.25 6.00 1.25 x
Total Keramik Warn
PEKERJAAN KAYU DAN ATAP
A G H B Balok Tarik
0 D 0 Kaki Kuda-kuda
0.00
Tiang Kuda-kuda
Dari Kuda-kuda ABC diketahui Skor DE + DF
<A = <B = 30 °
CD = 1/2 AC = 1/2 BC Skor EG + FH
AD = BD = 0
AC² = CD² + AD² Balok Pengunci
AC² = ( 1/2 AC² ) + ( 0 )² Balok Pengapit
AC² = 1/4 AC² + 0
4 AC² = AC² + 4 X 0
3 AC² = 0.00 `
AC² = 0.00 = 0
3 3
AC = Ѵ 0 = 0.0 Skor Angin
CD = 1/2 AC = 0.0
AD = EF = 0 Nok Gording
ED = DF = CD = 0.0 ( <C1 = <D2 = <E= 60° )
EG = FH = 1/2 CD = 0.0
Uraian Volume
0 x
02. Kayu 5 / 10
Gording
Uraian Volume
0 x
A G H B Balok Tarik
3.5 D 3.5 Kaki Kuda-kuda
7.00
Tiang Kuda-kuda
Dari Kuda-kuda ABC diketahui Skor DE + DF
<A = <B = 30 °
CD = 1/2 AC = 1/2 BC Skor EG + FH
AD = BD = 3.5
AC² = CD² + AD² Balok Pengunci
AC² = ( 1/2 AC² ) + ( 3.5 )² Balok Pengapit
AC² = 1/4 AC² + 12.25
4 AC² = AC² + 4 X 12.25
3 AC² = 49.00 `
AC² = 49.00 = 16.333
3
AC = Ѵ 16.333 = 4.0 4
CD = 1/2 AC = 2.0 Skor Angin
AD = EF = 3.5
ED = DF = CD = 2.0 ( <C1 = <D2 = <E= 60° ) Nok Gording
EG = FH = 1/2 CD = 1.0
C C
Uraian Volume
163 x
A
1.00 D D 1.5 B Kayu 5 / 10
AD = BD = 1.00 AD = BD = 1.5
AC² = CD² + AD² BC² = CD² + AD²
48
04. RANGKA PLAFON
Volume
Volume
Uraian Volume
144 x
Uraian Volume
436 x
05. PLAFON TRIPLEKS
06. KUSEN
1.52 0.060 x
0.58
2.16 0.060 x
1.32
2.16 0.060 x
0.77
2.16 0.060 x
0.72
Jendela Type J1
0.38 1.40 0.38 x
1.4
0.38
Pasang Daun Pintu Panel Kayu
Pintu Type P1 J
1.20 2.10 1.20 x
2.1
1.2
Pintu Type P2 J
0.65 2.10 0.65 x
2.1
0.65
Pintu Type P3 J
0.60 2.10 0.60 x
2.1 Daun Muka Be
0.6
08. PEKERJAAN ATAP
1.5 x
1.5 x
1.5 x
( 7.5 +
( 7.5 +
( 6 +
( 6 +
0.025
= 25.00
VOLUME PEKERJAAN
3.3 23.24
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
3.3 26.56
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
Total Pasangan 26.56 2.656
3.3 4.98
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu
2.16 x 1 1.56
Kosen Jendelah
1.52 x 0 0.00
3.3 4.98
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
3.3 26.56
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
3.3 0.00
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
3.3 1.66
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
3.3 39.84
Kosen Ventilasi
0.3 x 9 0.81
Kosen Pintu
2.16 x 1 2.16
Kosen Jendelah
1.52 x 6 5.29
Total Pasangan 31.58 3.15804
3.3 13.28
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 1 1.56
Kosen Jendelah
1.52 x 0 0.00
3.3 0.00
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
3.3 13.28
Kosen Ventilasi
0.3 x 6 0.54
Kosen Pintu Kabaya
2.16 x 1 2.85
Kosen Jendelah
1.9 x 4 4.41
3.3 0.00
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
3.3 1.66
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
3.3 1.66
Kosen Ventilasi
0.3 x 0 0.00
Kosen Pintu Kabaya
2.16 x 0 0.00
Kosen Jendelah
1.52 x 0 0.00
0.2 0.18
Jumlah Conopi 1 -
47.5 157.70
Total 138.53
Total Muka Belakang 2 277.06
0.3 x 1 0.18
Total 2 WC 1 0.18
7.0 0.00
7.0 56.00
6.0 24.00
7.0 0.00
7.0 0.00
4.0 0.00
0.60 4.20
0.57 0.00
0.9 x 1 0.63
Luas Alas
0.6 = 0.36 0.36
Luas Dinding
0.6 x 3.6 = 1.296
Luas Alas
6.0 = 7.5 7.50
Total Keramik Warna 20 x 25 Dinding 9.16
-
Total = 0.0
Total = 0 M
Uraian Volume
0.06 x 0.12 0.000
5 x 0 = 0
5 x 0 = 0
Total = 0 M
Uraian Volume
0.05 x 0.1 0
Total = 33.9
Total = 163 M
Uraian Volume
0.06 x 0.12 1.177
8 x 21 = 168
6 x 9.5 = 57
6 x 9.5 = 57
9 x 21 = 189
Total = 471 M
Uraian Volume
0.05 x 0.1 2.355
4 = 32
4 = 28
9 = 72
7 = 49
4 = 28
4 = 32
4 = 28
5 = 40
3 = 4.5
3 = 4.5
5 = 10
4 = 16
3 = 4.5
3 = 4.5
3 = 28.5
15 = 12
3 = 42
24 = 19.2
3 = 28.5
17 = 13.6
3 = 21
11 = 8.8
2 = 16
5 = 7.5
2 = 16
9 = 13.5
Uraian Volume
0.05 x 0.1 0.71805
Uraian Volume
0.05 x 0.07 1.52712
7.0 x 8.0 1 56
6.5 x 4.0 26
0.0 x 0.0 0
0.0 x 0.0 0
0.0 x 0.0 0
0.0 x 0.0 0
Entrans WC 1.0 x 1.5 1.5
1.5 x 1.5 x 1.0 2.25
Kayu 6 / 12
1.0 x 10 ) 10
4.00 + 4.00 + 4 +
0 + 0
25.00
PERHITUNGAN VOLU
#REF! : ###
#REF! : ###
#REF! : ###
Pembesiaan
No. Lokasi /
Sketsa / Gambar Bengkokan Panjang
Urut STA
Atas Bawah Besi
01 Pembesian Kolom
0.12
Pembesian Sloof
0.12
Pembesian Balok
0.12
04.
04.
1.86
3
Ukuran Tripleks
1.22 x 2.44 = 2.9768
0.61 0.8133
1.22 2.44
44.746
3.1913
4.703
3.1913
2.6874
6.0468
48.626
11.345 Ukuran Seng Gelombang
11.345 1.83 x 0.81 = 1.4823
17.647 1.7 x 0.7 = 1.19
63.235
63.235
44.118
44.118
8.4034
263.45 lembar
#REF! : #REF!
#REF! : #REF!
#REF! : #REF!
2.00
3.00
7.00
15.00
15.00
30.00
25.00
14.00
0.00
0.00
6.00
8.00
0.00
2.00
2.00
4.00
1.00
3.00
0.00
2.00
3.00
0.00
1.00
0.00
0.00
3.00
3.00
41.10
313.50
144.75
277.06
277.06
TABEL BERAT BESI
NO DIA BERAT
1 25 #VALUE!
2 22 #VALUE!
3 19 #VALUE!
4 16 #VALUE!
5 12 #VALUE!
6 10 #VALUE!
7 8 #VALUE!
8 6 #VALUE!
LEMBAR ISIAN
1 KEGIATAN
PEKERJAAN : REHAB JALAN SETAPAK P=25M, L=1.2M
LOKASI : RT 003
DESA : DESA LATTA
TAHUN ANGGARAN : 2018
2 PELAKSANA
DIBUAT : J NITALESSY
JABATAN : TIM PELAKSANA KEGIATAN
DISETUJUI : L.H. SOPAMENA, S.STP, MT
JABATAN : PENJABAT KEPALA DESA
NIP : 19820126200112 1 004
DIVERIFIKASI : V PATTY
JABATAN : SEKERTARIS DESA
REKAPITULASI
A PEKERJAAN PERSIAPAN
C ALAT
D BIAYA UMUM
E PEMBERSIHAN AKHIR
NILAI KONSTRUKSI
JUMLAH NILAI KONSTRUKSI
DIBULATKAN
TERBILANG : #NAME?
DIPERIKSA OLEH
TA ID KOTA AMBON
Jumlah Harga
(Rp.)
1,900,000.00
1,881,207.05
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
DIBUAT OLEH
TIM PELAKSANA KEGIATAN
J NITALESSY
A PEKERJAAN PERSIAPAN
1 Pembersihan Awal BR-20 HOK
2 Papan Kegiatan BR-9 Ls
3 Gambar Kerja BR-13 Ls
C ALAT
2 Skop BR-2 Bh
3 Benang Tukang BR-3 Tukal
4 Gerobak Dorong BR-4 Bh
5 Martil BR-5 Bh
7 Ember Cor BR-7 Bh
D HONOR
3 Insentif TPK BR-11 Ls
E PEMBERSIHAN AKHIR
1 Pemasangan Prasasti BR-10 Ls
2 Pembersihan Akhir BR-21 HOK
4 Administrasi + Dokumentasi BR-12 Ls
NGGARAN BIAYA (RAB)
HARGA JUMLAH
NO. URAIAN SATUAN VOLUME
(Rp.) (Rp.)
A UPAH
1 Mandor OH 190,000.00 0.13 23,940.00
2 Kepala Tukang OH 175,000.00 0.04 7,350.00
3 Tukang Batu OH 145,000.00 - -
4 Tukang Kayu OH 145,000.00 0.42 60,900.00
5 Tukang Besi OH 145,000.00 - -
6 Tukang Cat OH 145,000.00 - -
7 Tukang Listrik OH 145,000.00 - -
8 Pekerja OH 75,000.00 22.52 1,689,000.00
TOTAL I 1,781,190.00
B BAHAN - -
1 Pasir Urug M3 250,000.00 - -
2 Batu Kerikil Pecah ( 3 / 2 cm ) M3 250,000.00 - -
3 Batu Krikil (Kg) Kg 208.33 2,156.70 449,312.50
3 Pasir Beton Kg 227.27 1,875.30 426,204.55
4 Pasir Pasang M3 250,000.00 - -
5 Batu Kali M3 175,000.00 - -
6 Semen PC (Zak) Sak 75,000.00 - -
7 Semen PC (Kg) Kg 1,500.00 483.00 724,500.00
8 Pipa PVC dia. 2" M' 12,000.00 - -
TOTAL II 1,600,017.05
C ALAT - -
1 Pakuel Bh 90,000.00 - -
2 Skop Bh 85,000.00 2.00 170,000.00
3 Benang Tukang Tukal 10,000.00 5.00 50,000.00
4 Gerobak Dorong Bh 500,000.00 1.00 500,000.00
5 Martil Bh 50,000.00 2.00 100,000.00
6 Selang M' 15,000.00 - -
7 Ember Cor Bh 15,000.00 4.00 60,000.00
8 Gergaji Bh 50,000.00 - -
TOTAL III 880,000.00
D BIAYA UMUM - -
1 Papan Nama Proyek Bh 150,000.00 1.00 150,000.00
2 Prasasti Bh 500,000.00 1.00 500,000.00
3 Insentif Pekerja Ls 650,000.00 1.00 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00 1.00 1,000,000.00
5 Biaya Perencanaan Ls 1,000,000.00 1.00 1,000,000.00
TOTAL IV 3,300,000.00
GRAND TOTAL 7,561,207.05
ANALISA HARGA SATUAN
HARGA SATUAN
No. Uraian Kegiatan
(Rp.)
JUMLAH
(Rp.)
61,000.00
56,250.00
4,750.00
47,000.00
37,500.00
9,500.00
324,400.00
22,500.00
1,900.00
300,000.00
833,125.00
112,500.00
108,750.00
13,125.00
14,250.00
210,000.00
244,500.00
130,000.00
895,812.88
90,000.00
29,000.00
3,500.00
11,400.00
345,000.00
202,954.55
213,958.33
65,085.00
22,500.00
21,750.00
2,625.00
2,850.00
9,360.00
6,000.00
90,000.00
85,000.00
10,000.00
500,000.00
50,000.00
15,000.00
15,000.00
50,000.00
150,000.00
500,000.00
650,000.00
75,000.00
75,000.00
1,000,000.00
1,000,000.00
DAFTAR UPAH DAN HARGA BAHAN
HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)
A UPAH
1 Mandor OH 190,000.00
2 Kepala Tukang OH 175,000.00
3 Tukang Batu OH 145,000.00
4 Tukang Kayu OH 145,000.00
5 Tukang Besi OH 145,000.00
6 Tukang Cat OH 145,000.00
7 Tukang Listrik OH 145,000.00
8 Pekerja OH 75,000.00
9 Buruh Tidak Terlatih OH 85,000.00
B BAHAN
1 Kayu Klas I M3 6,500,000.00
2 Kayu Klas II M3 3,500,000.00
3 Papan Kayu Kls I M3 6,500,000.00
4 Papan Kayu Kls III M3 1,750,000.00
5 Pasir Urug M3 250,000.00
6 Batu Kerikil Pecah ( 3 / 2 cm ) M3 250,000.00
7 Pasir Pasang M3 250,000.00
8 Batu Kali M3 175,000.00
9 Pasir Beton Kg 227.27
10 Batu Krikil (Kg) Kg 208.33
11 Semen PC (Zak) Sak 75,000.00
12 Semen PC (Kg) Kg 1,500.00
13 Pipa PVC dia. 2" M' 12,000.00
C ALAT
1 Pakuel Bh 90,000.00
2 Skop Bh 85,000.00
3 Benang Tukang Tukal 10,000.00
4 Gerobak Dorong Bh 500,000.00
5 Martil Bh 50,000.00
6 Selang M' 15,000.00
Ember Cor Bh 15,000.00
Gergaji Bh 50,000.00
D BIAYA UMUM
1 Papan Nama Proyek Bh 150,000.00
2 Prasasti Bh 500,000.00
3 Insentif Pekerja Ls 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00
5 Biaya Perencanaan Ls 1,000,000.00
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : REHAB JALAN SETAPAK P=25M, L=1.2M
LOKASI : RT 003
DESA : DESA LATTA
Total 2.100