Sei sulla pagina 1di 203

Chapter 1 Overview of Hardware Installation ...............................................

1-1
1.1 Introduction to the Chapter ..................................................................... 1-1
1.2 Reference Guidance .............................................................................. 1-1
1.3 SoftX3000 Hardware Composition ......................................................... 1-1
1.3.1 Overview of OSTA Frame .............................................................. 1-1
1.3.2 Features of OSTA Frame............................................................... 1-2
1.3.3 Board Allocation of OSTA Frame................................................... 1-3
1.3.4 Overall Hardware Structure ........................................................... 1-3
1.4 Hardware Installation Procedure ............................................................ 1-4
1.4.1 Overall Hardware Installation Procedure ....................................... 1-4
1.4.2 Introduction to Installation Preparations ......................................... 1-5
1.4.3 Introduction to Installing Cabinets .................................................. 1-6
1.4.4 Introduction to Installing Internal Components ............................... 1-6
1.4.5 Introduction to Installing Power Cables and Protection
Grounding Cables ................................................................................... 1-6
1.4.6 Introduction to Installing Signal Cables .......................................... 1-6
1.4.7 Introduction to Installing Cabinet Fittings ....................................... 1-7
1.4.8 Introduction to Installing Peripherals .............................................. 1-7
1.4.9 Introduction to Hardware Installation Check .................................. 1-7
1.5 Installation Notices ................................................................................. 1-7
Chapter 2 Installation Preparations ............................................................... 2-1
2.1 Introduction to the Chapter ..................................................................... 2-1
2.2 Pre-Installation Tasks ............................................................................. 2-1
2.2.1 Preparing Technical Documents .................................................... 2-1
2.2.2 Organizing Installation Team ......................................................... 2-1
2.2.3 Preparing Auxiliary Devices ........................................................... 2-2
2.2.4 Preparing Tools and Meters ........................................................... 2-3
2.3 Checking Conditions of Equipment Room .............................................. 2-4
2.3.1 Introduction to Checking Procedure ............................................... 2-4
2.3.2 Checking Building Conditions of Equipment Room ....................... 2-4
2.3.3 Checking Environment Conditions ................................................. 2-4
2.3.4 Checking Power Supply Conditions ............................................... 2-5
2.3.5 Checking Grounding Conditions .................................................... 2-5
2.3.6 Checking Auxiliary Devices............................................................ 2-5
2.3.7 Checking Other Facilities ............................................................... 2-6
2.4 Unpacking and Accepting the Equipment .............................................. 2-6
2.4.1 Unpacking Requirements............................................................... 2-6
2.4.2 Unpacking Wooden Crate .............................................................. 2-7
2.4.3 Unpacking Cardboard Box ............................................................. 2-9
Chapter 3 Installing Cabinets ......................................................................... 3-1
3.1 Introduction to the Chapter ..................................................................... 3-1
3.2 Introduction to Cabinet ........................................................................... 3-1
3.3 Installing Cabinets on ESD-Preventive Floor ......................................... 3-1
3.3.1 Reference of N800 Support ........................................................... 3-1
3.3.2 Introduction to Installation Procedure on ESD-Preventive Floor .... 3-1
3.3.3 Planning Support Positions ............................................................ 3-2
3.3.4 Installing Supports and Slide Rails ................................................ 3-6
3.3.5 Installing Holder Fixing Components ............................................. 3-10
3.3.6 Leveling Cabinets .......................................................................... 3-10
3.3.7 Fixing Cabinets .............................................................................. 3-12
3.3.8 Performing Insulation Test ............................................................. 3-13
3.4 Installing Cabinets on Cement Floor ...................................................... 3-14
3.4.1 Introduction to Installation Procedure on Cement Floor ................. 3-14
3.4.2 Planning Cabinet Positions ............................................................ 3-15
3.4.3 Leveling Cabinets .......................................................................... 3-19
3.4.4 Fixing Cabinets .............................................................................. 3-20
3.4.5 Performing Insulation Test ............................................................. 3-21
Chapter 4 Installing Internal Components .................................................... 4-1
4.1 Introduction to the Chapter ..................................................................... 4-1
4.2 Introduction to Internal Components and Installation ............................. 4-1
4.2.1 Introduction to Internal Components .............................................. 4-1
4.2.2 Installation Procedure .................................................................... 4-5
4.2.3 Installation Notices ......................................................................... 4-5
4.3 Installing Internal Components ............................................................... 4-6
4.3.1 Installation Requirements .............................................................. 4-6
4.3.2 Installing iGWB and BAM Servers ................................................. 4-6
4.3.3 Installing Hard Disk Array .............................................................. 4-6
4.3.4 Installing LAN Switch ..................................................................... 4-7
4.3.5 Installing KVMS.............................................................................. 4-7
4.3.6 Installing MRS ................................................................................ 4-7
Chapter 5 Installing Power Cables and Protection Grounding Cables ...... 5-1
5.1 Introduction to the Chapter ..................................................................... 5-1
5.2 Introduction to Power Supply System and Protection Grounding
System ......................................................................................................... 5-1
5.2.1 Introduction to Power Supply System ............................................ 5-1
5.2.2 Introduction to Protection Grounding System ................................ 5-3
5.3 Installing Power Cables and Protection Grounding Cables .................... 5-4
5.3.1 Installation Procedure .................................................................... 5-4
5.3.2 Installation Notices ......................................................................... 5-6
5.3.3 Installing Power Cables for Internal Components .......................... 5-6
5.3.4 Installing Protection Grounding Cables for Internal
Components ............................................................................................ 5-13
5.3.5 Installing Protection Grounding Cables Between Cabinets ........... 5-15
5.3.6 Installing Power Cables and Protection Grounding Cables for
Cabinets .................................................................................................. 5-15
5.4 Installing Power Bus Cables from DC Power Distribution Cabinet to
DC Switchboard ........................................................................................... 5-19
5.4.1 Introduction to Power Bus Cables from DC Power Distribution
Cabinet to DC Switchboard..................................................................... 5-19
5.4.2 Connecting Power Bus Cables from DC Power Distribution
Cabinet to DC Switchboard..................................................................... 5-20
5.4.3 Making and Fixing OT Terminals ................................................... 5-21
5.4.4 Requirements for Installing OT Terminals ..................................... 5-22
5.4.5 Requirements for Laying Cables Inside DC Power Distribution
Cabinet .................................................................................................... 5-23
Chapter 6 Installing Signal Cables ................................................................. 6-1
6.1 Introduction to the Chapter ..................................................................... 6-1
6.2 Introduction to Signal Cables ................................................................. 6-1
6.2.1 Types of Signal Cables .................................................................. 6-1
6.2.2 Connection of Internal Signal Cables............................................. 6-1
6.3 Requirements and Modes of Laying Signal Cables ............................... 6-3
6.3.1 Requirements for Laying Signal Cables ......................................... 6-3
6.3.2 Modes of Laying Signal Cables ..................................................... 6-4
6.4 Installing Internal Signal Cables ............................................................. 6-6
6.4.1 Installation Procedure .................................................................... 6-6
6.4.2 Installing Straight Through Network Cable Between LAN
Switches .................................................................................................. 6-7
6.4.3 Installing Straight Through Network Cable Between
iGWB/BAM Server and LAN Switch ........................................................ 6-8
6.4.4 Installing Straight Through Network Cable Between LAN
Switch and HSCI ..................................................................................... 6-9
6.4.5 Installing FE Signal Cable Between HSCI and SIUI ...................... 6-10
6.4.6 Installing Serial Port Cable Between iGWB Servers ...................... 6-10
6.4.7 Installing Data Cable Between iGWB Server and Hard Disk
Array ....................................................................................................... 6-11
6.4.8 Installing Server/Switcher Cable .................................................... 6-11
6.4.9 Installing Serial Port Cable for Monitoring Power Distribution
Frame...................................................................................................... 6-12
6.4.10 Installing Clock Cable Between Frames ...................................... 6-13
6.5 Installing External Signal Cables ............................................................ 6-15
6.5.1 Installation Procedure .................................................................... 6-15
6.5.2 Installing Trunk Cable Between SoftX3000 and DDF .................... 6-15
6.5.3 Installing Clock Cable Between SoftX3000 and BITS .................... 6-17
6.5.4 Installing External Network Cables ................................................ 6-18
Chapter 7 Installing Cabinet Fittings ............................................................. 7-1
7.1 Introduction to the Chapter ..................................................................... 7-1
7.2 Installing ESD-Preventive Floor Holders and Recovering Floor ............. 7-1
7.2.1 Installing ESD-Preventive Floor Holders ........................................ 7-1
7.2.2 Adjusting Holder Height ................................................................. 7-2
7.2.3 Cutting and Recovering ESD-Preventive Floor.............................. 7-2
7.3 Installing Door Lintels ............................................................................. 7-2
7.4 Installing Cabinet Side Panels ................................................................ 7-4
7.5 Installing Front and Back Doors ............................................................. 7-4
7.6 Installing Protection Grounding Cable for Cabinet Doors ....................... 7-6
Chapter 8 Installing Peripherals ..................................................................... 8-1
8.1 Introduction to the Chapter ..................................................................... 8-1
8.2 Connecting to Terminal Equipment ........................................................ 8-1
8.3 Connecting to Alarm Devices ................................................................. 8-2
8.4 Grounding Requirements of Terminal Equipment .................................. 8-3
8.5 Laying Cables for Terminal Equipment .................................................. 8-3
Chapter 9 Hardware Installation Check ......................................................... 9-1
9.1 Introduction to the Chapter ..................................................................... 9-1
9.2 Checking Appearance of Hardware Components .................................. 9-1
9.2.1 Checking Cabinets ......................................................................... 9-1
9.2.2 Checking Cable Distribution ........................................................... 9-1
9.2.3 Checking Connectors and Sockets ................................................ 9-2
9.2.4 Checking Labels and Equipment Room Environment ................... 9-3
9.3 Checking Electrical Performance ........................................................... 9-3
9.3.1 Introduction to Electrical Performance Check ................................ 9-3
9.3.2 Introduction to Power Switches in Power Distribution Frame ........ 9-3
9.3.3 Introduction to Power Switches in MRS ......................................... 9-5
9.3.4 Checking Power Supply of Cabinets .............................................. 9-5
9.3.5 Checking Power Supply of Frames................................................ 9-6
9.3.6 Performing Board Power-On Test .................................................. 9-6
Appendjx A Installing Cabling Rack .............................................................. A-1
A.1 Introduction to the Appendix .................................................................. A-1
A.2 Introduction to Cabling Rack .................................................................. A-1
A.2.1 Functions of Cabling Rack ............................................................. A-1
A.2.2 Components of Cabling Rack ........................................................ A-1
A.2.3 Installation Modes .......................................................................... A-7
A.2.4 Cabling Rack Specifications .......................................................... A-7
A.3 Installing Cabling Rack .......................................................................... A-7
A.3.1 Installation Procedure .................................................................... A-7
A.3.2 Assembling Cabling Ladder ........................................................... A-8
A.3.3 Connecting and Installing Cabling Troughs ................................... A-9
A.3.4 Installing Turning Cabling Rack ..................................................... A-11
A.3.5 Installing Cabling Rack in Suspension Mounting Mode or
Ground Supporting Mode........................................................................ A-13
A.3.6 Installing Triangular Support .......................................................... A-15
A.3.7 Installing Cabling Rack over Cabinet............................................. A-16
A.3.8 Installing Accessories .................................................................... A-18
Appendix B Engineering Labels for Cables .................................................. B-1
B.1 Introduction to the Appendix .................................................................. B-1
B.2 Introduction to Labels ............................................................................. B-1
B.2.1 Functions of Engineering Labels ................................................... B-1
B.2.2 Label Material Specifications ......................................................... B-1
B.2.3 Type and Shape of Labels ............................................................. B-2
B.2.4 Printing Labels ............................................................................... B-3
B.2.5 Writing Labels ................................................................................ B-5
B.2.6 Affixing Labels ............................................................................... B-6
B.2.7 Information Carried on Labels ....................................................... B-9
B.2.8 Remarks ........................................................................................ B-9
B.3 Engineering Labels for External Cables of Alarm Box ........................... B-10
B.4 Engineering Labels for Ethernet Cables ................................................ B-11
B.4.1 Introduction to the Labels .............................................................. B-11
B.4.2 Label Information Meanings .......................................................... B-11
B.4.3 Label Example ............................................................................... B-12
B.5 Engineering Labels for Optical Fibers .................................................... B-13
B.5.1 Introduction to the Labels .............................................................. B-13
B.5.2 Labels for Fiber that Connects Two Devices ................................. B-13
B.5.3 Labels for Fiber that Connects the Device and the ODF ............... B-15
B.6 Engineering Labels for Trunk Cables ..................................................... B-16
B.6.1 Introduction to the Labels .............................................................. B-16
B.6.2 Labels for Trunk Cable that Connects Two Devices ..................... B-16
B.6.3 Labels for Trunk Cable that Connects the Device and the DDF .... B-17
B.7 Engineering Labels for Subscriber Cables............................................. B-19
B.7.1 Introduction to the Labels .............................................................. B-19
B.7.2 Label Information Meanings .......................................................... B-19
B.7.3 Label Example ............................................................................... B-20
B.8 Engineering Labels for Power Cables .................................................... B-20
B.8.1 Labels for DC Power Cables ......................................................... B-20
B.8.2 Labels for AC Power Cables ......................................................... B-22
Appendix C Assembling Cable Connectors .................................................. C-1
C.1 Introduction to the Appendix .................................................................. C-1
C.2 Assembling Power Cable Connector ..................................................... C-1
C.2.1 Introduction to Assembly Procedure ............................................. C-1
C.2.2 Assembling Power Cable Connector............................................. C-2
C.2.3 Application of Crimping Tool ......................................................... C-6
C.3 Assembling RJ45 Connector ................................................................. C-8
C.3.1 Introduction to Assembly Procedure ............................................. C-8
C.3.2 Assembling RJ45 Connector ......................................................... C-8
C.4 Assembling SMB Connector .................................................................. C-13
C.4.1 Introduction to Assembly Procedure ............................................. C-13
C.4.2 Assembling SMB Connector ......................................................... C-14
Appendix D Requirements for Equipment Operating Environment ........... D-1
D.1 Observed Standards .............................................................................. D-1
D.2 Requirements for Equipment Room ...................................................... D-1
D.2.1 Site Requirements ......................................................................... D-1
D.2.2 Equipment Room Composition...................................................... D-2
D.2.3 Building Requirements .................................................................. D-3
D.2.4 Humidity and Temperature Requirements .................................... D-5
D.2.5 Air Cleanness Requirements......................................................... D-5
D.2.6 Erosive Gas Condition Requirements ........................................... D-6
D.2.7 Electromagnetic Requirements ..................................................... D-6
D.2.8 ESD-Preventive Requirements ..................................................... D-7
D.2.9 Lightning Protection Requirements ............................................... D-7
D.3 Requirements for Power Supply ............................................................ D-10
D.3.1 Requirements for AC Power Supply .............................................. D-10
D.3.2 Suggestions on AC Power Supply ................................................ D-11
D.3.3 Requirements for DC Power Supply ............................................. D-11
D.3.4 Suggestions on DC Power Supply ................................................ D-12
Index .................................................................................................................
HUAWEI

U-SYS SoftX3000 SoftSwitch System


Hardware Installation Manual

V300R003

Huawei Technologies Proprietary


U-SYS SoftX3000 SoftSwitch System
Hardware Installation Manual

Manual Version T2-010462-20050331-C-3.30

Product Version V300R003

BOM 31041762

Huawei Technologies Co., Ltd. provides customers with comprehensive technical support
and service. Please feel free to contact our local office or company headquarters.

Huawei Technologies Co., Ltd.

Address: Administration Building, Huawei Technologies Co., Ltd.,

Bantian, Longgang District, Shenzhen, P. R. China

Postal Code: 518129

Website: http://www.huawei.com

Email: support@huawei.com

Huawei Technologies Proprietary


Copyright © 2005 Huawei Technologies Co., Ltd.

All Rights Reserved

No part of this manual may be reproduced or transmitted in any form or by any


means without prior written consent of Huawei Technologies Co., Ltd.

Trademarks

, HUAWEI, C&C08, EAST8000, HONET, , ViewPoint, INtess, ETS, DMC,


TELLIN, InfoLink, Netkey, Quidway, SYNLOCK, Radium, M900/M1800,
TELESIGHT, Quidview, Musa, Airbridge, Tellwin, Inmedia, VRP, DOPRA,
iTELLIN, HUAWEI OptiX, C&C08 iNET, NETENGINE, OptiX, iSite, U-SYS, iMUSE,
OpenEye, Lansway, SmartAX, infoX, and TopEng are trademarks of Huawei
Technologies Co., Ltd.

All other trademarks and trade names mentioned in this manual are the property of
their respective holders.

Notice

The information in this manual is subject to change without notice. Every effort has
been made in the preparation of this manual to ensure accuracy of the contents,
but all statements, information, and recommendations in this manual do not
constitute the warranty of any kind, express or implied.

Huawei Technologies Proprietary


About This Manual

Release Notes

This manual applies to U-SYS SoftX3000 SoftSwitch System V300R003 (hereinafter


referred to as SoftX3000).

Related Manuals

The related manuals are listed in the following table.

Manual Content
U-SYS SoftX3000 SoftSwitch It provides an overall introduction to the
System Technical SoftX3000, including product features,
Manual-System Description applications, and technical specifications.
It details on the hardware architecture,
U-SYS SoftX3000 SoftSwitch
component interworking mechanism, and
System Technical
subsystems of alarm, billing, and clock in the
Manual-System Principle
SoftX3000.
It details the features and technical
U-SYS SoftX3000 SoftSwitch specifications of the hardware components of
System Hardware Description the SoftX3000, including cabinets, frames,
Manual boards, cables, and cabinet internal
components.
It covers various services and functions
supported by the SoftX3000, including voice
U-SYS SoftX3000 SoftSwitch services, supplementary services, IP Centrex
System Service and Features services, multi-media services, value added
Manual services, dual homing functions, charging
functions, IPTN functions, remote network
access functions, and so on.
It details the installation procedure of the
U-SYS SoftX3000 SoftSwitch
SoftX3000 hardware components, and matters
System Hardware Installation
needing attention during the installation
Manual
process.

It covers the detailed procedure of installing the


U-SYS SoftX3000 SoftSwitch SoftX3000 software, including BAM server,
System Software Installation emergency workstation, and client, focusing on
Manual the key points that might cause installation
failure.

U-SYS SoftX3000 SoftSwitch It guides the maintenance engineers to perform


System Routine Maintenance daily maintenance, monthly maintenance, and
Guide yearly maintenance tasks on the SoftX3000.

Huawei Technologies Proprietary


Manual Content
It guides the maintenance engineers to perform
U-SYS SoftX3000 SoftSwitch
recovery operations in the case of emergencies,
System Emergency
such as congestion of global service, AMG, and
Maintenance Manual
TMG, and failure of host and BAM.
It guides the maintenance engineers on how to
U-SYS SoftX3000 SoftSwitch replace hardware components of the
System Part Replacement Guide SoftX3000, such as boards, fan frame, LAN
Switch, and hard disk.
It guides the engineers how to configure various
U-SYS SoftX3000 SoftSwitch
data in the SoftX3000, including configuration
System Operation
steps, preparations, database table referencing
Manual-Configuration Guide
relationships, and command parameters.

It guides the engineers how to configure various


U-SYS SoftX3000 SoftSwitch
data in the SoftX3000, including networking
System Operation
example, configuration script, key parameters
Manual-Configuration Examples
and debugging guidance.
U-SYS SoftX3000 SoftSwitch It guides the engineers how to perform traffic
System Operation measurement operations and how to analyze
Manual-Traffic Measurement traffic measurement results.

It guides the engineers how to use the GUI on


U-SYS SoftX3000 SoftSwitch various clients of the SoftX3000, including
System Operation Manual-GUI operations on menus and navigation tree. In
Guide addition, it introduces the operations on
TableBrowse.
It guides the engineers how to install and use
the software related to the BAM, including
U-SYS SoftX3000 SoftSwitch
remote maintenance software, anti-virus
System BAM User Manual
software, system customized software, and so
on.

It elaborates on the functioning principle of the


U-SYS iGateway Bill User
iGateway Bill. Also, it teaches you on how to
Manual
install, maintain, and operate the product.

Organization

The manual presents the procedures for installing the SoftX3000 hardware
components and attentions during installation.
z Chapter 1 Overview of Hardware Installation gives an introduction to the
procedure for installing the SoftX3000 equipment.
z Chapter 2 Installation Preparations lists in detail the preinstallation tasks,
including preparing installation technical documents, tools and meters, and
checking equipment room conditions.

Huawei Technologies Proprietary


z Chapter 3 Installing Cabinets describes in detail how to position, adjust and fix
N68-22 cabinet and combine adjacent cabinets.
z Chapter 4 Installing Internal Components presents the installation of iGWB
server, BAM server, hard disk array, LAN Switch, KVM/LCD switcher, and
boards in basic and expansion frames, as well as installation attentions.
z Chapter 5 Installing Power Cables and Protection Grounding Cables briefs
the laying of power cables and protection grounding cables.
z Chapter 6 Installing Signal Cables describes the internal cables and external
cables, including category, appearance, connection method and label sticking
method.
z Chapter 7 Installing Cabinet Fittings presents the installation of door lintel,
side panel and front and back doors.
z Chapter 8 Installing Peripherals describes the installation of terminal
equipment, alarm device and auxiliary cables.
z Chapter 9 Hardware Installation Check defines the points to check after
hardware installation completes.
z Appendix A Installing Cabling Rack introduces the parts of cabling rack and
the specific installation method.
z Appendix B Engineering Labels for Cables details the specifications of
project labels on cables.
z Appendix C Assembling Cable Connectors presents the assembly methods
for power cable connector, RJ45 connector, and SMB connector.
z Appendix D Requirements for Equipment Operating Environment
describes the requirements for the operating environment of the equipment..

Intended Audience

The manual is intended for the following readers:


z NGN network planning personnel and decision maker
z NGN network management personnel
z NGN system engineer

NGN system engineer Conventions

The manual uses the following conventions:

I. General conventions

Convention Description
Arial Normal paragraphs are in Arial.
Boldface Headings are in Boldface.

Huawei Technologies Proprietary


Convention Description
Courier New Terminal Display is in Courier New.

II. Symbols

Eye-catching symbols are also used in the manual to highlight the points worthy of
special attention during the operation. They are defined as follows:

Caution, Warning, Danger Means reader be extremely careful during the


operation.

Note, Means a complementary description..

Environmental Protection

This product has been designed to comply with the requirements on environmental
protection. For the proper storage, use and disposal of this product, national laws and
regulations must be observed.

Huawei Technologies Proprietary


Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Table of Contents

Table of Contents

Chapter 1 Overview of Hardware Installation............................................................................. 1-1


1.1 Introduction to the Chapter ................................................................................................ 1-1
1.2 Reference Guidance.......................................................................................................... 1-1
1.3 SoftX3000 Hardware Composition .................................................................................... 1-1
1.3.1 Overview of OSTA Frame ....................................................................................... 1-1
1.3.2 Features of OSTA Frame........................................................................................ 1-2
1.3.3 Board Allocation of OSTA Frame............................................................................ 1-3
1.3.4 Overall Hardware Structure..................................................................................... 1-3
1.4 Hardware Installation Procedure ....................................................................................... 1-4
1.4.1 Overall Hardware Installation Procedure ................................................................ 1-4
1.4.2 Introduction to Installation Preparations.................................................................. 1-5
1.4.3 Introduction to Installing Cabinets ........................................................................... 1-6
1.4.4 Introduction to Installing Internal Components........................................................ 1-6
1.4.5 Introduction to Installing Power Cables and Protection Grounding Cables ............ 1-6
1.4.6 Introduction to Installing Signal Cables................................................................... 1-6
1.4.7 Introduction to Installing Cabinet Fittings ................................................................ 1-7
1.4.8 Introduction to Installing Peripherals ....................................................................... 1-7
1.4.9 Introduction to Hardware Installation Check ........................................................... 1-7
1.5 Installation Notices............................................................................................................. 1-7

Chapter 2 Installation Preparations............................................................................................. 2-1


2.1 Introduction to the Chapter ................................................................................................ 2-1
2.2 Pre-Installation Tasks ........................................................................................................ 2-1
2.2.1 Preparing Technical Documents ............................................................................. 2-1
2.2.2 Organizing Installation Team .................................................................................. 2-1
2.2.3 Preparing Auxiliary Devices .................................................................................... 2-2
2.2.4 Preparing Tools and Meters.................................................................................... 2-3
2.3 Checking Conditions of Equipment Room......................................................................... 2-4
2.3.1 Introduction to Checking Procedure........................................................................ 2-4
2.3.2 Checking Building Conditions of Equipment Room ................................................ 2-4
2.3.3 Checking Environment Conditions .......................................................................... 2-4
2.3.4 Checking Power Supply Conditions ........................................................................ 2-5
2.3.5 Checking Grounding Conditions ............................................................................. 2-5
2.3.6 Checking Auxiliary Devices..................................................................................... 2-5
2.3.7 Checking Other Facilities ........................................................................................ 2-6
2.4 Unpacking and Accepting the Equipment.......................................................................... 2-6
2.4.1 Unpacking Requirements........................................................................................ 2-6
2.4.2 Unpacking Wooden Crate ....................................................................................... 2-7

Huawei Technologies Proprietary

i
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Table of Contents

2.4.3 Unpacking Cardboard Box ...................................................................................... 2-9

Chapter 3 Installing Cabinets....................................................................................................... 3-1


3.1 Introduction to the Chapter ................................................................................................ 3-1
3.2 Introduction to Cabinet....................................................................................................... 3-1
3.3 Installing Cabinets on ESD-Preventive Floor .................................................................... 3-1
3.3.1 Reference of N800 Support .................................................................................... 3-1
3.3.2 Introduction to Installation Procedure on ESD-Preventive Floor ............................ 3-1
3.3.3 Planning Support Positions ..................................................................................... 3-2
3.3.4 Installing Supports and Slide Rails.......................................................................... 3-6
3.3.5 Installing Holder Fixing Components .................................................................... 3-10
3.3.6 Leveling Cabinets.................................................................................................. 3-10
3.3.7 Fixing Cabinets...................................................................................................... 3-12
3.3.8 Performing Insulation Test .................................................................................... 3-13
3.4 Installing Cabinets on Cement Floor................................................................................ 3-14
3.4.1 Introduction to Installation Procedure on Cement Floor ....................................... 3-14
3.4.2 Planning Cabinet Positions ................................................................................... 3-15
3.4.3 Leveling Cabinets.................................................................................................. 3-19
3.4.4 Fixing Cabinets...................................................................................................... 3-20
3.4.5 Performing Insulation Test .................................................................................... 3-21

Chapter 4 Installing Internal Components.................................................................................. 4-1


4.1 Introduction to the Chapter ................................................................................................ 4-1
4.2 Introduction to Internal Components and Installation ........................................................ 4-1
4.2.1 Introduction to Internal Components ....................................................................... 4-1
4.2.2 Installation Procedure ............................................................................................. 4-5
4.2.3 Installation Notices .................................................................................................. 4-5
4.3 Installing Internal Components .......................................................................................... 4-6
4.3.1 Installation Requirements........................................................................................ 4-6
4.3.2 Installing iGWB and BAM Servers .......................................................................... 4-6
4.3.3 Installing Hard Disk Array........................................................................................ 4-6
4.3.4 Installing LAN Switch .............................................................................................. 4-7
4.3.5 Installing KVMS ....................................................................................................... 4-7
4.3.6 Installing MRS ......................................................................................................... 4-7

Chapter 5 Installing Power Cables and Protection Grounding Cables.................................... 5-1


5.1 Introduction to the Chapter ................................................................................................ 5-1
5.2 Introduction to Power Supply System and Protection Grounding System ........................ 5-1
5.2.1 Introduction to Power Supply System ..................................................................... 5-1
5.2.2 Introduction to Protection Grounding System ......................................................... 5-3
5.3 Installing Power Cables and Protection Grounding Cables............................................... 5-4
5.3.1 Installation Procedure ............................................................................................. 5-4
5.3.2 Installation Notices .................................................................................................. 5-6
5.3.3 Installing Power Cables for Internal Components................................................... 5-6

Huawei Technologies Proprietary

ii
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Table of Contents

5.3.4 Installing Protection Grounding Cables for Internal Components......................... 5-13


5.3.5 Installing Protection Grounding Cables Between Cabinets .................................. 5-15
5.3.6 Installing Power Cables and Protection Grounding Cables for Cabinets.............. 5-15
5.4 Installing Power Bus Cables from DC Power Distribution Cabinet to DC Switchboard .. 5-19
5.4.1 Introduction to Power Bus Cables from DC Power Distribution Cabinet to DC
Switchboard.................................................................................................................... 5-19
5.4.2 Connecting Power Bus Cables from DC Power Distribution Cabinet to DC
Switchboard.................................................................................................................... 5-20
5.4.3 Making and Fixing OT Terminals .......................................................................... 5-21
5.4.4 Requirements for Installing OT Terminals ............................................................ 5-22
5.4.5 Requirements for Laying Cables Inside DC Power Distribution Cabinet .............. 5-23

Chapter 6 Installing Signal Cables .............................................................................................. 6-1


6.1 Introduction to the Chapter ................................................................................................ 6-1
6.2 Introduction to Signal Cables............................................................................................. 6-1
6.2.1 Types of Signal Cables ........................................................................................... 6-1
6.2.2 Connection of Internal Signal Cables...................................................................... 6-1
6.3 Requirements and Modes of Laying Signal Cables........................................................... 6-3
6.3.1 Requirements for Laying Signal Cables.................................................................. 6-3
6.3.2 Modes of Laying Signal Cables............................................................................... 6-4
6.4 Installing Internal Signal Cables ........................................................................................ 6-6
6.4.1 Installation Procedure ............................................................................................. 6-6
6.4.2 Installing Straight Through Network Cable Between LAN Switches....................... 6-7
6.4.3 Installing Straight Through Network Cable Between iGWB/BAM Server and LAN
Switch............................................................................................................................... 6-8
6.4.4 Installing Straight Through Network Cable Between LAN Switch and HSCI.......... 6-9
6.4.5 Installing FE Signal Cable Between HSCI and SIUI ............................................. 6-10
6.4.6 Installing Serial Port Cable Between iGWB Servers............................................. 6-10
6.4.7 Installing Data Cable Between iGWB Server and Hard Disk Array ...................... 6-11
6.4.8 Installing Server/Switcher Cable ........................................................................... 6-11
6.4.9 Installing Serial Port Cable for Monitoring Power Distribution Frame................... 6-12
6.4.10 Installing Clock Cable Between Frames ............................................................. 6-13
6.5 Installing External Signal Cables ..................................................................................... 6-15
6.5.1 Installation Procedure ........................................................................................... 6-15
6.5.2 Installing Trunk Cable Between SoftX3000 and DDF ........................................... 6-15
6.5.3 Installing Clock Cable Between SoftX3000 and BITS........................................... 6-17
6.5.4 Installing External Network Cables ....................................................................... 6-18

Chapter 7 Installing Cabinet Fittings........................................................................................... 7-1


7.1 Introduction to the Chapter ................................................................................................ 7-1
7.2 Installing ESD-Preventive Floor Holders and Recovering Floor........................................ 7-1
7.2.1 Installing ESD-Preventive Floor Holders................................................................. 7-1
7.2.2 Adjusting Holder Height .......................................................................................... 7-2
7.2.3 Cutting and Recovering ESD-Preventive Floor....................................................... 7-2

Huawei Technologies Proprietary

iii
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Table of Contents

7.3 Installing Door Lintels ........................................................................................................ 7-2


7.4 Installing Cabinet Side Panels ........................................................................................... 7-4
7.5 Installing Front and Back Doors......................................................................................... 7-4
7.6 Installing Protection Grounding Cable for Cabinet Doors.................................................. 7-6

Chapter 8 Installing Peripherals .................................................................................................. 8-1


8.1 Introduction to the Chapter ................................................................................................ 8-1
8.2 Connecting to Terminal Equipment ................................................................................... 8-1
8.3 Connecting to Alarm Devices ............................................................................................ 8-2
8.4 Grounding Requirements of Terminal Equipment ............................................................. 8-3
8.5 Laying Cables for Terminal Equipment ............................................................................. 8-3

Chapter 9 Hardware Installation Check....................................................................................... 9-1


9.1 Introduction to the Chapter ................................................................................................ 9-1
9.2 Checking Appearance of Hardware Components ............................................................. 9-1
9.2.1 Checking Cabinets .................................................................................................. 9-1
9.2.2 Checking Cable Distribution.................................................................................... 9-1
9.2.3 Checking Connectors and Sockets ......................................................................... 9-2
9.2.4 Checking Labels and Equipment Room Environment ............................................ 9-3
9.3 Checking Electrical Performance....................................................................................... 9-3
9.3.1 Introduction to Electrical Performance Check......................................................... 9-3
9.3.2 Introduction to Power Switches in Power Distribution Frame ................................. 9-3
9.3.3 Introduction to Power Switches in MRS.................................................................. 9-5
9.3.4 Checking Power Supply of Cabinets....................................................................... 9-5
9.3.5 Checking Power Supply of Frames......................................................................... 9-6
9.3.6 Performing Board Power-On Test........................................................................... 9-6

Appendjx A Installing Cabling Rack............................................................................................A-1


A.1 Introduction to the Appendix..............................................................................................A-1
A.2 Introduction to Cabling Rack .............................................................................................A-1
A.2.1 Functions of Cabling Rack......................................................................................A-1
A.2.2 Components of Cabling Rack .................................................................................A-1
A.2.3 Installation Modes...................................................................................................A-7
A.2.4 Cabling Rack Specifications ...................................................................................A-7
A.3 Installing Cabling Rack......................................................................................................A-7
A.3.1 Installation Procedure .............................................................................................A-7
A.3.2 Assembling Cabling Ladder....................................................................................A-8
A.3.3 Connecting and Installing Cabling Troughs............................................................A-9
A.3.4 Installing Turning Cabling Rack ............................................................................A-11
A.3.5 Installing Cabling Rack in Suspension Mounting Mode or Ground Supporting Mode.
........................................................................................................................................A-13
A.3.6 Installing Triangular Support.................................................................................A-15
A.3.7 Installing Cabling Rack over Cabinet....................................................................A-16
A.3.8 Installing Accessories ...........................................................................................A-18

Huawei Technologies Proprietary

iv
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Table of Contents

Appendix B Engineering Labels for Cables ...............................................................................B-1


B.1 Introduction to the Appendix..............................................................................................B-1
B.2 Introduction to Labels ........................................................................................................B-1
B.2.1 Functions of Engineering Labels ............................................................................B-1
B.2.2 Label Material Specifications ..................................................................................B-1
B.2.3 Type and Shape of Labels......................................................................................B-2
B.2.4 Printing Labels ........................................................................................................B-3
B.2.5 Writing Labels .........................................................................................................B-5
B.2.6 Affixing Labels.........................................................................................................B-6
B.2.7 Information Carried on Labels ................................................................................B-9
B.2.8 Remarks..................................................................................................................B-9
B.3 Engineering Labels for External Cables of Alarm Box ....................................................B-10
B.4 Engineering Labels for Ethernet Cables .........................................................................B-11
B.4.1 Introduction to the Labels .....................................................................................B-11
B.4.2 Label Information Meanings .................................................................................B-11
B.4.3 Label Example ......................................................................................................B-12
B.5 Engineering Labels for Optical Fibers .............................................................................B-13
B.5.1 Introduction to the Labels .....................................................................................B-13
B.5.2 Labels for Fiber that Connects Two Devices........................................................B-13
B.5.3 Labels for Fiber that Connects the Device and the ODF......................................B-15
B.6 Engineering Labels for Trunk Cables ..............................................................................B-16
B.6.1 Introduction to the Labels .....................................................................................B-16
B.6.2 Labels for Trunk Cable that Connects Two Devices ............................................B-16
B.6.3 Labels for Trunk Cable that Connects the Device and the DDF ..........................B-17
B.7 Engineering Labels for Subscriber Cables......................................................................B-19
B.7.1 Introduction to the Labels .....................................................................................B-19
B.7.2 Label Information Meanings .................................................................................B-19
B.7.3 Label Example ......................................................................................................B-20
B.8 Engineering Labels for Power Cables .............................................................................B-20
B.8.1 Labels for DC Power Cables ................................................................................B-20
B.8.2 Labels for AC Power Cables.................................................................................B-22

Appendix C Assembling Cable Connectors ...............................................................................C-1


C.1 Introduction to the Appendix .............................................................................................C-1
C.2 Assembling Power Cable Connector ................................................................................C-1
C.2.1 Introduction to Assembly Procedure.......................................................................C-1
C.2.2 Assembling Power Cable Connector......................................................................C-2
C.2.3 Application of Crimping Tool...................................................................................C-6
C.3 Assembling RJ45 Connector.............................................................................................C-8
C.3.1 Introduction to Assembly Procedure.......................................................................C-8
C.3.2 Assembling RJ45 Connector ..................................................................................C-8
C.4 Assembling SMB Connector ...........................................................................................C-13
C.4.1 Introduction to Assembly Procedure.....................................................................C-13

Huawei Technologies Proprietary

v
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Table of Contents

C.4.2 Assembling SMB Connector.................................................................................C-14

Appendix D Requirements for Equipment Operating Environment.........................................D-1


D.1 Observed Standards .........................................................................................................D-1
D.2 Requirements for Equipment Room..................................................................................D-1
D.2.1 Site Requirements ..................................................................................................D-1
D.2.2 Equipment Room Composition...............................................................................D-2
D.2.3 Building Requirements ...........................................................................................D-3
D.2.4 Humidity and Temperature Requirements .............................................................D-5
D.2.5 Air Cleanness Requirements..................................................................................D-5
D.2.6 Erosive Gas Condition Requirements ....................................................................D-6
D.2.7 Electromagnetic Requirements ..............................................................................D-6
D.2.8 ESD-Preventive Requirements...............................................................................D-7
D.2.9 Lightning Protection Requirements ........................................................................D-7
D.3 Requirements for Power Supply .....................................................................................D-10
D.3.1 Requirements for AC Power Supply.....................................................................D-10
D.3.2 Suggestions on AC Power Supply........................................................................D-11
D.3.3 Requirements for DC Power Supply.....................................................................D-11
D.3.4 Suggestions on DC Power Supply .......................................................................D-12

Index ................................................................................................................................................ i-1

Huawei Technologies Proprietary

vi
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 1 Overview of Hardware Installation

Chapter 1 Overview of Hardware Installation

1.1 Introduction to the Chapter

According to the normal installation sequence, equipment installation can be divided


into three major stages:
z Hardware installation
z Software installation
z Data configuration and system commissioning
This chapter contains the following sections:
z SoftX3000 Hardware Composition
z Hardware Installation Procedure
z Installation Notices

1.2 Reference Guidance

Before and during hardware installation procedure, you will need referential guidance.

Table 1-1 lists the manuals for reference.

Table 1-1 Manuals used during hardware installation

Manual name Contents


Hardware Description Manual Hardware architecture and components
Software installation manual Software installation procedures
Operation Manual-Configuration
Guide Data configuration and software
Operation Manual-Configuration commissioning
Example

1.3 SoftX3000 Hardware Composition

1.3.1 Overview of OSTA Frame

The SoftX3000 adopts open standard telecom architecture (OSTA) platform as its
hardware platform. The OSTA platform has shared resource bus and Ethernet bus at

Huawei Technologies Proprietary

1-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 1 Overview of Hardware Installation

the same time. It features good versatility and high reliability, and is applicable for
switching and transmitting length-variable data of the softswitch.

The standard frame (19 inches wide and 9U high) is used for the OSTA platform, and
the internal boards are inserted symmetrically into the backplane, as shown in
Figure 1-1.

(2) (3) (2) (1)

(4)

(5)

(6)

(7) (8) (7) (9) (1)

(1) Power boards (2) Interface boards (3) Ethernet communication boards
(4) Back boards (5) Backplane (6) Front boards
(7) Service boards (8) System management boards (9) Alarm board
Figure 1-1 Overall structure of OSTA frame

In the OSTA frame, the front boards include:


z Service boards
z System management boards
z Alarm board
z Power boards
The back boards include:
z Interface boards
z Ethernet communication boards
z Power boards

1.3.2 Features of OSTA Frame

The board allocation design in the OSTA frame enjoys the following features
z Different function design of front boards and back boards
z Simple board design
z Same functions of each board
z Simple hardware
z Reliable
z Adaptable frame
z Flexible configuration

Huawei Technologies Proprietary

1-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 1 Overview of Hardware Installation

1.3.3 Board Allocation of OSTA Frame

All OSTA frames share the same hardware architecture. Each frame is designed with
21 standard slots. The following boards are always configured in fixed positions:
z System Management Units (SMUIs)
z System Interface Units (SIUIs)
z Hot-Swap and Control Units (HSCIs)
z Alarm Units (ALMIs)
z Universal Power Modules (UPWRs) (occupying the width of 2 standard board
slots)
These boards occupy 9 slots in total. The remaining 12 slots are used for service
boards and interface boards.

1.3.4 Overall Hardware Structure

The SoftX3000 is composed of the following major hardware modules:


z OSTA frames
z Core LAN Switches
z Back administration module (BAM)
z iGateway Bill (iGWB)
The OSTA frames compose the host of the SoftX3000, and are responsible for service
processing and resource management

The BAM and iGWB compose the background, implementing equipment operation and
maintenance, and bill management.

The core LAN Switches connect and provide communication channels between the
host and the background.

Figure 1-2 shows the hardware architecture of the SoftX3000.

Huawei Technologies Proprietary

1-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 1 Overview of Hardware Installation

To the billing
FE FE center

Frame 0
FE

Active iGWB To the billing


center

LAN Switch 0
3 x FE
Frame 1
Standby iGWB

LAN Switch 1
BAM
Frame 2 Background
LAN Switch

To NMS

Emergency
Frame 17 workstation
WS WS WS
Host

FE: Fast Ethernet GE: Gigabit Ethernet WS: Workstation


Figure 1-2 Hardware architecture of the SoftX3000

1.4 Hardware Installation Procedure

1.4.1 Overall Hardware Installation Procedure

The quality of installation determines the long-term, safe and stable operation of the
SoftX3000. Therefore, conduct the installation strictly according to the manual. This will
reduce the unstable factors to the equipment operations and improve the reliability of
the equipment.

Figure 1-3 shows the overall procedure for installing the hardware components of the
SoftX3000.

Huawei Technologies Proprietary

1-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 1 Overview of Hardware Installation

Start

Preparations

Installing cabinets

Installing cabinet components

Installing power cables and protection


grounding cables

Installing signal cables

Installing cabinet fittings

Installing peripherals

Hardware installation check

End

Figure 1-3 Procedure for installing hardware components of the SoftX3000

1.4.2 Introduction to Installation Preparations

In this step, you must read the related contents in this manual and the following two
manuals:
z U-SYS SoftX3000 SoftSwitch System Technical Manual
z U-SYS SoftX3000 SoftSwitch System Hardware Description Manual
Familiarize yourself with the overall hardware architecture and the technical
specifications of the equipment, and the prerequisite for equipment installation:

Prepare installation tools.

Huawei Technologies Proprietary

1-5
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 1 Overview of Hardware Installation

Install the auxiliary cabling rack or cabling trough according to the project design
documents and the actual conditions of the equipment room.

1.4.3 Introduction to Installing Cabinets

In this step, you will do the following operations:


z Install the cabinets
z Combine the adjacent cabinets according to the project design documents

1.4.4 Introduction to Installing Internal Components

In this step, according to the actual configuration, you will install some or all of the
following components:
z iGWB server
z BAM server
z Hard disk array
z LAN Switch
z Keyboard, video, mouse, and switcher (KVMS)
z Media resource server (MRS)
z Cabling trough
z Blank filler panel
Also insert the boards into the frames.

1.4.5 Introduction to Installing Power Cables and Protection Grounding


Cables

After the cabinets are installed completely, you will install protection grounding cables.

This step has two purposes:


z Ensure that the equipment is correctly grounded
z Prevent the equipment from electrostatic discharge (ESD) damage during the
subsequent installation
After installing the power cables, do not use them directly to power the system. Instead,
Power on the system following the power-on steps after the quality checks and
power-on test.

1.4.6 Introduction to Installing Signal Cables

The internal cables include:


z Network cables
z Serial port cables

Huawei Technologies Proprietary

1-6
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 1 Overview of Hardware Installation

z Data cables
z Monitoring cables
z Internal clock cables
The external cables include:
z External clock cables
z Trunk cables
z External network cables

1.4.7 Introduction to Installing Cabinet Fittings

This section introduces you to the installation of the cabinet fittings, including:
z ESD-preventive floor holder
z Cabinet door lintel
z Front doors
z Back doors
z Side panels

1.4.8 Introduction to Installing Peripherals

This section introduces you to the installation of the peripherals, including:


z Maintenance terminal system
z Alarm box
z Other network devices

1.4.9 Introduction to Hardware Installation Check

This step is a prerequisite of starting software installation.

Rectify the unqualified installation items according to the criteria.

For the checklist and criteria, refer to Chapter 9 "Hardware Installation Check" in this
manual.

1.5 Installation Notices

This manual helps you install the hardware components and cables of the SoftX3000.
However, the provided information might not cover all possible site conditions and
optional devices in the actual installation procedure. Therefore, you need use specific
methods based on the actual site conditions.

Before installation, carefully read the Site Survey Report to clarify the following
contents:
z The position and state of the equipment in the network

Huawei Technologies Proprietary

1-7
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 1 Overview of Hardware Installation

z Interface types of line transmission device


z Length of cables
z Accounting modes of access devices
To facilitate the installation, confirm whether or not the customer’s order for the
equipment is changed greatly.

Huawei Technologies Proprietary

1-8
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 2 Installation Preparations

Chapter 2 Installation Preparations

2.1 Introduction to the Chapter

This chapter contains the following sections:


z Pre-Installation Tasks
z Checking Conditions of Equipment Room
z Unpacking and Accepting the Equipment

2.2 Pre-Installation Tasks

2.2.1 Preparing Technical Documents

You must carefully read the following technical documents before installation to get
detailed information about the project.
z Network Plan, Equipment Room Design, and Construction Diagram: Prepared by
the design company consigned by you. The copies shall be provided to the
equipment suppliers before delivery.
z Site Survey Report: Filled out on site by the Huawei engineering personnel.
z Engineering Design Document: Delivered with the equipment. It is made by
Huawei based on the equipment configuration of each site.
z The documentation package: Delivered with the equipment. It is provided by
Huawei Technologies, Co., Ltd. The package includes Technical Manual,
Hardware Description Manual, Installation Manual, Operation Manual and
Maintenance Manual.
z Other project related documents, including contracts and agreements,
configuration table, and package list.

2.2.2 Organizing Installation Team

During the installation of the equipment, it is recommended to arrange your technical


personnel to participate in installation training to get to know the system networking,
equipment power supply, cable connection, and operation and maintenance, and to
take over the equipment after installation.

The following two points must be noted when you are organizing the installation team:
z With the project service mode, the installation procedure is conducted by
technical personnel from the equipment supplier, and your technical personnel

Huawei Technologies Proprietary

2-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 2 Installation Preparations

are for assistance. If the installation project is contracted out to the cooperation
party entrusted by the supplier, the technical personnel from the contracted party
must be strictly trained and examined by the supplier, to master the system
installation and commissioning methods, and they cannot join in the system
installation and debugging until obtaining the qualification admission;
z With the supervision and debugging mode or supervision and service mode, the
installation procedure is conducted by your technical personnel, and the
technical personnel from the supplier are responsible for hardware installation
check, supervision and technical support as the project supervisor.

2.2.3 Preparing Auxiliary Devices

I. Digital Distribution Frame

If E1 trunk cables are led out of the SoftX3000 cabinet in the networking scheme, the
qualified digital distribution frame (DDF) must be configured according to the
international requirements. Before the installation, you must complete the installation
or expansion for the DDF. According to the capacity of the project and future
expansion, the capacity of the DDF must be figured out. For the convenience of
soldering the connectors of trunk cables at the DDF side, refer to the contract
checklist for the model of the trunk cables used in the SoftX3000, or consult the
engineering designer at local office.

II. Optical Transmission Equipment

If there is auxiliary optical transmission equipment, check the following items before
the SoftX3000 hardware installation:
z The optical transmission equipment has been installed.
z The optical transmitter and receiver have been installed and debugged.
z Optical fibers have been laid.
z The fiber tails from connection box are marked,
z The connectivity of the optical fibers has been checked.
z The cabling rack and distribution frame have been installed.

III. Interface to IP network

The SoftX3000 is connected to IP network through 100 Mbit/s standard Ethernet port,
and then connected to the devices over the network. In this case, you must install
routers and LAN Switches, and lay the network cables to prepare the interfaces to the
IP network before installation, thus ensuring that the SoftX3000 can access the IP
network normally.

Huawei Technologies Proprietary

2-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 2 Installation Preparations

IV. Building Integrated Timing Supply System

The SoftX3000 provides embedded signaling gateway. When it also serves as


signaling gateway to get interconnected with SS7 links, it must synchronize the clock
of the links at the opposite end. If the building integrated timing supply system (BITS)
is provided by you, you must complete installing the BITS and make access
preparation before the SoftX3000 hardware installation.

2.2.4 Preparing Tools and Meters

The tools and meters as shown in Table 2-1 must be prepared before installation.

Table 2-1 List of tools and meters

Measurin
g and Angle square, long tape, ruler(1 m), powder marker
marking- and pencil
off tools

Drilling Percussion drill (one), drill bits (φ6, φ8, φ10, φ12,
tools φ14, φ16), vacuum cleaner (one)
Straight screwdriver M3 – M6
Cross screwdriver M3 – M6
General-purpo
Firming
se tools Monkey wrench, torque wrench
tools
Socket wrench M10, M13, M16, M18
Double offset ring spanner M10, M13, M16, M18
Sharp-nose pliers, diagonal pliers, vice, hand-held
Locksmit
electric drill, file, Handsaw, ripping bar, rubber
h tools
hammer, nail hammer
Auxiliary Brush, nippers, paper knife, bellows, electric iron,
tools soldering tin wire, forklift, ladder

Industrial horizontal ruler, ground resistance tester (optional),


ESD-preventive wrist strap, cable winding gun, cable peeler
Special tools (optional), pressing pincers (optional), pressing pincers with
crystal head, wire punchdown tool (optional), SMB coaxial trunk
self-ring cable
Multimeter, 500 V megohm meter (used to measure the
Meters insulation impedance)

Huawei Technologies Proprietary

2-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 2 Installation Preparations

Note:
z The equipment supplier provides the list of tools and instruments, and you decide
the suppliers of tools and meters.
z All the meters must be qualified through the measurement calibration before use.

2.3 Checking Conditions of Equipment Room

2.3.1 Introduction to Checking Procedure

Upon arrival on site, the project supervisor must check the construction conditions
according to Project Technical Specifications and Inspection Specifications for the
Lightning Protection and Grounding of Communications Equipment, and fill out the
Installation Environment Checklist based on the check results. After confirming that all
conditions are ready, sign Kickoff Agreement with the customer and formulate the
Project Installation Plan. In case the project preparation made by the customer is not
sufficient to meet the kickoff requirement, fill up the “Onsite Work Liaison Form” to
state the reasons to the customer. If the customer insists on kicking off the installation,
the customer should commit the completion time for project preparation and sign it.
For a project in which the rework is impossible or the rework still fails to meet the
project requirement, a memo is required to be signed between the parties.

2.3.2 Checking Building Conditions of Equipment Room

Check the area, height, load bearing capacity, and groove distribution of the
equipment room. If any item does not meet the requirements, suggest the customer
to reconstruct.

2.3.3 Checking Environment Conditions

The check items include:


z The illumination conditions must satisfy the requirements for equipment
maintenance. There must be normal illumination, standby illumination, and
emergency illumination systems.
z The air-conditioning and ventilation systems can ensure the temperature and
humidity requirements.
z Effective ESD-preventive measures are taken.
z The equipment room has sufficient fire-fighting facilities.
z The equipment room meets the quake-proof requirements. The floor in the
equipment room is solid enough to install and fasten the equipment.

Huawei Technologies Proprietary

2-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 2 Installation Preparations

z Safe lightning-proof measures are taken for the equipment room.

2.3.4 Checking Power Supply Conditions

The check items include:


z The AC power supply facilities are complete, and the power meets the
requirement. Besides the mains power supply, there must be standby power
supply by diesel generator.
z The DC power distribution devices can provide stable power supply, and the
output voltage is within the specified range.
z There are enough available storage batteries to ensure the equipment able to
run in case of power supply accident.
z The AC power distribution system has independent AC protection ground.

2.3.5 Checking Grounding Conditions

Good grounding is the basis ensuring the stable running of the equipment, and
preventing the equipment from lightning and interference. In this case, it is required to
carefully check the grounding conditions of the site, and take correct grounding
measures.

The grounding impedance for the equipment building must be not more than 1Ω.

The grounding impedance of the equipment must meet the relative stipulation of the
country if it is stricter than the specifications shown in Table 2-2.

Table 2-2 Grounding impedance requirements for switching equipment

Capacity of equipment Grounding impedance


Less than 2000 local subscribers ≤5Ω

Not more than 10000 local subscribers


≤3Ω
Not more than 2000 toll calls
More than 10000 local subscribers
≤ 1Ω
More than 2000 toll calls

2.3.6 Checking Auxiliary Devices

The SoftX3000 is running over the network. Before installing the SoftX3000, it is
required to check whether the auxiliary transmission devices are installed, for
example, whether the optical terminator is installed and commissioned, whether
optical fibers are laid, and whether cabling rack and cable distribution rack are
installed.

Huawei Technologies Proprietary

2-5
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 2 Installation Preparations

2.3.7 Checking Other Facilities

There must be a workbench in compliance with ESD-preventive requirements in the


control room, used to install maintenance terminal, network management workstation
and printer.

Desk, chair, power socket for computer, and phone set are necessary during
installation. It is required to prepare for any possibilities according to the site
conditions.

2.4 Unpacking and Accepting the Equipment

2.4.1 Unpacking Requirements

After the project begins, the project supervisor should check the goods together with
the customer.

First check whether the total number of goods against the packing list attached to the
packing box, whether the destination address of goods is consistent with the actual
installation site, whether the physical appearance of the packing case is good and
whether the chassis is placed correctly.

If such things as serious damage to the outer package, water on the outside
packaging box, or rust/water on the equipment is identified, stop unpacking
immediately and find the cause. Then, feed back the situation to the local
representative office.

Caution:

To protect the equipment and find out the cause, place the unpacked equipment
indoor for proper storage and shot the site storage environment, the rusted or
corroded equipment/packing boxes/packaging materials. Then, properly keep these
photos and store the unpacked packing boxes as well as packaging materials.

Now, open the case marked with the label indicating “Packing list inside”, take out the
packing list, and check the goods against the list. In case any good is wrong or
missing, please fill out Goods Error Feedback Form. In case any good is damaged,
please fill out Goods Replacement Application Form, and finally fill out the Packing
List together with the customer.

Huawei Technologies Proprietary

2-6
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 2 Installation Preparations

Caution:

z During the transportation and handling of products, spare parts or components,


make sure to avoid the collision of such things against doors, walls or shelves.
z When transporting, handling and installing the equipment, it is forbidden to reach
the uncoated metal surface of equipment parts or components with sweaty or dirty
gloves.

2.4.2 Unpacking Wooden Crate

I. Overview of Unpacking Wooden Crate

Caution:

The wooden case is direction-oriented and should not be placed upside down.
Otherwise, fatal damages would be caused to the product.

Wooden crate is used to package cabinets and batteries. A packaged cabinet is


composed of wooden board, angle steel, tongue, and foam corner protector. Before
unpacking the wooden crate, move the packing crate to the equipment room or
nearby (if there is sufficient space), to avoid damage to the cabinet when moving the
cabinet.

II. Operation Procedures of Unpacking Wooden Crate

The unpacking steps are as follows.


1) Insert the spanner into the tongue holes in the cover, and turn the spanner to
straighten the tongues, as shown in Figure 2-1. You can also use screwdriver or
hammer to straighten the tongues.

Huawei Technologies Proprietary

2-7
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 2 Installation Preparations

(2) (1)

(3)

(4)

(1) Angle steel (2) Wooden board


(3) Tongue (4) Spanner
Figure 2-1 Straightening the tongue

2) Lift and remove the covers, as shown in Figure 2-2.

Figure 2-2 Removing the cover

Huawei Technologies Proprietary

2-8
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 2 Installation Preparations

3) Straighten the tongues in the surrounded wooden board, and then remove the
surrounded wooden board, as shown in Figure 2-3.

Figure 2-3 Removing the surrounded wooden boards

III. Unpacking Other Wooden Crates

When moving or lifting the cabinet, use both hands to hold the firm parts of the
cabinet, such as brackets or major frames, instead of other parts, such as cable
brackets and cable fixing beam, to avoid damage to the cabinet or personal injury.
Remove the lining boards of the cabinet on the installation site to avoid damage to
signal cables and boards when moving or lifting the cabinet.

2.4.3 Unpacking Cardboard Box

I. Overview of Unpacking Cardboard Box

Cardboard box is used to package cables, delivery accessories, and terminal devices.

Adopt ESD-preventive measures when you unpack the parts delivered in


ESD-preventive plastic bags.

In addition, the environment temperature and humidity must be noticed. In the


ESD-preventive plastic bag, there is silica-gel drier to absorb the moisture in the bag
and keep the bag dry inside. When the device is moved from a cold and dry place to

Huawei Technologies Proprietary

2-9
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 2 Installation Preparations

a warmer and wetter place, do no unpack until 30 minutes later. Otherwise, the
moisture will condense on the surface of the device, and damage it.

II. Operation Procedures of Unpacking Cardboard Box

The unpacking steps are as follows:


1) Check the label on the cardboard box to get information about the type and
quantity of the components in the box.
2) Use tilted-nose pliers to cut the packaging straps.
3) Use paper knife to cut the tapes along the seam of box cover.
Do not insert the knife too deep, or you will scratch the internal device.
4) Open the cardboard box.
5) Check the components in the boxes based on the packing checklist.
6) Sign the acceptance document.
Do NOT discard cardboard box with components left inside to avoid troubles to the
installation. It is recommended that one person is responsible for one cardboard box.
Before unpacking next cardboard box, be sure to check the current cardboard box to
see if it is empty.

Huawei Technologies Proprietary

2-10
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

Chapter 3 Installing Cabinets

3.1 Introduction to the Chapter

This chapter contains the following sections:


z Introduction to Cabinet
z Installing Cabinets on ESD-Preventive Floor
z Installing Cabinets on Cement Floor

3.2 Introduction to Cabinet

The SoftX3000 adopts standard 19-inch N68-22 cabinet, made of sheet metal and
featuring simple structure and universal usability. Three cabinets can satisfy the
requirement for full configuration of the SoftX3000.

According to different equipment rooms, a cabinet can be installed on cement floor or


ESD-preventive floor. If two or more cabinets are placed in the same row, they must be
connected and fixed.

Note:
Wear clean gloves when touching the surfaces of cabinets or frames.

3.3 Installing Cabinets on ESD-Preventive Floor

3.3.1 Reference of N800 Support

If N68-22 cabinets are installed in the equipment room with ESD-preventive floor, N800
series supports are used. Refer to chapter 1 “Cabinet and Internal Components” of
U-SYS SoftX3000 SoftSwitch System Hardware Description Manual for the
introduction of N800 support.

3.3.2 Introduction to Installation Procedure on ESD-Preventive Floor

Figure 3-1 shows the procedure for installing cabinets on ESD-preventive floor.

Huawei Technologies Proprietary

3-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

Start

Plan support positions

Install supports and slide rails

Install ESD-preventive floor


holder fixing components

Position cabinets

Level cabinets

Combine cabinets

Fix cabinets

Pass the N
insulation test?

Y
End

Figure 3-1 Procedure for installing cabinets on ESD-preventive floor

When two or more cabinets are placed in the same row, they must be connected and
fixed. Generally, internal components and cables are installed before the floor holder
installation, floor recovering, door lintel installation and door installation are
implemented. For detailed information, see Chapter 7 "Installing Cabinet Fittings" in
this manual.

3.3.3 Planning Support Positions

I. Determining cabinet positions

Before installing cabinets, plan available space of the equipment room. Keep sufficient
space around cabinets for maintenance and operation purposes, as shown in
Figure 3-2 and Figure 3-3.

Huawei Technologies Proprietary

3-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

II. Marking installation hole positions

To mark installation hole positions, do as follows:


1) Specify installation positions for the supports with reference to the benchmark
dimensions and the support dimensions specified in the construction plan.
2) Mark a few points for line drawing with a long tape, and draw two straight lines
parallel to the benchmark with a distance of 690 mm between them.
3) According to the design requirements, specify the installation holes for the first
support on the two lines.
4) With these holes as reference, mark the installation holes for other supports one
by one.
5) To avoid faults, measure all location lines again after marking the holes to ensure
correct dimensions.
Figure 3-2 shows the holes for installing supports for a single cabinet. Figure 3-3 shows
the holes for installing supports for multiple cabinets in a row.

€800

€800

690 800
4-∅16

€800

354

600

€800

Figure 3-2 Hole positions for installing support for a single cabinet

Huawei Technologies Proprietary

3-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

€800
€800

4- ∅16 690 800

€800

354 354 354


€800 600 600 600

Figure 3-3 Hole positions for installing supports for multiple cabinets in a row

It is also available to use line drawing template to mark the positions of the expansion
bolt holes. Based on the cabinet layout, place the line drawing template on the floor, as
shown in Figure 3-4. To mark the hole positions for all expansion bolts on the floor, use
the template (each cabinet has four expansion bolts). The half-circle gap on the
template indicates the front direction of the cabinet.

Huawei Technologies Proprietary

3-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

690 800

Back

Left Right
354

600 Front

Figure 3-4 Line drawing template (used for installation on ESD-preventive floor)

Note:
Be sure to use the template in correct direction.

III. Drilling holes

To fix supports onto ground with M12 expansion bolts, it is required to drill holes for the
expansion bolts using a percussion drill with bit φ16.

To drill a hole, do as follows:


1) Keep the drilling bit vertical to the ground and hold tight the drillstock to make
holes 52 mm to 60 mm deep. The depth of the holes must be within 52 mm to 60
mm. Otherwise the expansion bolts cannot be fastened. Make sure that the depths
of all holes are the same.
2) Clean the dust inside the holes with a vacuum cleaner.
3) Measure the depth to make sure that the depths of all holes are the same.
If the ground is too hard or smooth to settle the drill bit, punch a sample pit first for easy
drilling.

Huawei Technologies Proprietary

3-5
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

Drawing lines and drilling holes are the fundamental work for hardware installation.
Good quality is the prerequisite to guarantee the quality of the overall installation. If the
accuracy is not high enough, the future work will be greatly affected.

Note:
The depth of drilled hole must be 52 mm to 60 mm. A depth less than 52 mm or more
than 60 mm will cause the expansion bolt unable to be installed or fastened.

3.3.4 Installing Supports and Slide Rails

I. Installing expansion bolts

Before fixing expansion bolts, clean up the dust inside and around the holes with a
vacuum cleaner. Measure the distance between the holes, and place the supports to
check whether the supports and holes match exactly. For the holes with big deviation,
plan and drill new holes before installing expansion bolts in them.

To install an expansion bolt, do as follows:


1) Take expansion tube and nut off the expansion bolt, and put them vertically into a
hole after guiding rib on expansion nut has been inserted in to guiding slot of the
expansion tube.
2) Strike directly on expansion tube with a rubber hammer until it is completely driven
into the ground.
Figure 3-5 shows the installation of expansion tube and expansion nut.

(1)

(2)

(3)

(4)

(1) Expansion tube (2) Guiding slot of expansion tube


(3) Expansion nut (4) Guiding rib of expansion nut

Figure 3-5 Installation of expansion tube and expansion nut

Huawei Technologies Proprietary

3-6
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

Note:
The guiding rib on expansion nut must be inserted into the guiding slot on expansion
tube before the tube is driven into the ground. Otherwise, the expansion bolt could not
be installed and fastened normally.

II. Adjusting support height

To ensure that the upper surface of slide rails and the upper surface of ESD-preventive
floor are on the same level after the supports and sidle rails are assembled, it is
required to adjust all the supports to the preset height before installation.

To adjust the support height, do as follows:


1) Measure the height of the upper surface of the ESD-preventive floor.
2) Make the value minus the height of the slide rail (50 mm) to get the preset height of
the supports.
3) According to the ESD-preventive floor height mark on the supports, adjust all the
supports to the preset height and tighten the height-locking bolts to 45 Nm with a
torque spanner.
4) Tighten the bolts in the middle and then those at both sides, as shown in
Figure 3-6.

(1)

(2)

(1) Height-locking bolt (middle) (2) Height-locking bolt (side)


Figure 3-6 Connection of support and floor

III. Assembling supports and slide rails

To assemble the supports and slide rails, do as follows:

Huawei Technologies Proprietary

3-7
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

1) Assemble the supports and slide rails together with M12x30 bolts, spring washers
and flat washers, as shown in Figure 3-7.
2) Correct the support positions before fastening all bolts to make the diagonal lines
(A and B shown in Figure 3-7) of the two slide rails are equal in length.

Figure 3-7 Assembly of support and slide rails

IV. Fixing supports

To fix the supports, do as follows:


1) Align the support installation holes with the corresponding expansion bolt holes.
2) Fit the spring and flat washers on M12x60 bolts, and insert the bolts vertically into
the expansion bolt holes through the support installation holes.
3) Correct the support positions and screw M12x60 bolts to 45 Nm, as shown in
Figure 3-8.

Huawei Technologies Proprietary

3-8
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

(1)
(2)
(3)

(1) Bolt M12x60 (2) Spring washer 12 (3) Flat washer 12


Figure 3-8 Assembly of supports and slide rails

When installing supports for a row of cabinets, align all supports by front side and keep
the spacing between adjacent supports as 128 mm for convenience of connecting
cabinets, as shown in Figure 3-9.

128

Figure 3-9 Relative positions of supports

Huawei Technologies Proprietary

3-9
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

3.3.5 Installing Holder Fixing Components

Floor holder fixing components are used to fix front floor holder and back floor holder.
Before the cabinets are positioned, the floor holder fixing components must be fixed
under the slide rails, as shown in Figure 3-10.

(1)

(1) Holder fixing


Figure 3-10 Installation of floor holder fixing components

3.3.6 Leveling Cabinets

I. Positioning cabinets

To position a cabinet, do as follows:


1) Determine the front view of a cabinet.
2) Lift it onto slide rails.
3) Align the four fixing holes in the cabinet with the four holes in the slide rails.

II. Installing insulation plates

Put the installation plates on the slide rails under the cabinet, as shown in Figure 3-11.
Each cabinet requires two insulation plates.

Huawei Technologies Proprietary

3-10
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

(1)
(2)

(3)
(4)
(5)

(6)

(1) Bolt M12x45 (2) Spring washer 12 (3) Insulating plate


(4) Washer (5) Flat washer 12, nut 12 (6) Slide rail
Figure 3-11 Leveling and fixing a cabinet

III. Leveling cabinets

To level the cabinets, do as follows:


1) Place horizontal rulers in both longitudinal and latitudinal directions on the top
surface of the cabinet to check the levelness.
2) Use washers to adjust the cabinet height to keep the cabinet horizontal, as shown
in Figure 3-11.

Note:
The washers for leveling must be installed between the insulation plates and slide rails.
Otherwise, insulation will not work.

Huawei Technologies Proprietary

3-11
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

3.3.7 Fixing Cabinets

I. Fixing bottom of cabinet

To fix the cabinet bottom, do as follows:


1) Fit the spring washers on M12x45 bolts (the big flat washers and insulation
coverings have been installed in the cabinet).
2) Insert the bolts vertically into the connection holes in the slide rails through the
lower enclosure frame of the cabinet.
3) Fit the flat washers and nuts and screw M12x45 bolts to 45 Nm, as shown in
Figure 3-11. Be sure to fasten the bolts in cross way to reduce the stress between
bolts and cabinet.

II. Fixing top of combined cabinets

When two or more cabinets are installed, they must be combined. The cabinets are
combined and fixed by connecting plates.

The connecting plates for combining cabinets are installed on the top of cabinets and
they are delivered with cabinets, as shown in Figure 3-12.

To connect two adjacent cabinets, do as follows:


1) Disassemble the connecting plates of the two adjacent cabinets.
2) Reassemble them according to Figure 3-12

Huawei Technologies Proprietary

3-12
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

1 2 3

4 5 6 7

Figure 3-12 Installation of connecting plate for combining cabinets

3.3.8 Performing Insulation Test

To test the insulation effect of the cabinets, do as follows:


1) Set the multimeter to megohm range.
2) Measure the impedance between the supports and cabinets.
If the impedance measured is more than 5 megohm, it indicates that the cabinets are
insulated from the supports. In this case, you can end the installation.

Otherwise, do as follows:
1) Disassemble all installed components.
2) Check whether the insulation parts have been installed or whether the insulation
parts have been damaged.

Huawei Technologies Proprietary

3-13
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

3.4 Installing Cabinets on Cement Floor

3.4.1 Introduction to Installation Procedure on Cement Floor

If N68-22 cabinet is installed on cement floor, it can be fixed by expansion bolts directly.

Caution:

During installation, the insulation plates between each cabinet and floor, as well as the
insulation coverings for expansion bolts must be correctly installed, to make the whole
set of equipment insulated from the ground before protection grounding cables are
connected, and to meet the insulation requirements.

Figure 3-13 shows the procedure of installing cabinet on cement floor.

Start

Plan cabinet positions

Install expansion bolts

Position cabinets

Level cabinets

Combine cabinets

Fix cabinets

Pass the N
insulation test?

Y
End

Figure 3-13 Procedure for installing cabinets on cement floor

Huawei Technologies Proprietary

3-14
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

When two or more cabinets are placed in the same row, they must be combined and
fixed.

3.4.2 Planning Cabinet Positions

I. Determining cabinet positions

Before installing cabinets, plan the available space of the equipment room. Keep
sufficient space around the cabinets for maintenance and operation purposes, as
shown in Figure 3-14 and Figure 3-15.

II. Marking installation hole positions

To mark installation hole positions, do as follows:


1) Specify the positions for the expansion bolts with reference to the dimensions of
planned positions and the dimensions of the holes for installing cabinet specified
in the construction plan.
2) Mark a few points for line drawing with a long tape and draw two straight lines
parallel to the benchmark with a distance of 687 mm between them.
3) According to the design requirements, specify the expansion bolt holes for the first
cabinet.
4) With these holes as reference, mark the expansion bolt holes for other cabinets
one by one.
5) To avoid faults, measure all location lines again after marking the holes, to ensure
correct dimensions.
Figure 3-14 shows the layout of expansion bolt holes for a single cabinet. Figure 3-15
shows the layout of expansion bolt holes for multiple cabinets in a row.

Huawei Technologies Proprietary

3-15
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

€800

€800

687 800
4- ∅16

€800

413

600

€800

Figure 3-14 Hole positions for expansion bolts used for a single cabinet

Huawei Technologies Proprietary

3-16
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

€800
€800

4- ∅16 687 800

€800

413 413 413


€800 600 600 600

Figure 3-15 Hole positions for expansion bolts used for multiple cabinets in a row

It is also available to use line drawing template to mark the positions of the expansion
bolt holes. Based on the cabinet layout, place the line drawing template on the floor, as
shown in Figure 3-16. To mark the hole positions for all expansion bolts on the floor, use
the template (each cabinet has four expansion bolts). The half-circle gap on the
template indicates the front direction of the cabinet.

Huawei Technologies Proprietary

3-17
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

687 800

Back

Left Right
413

600 Front

Figure 3-16 Line drawing template (used for installation on cement floor)

Note:
Be sure to use the template in correct direction.

III. Drilling holes

To fix cabinets onto ground with M12 expansion bolts, it is required to drill holes for
expansion bolts using a percussion drill with bit φ16.

To drill a hole, do as follows:


1) Keep the drilling bit vertical to the ground and hold tight the drillstock to make
holes 52 mm to 60 mm deep. The depth of the holes must be within 52 mm to 60
mm. Otherwise the expansion bolts cannot be fastened. Make sure that the depths
of all holes are the same.
2) Clean the dust inside the holes with a vacuum cleaner.
3) Measure the depth to make sure that the depths of all holes are the same.
If the ground is too hard or smooth to settle the drill bit, punch a sample pit first for easy
drilling.

Huawei Technologies Proprietary

3-18
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

Drawing lines and drilling holes are the fundamental work for hardware installation.
Good quality is the prerequisite to guarantee the quality of the overall installation. If the
accuracy is not high enough, the future work will be greatly affected.

Note:
The depth of the drilled hole must be 52 mm to 60 mm. A depth less than 52 mm or
more than 60 mm will cause the expansion bolt unable to be installed or fastened.

IV. Installing expansion bolts

Before fixing expansion bolts, clean up the dust inside and around the holes using a
vacuum cleaner. Measure the distance between the holes. For the holes with big
deviation, plan and drill new holes before installing expansion bolts in them.

To install an expansion bolt into a hole, do as follows:


1) Take the expansion tube and nut off the expansion bolt.
2) Put them vertically into the hole after guiding rib on expansion nut has been
inserted into the guiding slot of the expansion tube.
3) Strike directly on expansion tube with a rubber hammer until it is completely driven
into the ground.
Figure 3-5 shows the installation of expansion tube and expansion nut.

3.4.3 Leveling Cabinets

I. Positioning cabinets

To position a cabinet as shown in Figure 3-17, do as follows:


1) Lay insulation plates on the floor (two plates for each cabinet).
2) Place a cabinet at the planned position.
3) Align the installation holes in the cabinet with the corresponding expansion bolt
holes.

II. Leveling cabinet

To level the cabinets, do as follows:


1) Place horizontal rulers in both longitudinal and latitudinal directions on the top
surface of cabinets to check the levelness of the cabinets.
2) Use washers under the insulation plates to adjust the cabinet height to keep the
cabinets horizontal, as shown in Figure 3-17.

Huawei Technologies Proprietary

3-19
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

3) Align all cabinets.

(1)

(2)

(3)

(4)

(1) Bolt M12x70 (2)Spring washer 12


(3) Insulating plate (4) Washer
Figure 3-17 Placing and securing the cabinet

Note:
The washers for leveling must be installed between insulation plates and floor.
Otherwise, insulation will not work.

3.4.4 Fixing Cabinets

I. Fixing bottom of cabinet

To fix the cabinet bottom, do as follows:


1) Fit the spring washers on M12x70 bolts (the big flat washers and insulation
coverings have been installed in the cabinet).
2) Insert the bolts vertically into the expansion bolt holes in the slide rails through the
lower enclosure frame of the cabinet.
3) Screw M12x70 bolts to 45 Nm, as shown in Figure 3-17.

Huawei Technologies Proprietary

3-20
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

II. Fixing top of combined cabinets

When two or more cabinets are installed, they must be combined and fixed by
connecting plates.

The connecting plates for combining two cabinets are installed on the top of cabinets
and they are delivered with cabinets, as shown in Figure 3-18.

To combine two adjacent cabinets, do as follows:


1) Disassemble the connecting plates of the two adjacent cabinets.
Reassemble them according to Figure 3-18.

1 2 3

4 5 6 7

Figure 3-18 Installation of connecting plate for combining cabinets

3.4.5 Performing Insulation Test

To test the insulation effect of the cabinets, do as follows:

Huawei Technologies Proprietary

3-21
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 3 Installing Cabinets

1) Set the multimeter to megohm range.


2) Measure the impedance between expansion bolts M12x70 and cabinets.
If the impedance measured is more than 5 megohm, it indicates that the cabinets are
insulated from the expansion bolts. In this case, you can end the installation.

Otherwise, do as follows:
1) Disassemble all installed components.
2) Check whether the insulation parts have been installed or whether the insulation
parts have been damaged.

Huawei Technologies Proprietary

3-22
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 4 Installing Internal Components

Chapter 4 Installing Internal Components

4.1 Introduction to the Chapter

This chapter contains the following sections:


z Introduction to Internal Components and Installation
z Installing Internal Components

4.2 Introduction to Internal Components and Installation

4.2.1 Introduction to Internal Components

Based on different internal components configured, the N68-22 cabinets can be divided
into integrated configuration cabinet, service processing cabinet, media resource
service (MRS) cabinet.

The internal components in the integrated configuration cabinet include iGWB server,
BAM server, hard disk array, LAN Switch, KVMS, and basic and expansion frames.
Figure 4-1 shows the full configuration of an integrated configuration cabinet.

Huawei Technologies Proprietary

4-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 4 Installing Internal Components

Power distribution frame


(2U)

Expansion frame/Media
resource frame/MRS6100
(9U)

Air deflector (2U)

Basic frame (9U)

Air deflector (2U)


Blank filler panel (1U)
KVMS(1U)
LAN Switch 3 (1U)
Cabling trough (1U)
LAN Switch 2 (1U)
Cabling trough (1U)

Blank filler panel (3U)

BAM(2U)

Standby iGWB (2U)

Active iGWB (2U)


LAN Switch 1 (1U)
Cabling trough (1U)
LAN Switch 0 (1U)
Blank filler panel (2U)

Blank filler panel (2U)

Figure 4-1 Full configuration of integrated configuration cabinet

Huawei Technologies Proprietary

4-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 4 Installing Internal Components

Note:
The active iGWB server is labeled as iGWB (M), and the standby iGWB server as
iGWB (S).

The number of service processing cabinets configured is determined based on the


system capacity. Figure 4-2 shows the full configuration of four service processing
cabinets. The frames are installed from bottom to top according to the specific system
capacity.

Service processing cabinet 1 Service processing cabinet 2 Service processing cabinet 3 Service processing cabinet 4

Power distribution frame (2U) Power distribution frame (2U) Power distribution frame (2U) Power distribution frame (2U)

Media resource frame/ Media resource frame/ Media resource frame/ Media resource frame
expansion frame (9U) expansion frame (9U) expansion frame (9U) (9U)

Air deflector (2U) Air deflector (2U) Air deflector (2U) Air deflector (2U)

Expansion frame (9U) Expansion frame (9U) Expansion frame (9U) Expansion frame (9U)

Air deflector (2U) Air deflector (2U) Air deflector (2U) Air deflector (2U)

Expansion frame (9U) Expansion frame (9U) Expansion frame (9U) Expansion frame (9U)

Air deflector (2U) Air deflector (2U) Air deflector (2U) Air deflector (2U)

Expansion frame (9U) Basic frame (9U) Expansion frame (9U) Expansion frame (9U)

Blank filler panel (2U) Blank filler panel (2U) Blank filler panel (2U) Blank filler panel (2U)

Figure 4-2 Full configuration of service processing cabinets

Three service processing cabinets can meet the requirements for the full configuration
of the system. When there are more than one service processing cabinets, the second
service processing cabinet must be configured with a basic frame in the first frame
position.

If the SoftX3000 system has no independent MRS, media resource frames must be
configured in the service processing cabinet, and media resource boards are installed

Huawei Technologies Proprietary

4-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 4 Installing Internal Components

in the frames. If the SoftX3000 system has independent MRS, it is not required to
configure media resource frames in the service processing cabinet. In the MRS cabinet,
only MRS is configured, as shown in Figure 4-3.

Power distribution frame (2U)

Blank filler panel (3U)

Blank filler panel (3U)

Blank filler panel (3U)

Blank filler panel (2U)

MRS (13U)

Blank filler panel (3U)

Blank filler panel (2U)

Blank filler panel (2U)

Blank filler panel (3U)

Blank filler panel (3U)

Blank filler panel (3U)

Blank filler panel (2U)

Blank filler panel (2U)

Figure 4-3 Configuration of MRS cabinet

Huawei Technologies Proprietary

4-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 4 Installing Internal Components

4.2.2 Installation Procedure

Figure 4-4 shows the procedure for installing internal components.

Cabinet installation completed

Installing iGWB server

Installing BAM

Installing hard disk array

Installing LAN Switch

Installing KVMS

Installing MRS

Component installation completed

Figure 4-4 Installation process of intra-cabinet components

4.2.3 Installation Notices

When installing internal components, it is required to place each component with care
into corresponding guide rails in the cabinet, and then insert it slightly into the cabinet.
The component installation sequence inside the cabinet is from bottom upward for the
sake of cabinet stability and convenience in operation.

When fixing internal components and blank filler panels, it is required to put the bolts
into the installation holes on the mount angles of each component, and then fix the
component on the mount angles at both sides of the cabinet. If there are more than two
bolts for a component, it is required to first fix the four bolts at the four corners in
diagonal direction, and then fasten other bolts in sequence.

Blank filler panel is fixed on the mount angles at both sides of the cabinet by lockers. To
pull out blank filler panel, you must first press down the lockers and then loose them.

Huawei Technologies Proprietary

4-5
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 4 Installing Internal Components

During installation, you must ensure the mount angles in correct order, to keep even
space between components, between blank filler panels, and between component and
blank filler panel.

4.3 Installing Internal Components

4.3.1 Installation Requirements

The iGWB server, BAM server, hard disk array, LAN Switch and KVMS must be
installed in corresponding frames in the integrated configuration cabinet and service
processing cabinet in the sequence from bottom to top. The MRS is configured in a
separate cabinet.After the above components have been installed, refer to the methods
introduced in Chapter 5 "Installing Power Cables and Protection Grounding Cables" in
this manual to connect protection grounding cables of the cabinets, and of basic and
expansion frames, and then insert the boards into basic and expansion frames.

4.3.2 Installing iGWB and BAM Servers

Note:
The guide rails delivered with the servers cannot be used in the SoftX3000 cabinet. The
guide rails for the internal components of the cabinet have been assembled before
delivery.

The installation steps are as follows:


1) Put the iGWB server and BAM server on the corresponding positions.
2) Fix the mount angles of the servers to the mount angles on the lateral columns in
front of the cabinet with the captive screws delivered with the servers.

4.3.3 Installing Hard Disk Array

This step is available only when iGWB uses IBM server.

The installation steps are as follows:


1) Place the hard disk array into the corresponding position in the integrated
configuration cabinet.
2) Fix the mount angles on both sides of the hard disk array onto the mount angles on
the lateral columns in front of the cabinet with panel fasteners.

Huawei Technologies Proprietary

4-6
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 4 Installing Internal Components

4.3.4 Installing LAN Switch

Caution:

Do not use the mount angle delivered with the LAN Switch. Use the one delivered with
the SoftX3000 cabinet.

The mount angle is Huawei purple-gray, which is consistent with the color of the
cabinet.

The installation steps are as follows:


1) Install the mount angles of LAN Switch.
2) Place the LAN Switch onto corresponding guide rails and insert it.
3) Fix the LAN Switch with captive fasteners.

4.3.5 Installing KVMS

The installation steps are as follows:


1) Place the KVMS into corresponding position in the integrated configuration
cabinet.
2) Fix the mount angles on both sides of the KVMS onto the mount angles on the
lateral columns in front of the cabinet with captive fasteners delivered with the
iGWB server and BAM server.
3) Install anti-tilt angles on the two rear sides of the KVMS to avoid tilt of the rear part
when the LCD/keyboard is pulled out of the cabinet.
4) Fix the anti-tilt angles to the mount angles on the lateral columns at the back of the
cabinet with screws.

4.3.6 Installing MRS

The installation steps are as follows:


1) Place the MRS onto the guide rails in corresponding frame.Insert it into the cabinet
on an even level.Fix the mount angles on both sides of the MRS onto the mount
angles on the lateral columns in front of the cabinet with panel fasteners.

Huawei Technologies Proprietary

4-7
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 4 Installing Internal Components

Note:
The MRS is an optional device of the system. If the system adopts the media resource
frame (configured with MRCA/MRIA boards) as the embedded MRS, this step can be
omitted.

Huawei Technologies Proprietary

4-8
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

Chapter 5 Installing Power Cables and Protection


Grounding Cables

5.1 Introduction to the Chapter

This chapter contains the following sections:


z Introduction to Power Supply System and Protection Grounding System
z Installing Power Cables and Protection Grounding Cables
z Installing Power Bus Cables from DC Power Distribution Cabinet to DC
Switchboard

5.2 Introduction to Power Supply System and Protection


Grounding System

5.2.1 Introduction to Power Supply System

I. Power Supply Path of PDF

All SoftX3000 cabinets are N68-22 cabinets. Generally, an N68-22 cabinet is powered
by two independent –48V DC power. The power of the components in the cabinet is
controlled by the power distribution frame (PDF). Figure 5-1 shows the power supply
path in a PDF.

-48V1
-48V2

Power distribution frame

SW1 SW2 SW3 SW4 SW5 SW6

Figure 5-1 Power supply path of a PDF

To enhance the reliability of the power supply to internal components of the cabinet, the
PDF combines two input power into one using a large-power diode, and exports to the
six power switches (SW1–SW6) on its panel through a power bus cable. Each of the six

Huawei Technologies Proprietary

5-1
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

switches power some of the components in the cabinet. When one of the input power
fails, the other can still power the internal components of the cabinet.

II. Power Supply Path in the Cabinets

There are three types of SoftX3000 cabinet—integrated configuration cabinet, service


processing cabinet, and media resource server (MRS) cabinet. The components
configured in these cabinets are different from one another, and so does their (primary)
power supply system. Figure 5-2 shows the details of the (primary) power supply
system in the cabinets.

PDF PDF PDF


SW1 SW2 SW3 SW4 SW5 SW6 SW1 SW2 SW3 SW4 SW5 SW6 SW1 SW2 SW3 SW4 SW5 SW6

1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6

1
Expansion frame 5 Expansion frame
1/Media resource 6 5/Media resource 2 Blank filler panel
frame frame

4 2
Basic frame 0 Expansion frame 4
5 3
1
MRS frame
KVMS 1 2
LAN Switch 1 2
3
LAN Switch 0 3 Expansion frame 3
4

BAM (3,4)
5
Standby iGWB (2,3) Expansion frame 2
Active iGWB (2,4) 6 Blank filler panel

Blank filler panel


Blank filler panel

Integrated configuration cabinet Service processing cabinet MRS cabinet

Figure 5-2 Primary power supply system in SoftX3000 cabinets

As shown in Figure 5-2, except for the LAN Switch 0, LAN Switch 1, and KVM/LCD
switcher (KVMS), all other components are controlled by two power switches. Table 5-1
details the mapping between components and control switches.

Huawei Technologies Proprietary

5-2
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

Table 5-1 Mapping between components and control switches

Cabinet Component Control switch


Active iGWB SW2, SW4
Standby iGWB SW1, SW3
BAM SW3, SW4
Hard disk array(only
when iGWB uses SW1, SW6
IBM server)
Integrated configuration cabinet
LAN Switch 0 SW3
LAN Switch 1 SW2
KVMS SW4
Basic frame (frame
SW4, SW5
0)
Expansion frame 1 SW5, SW6
Expansion frame 2 SW5, SW6

Expansion frame 3 SW3, SW4


Service processing cabinet
Expansion frame 4 SW2, SW3
Expansion frame 5 SW1, SW2
MRS cabinet MRS6000 frame SW1, SW2

In actual deployment, the configurations of the service processing cabinet and the MRS
cabinet might vary from Figure 5-2. Therefore, always carefully examine the mapping
between the PDF and all components before power on.

5.2.2 Introduction to Protection Grounding System

The SoftX3000 equipment adopts joint grounding mode. The protection grounding
cables for each cabinet are connected to DC power distribution cabinet that conducts
grounding, and all cabinets are connected by protection grounding cables as an
equipotential system.

The input terminals of backhaul ground (BGND) and protection ground (PGND) of the
cabinet have been connected before delivery to ensure they are equipotential. The
protection grounding cables of the internal components of a cabinet are interconnected
through the grounding bars on the side columns of cabinets. Through the protection
grounding cables of the cabinet, the grounding bars are connected to the protection
ground of the DC power distribution cabinet, which is connected with the protection
grounding bus in equipment room.

Huawei Technologies Proprietary

5-3
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

The protection grounding cables of a cabinet include:


z Protection grounding cables for service frames,
z Protection grounding cables for iGWB and BAM,
z Protection grounding cable for KVMS,
z Protection grounding cable for LAN Switch,
z Protection grounding cable for MRS,
z Protection grounding cables for cabinet doors, and
z Protection grounding cables for connecting grounding bars of adjacent cabinets.
Refer to Refer to chapter 4 “Cables” of U-SYS SoftX3000 SoftSwitch System Hardware
Description Manual for the appearances, models, and specifications of protection
grounding cables.

5.3 Installing Power Cables and Protection Grounding


Cables

5.3.1 Installation Procedure

The process for installing power cables and grounding cables is shown in Figure 5-3

Huawei Technologies Proprietary

5-4
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

Installing cabinets and


internal components
complete

Install power cables for internal


components

Install protection grounding cables for


connecting grounding bars of adjacent
cabinets

Is DC power distribution
cabinet provided together
with SoftX3000
Yes cabinets? No

Install power and protection


Install DC power distribution cabinet
grounding cables from DC
distribution cabinet provided by the
customer to SoftX3000 cabinets
Install protection grounding cables from
DC power distribution cabinet to
protection grounding bus in equipment
room

Install power and protection grounding


cables from DC distribution cabinet to
SoftX3000 cabinets

Install power bus cables from DC power


distribution cabinet to power room (DC
switchboard)

Installing power cables and


protection grounding cables
complete

Figure 5-3 Procedure for installing power cables and protection grounding cables

Huawei Technologies Proprietary

5-5
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

5.3.2 Installation Notices

Generally, DC power distribution cabinet is provided by the customer. If DC power


distribution cabinet is provided together with the SoftX3000 equipment, refer to its
delivery-attached manuals.

The protection grounding bar of DC power distribution cabinet must be correctly


connected to the nearest protection grounding bar offered by the customer through
PGND grounding bus cable. The protection grounding cable uses green and yellow
plastic insulation copper core wires whose core area is the same as that of power
cable.

The internal power cables of N68-22 cabinets have been connected to the
corresponding connecting terminals of power distribution frames before delivery. After
the internal components have been installed completely, connect the other ends of the
power cables to the components.

Before installation, mark or stick labels on both ends of each power cable and
protection grounding cable to identify the device that the cable is connected to, and to
ensure correct connection. For information about filling in and sticking engineering
labels, refer to Appendix B "Engineering Labels for Cables" in this manual.

Only trained professionals can hot-line work on devices with –48V power terminals like
the PDF and service frames.

5.3.3 Installing Power Cables for Internal Components

I. Installing power cable for service frame

Service frames include basic frame and expansion frame. Each service frame has one
input power cable when single power supply is adopted, and has two input power
cables when dual power supplies are adopted. The power cables that are connected to
the frames in different locations have different lengths. Figure 5-4 shows the
appearance of the power cable.

Figure 5-4 Appearance of power cable for service frame

Huawei Technologies Proprietary

5-6
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

The model of power cable for service frame is UL1015, and its core area is 10AWG
(about 5.3 mm2). The end connecting to power distribution frame has two cord end
terminals (X2, X4), and the other end connecting to service frame has two OT terminals
(X1, X3). The blue cable corresponds to –48 VDC, and the black one corresponds to
BGND.

To install the power cable, do as follows:


2) Insert cord end terminals into the output connection holes marked –48V and
BGND on the power distribution frame according to corresponding colors, and
fasten the fastening screws.
3) Connect OT terminals to the filter on the back cover plate of service frame, and
fasten the screws on the filter.
4) Lay out cables along outside of the right cabling trough and bind them.

II. Installing power cable for iGWB or BAM

The power cables for iGWB and BAM are made of 16AWG UL1015 wires (with cross
section about 1.3mm2). One end of the power distribution frame is cord end terminal,
and the power input end is UT terminal. The blue cable corresponds to –48V, and the
black one corresponds to GND. Figure 5-5 shows the appearance of the cable.

Figure 5-5 Appearance of server power cable

The SoftX3000 adopts 2U server, the power input part of which is shown in Figure 5-6.
The DC input power socket is located in the rightmost at the back of the server, with two
power modules which enable implementation of dual power supplies.

(1) DC input power socket (2) Monitor port


(3) 10M/100M autosensing network port
(4) Mouse/keyboard integrated port (5) Serial port
(6) 10M/100M autosensing port of network card (7) Grounding bolt
Figure 5-6 Rear panel of BAM Server

Huawei Technologies Proprietary

5-7
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

To install the power cable, do as follows:


1) Connect the power cables (bound on the rear column of the rack) provided by the
power distribution frame to the DC power socket in the rear panel of BAM server.
“–” jack is for –48V power cable, and “+” jack for GND.
2) Connect the chassis grounding cable for BAM Server to the grounding bolt on the
rear panel of the server. Connect the other end to the PGND busbar of the cabinet.

III. Installing power cable for hard disk array

The power cable of hard disk array is provided by the manufacturer of hard disk array,
the cable color definition is different from Huawei’s specification. The end connected to
the power distribution frame is cord end terminal, on which the blue cable is labeled
“–48V”, the brown end is labeled “GND” and the greenish yellow one is labeled “PGND”.
The outline of the cable is shown in Figure 5-7.

Figure 5-7 Outline diagram of power cable on hard disk array

To install the power cable, do as follows:


1) Insert the –48V and cord end terminal into the corresponding hole on the power
input bar at the back of the power distribution frame.
2) Fasten the fixing screw.
3) Lay out the power cable down along the cabling trough.
4) Insert the other end of the cable into the power input port J1 on hard disk array.
5) Connect the protection grounding cable to the grounding bar of the cabinet.
The hard disk array has dual power supplies. The two power supply modules
correspond to two power input ports marked J1 on the back cover of the hard disk array.
Figure 5-8 shows one of the power input ports.

Huawei Technologies Proprietary

5-8
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

Figure 5-8 Power Input interface on hard disk array

IV. Installing power cable for KVMS

The power cable for KVMS is made of 16 AWG UL1015 wires (with the core area about
1.3 mm2). One end to the power distribution frame has two cord end terminals and the
other end has two OT terminals. The blue cable corresponds to –48V, and the black
one corresponds to GND. Figure 5-9 shows its appearance.

Figure 5-9 Appearance of power cable for KVMS

To install the power cable, do as follows:


1) Insert the cord end terminals into the output connection holes marked “–48V” and
“BGND” on the power distribution frame according to corresponding colors, and
fasten the fastening screws.
2) Lay out the power cable downward along the cabling trough at the left side.
3) Insert the OT terminals into the wire post of the switcher according to the principle
“blue for –48V, black for RTN”, and fasten the cruciform screws, as shown in
Figure 5-10.

Huawei Technologies Proprietary

5-9
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

Figure 5-10 Connection of power cable and protection grounding cable of KVMS

V. Installing power cable for LAN Switch

The power cable for LAN Switch is made of 16AWG UL1015 wires, both ends of which
are cord end terminals. Figure 5-11 shows its appearance.

Figure 5-11 Appearance of LAN Switch power cable

The power input module of LAN Switch is located at the left-back and there is a plastic
socket, which is similar to the output connection holes on power distribution frame.
Besides, there is a power switch at the leftmost, as shown in Figure 5-12:

(1) (2)
BGND
-48--60

(1) Power switch (2) DC power input

Figure 5-12 Power switch on LAN Switch

To install the power cable, do as follows:


1) Insert one end into the output connection holes on the power distribution frame
according to the cable labels, and fasten the fastening screws.

Huawei Technologies Proprietary

5-10
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

2) Insert the other end into the plastic socket at the back of the LAN Switch, and
fasten the captive screws.
3) Lay out the cable along the inside of the mount angle on the left column.
4) Bind the redundant at the bundling bar nearby.

VI. Installing power cable for MRS

The MRS is configured in the MRS cabinet independently with dual power supplies.
Figure 5-13 shows the appearance of its power cable.

Figure 5-13 Appearance of MRS power cable

Figure 5-14 shows the connection of the power cable for the MRS.

Huawei Technologies Proprietary

5-11
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

(1) Grounding bar (2) Power distribution frame (3) Blank filler panel (4) MRS frame
Figure 5-14 Connection of power cables in MRS cabinet

Huawei Technologies Proprietary

5-12
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

5.3.4 Installing Protection Grounding Cables for Internal Components

I. Installing protection grounding cable for service frame

The protection grounding cables for service frame are 10AWG green and yellow cables.
To install them for service frame, use two protection grounding cables to connect the
two grounding terminals on the back cover plate of fan box in service frame to the
grounding bars at both sides of cabinet respectively.

II. Installing protection grounding cable for iGWB or BAM

The grounding cable for iGWB or BAM is 16AWG UL1015. Figure 5-15 shows the
appearance of the cable.

Figure 5-15 Appearance of PGND cable for iGWB and BAM

To install the protection grounding cables for the iGWB and BAM, proceed as follows:
1) Connect the UT terminal to PGND terminal of the iGWB and BAM.
2) Connect the OT terminal to the grounding bar.

III. Installing protection grounding cable for KVMS

The protection grounding cable for KVMS is made of 14AWG wires (green and yellow,
with core area about 2.1 mm2). The appearance of the protection grounding cable for
the KVMS is similar to the one for the iGWB and BAM. Refer to Figure 5-15 for details.

To install the protection grounding cable, do as follows:


1) Connect the OT terminal to proper position on the grounding bar nearby.
2) Fix the OT terminal with screw.
3) Fix the UT terminal to PGND terminal of the KVMS.

IV. Installing protection grounding cables for LAN Switch

The grounding point for the LAN Switch is located on the back panel of the chassis, as
shown in Figure 5-16.

Huawei Technologies Proprietary

5-13
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

SLOT2

(1)

(1) Grounding point


Figure 5-16 Grounding point LAN Switch shell

The protection grounding cable is delivered together with the LAN Switch. Proceed as
follows to install the PGND cable for the LAN Switch:

One end is connected to the grounding pole on the back panel of the LAN Switch, and
the other end is well grounded nearby.

V. Installing protection grounding cable for MRS

The grounding point of the MRS is located on the back panel of the chassis, as shown
in Figure 5-17.

-48V GND -48V GND

(1)

(1) Grounding point


Figure 5-17 Grounding point of MRS

The protection grounding cable is green and yellow wire of 10AWG. Proceed as follows
to install the PGND cable for MRS:
1) Connect one end of the PGND cable to the grounding pole on the back panel of
the MRS.
2) Connect the other end to proper position on the grounding bar nearby.

Huawei Technologies Proprietary

5-14
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

5.3.5 Installing Protection Grounding Cables Between Cabinets

Note:
For the convenience of installing and binding other cables, the grounding bars of
adjacent cabinets are interconnected after all cables of the equipment have been
installed.

To install protection grounding cables between cabinets, use 10AWG cables (300 mm
long) to connect the upper, middle, and lower parts of the grounding bars of adjacent
cabinets, as shown in Figure 5-18.

5.3.6 Installing Power Cables and Protection Grounding Cables for Cabinets

I. Introduction to installing power cables for cabinets

There might be two cases when you install power cables and protection grounding
cables to a cabinet, that is, if DC power distribution cabinet is provided together with the
SoftX3000 equipment, and if only DC power switchboard is configured in the equipment
room. For detailed information, see the contents later in this section.

II. Connecting cables from DC power distribution cabinet to SoftX3000


cabinet

Note:
Before connecting power cables and protection grounding cables, measure the
distance between protection grounding bar and power distribution cabinet, and the
distance between DC power distribution cabinet and connecting terminals of the power
distribution frame in the cabinet. If a used cable is not long enough, stop your work and
replace it with a new one. Do not splice cables by connectors or soldering.
It is required to stick labels at both ends of a power cable where they are 30 mm away
from the root of the cable.

Figure 5-18 shows the connection of power cables from the DC power distribution
cabinet to the SoftX3000 cabinet.

Huawei Technologies Proprietary

5-15
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

(2)
-48V1

BGND

PGND
BGND
BGND
PGND

PGND

-48V1
-48V2
-48V1

-48V1
-48V2

-48V2
-48V2

GND
(1)
GND (3) (3) (3)
PGND

(4)

(1) To DC power switchboard (2) DC power distribution cabinet


(3) SoftX3000 cabinet (4) Protection grounding bar in equipment
room
Figure 5-18 Connecting power cables and protection grounding cables between DC
power distribution cabinet and SoftX3000 cabinet

The following describes how to connect power cables and protection grounding cables
from DC power distribution cabinet to a SoftX3000 cabinet:
1) Insert the cord end terminals (as shown in Figure 5-19) of the two blue power
cables into the connecting terminals marked “–48V1” and “–48V2” on the power
distribution frame in the cabinet and fasten them.
2) Connect the other ends of the two blue cables to the corresponding output
connectors marked “–48V1” and “–48V2” in the DC power distribution cabinet, for
example, the “–48V1” and “–48V2” power cables in the third cabinet must be
connected to the third output connectors of “–48V1” and “–48V2” in the DC power
distribution cabinet.

Figure 5-19 Cord end terminal of power cable

Huawei Technologies Proprietary

5-16
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

3) Use the black BGND cables to connect the connecting terminals marked “BGND”
on the power distribution frame of the cabinet, and the GND grounding bars in the
DC power distribution cabinet.
4) Connect one end of the protection grounding cable (yellow or green and yellow) to
the connecting terminal marked “PGND” in the power distribution frame of the
cabinet, and connect the other end to the protection grounding bar in the
equipment room.
For –48V1 and –48V2 connecting terminals, it is required to use the upper group first,
and then the lower group. For each group, it is required to use the connecting terminals
from left to right (viewed from the front side) one by one. The terminals for positive line
bank and lightning protection ground are used sequentially from left to right.

Note:
In other cases when power cables are led from DC power distribution cabinet, (for
example, to connect protection grounding cables for a terminal), reverse principle is
applied, that is, the terminals are used from down to top and from right to left, to
facilitate future expansion and connection.

If DC power distribution cabinet is not configured in the equipment room, do as follows:


1) Connect the power cables led from –48V1 and –48V2 connecting terminals of the
SoftX3000 cabinet to –48 VDC negative line bank of DC switchboard (or DC
power supply);
2) Connect the power cable led from GND connecting terminal of the SoftX3000
cabinet to –48 VDC positive line bank of DC switchboard (or DC power supply);
3) Connect the protection grounding cable led from the PGND connecting terminal of
the SoftX3000 cabinet to the protection grounding bar nearby provided by the
customer. The cable material must be the green and yellow plastic insulation
copper core wire whose core area is the same as that of power cable.

III. Laying power cables and protection grounding cables at SoftX3000 sdie

When downward cabling is used, the steps to laying power cables and protection
grounding cables at the SoftX3000 cabinet side are as follows:
1) Lead the power cables and protection grounding cables into the cabinet through
rodent-proof net at the bottom of the cabinet.
2) Lay the power cables and protection grounding cables along the cabling troughs
on the side columns of the cabinet until they reach the top of cabinet.
3) Connect the power cables and protection grounding cables to the corresponding
connecting terminals in the power distribution frame.

Huawei Technologies Proprietary

5-17
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

When upward cabling is used, the steps to laying power cables and protection
grounding cables at the SoftX3000 cabinet side are as follows:
1) Lay the power cables and protection grounding cables on the top of cabinet.
2) Connect the protection grounding cables to the grounding bolts.
3) Lead the protection grounding cables out from the grounding bolts.
4) Pass the power cables and protection grounding cables trough the cabling holes in
the top of the cabinet.
5) Connect the power cables and protection grounding cables to the corresponding
connecting terminals in the power distribution frame.
To lay the power and protection grounding cables, straight and even appearance is
required, and different colors must be separated, and the cables must be bound every
200 mm.

After the power and protection grounding cables are laid out, it is required to cut the
rubber cover to match the size of the left space of the cabling hole.

Note:
When power cables and protection grounding cable are laid outside cabinet, they must
be bound separately. When cables are laid inside cabinet, power cables and protection
grounding cable are bound separate from signal cables.

IV. Laying power and protection grounding cables in DC power distribution


cabinet

To lay the power cables and protection grounding cables in the DC power distribution
cabinet, do as follows:
1) Lead the power cables (settled according to colors) into DC power distribution
cabinet through cabling holes in the top of the cabinet
2) Lay and bind the power cables along the side columns, until they reach
corresponding bus bars.
3) Lay and bind them along the beam of the cabinet. Ensure that the cables are laid
inside the cabinet with smooth and uncrossed appearance.
4) Add flat washers and spring washers to connect OT terminals to GND copper bus
bar and –48V wire post.

Huawei Technologies Proprietary

5-18
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

Note:
z When power cables and protection grounding cable are laid outside cabinet, they
must be bound separately. When cables are laid inside cabinet, power cables and
protection grounding cable are bound separate from signal cables.
z It is required to keep proper redundancy for the cables, and to cut out the surplus
parts. When you make an OT terminal for a cable, be sure to cover it with
heat-shrinkable tube, solder it (soldering is not allowed when you make a cable with
large core area), and shrink the heat-shrinkable tube.

5.4 Installing Power Bus Cables from DC Power Distribution


Cabinet to DC Switchboard

5.4.1 Introduction to Power Bus Cables from DC Power Distribution Cabinet


to DC Switchboard

Power bus cables are used to connect DC power distribution cabinet and DC
switchboard.

Generally provided by the customer, a power bus cable in the power room includes
–48 VDC cable (blue) and BGND cable (black). The specifications of power bus cables
are determined according to the result of site survey.

Note:
The core area of power bus cable from DC switchboard to DC power distribution
cabinet is designed according to the parameters such as loop length of the power bus
cable, terminal load payload capacity for the engineering and design voltage drop.

If a large-core-area power cable is required, you can connect two or more power cables
in parallel to meet the requirement. For example, if there are only 120 mm2 power
cables, but a 240 mm2 power cable is required, you can use two 120 mm2 power cables
in parallel connection as one power cable.

Refer to Appendix C Calculating Core Area of Power Bus Cable for the calculation of
core area of power bus cables.

Huawei Technologies Proprietary

5-19
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

5.4.2 Connecting Power Bus Cables from DC Power Distribution Cabinet to


DC Switchboard

Figure 5-20 shows the connection of the power bus cables for the auxiliary DC power
distribution cabinet of the SoftX3000 cabinet. For detailed information on connecting
power bus cables, refer to User Manual delivered with the DC power distribution
cabinet.

(1) GND lead-in terminal block (2) –48V1 power lead-in terminal
block
(3) –48V2 power lead-in terminal block (4) PGND lead-in terminal block
(5) –48V1 output terminal block (6) –48V2 output terminal block
(7) GND output terminal block (8) PGND output terminal block
(9) GND lead-in terminal block for downward cabling of the
system
Figure 5-20 Connecting terminals in DC power distribution cabinet

Two groups of primary power supplies are used for a DC power distribution cabinet,
and there are five bus cables: one –48V1 bus cable, one –48V2 bus cable, two GND
bus cables and one PGND bus cable.

The following describes how to connect the power bus cables between the DC power
distribution cabinet and the DC switchboard:
1) Connect –48V1 bus bar in the DC power distribution cabinet to –48 VDC negative
line bank in the active DC switchboard (or active DC power supply),

Huawei Technologies Proprietary

5-20
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

2) Connect –48V2 bus bar in the DC power distribution cabinet to –48 VDC negative
line bank in the standby DC switchboard (or standby DC power supply).
3) Connect the GND bus bars in the DC power distribution cabinet to the –48 VDC
positive line banks in the active and standby DC switchboards (or active and
standby DC power supplies) respectively.
If there is only one power supply device, connect both of the –48V1 and –48V2 bus
bars of the DC power distribution cabinet with the –48 VDC output terminals of the DC
switchboard (or DC power supply).

Note:
The PGND grounding bar of the DC power distribution cabinet must be reliably
connected to the protection grounding bar provided by the customer through grounding
bus cable.

5.4.3 Making and Fixing OT Terminals

To make an OT terminal for a power bus cable or protection grounding cable at DC


power distribution cabinet side, do as follows:
1) Cover the cable with a heat-shrinkable tube.
2) Solder (soldering is not allowed when you make a cable with large core area) or
press the OT terminal tightly.
3) Shrink the heat-shrinkable tube, and ensure that no bare wires or OT terminal
handle exist.
To fix an OT terminal at DC power distribution cabinet side, add flat washers and spring
washers to make the terminal fixed firmly, and to ensure secure contact, as shown in
Figure 5-21.

Note:
Proper redundancy for power bus cables can be kept at bending angles, but other
surplus parts must be cut out. If the surplus parts are cut out, OT terminal must be
remade.

Huawei Technologies Proprietary

5-21
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

(1)

(2)

(3)

(6) (5) (4)

(1) Cable (2) Heat-shrinkable tube (3) Nut


(4) Spring washer (5) Flat washer (6) Connection bolt
Figure 5-21 Connecting OT terminal

5.4.4 Requirements for Installing OT Terminals

If it is necessary to install two or more cables on a wire post, install the OT terminals
crosswise or back-to-back without being overlapped. If the OT terminals have to be
overlapped, bend the terminals by 45 degree or 90 degree and install the biggest OT
terminal at lower position. This rule is adaptable to all situations where OT terminals are
installed. Figure 5-22 shows the overlapped OT terminals.

Huawei Technologies Proprietary

5-22
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

45° (1)
90°
(2)

(2)
(3) (3)
(1)
(4)

(1) (1)

(2)
(2)

(3)
(3)

(5) (6)

(1)Flat washer (2)Nut (3) Spring washer


(4) 45 degree or 90 degree of bending (5) Back-to-back installation
(6) Cross installation
Figure 5-22 Installing two OT terminals

5.4.5 Requirements for Laying Cables Inside DC Power Distribution Cabinet

The requirements for laying cables inside DC power distribution cabinet are as follows:
z The cables laid inside DC power distribution cabinet are smooth and not crossed,
and the cables in different colors are bound separately.
z Proper redundancy for cables is kept and the surplus parts are cut out.
z Both ends of a cable have labels made by Huawei Technologies and marked
corresponding serial number. The labels are stuck 30 mm away from the cable
root.
z The cables are bundled by different cable ties according to the actual conditions.
The cable ties face the same direction after the cables are bundled, and the burrs
of the cable ties must be sheared.
Figure 5-23 shows the DC power distribution cabinet when the cables are laid in
upward cabling mode.

Huawei Technologies Proprietary

5-23
Hardware Installation Manual Chapter 5 Installing Power Cables and
U-SYS SoftX3000 SoftSwitch System Protection Grounding Cables

Figure 5-23 Upward cabling for DC power distribution cabinet

Huawei Technologies Proprietary

5-24
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

Chapter 6 Installing Signal Cables

6.1 Introduction to the Chapter

This chapter contains the following sections:


z Introduction to Signal Cables
z Requirements and Modes of Laying Signal Cables
z Installing Internal Signal Cables
z Installing External Signal Cables

6.2 Introduction to Signal Cables

6.2.1 Types of Signal Cables

The signal cables are divided into internal signal cables and external signal cables.
Among the external signal cables, the clock cable, trunk cable and external network
cable are optional depending on the actual hardware configuration.

The internal signal cables that need to be installed on site include:


z Straight through network cable between LAN Switches
z Straight through network cable between iGWB/BAM and LAN Switch
z Straight through network cables between boards in service frame and LAN Switch
z FE signal cable between HSCI and SIUI
z Serial port cable between iGWB servers
z Data cable between iGWB server and hard disk array (only when iGWB uses IBM
server)
z Server/Switcher cable
z Serial port cable for monitoring power distribution frame
z Internal clock cable(optional)
The external signal cables include:
z Trunk cable(optional)
z External clock cable(optional)
z External network cable

6.2.2 Connection of Internal Signal Cables

Figure 6-1 shows the method of connecting internal cables installed on site. Table 6-1
shows the relationships between numbers and names of internal cables.

Huawei Technologies Proprietary

6-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

(1)
23

24

(2)
48
2M-A 2M-A
50
40 39 2M-B 2M-B

8k-B

8k-B
25
44 43
26

28
E1/T1 E1/T1

8k-A

8k-A
27

46 45

(3)
47
47 49
48 50 2M-A 2M-A
49
4 2M-B
43 44 45 2M-B
6 42 41

8k-A

8k-A
29

23 24

E1/T1 E1/T1
30 8k-B

8k-B
31 32

W10 W9 W8

KVMS

41 39
LAN Switch1
34 36 38

42 40
LAN Switch0
33 35 37

(4)

W3 W2

34
BAM
33

W8

36
Standby iGWB
35

W9

38
3
52 Active iGWB
7
W10

(1) Power distribution frame (2) Expansion frame


(3) Basic frame (4) Hard disk array
Figure 6-1 Connection of internal cables in integrated configuration cabinet

Huawei Technologies Proprietary

6-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

Table 6-1 Relation between the number and name of internal cables in integrated
configuration cabinet

Serial Cable
Cable name Quantity
No. number
Interconnecting serial port cable between
1 52 1
iGWBs
Straight through network cables between
2 33 – 38 6
iGWB/BAM and LAN Switch
Straight through network cable between
3 39 – 42 4
HSCI board and LAN Switch
Serial port cable for monitoring power
4 23 – 24 2
distribution frame
5 47 – 50 2-MHz clock cable 4

6 43 – 46 8-kHz clock cable 4


7 25 – 32 FE cable between HSCI and SIUI 8
8 W8 – W10 Server/Switcher cable 3
Data cable between iGWB and hard disk
9 W2 – W3 2
array

Except for the LAN Switch, the cables in Figure 6-1 are all connected at the back of the
cabinet. The straight through network cables between LAN Switches connect the
network ports in the GE subboards marked Slot1 at the back of the LAN Switches.
These cables are indicated in Figure 6-1.

6.3 Requirements and Modes of Laying Signal Cables

6.3.1 Requirements for Laying Signal Cables

Each cable must be marked or stuck with engineering labels at both ends before it is
installed, to indicate the connected equipment and sequence. For detailed information,
refer to Appendix B “Engineering Labels for Cables” of this manual.

Different types of cables (for example, power cable, signal cable and protection
grounding cable) must be bound separately. If the cables are laid inside the cabinet, the
power cables and protection grounding cables must be bound separate from the signal
cables.

When cables are laid vertically, they must be laid and bound along the left and right
columns. When cables are laid horizontally, they must be laid and bound along the
binding bars.

Huawei Technologies Proprietary

6-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

If power cables and signal cables are laid in a groove, they must not be bound together,
and a distance of at least 50 mm between them must be ensured.

Joint parts of connectors must be secure and in good contact.

Cables must be bound in order and with proper tightness.

6.3.2 Modes of Laying Signal Cables

There is one rectangle cabling holes at each of the four corners on the top of cabinet
and of the four corners at the bottom of cabinet. All the cabling holes have rodent-proof
nets. Figure 6-2 shows the positions of the four cabling holes on the top of as cabinet as
indicated by arrows.

Huawei Technologies Proprietary

6-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

Figure 6-2 External cabling holes on the cabinet

According to the actual conditions of the equipment room, the cables led in and out of
cabinet can be laid through the cabling holes on the top or bottom of cabinet.

To lay the cables, lead the cables into the cabinet through the two back cabling holes on
the top or bottom of the cabinet, and lay them along the side columns of the cabinet into
corresponding cabling frame under each LAN Switch. Then, lay the cables through the
cabling frames and insert them into corresponding sockets on the front panels of LAN
Switches. Be sure to get the cables in order and fix them in the wire bushing.

Huawei Technologies Proprietary

6-5
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

At the cabling holes, there is rodent-proof net, through which cables shall pass. The
size of the cabling holes must be proper so that no space is left around the cables.

The external cables are laid through cabling trough or cabling rack. For the methods for
installing cabling rack, refer to Appendix A “Installing Cabling Rack” in this manual.

6.4 Installing Internal Signal Cables

6.4.1 Installation Procedure

Figure 6-3 shows the procedure for installing the internal signal cables.

Huawei Technologies Proprietary

6-6
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

Power cable and protection grounding cable


installation complete

Installing straight through network cable between


LAN Switches

Installing straight through network cable between


iGWB/BAM and LAN Switch

Installing straight through cable between board in


service frame and LAN Switch

Installing FE signal cable between HSCI and SIUI

Installing serial port cable between iGWB servers

Installing data cable between iGWB server and


hard disk array

Installing Server/Switcher cable

Installing cable for monitoring power distribution


frame

Installing internal clock cable (optional)

Internal cable
installation complete

Figure 6-3 Procedure for installing internal signal cables

6.4.2 Installing Straight Through Network Cable Between LAN Switches

The two S3528G LAN Switches are interconnected through three straight through
cable, and they work in dual backup mode. The dual backup mode, which is adopted to
ensure data security, means that the two LAN Switches detect each other's heartbeat
signals.

Huawei Technologies Proprietary

6-7
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

The three straight through cables respectively connects the FE interfaces 22, 23, and
24 of the two S3528G. Table 6-2 shows the connection mapping between the two LAN
Switches.

Table 6-2 Connection mapping of straight through cables between the two LAN
Switches

0#LAN Switch 1#LAN Switch

22 22

23 23
24 24

Before delivery, the FE interfaces 22, 23, and 24 of the two S3528G have been bound
logically as three interfaces. This ensures the security and reliability. If you want to
modify the settings of the two LAN Switches, refer to U-SYS SoftX3000 SoftSwitch
System Part Replacement Guide for details.

6.4.3 Installing Straight Through Network Cable Between iGWB/BAM Server


and LAN Switch

The integrated configuration cabinet has three servers: two iGWB servers and one
BAM server. Each server uses two straight through network cables to connect with the
active and standby LAN Switches. The upper network port is connected to LAN Switch
0, and the lower network port is connected to LAN Switch 1, as shown in Figure 6-1.

Because the ports of LAN Switches are arranged on the front panels, while the ports of
the servers are arranged on the back panels of the servers, back cabling is required to
lay the network cables which connect the servers and LAN Switches.

To install a pair of cable for a LAN Switch and a server, do as follows:


1) Insert the crystal connectors at one end of the network cables into the ports of the
LAN Switches, and leave some surplus.
2) Lead the cables through the cabling frame under each LAN Switch to the back of
the cabinet.
3) Separate the cables and lay them downward along the vertical cabling troughs at
both sides.
4) Insert the crystal connectors at the other end into corresponding ports of a server,
as shown in Figure 6-4.
The cable connection positions on the front panel of the LAN Switch depend on the port
configuration scheme.

Huawei Technologies Proprietary

6-8
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

Figure 6-4 Connection position of straight through network cable on server

Note:
z The BAM and the emergency workstation connect the LAN Switch with straight
through cables. In this way, the emergency workstation can back up the data from
the BAM.
z Connect two straight through cables with the emergency workstation and leave
them disconnected from the LAN Switch when the BAM is normal. When the BAM is
faulty, immediately connect the two cables with the active and standby core LAN
Switches. Refer to Figure 8-1 in chapter 8 for the cable connection of the emergency
workstation.

6.4.4 Installing Straight Through Network Cable Between LAN Switch and
HSCI

The service frames in the SoftX3000 communicate with each other through LAN Switch
and the service boards are connected to LAN Switch through network ports.

In the integrated configuration cabinet and service processing cabinet, each of the
active and standby HSCIs in both basic frame and expansion frame has six
10/100Mbit/s network ports. The ports marked 10/100BT6 at the uppermost position of
the active and standby HSCIs are connected to the active and standby LAN Switches
respectively through straight through cables, implementing the communication
between the service processing subsystem and BAM, and the interconnection between
the service processing frames. The HSCI in slot 7 is connected to LAN Switch 1, and

Huawei Technologies Proprietary

6-9
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

the HSCI in slot 9 is connected to LAN Switch 0. The connection positions of the cables
on the front panels of LAN Switches are determined by the port configuration scheme.

Because the SoftX3000 adopts back cabling mode, but the network port of LAN Switch
is on the front panel, the network cables from LAN Switch must be led to the cabinet
back through the cabling frame under the LAN Switch. The cables must be arranged
well in the cabling frame.

The network cables between service boards in the expansion frames in service
processing cabinet and LAN Switches in the integrated configuration cabinet must be
laid outside cabinets. For detailed information about installing and laying these cables,
refer to Section 6.3.2 Modes of Laying Signal Cables.

6.4.5 Installing FE Signal Cable Between HSCI and SIUI

Straight through network cable is used as the FE signal cable to HSCI and SIUI.
Figure 6-5 shows the cable connection.

Figure 6-5 Connection position of FE cable between HSCI and SIUI

6.4.6 Installing Serial Port Cable Between iGWB Servers

It is required to connect the two iGWB servers in the integrated configuration cabinet
using serial port cable. The purposes are as follows:
z To ensure the dual backup working mode and security of the iGWB servers.
z To create a second path transmitting the heartbeat signals for iGWB dual-machine
backup.

Huawei Technologies Proprietary

6-10
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

The connection port is the RS232 serial port at the right on the back panel of the iGWB
server, as shown in Figure 6-4.

Note:
The master and slave iGWB servers are connected to the bill console or network
management device through HUB. The external network cable connecting with the
HUB also serves as the first heartbeat signal transfer path for the dual backup mode of
iGWB.

6.4.7 Installing Data Cable Between iGWB Server and Hard Disk Array

Two pieces of SCSI data cables between iGWB servers and hard disk array are
provided by the manufacturer of hard disk array. One end of the data cable connects
with the SCSI slot on an iGWB server, and the other end connects to the SCSI socket
on the upper part of hard disk array, as shown in Figure 6-6 and Figure 6-7.

Figure 6-6 Connection position of data signal cable on iGWB server

Figure 6-7 Connection position of data signal cable on hard disk array

6.4.8 Installing Server/Switcher Cable

A server/switcher cable is composed of keyboard cable, mouse cable and display cable,
and it is delivered together with a server. At the KVM/LCD switcher side, these three

Huawei Technologies Proprietary

6-11
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

cables are connected with the mouse port, keyboard port and display port, and they are
combined as one cable and connected with the OUT port on the server through a
D-shape connector. The connection relations are “BAM-PC1”,”iGWB(M)-PC2” and
“iGWB(S)-PC3”. Figure 6-8 shows the connection of the cables.

-48V

GND PGND KVM/LCD switcher PC4 PC3 PC2 PC1

BAM

iGWB(S)

iGWB(M)

Figure 6-8 Connection of server/switcher cables

The KVM/LCD switcher is used to switch the keyboard signals, mouse signals and
video signals connected with different servers.

The surplus parts of keyboard cable, mouse cable and display cable can be bound
along the binding bar in order. Be sure to separate them from power cables.

6.4.9 Installing Serial Port Cable for Monitoring Power Distribution Frame

To install serial port cable, do as follows:


1) Connect one end of the cable to the serial port socket of the monitor board behind
the power distribution frame.
2) Connect the other end to the monitor port COM3 of the SIUI.
In the integrated configuration cabinet, the serial port is connected to the SIUI board in
the basic frame. In the service processing cabinet, the serial port is connected to the
SIUI board of the second service frame from top downward.

Because MRS cabinet has no service frame, the serial port cable need to be connected
to the serial port COM3 on the SIUI board of the uppermost service frame in an
adjacent service processing cabinet.

The cable is bound and laid along the outer side of cabling trough in the right back of
the cabinet.

Huawei Technologies Proprietary

6-12
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

6.4.10 Installing Clock Cable Between Frames

I. Connecting Clock Cables

There are two types of internal clock cables: 2 MHz and 8 MHz.

Two CKII boards are connected to the active EPII board in the same frame through two
2 MHz clock cables. Figure 6-9 shows the connection of the 2 MHz clock cables.

Figure 6-9 Connection positions of 2 MHz clock cables

If more than one pair of EPII boards are configured, lead out two 2 MHz clock cables
from another active EPII, and connect them to the interfaces LINE2 of the active and
standby CKII boards.

The CKII board provides 16 channels of 8 kHz clock sources to other frames without
clock boards through 8 kHz internal clock cables. The clock sources are connected to
the EPII boards of such frames through cables, to realize the clock synchronization and
hardware changeover between active and standby clock boards. Figure 6-10 shows
the connection positions of 8 kHz clock cables.

Huawei Technologies Proprietary

6-13
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

Figure 6-10 Connection positions of 8 kHz clock cables

II. Laying Clock Cables

The 2 MHz synchronous clock cables are used connect the CKIIs and EPIIs in the
same frame, so they are laid and bound along the cabling trough of the frame.

To lay the 8 KHz clock cables, do as follows:


1) Lay the 8 KHz clock cables of the basic frame in the integrated configuration
cabinet directly into the cabling trough of the frame.
2) Separate cables to both sides of the cabinet, and lay them upward to the EPIIs in
the expansion frame of the cabinet.
3) Lay the clock cables to other cabinets downward along the cabinet.
4) Lead them out of the cabinet from the bottom, and then into the other two service
cabinets from the bottom.
5) Connect them to the EPIIs in the service frames.

Huawei Technologies Proprietary

6-14
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

6.5 Installing External Signal Cables

6.5.1 Installation Procedure

Figure 6-11 shows the procedure for installing external signal cables.

Internal signal cables installation


complete

Installing external clock cable (optional)

Installing trunk cable (optional)

Installing external network cable

External signal cables installation


complete

Figure 6-11 Flow of installing external signal cable

Note:
In normal cases, the trunk cables and external clock cables are bound together. In this
case, it is unimportant whether the trunk cables or the external clock cables are
installed first.

6.5.2 Installing Trunk Cable Between SoftX3000 and DDF

I. Connecting Trunk Cables

The EPII boards are configured in active/standby mode, but only the active EPII board
is connected to the trunk cable through its DB50 trunk socket, as shown in Figure 6-12.

To connect the trunk cables, do as follows:


1) Lead them out of the front panel of the EPII and down to the cabling trough of the
cabinet.

Huawei Technologies Proprietary

6-15
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

2) Lay them horizontally and then upward or downward along the left column of the
cabinet.
3) Lead them out of the cabinet.
4) Lay them along the external cabling rack or cabling trough.
5) Connect them to the cable distribution rack in the equipment room.

EPII

(2)
(1) (3)

(1) 50-pin socket (2) Main label (3) 8-E1 trunk cable
Figure 6-12 Connection position of trunk cable

II. Laying Trunk Cables

Before laying the trunk cables, measure the required length first. If the cables are not
long enough during the actual cabling, select other proper cables instead. In special
cases, splice cables for extension using dedicated coaxial cable connector, while
soldering is prohibited.

In the equipment room with ESD-preventive floor, it is recommended to adopt


downward cabling mode, which can ensure better appearance and easy cabling. If you
use upward cabling mode, configure a cabling rack above the cabinet to lay the cables.

If you use downward cabling mode, do as follows:


1) Bend the cables at the bottom of the cabinet and reserve some surplus. Do not
tighten the cables at the bottom of the cabinet when leading them out.
2) Lead them into the cabinet, and lay them along both sides of the cabinet.
3) Distribute them to the frames one by one. Other cabling positions or directions are
not allowed.
If you use upward cabling mode, do as follows:
1) Bend the cables at the top of the cabinet and reserve some surplus.

Huawei Technologies Proprietary

6-16
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

2) If cabling ladder is used, lay the cables by the side of the ladder instead of
between the ladder rungs. If the distance between the cabling ladder and the
cabling trough on the top of the cabinet is within 0.8 m, lay the cables directly on
the cabling trough; if the distance between the cabling ladder and the cabling
trough on the top of the cabinet is more than 0.8 m, use downward cabling ladder.
3) Fix the cables on the downward cabling ladder, and do not pull the cables too tight.

6.5.3 Installing Clock Cable Between SoftX3000 and BITS

I. Connecting Clock Cables

According to different signal types, the 75 ohm coaxial cables transmitting BITS clock
signals are connected with the corresponding SMB connectors BITS1 and BITS2 of the
CKII boards in the basic frame, as shown in Figure 6-13.

Figure 6-13 Connection of external clock cable

At the BITS device side, the connection positions are:


z “ER1” and “ER2” of “2M bit/s-IN” when the synchronous signal is 2 Mbit/s signal.
Two synchronous signals are required at the same time and used in
active/standby mode.
z “2MR1” and “2MR2” when the synchronous signal is 2 MHz signal. Two
synchronous signals are required at the same time and used in active/standby
mode.

Huawei Technologies Proprietary

6-17
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 6 Installing Signal Cables

II. Laying Clock Cables

To lay external clock cables, bind them together with trunk cables with the same cabling
method for trunk cables.

6.5.4 Installing External Network Cables

I. Introduction to External Network Cables

The external network cables are used to connect the SoftX3000 with external network
devices, and the external network ports in the SoftX3000 are provided by the
corresponding back interface boards.

The media resource server (MRS) is also connected to the SoftX3000 through external
networking devices. The active and standby media resource interface boards (MRIAs),
media processor cards (MPCs) and shelf control cards (SCCs) are connected to the
external routers or LAN Switches through the external network cables.

II. Connecting External Network Cables

The connecting positions of external network cables depend on the specific device
connected with the SoftX3000. Take the connection between the SoftX3000 and IAD
for example, the IAD is generally installed inside residential community or enterprise
network, and it connects to the SoftX3000 through router or LAN Switch. One end of
external network cable is connected to 10/100Mbit/s Ethernet ports on IFMI board in
the SoftX3000, and the other end is connected with router or LAN Switch. The specific
connection positions are determined by the port configuration scheme.

When the IAD is connected to the MRIA board of the SoftX3000 through external
networking devices, the network cable is connected to the middle network port in the
MRIA board.

III. Cabling

To lay external network cables, bind them together with trunk cables, with the same
cabling method as the trunk cables.

Huawei Technologies Proprietary

6-18
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 7 Installing Cabinet Fittings

Chapter 7 Installing Cabinet Fittings

7.1 Introduction to the Chapter

This chapter contains the following sections:


z Installing ESD-Preventive Floor Holders and Recovering Floor
z Installing Door Lintels
z Installing Cabinet Side Panels
z Installing Front and Back Doors
z Installing Protection Grounding Cable for Cabinet Doors

7.2 Installing ESD-Preventive Floor Holders and Recovering


Floor

7.2.1 Installing ESD-Preventive Floor Holders

The floor holder-slide rail assemblies are used to support ESD-preventive floor around
the cabinet. The assemblies include front floor holder, back floor holder, and side floor
holder. Front and back floor holders are fixed on the holder fixing components, and side
floor holders are fixed on the supports at both ends of a cabinet row.

To install the floor holders, do as follows:


1) Use M12 bolts, spring washers, and flat washers to fix the front and back floor
holders of each cabinet onto the holder fixing components.
2) Insert M12x30 bolts through the bolt holes of side floor folders and front and back
floor folders to fix the side floor holders onto the supports at both ends of a cabinet
row, as shown in Figure 7-1.

Huawei Technologies Proprietary

7-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 7 Installing Cabinet Fittings

(1) Cabinet (2) Slide rail (3) Support (4) Bolt M12x30
(5) Spring washer 12 (6) Flat washer 12 (7) Front floor holder
(8) Holder fixing component (9) Side floor holder
Figure 7-1 Fixing floor holders and slide rails

7.2.2 Adjusting Holder Height

To adjust the height of a floor holder, do as follows:


1) Loosen the bolts M12 in the floor holder.
2) Adjust the height of the floor holder to make its upper plane on the same height as
the lower plane of the ESD-preventive floor.
3) Secure the bolts M12.

7.2.3 Cutting and Recovering ESD-Preventive Floor

In this step, cut the ESD-preventive floor around the cabinet to match the border of the
cabinet according to actual conditions on site and then recover the floor.

7.3 Installing Door Lintels

Each cabinet has four door lintels, which are installed on the upper and lower enclosure
frames at the front and back of the cabinet.

To install door lintels, do as follows:

Huawei Technologies Proprietary

7-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 7 Installing Cabinet Fittings

1) Align the door lintels with the mount brackets on the upper and lower enclosure
frames.
2) Put the hooks of the door lintels into the slots of the mount brackets.
3) Use four M3 countersunk screws to fasten the door lintels, as shown in Figure 7-2.
Figure 7-3 shows the cabinet with door lintels.

Mount bracket trough

Buckle

Door lintel

Rack

M3 countersunk screw

Figure 7-2 Installation of door lintel

Figure 7-3 Cabinet with door lintels

Huawei Technologies Proprietary

7-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 7 Installing Cabinet Fittings

7.4 Installing Cabinet Side Panels

A cabinet row has four side panels at both ends. Each end has two side panels are
installed on the flat column of the cabinet.

To install the side panels, do as follows:


1) Loosen the clamping pole on the flat column.
2) Make the slot of a side panel onto the clamping pole downward, and buckle the
side panel into the open slot of the mount bracket.
3) Align the installation holes and secure the two M6 countersunk screws, as shown
in Figure 7-4.

Clamping bolt
Side panel
fixing slot

Countersunk screw

Figure 7-4 Installation of side panel

7.5 Installing Front and Back Doors

A front door is composed of left door panel and right door panel, the same as the back
door. Before installing the front and back doors, it is required to complete the installation
of all frames, internal components, and circuit boards, as well as the connection of
cables. The front and back doors must not be installed until all other hardware devices
are installed completely.

Figure 7-5 shows the installation of the front and back doors. The installation procedure
is as follows:

Huawei Technologies Proprietary

7-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 7 Installing Cabinet Fittings

1) Align the lower pin of a door panel with the pin hole on the lower enclosure frame
of the cabinet to install the lower border of the door panel.
2) Pull down the shuffle pin at the upside of the door, and align the hole for the pin on
the door panel with the pin hole on the upper enclosure frame.
3) Release the shuffle pin to let the shuffle pin return to the original position by the
spring.
The door panel is installed on the cabinet.

(2)

(1)

(1) Direction A: Align the lower pin of the door with the pin hole on the lower enclosure frame of
the cabinet to install the lower border of the door.
(2) Pull down the shuffle pin, align hole for the shuffle pin on the door panel with the pin hole on
the upper enclosure frame. Then release the shuffle pin, and the shuffle pin returns to the
original position, thus the door is installed on the cabinet.
Figure 7-5 Installation of front and back doors

Huawei Technologies Proprietary

7-5
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 7 Installing Cabinet Fittings

Note:
z The shuffle pins have been installed on the doors before delivery.
z After the front and back doors and side panels are installed, it is required to install
protection grounding cables at the positions of lower pins to ensure reliable
grounding for the cabinet. For the specific installation method, see Section 5.3.4 in
Chapter 5 "Installing Power Cables and Protection Grounding Cables" in this
manual.
z After the front doors are installed, stick the product brand in the concave on the
upper part of front door.

7.6 Installing Protection Grounding Cable for Cabinet Doors

After the side panels, front door, and back doors are installed, it is required to use
protection grounding cables to connect the grounding points on the door panels and the
grounding bolt on the cabinet base, as shown in Figure 7-6.

(2)
(1)
(5)

(6) (8)

(4)
(9) (3)
(7)
(10)

(1) Front or back door (2) Side panel (3)Cabinet base


(4) Grounding point of base (5) Grounding bar on side column
(6) Grounding point on side pane
(7) Grounding point on front or back door (8) Protection grounding cable for cabinet base
(9) Protection grounding cable for side panel
(10) Protection cable for front/back door
Figure 7-6 Downward cabling of protection grounding cable of cabinet

Huawei Technologies Proprietary

7-6
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 7 Installing Cabinet Fittings

There are four protection grounding cables for side panels under the cabinet, and they
are used to connect the grounding points on the side panels and the grounding points
of the cabinet base. Meanwhile, there are four protection grounding cables for front and
back doors under the cabinet, used to connect the grounding points on the front and
back doors and the grounding points on the cabinet base. The protection grounding
cables for cabinet doors are installed after the side cabinet doors are installed.

Huawei Technologies Proprietary

7-7
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 8 Installing Peripherals

Chapter 8 Installing Peripherals

8.1 Introduction to the Chapter

This chapter contains the following sections:


z Connecting to Terminal Equipment
z Connecting to Alarm Devices
z Grounding Requirements of Terminal Equipment
z Laying Cables for Terminal Equipment

8.2 Connecting to Terminal Equipment

Generally, the SoftX3000 is connected to multiple computer terminals (workstations),


which are used as operation and maintenance terminal, billing terminal and alarm
terminal respectively. Each terminal is connected to the BAM server by network cables.
Besides, the SoftX3000 can be connected to remote maintenance terminals through
Modem. Figure 8-1 shows the connection of terminal systems.

Client External LAN Switch

NI 3 LAN Switch 1 NI 3
NI 2 NI 2
NI 1 NI 1
LAN Switch 0
NI 0 NI 0
Alarm
SP 1 box
SP 2

Emergency BAM
workstation

PSTN

Modem Modem Remote


client

Figure 8-1 Schematic diagram of the terminal system connection

Huawei Technologies Proprietary

8-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 8 Installing Peripherals

When the BAM server works normally, it is not required to connect the two cables
indicated by the dotted lines in Figure 8-1 to the LAN Switches. Once BAM server fails,
use these two cables to connect the emergency workstation with the active and
standby LAN Switches, and make the emergency workstation take over the BAM
server.

Note:
The emergency workstation communicates with the alarm box through the program
convert.exe after they are connected.

The SoftX3000 also enables remote access mode through iWEB remote maintenance
terminal over Internet. Compared with the traditional Modem dial-up mode, the iWEB
mode is more efficient in remote maintenance, data encryption and ciphered
transmission, thus ensuring the security of the equipment.

8.3 Connecting to Alarm Devices

Figure 8-2 shows the composition and connection of alarm system of the SoftX3000.
The alarm box is connected to alarm clients through serial ports.

Power alarm

Environment 10 Mbit/s 10Mbit/s RS232 Alarm


alarm ALUI SMUI BAM WS
box

Collected
alarm

Figure 8-2 Composition of alarm system

The universal alarm box adopts box structure, with advanced technology, high
operability, maintainability and security. Figure 8-3 shows the appearance of the alarm
box.

Huawei Technologies Proprietary

8-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 8 Installing Peripherals

Figure 8-3 Appearance of alarm box

For detailed information about alarm box installation and cable connection, refer to
Universal Alarm Box User Manual delivered with the alarm box.

8.4 Grounding Requirements of Terminal Equipment

The terminals are generally powered by 200 VAC. The power supply system must have
a protection grounding end, and use the 3-core plug and socket.

The cable that connects the terminal equipment with the SoftX3000 can be the
following:
z RJ45 network cable
z RS232 serial port cable
z RS422 serial port cable
Connect the protection grounding cables with the same protection grounding bar of the
SoftX3000 cabinet. The cross-sectional area should be more than equal to 4 mm2.

8.5 Laying Cables for Terminal Equipment

The alarm box, Hub, Modem and other terminals (workstations) are generally installed
in the maintenance room. The modes of cabling and connecting cables for BAM and
iGWB servers and Hub are similar to those for cabling and connecting external clock
cables and trunk cables. It is required to lead network cables into the maintenance
room through cabling trough or cabling rack. The power cables of terminals, signal

Huawei Technologies Proprietary

8-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 8 Installing Peripherals

cables of monitors, and network cables of Hub must be laid in order and bound
separately. To ensure the safety of both personnel and equipment, the power system
must be reliably grounded.

Huawei Technologies Proprietary

8-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 9 Hardware Installation Check

Chapter 9 Hardware Installation Check

9.1 Introduction to the Chapter

After hardware installation, it is necessary to check the hardware installation quality


before subsequent software installation and system commissioning.

This chapter contains the following sections:


z Checking Appearance of Hardware Components
z Checking Electrical Performance

9.2 Checking Appearance of Hardware Components

The appearance check is to review the whole installation procedures. The check items
cover cabinets, cable distribution, connectors, sockets, labels and on-site environment,
which are described below.

9.2.1 Checking Cabinets

The cabinet check covers the following aspects:


z The cabinets in a row are in order, and either front or back plane of the cabinets is
smooth.
z All bolts are screwed tightly. All bolts have flat washers and spring washers, and
they are fixed in correct direction.
z Components and wires of the cabinets are complete and in good condition. All
labels are correct, clear and complete.
z There are no surplus cable ties, stubs or other sundries in the cabinets. The front
and back doors and side panels are clean without defilement or handprint.
z After all cables are laid, the small cover plates on both the top and bottom of
cabinets cover corresponding cabling holes, thus prevent animals or dust from
entry.

9.2.2 Checking Cable Distribution

I. Checking power cables and protection grounding cables

The check items include:


z The power cables and protection grounding cables from the DC power distribution
cabinet to power distribution frames in the cabinets are connected securely.

Huawei Technologies Proprietary

9-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 9 Hardware Installation Check

z The power cables and protection grounding cables from power distribution frames
to network equipment are connected securely, and the protection grounding
cables of all network equipment are connected securely.
z Grounding polarities are correct and their contacts are good.
z The power cables and protection grounding cables are not laid together with signal
cables.

II. Checking network cables and clock cables in cabinet

The check items include:


z The cable connections are correct and firm.
z The cable ties are in correct positions and are spaced properly.
z The cable ties are not overlapped and there are no sharp ends.

III. Checking trunk cables, clock cables, and network cables outside cabinet

The check items include:


z The cables are not stretched at turnings.
z The cabling route is consistent with related specifications and the cable ties are
spaced properly.
z The cabling is straight and smooth, there is no cable crossover in the cabinet, and
cables outside the cabinet are bundled according to different cabinets they are
connected to.
z The cables in cabling troughs and cabling ladders are orderly arranged and all the
cables are bundled without damage in the coating.
z Redundant cables are left for future use and the cable ties have no sharp ends or
overlaps.

9.2.3 Checking Connectors and Sockets

I. Checking connectors

The latches of cable connectors are tightly locked, and the coaxial cable connectors
are fastened tightly.

II. Checking sockets

The sockets include trunk cable sockets, network cable sockets and HEADER sockets
for all backplanes. There is no lack of pins or short circuit resulting from bent pins.

Huawei Technologies Proprietary

9-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 9 Hardware Installation Check

9.2.4 Checking Labels and Equipment Room Environment

I. Checking cable labels

All labels are clean, tidy and in correct positions, and the marks are clear.

II. Checking environment of equipment room

There are no such sundries as cable ties, stubs and dryer bags left below the cabling
trough, cabinets and movable floor around the cabinet.

There are no useless objects in the equipment room and all the necessities are neatly
arranged in the room.

The workbench and movable floor are clean and tidy.

Perform electrical check after completing appearance check.

9.3 Checking Electrical Performance

9.3.1 Introduction to Electrical Performance Check

The electrical performance check must be performed strictly following the checking
steps determined by the power supply relations. That is, first check the power supply to
the cabinet, then check the power supplies to the frames, and finally check the power
supplies to boards.

9.3.2 Introduction to Power Switches in Power Distribution Frame

Figure 9-1 shows the appearance of the front panel of the power distribution frame.

Huawei Technologies Proprietary

9-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 9 Hardware Installation Check

(1) Running indicator (2) Alarm indicator (3) Alarm sound switch
(4) – (6) –48V1 output switches (7) – (9) –48V2 output switches
(10) Lightning protection unit panel
Figure 9-1 Front panel of power distribution frame

There are two indicators on the front panel of the power distribution frame, and their
meanings are shown in Table 9-1.

Table 9-1 Meanings of indicators

Indicator Identifier Color Status Meaning


Flashin
g
There is power in, and the power
frequen
distribution frame works normally
cy: 0.5
Hz
The communication between the
Running Flashin
RUN Green power distribution frame and the
indicator g
SMUI is abnormal. The power
frequen
distribution frame does not work
cy: 4 Hz
normally.
There is no power in, or the power
Always
distribution frame comes across
off
fault.

Always
on or There is fault occurring to the
Alarm fast power distribution frame.
ALM Red flashing
indicator
Always
There is no fault.
off

The alarm sound switch on the front panel is used to select whether to listen to the
alarm sound for the power distribution frame. If the switch is “ON”, there will be alarm

Huawei Technologies Proprietary

9-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 9 Hardware Installation Check

sound in case of fault in the power distribution frame. If the switch is “OFF”, there will be
no alarm sound even when there is fault occurring to the power distribution frame.

Note:
To make a full check on the monitoring function of the power distribution frame, set the
MONITOR ALARM to “ON” when performing electrical check to the equipment.

9.3.3 Introduction to Power Switches in MRS

There are two power switches on the MRS chassis, located at the upper right of the
front panel and marked Feed A and Feed B. They respectively correspond to –48 VDC
input A and input B.

There is no independent power switch on other service frame, whose input power
supply is controlled by the corresponding switch in the power distribution frame.

9.3.4 Checking Power Supply of Cabinets

The check on power supply for cabinets is to see whether there is short circuit in all
output power lines from the DC power distribution frame, whether the input DC voltage
to the SoftX3000 cabinets is normal and whether the visual and audible alarm function
of the frames in all cabinets is normal. The check steps are described as follows:
1) Shut down the input power supply of the DC power distribution frame, set the
multimeter to ohm range and check the resistance between the output power
supplies and between working grounding line (GND) and protection grounding line
(PGND) of the DC power distribution frame. There is no short circuit between the
output power supplies.
2) Confirm that all the switches in the power distribution frame on the cabinet top are
turned off, and then turn on the switch of the DC power distribution cabinet. In the
case of no load, use the multimeter to check whether the output power supply is
within the allowed voltage range (–57V to –40V). At this time, red “ALM” indicator
on the distribution box must flash and the buzzer will give off audible alarm upon
setting the ALARM switch to “ON”.
If any of the above items does not meet the requirement, find out the reason and
perform troubleshooting before the next step.

Huawei Technologies Proprietary

9-5
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Chapter 9 Hardware Installation Check

9.3.5 Checking Power Supply of Frames

The check on power supply for frames is to set whether there is short circuit in all output
power lines from the power distribution frame of the cabinet, and whether the input DC
voltage to the intra-cabinet components is normal. The check steps are as follows:
1) Pull out all boards from the backplanes in the cabinet, and set all the switches of
the distribution box on the cabinet top to position “ON”. At this time, there is no
power alarm or audible alarm. The green “RUN” indicator flashes and the red
“ALM” indicator does not light.
2) Check –48 VDC power supply, and the voltage, There is –48 VDC power supply to
all the components, service frames and other devices, and their voltage is within
the correct range (–57 V to –40 V).
If any of the above items does not meet the requirement, find out the reason and
perform troubleshooting before the next step.

9.3.6 Performing Board Power-On Test

The working status of a board powered on can be known from the indicators on the
board front panel. For the meanings of indicators, refer to U-SYS SoftX3000 SoftSwitch
System Technical Manual Architecture and Principle.

The check steps are as follows:


1) Input and output cables of –48 VDC power supply are correctly connected and the
connection cables are firm.
2) Set all the switches on power distribution frame to “OFF”. Insert the power boards
in the frames, and then turn on the switches on the power distribution frame. The
power boards and the fans in frames work normally.
3) Set all the switches on the power distribution frame to “OFF” once again, then
insert the boards into the slots on the backplanes and fasten the front panels of the
boards.
4) Set the power switches on the power distribution frame to “ON”. At this time, all
board indicators are normal. If the indicators of all boards in a frame do not light
after the power switches are turned on, it indicates that there is no –48 VDC input
or there is connection error at the input terminals. If the power switch jumps upon
being closed, it means there would be short circuit or error of connection of the
output terminals (short circuit).

Huawei Technologies Proprietary

9-6
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

Appendjx A Installing Cabling Rack

A.1 Introduction to the Appendix

This appendix contains the following sections:


z Introduction to Cabling Rack
z Installing Cabling Rack

A.2 Introduction to Cabling Rack

A.2.1 Functions of Cabling Rack

When upward cabling mode is used, it is required to install cabling rack in equipment
room to lay cables, to reinforce cabinet connections and to enhance shockproof
performance.

A.2.2 Components of Cabling Rack

Figure A-1 shows the channel-section steel.

Figure A-1 Channel-section steel

Figure A-2 shows the channel-section connecting piece.

Huawei Technologies Proprietary

A-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

Figure A-2 Channel-section connecting piece

Figure A-3 shows the cross stay 200 mm long.

Figure A-3 Cross stay (200 mm)

Figure A-4 shows the cross stay 400 mm long.

Figure A-4 Cross stay (400 mm)

Figure A-5 shows the cross stay 600 mm long.

Figure A-5 Cross stay (600 mm)

Figure A-6 shows the angel connecting piece.

Huawei Technologies Proprietary

A-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

Figure A-6 Angle connecting piece

Figure A-7 shows the cable-trough clip.

Figure A-7 Cable-through clip

Figure A-8 shows the triangular support for 200 mm-wide cabling ladder.

Figure A-8 Triangular support (for 200 mm-wide cabling ladder)

Figure A-9 shows the triangular support for 400 mm-wide cabling ladder.

Huawei Technologies Proprietary

A-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

Figure A-9 Triangular support (for 400 mm-wide cabling ladder)

Figure A-10 shows the triangular support for 600 mm-wide cabling ladder.

Figure A-10 Triangular support (for 600 mm-wide cabling ladder)

Figure A-11 shows the connecting clip for cabling trough.

Figure A-11 Connecting clip for cabling trough

Figure A-12 shows the fixing clip for cabling trough.

Huawei Technologies Proprietary

A-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

Figure A-12 Fixing clip for cabling trough

Figure A-13 shows the cabling trough 200 mm long.

Figure A-13 Cabling trough (200 mm)

Figure A-14 shows the cabling trough 400 mm long.

Figure A-14 Cabling trough (400 mm)

Figure A-15 shows the insulating washer.

Figure A-15 Insulating washer

Huawei Technologies Proprietary

A-5
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

Figure A-16 shows the insulating plate.

Figure A-16 Insulating plate

Figure A-17 shows the end cover.

Figure A-17 End cover

Figure A-18 shows bolt B (M8 x 20).

Figure A-18 Bolt B (M8 x 20)

Figure A-19 shows the movable cable bushing.

Figure A-19 Movable cable bushing

Huawei Technologies Proprietary

A-6
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

A.2.3 Installation Modes

The cabling rack can be installed in four different modes:


z Install a suspender on the ceiling to hang the cabling rack (hereinafter referred to
as the “suspension mounting mode”).
z Install a bracket on the ground to support the cabling rack (hereinafter, referred to
as the “ground supporting mode”).
z When the cabling rack is placed against the wall, install a triangular support on the
wall to support the cabling rack.
z When the cabling rack passes over the cabinet, install a shockproof support or a
ladder on the cabinet to support the cabling rack.

A.2.4 Cabling Rack Specifications

Cabling rack is made of cabling ladder, and cabling trough which is optional
component.

The cabling ladder and the cabling trough have the following specifications:
z 200mm-wide cabling ladder matches the 200mm-wide cabling trough;
z 400mm-wide cabling ladder matches the 400mm-wide cabling trough;
z 600mm-wide cabling ladder matches the 200mm +400mm-wide cabling trough.
It is recommended to use 400mm-wide cabling ladder over the cabinet, and not to use
cabling trough, to facilitate cabling and to improve the heat dissipation of the system.

A.3 Installing Cabling Rack

A.3.1 Installation Procedure

Caution:

The cabling rack must be insulated from the floor, ceiling and walls.

Figure A-20 shows the procedure of installing cabling rack.

Huawei Technologies Proprietary

A-7
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

Start

Mart drilling position

Assemble cabling
ladder

Check drilling position

Drill the hole Φ8


for 60mm

Secure the cabling


ladder (on ground,
rooftop, or wall)

Install cabling N
trough

Y
Install and secure
cabling trough

Install accessories
including cable-
through rack, cable
baffle ring, end cover,
and protective cable
sheathing

End

Figure A-20 Procedure of installing cabling rack

A.3.2 Assembling Cabling Ladder

The cabling ladder uses channel-section steel and cross stays for form its
framework. .The channel-section steel functions as the vertical beams of the cabling
ladder and the cross stays function as the horizontal beams. To assemble a cabling
ladder, use fastener to connect the cross stays with the channel-section steel. The
spacing between two cross stays is 250 mm. Because the spacing between holes in the
channel-section steel is 50 mm, install one cross stay every five trough holes. When the
assembled cabling ladder is used for horizontal installation, the bolt head of the cabling
ladder should face downward to ensure that there is no protrusion on the ladder surface

Huawei Technologies Proprietary

A-8
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

and to facilitate the installation of cabling trough. Figure A-21 shows the basic structure
of cabling ladder.

(1) Fastener (2) Cross stay (3) Channel-section steel


Figure A-21 Basic structure of a cabling ladder

If a longer cabling ladder is required, you can join several cabling ladders in an “end to
end” fashion. The channel-section connecting piece is used to connect ladders, as
shown in Figure A-22. If the length of a cabling ladder is not an integral multiple of 2.5 m,
cut off the remaining part. Use brush the paint the cross section to ensure protection
against corrosion and to provide aesthetic look for the ladder.

(1) Channel-section steel (2) Channel-section connecting piece


Figure A-22 Connections between two cabling ladders

A.3.3 Connecting and Installing Cabling Troughs

Because cabling trough is cone-shaped, you can insert the smaller end of a cabling
trough to the bigger end of another. The depth of inserted part is 250 mm. When

Huawei Technologies Proprietary

A-9
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

200mm-wide or 400mm-wide cabling trough is used, directly place the cabling trough
on cabling ladder, and secure the cabling trough on the cabling ladder with fixing clips.
For each segment of the cabling trough, four such clips are used and they should be
symmetrical at both sides. Figure A-23 shows the connection of cabling troughs.

(1) Cabling trough (2) Fixing clip of the cabling trough


(3) Cabling ladder (4) Baffle ring
Figure A-23 Connection of cabling troughs (200mm or 400mm wide)

If a cabling trough is installed on 600mm-wide cabling ladder, it can be formed by


means of joining a 200mm-wide trough and a 400mm-wide trough together with
connecting clips. For each segment of cabling trough, three connecting clips are
required. To install a cabling trough, secure it on cabling ladder with fixing clips. If a
longer cabling trough is required, the connecting method is same as that mentioned
earlier. Here, follow the principle “extended first and fixed next”. Figure A-24 shows the
structure of 600mm-wide trough.

(1) Cabling ladder (600 mm wide)


(2) Cabling trough (200 mm wide)
(3) Connecting clip for cabling trough
(4) Fixing clip for cabling trough
(5) Cabling trough (400 mm wide)
Figure A-24 Structure of 600mm-wide cabling trough

Huawei Technologies Proprietary

A-10
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

A.3.4 Installing Turning Cabling Rack

I. Connecting cabling racks on a horizontal surface

When a cabling rack has to turn perpendicularly on a horizontal surface, there are two
different installation ways with regard to whether the cabling trough is adopted or not.
z Cabling trough is not adopted
If the crossed cabling racks consist of only cabling ladders, use angle connecting
pieces and fasteners to joint the two cabling ladders. Make sure that the two cabling
ladders are on the same horizontal surface as shown in Figure A-25.

(1) Angle connecting piece


Figure A-25 Cabling ladders turning on a horizontal surface

z Cabling trough is adopted


When either or both of the crossed cabling racks have cabling troughs, there must be a
height difference between the two cabling racks, that is, the height of the cabling ladder
of one cabling rack must be the same as the height of the cabling trough of another
cabling rack, to ensure that the cables shall not encounter any trouble while turning on
the cabling rack. The installation is shown in Figure A-26. In the installation, angle
connecting pieces and fasteners are also used, whereas the installation method of the
angle connecting pieces is different from that in as shown in Figure A-25.

(1) Angle connecting piece


Figure A-26 Cabling rack with cabling trough turning on a horizontal surface

Huawei Technologies Proprietary

A-11
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

II. Connecting cabling racks not in horizontal surface

When you want to connect cabling ladders not in a horizontal surface, use a segment of
cabling ladder to make a climbing ladder. Use angle connecting pieces and fasteners to
connect the cabling ladder and climbing ladder. Figure A-27 shows the vertical
connection of cabling ladders, in which the left figure shows front view of the connection,
and the right figure shows the side view of the connection. Pay attention to the
installation of the angle connecting pieces shown in the figure. Figure A-28 shows the
sloping connection of cabling ladders.

(1) Cable bushings (2) End cover (3) Cabling trough


(4) Cabling ladder (5) Angle connecting piece (6) Angle connecting piece
Figure A-27 Vertical connection of cabling ladders

(1) Angle connecting piece (2) Angle connecting piece


Figure A-28 Sloping connection of cabling ladders

III. Connecting cabling ladder onto wall

When the cabling rack has to be connected to the wall, use the installation method as
shown in Figure A-29. The connecting components include angle connecting piece,

Huawei Technologies Proprietary

A-12
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

insulating plate, insulating washer, fastener and expansion bolt. Insulating plate and
insulating washer are used to ensure insulation between the cabling rack and the wall.
Meanwhile, big flat washer (φ8 of GB96-85) is used to replace the washer for the
expansion bolt to increase the contact area between the washer and the insulating
washer

(1) Insulating washer (2) Insulating plate (3) Big flat washer
(4) Spring washer (5) Nut (6) Channel-section steel
(7) Angle connecting piece (8) Expansion bolt
Figure A-29 Connecting the cabling rack into the wall

A.3.5 Installing Cabling Rack in Suspension Mounting Mode or Ground


Supporting Mode

You can use suspension mounting mode or ground supporting mode when cabling rack
is not placed against the wall. The suspension mounting mode is similar to the ground
supporting mode, except that in the former installation mode, the cabling rack is
connected to the ceiling, while in the latter the cabling rack is connected to the ground.
The connecting components include channel-section steels, angle connecting pieces,
fasteners and expansion bolts. To install a cabling rack in suspension mounting mode
or ground supporting mode, use two pieces of channel-section steels to connect the
cabling ladder to the ceiling or the ground. The installation method is the same as that
of connecting cabling rack to the wall.

Each piece of channel-section steel is 2.5 m long. You can cut proper length according
to the heights of the cabling rack and of the equipment room. If the required length is

Huawei Technologies Proprietary

A-13
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

longer than 2.5 m, connect two pieces of channel-section steel by channel-section


connecting piece with the same method as connecting cabling ladders. Meanwhile,
paint the cut cross sections.

Because the spacing between the holes in the channel-section steel is 50 mm, the
spacing between the suspenders or between the supporting levers must be an integral
multiple of 50 mm. Otherwise, it is impossible to proceed with the installation. It is
recommended that each segment of the cabling ladder is hung or supported by two
sets of suspenders or supporting levers, and the spacing between two suspenders or
between two supporting levers is 1250 mm .

When the suspension mounting mode or ground supporting mode is adopted, the
suspenders or the supporting levers have to be installed at the outer side of the cabling
ladder to facilitate the placement of cabling trough. Meanwhile, insulating plate and
insulating washer must be used to ensure the insulation between the suspension
components and the ceiling, or between the ground supporting components and the
ground, as shown in Figure A-30.

(1) Angle connecting piece (2) Channel-section steel (3) Washer 8 (GB96-85)
(4) Insulating washer (5) Insulating plate (6) Expansion bolt
Figure A-30 Suspension mounting mode or ground supporting mode

Huawei Technologies Proprietary

A-14
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

A.3.6 Installing Triangular Support

Note:
The spacing between two triangular supports must be an integral multiple of 50 mm;
otherwise, cabling ladders cannot be connected and fixed to triangular supports. A
spacing of 1250 mm is recommended between two triangular supports, that is, each
segment of cable ladder is supported by two triangular supports.

When cabling rack is placed against the wall, a triangular support is used to support the
cabling rack. The triangular support adopts a welded structure, and it is fixed onto the
wall by expansion bolts. It provides holes in its horizontal beam for installing cabling
ladder. The triangular support has three specifications corresponding to the
200mm-wide, 400mm-wide, and 600mm-wide cabling ladders respectively. A larger
triangular support can be used to support smaller cabling ladder, but it is not
recommended here. The sizes of their installation holes in the wall are the same.

To install a triangular support, use expansion bolts to fix the support onto the wall. Use
big flat washers (φ8 of GB96-85) to replace the flat washers of the expansion bolts.
Meanwhile, install two insulating plates between the vertical beam of the triangular
support and the wall, and install an insulating washer between the nut and the vertical
beam.

To install cabling ladder onto the triangular support, place it directly on the horizontal
beam of the triangular support. Align the holes on the lower side of the channel-section
steel with the holes in the horizontal beam of the triangular support, and then fix them
with fasteners, as shown in Figure A-31.

Huawei Technologies Proprietary

A-15
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

(1) Cabling ladder (2) Insulating plate (3) Expansion bolt


(4) Vertical beam of triangular support (5) Triangular support
(6) Horizontal beam of triangular support
Figure A-31 Installation of triangular support

A.3.7 Installing Cabling Rack over Cabinet

I. Introduction to installation ways

Cabling rack can be installed over the cabinet in the following two ways (Generally,
cable distribution trough is not configured on the top of cabinet for the purpose of
improving system heat dissipation).
z If shockproof support is installed on the cabinet, connect the cabling rack with the
quake-proof support.
z If no shockproof support is installed on the cabinet, connect the cabling rack with
the cabinet by climbing ladder.

II. Connecting cabling rack with shockproof support

Shockproof support on the top of cabinet is welded with channel steel, and it can meet
the strength requirements. It can be fixed to the two bolt holes on top of cabinet. There
are bolt holes on the top plate of the shockproof support, used for fixing and bearing the
cabling rack (cabling ladder). Figure A-32 and Figure A-33 show the connection
method.

Huawei Technologies Proprietary

A-16
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

(1) Cabinet (2) Shockproof support (3) Flat washer 8


(4) Spring washer (5) Blot M8x20
Figure A-32 Connection of cabinet and shockproof support

(1) Cabinet (2) Shockproof support (3) Cabling rack


(4) Flange bolt M8x20 (5) Flange nut M8
Figure A-33 Connection of cabling rack and shockproof support

Huawei Technologies Proprietary

A-17
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

III. Connecting cabling rack with climbing ladder

If there is no support installed on the top of cabinet, use climbing ladder based on the
size of the connecting holes provided on the top of cabinet. For specific connecting
method for climbing ladder, refer to the right figure in Figure A-27 or Figure A-28.

A.3.8 Installing Accessories

I. Installing cable-through clip

Cable-through clip can be divided into two types according to whether cabling rack has
cabling trough or not. Figure A-34 illustrates the case when cabling trough is not
configured on cabling rack, in which, upward cable-through clip is used. When cabling
trough is configured on cabling rack, downward cable-through clip is used to ensure
that the upper plane of cable-through clip stays on the same level with the uppermost
plane of cabling rack, and to facilitate cabling. Generally, cable-through clip is installed
on the cabling ladder on the top of cabinet, and the required quantity and location
depend on actual conditions of the installation site.

(1) Cable-through clip (2) Upper hole of cable-through clip


(3) Lower hole of cable-through clip
Figure A-34 Installation of cable-through clip when cabling trough is not configured on
cabling rack

II. Installing baffle rings

Baffle rings are directly snapped at both sides of a cabling trough. Configuring baffle
rings can increase the height of a cabling trough to prevent cables from going beyond
the cabling trough. Each segment of cabling trough uses four such rings and they are
distributed evenly at both sides, as shown in Figure A-23.

Huawei Technologies Proprietary

A-18
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendjx A Installing Cabling Rack

III. Installing end covers

End covers are installed at the ends of a cabling ladder. Wherever possible, end covers
must be installed to provide better appearance and prevents unintended damage to
cables.

IV. Intalling cable bushings

Cable bushings are installed at the bottom edge of a cabling trough, used to prevent
cables from any possible damage. Any uncovered bottom edge of cabling troughs must
be installed with cable bushing. Left part in Figure A-27 shows the installation of end
cover and cable bushing.

Huawei Technologies Proprietary

A-19
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Appendix B Engineering Labels for Cables

B.1 Introduction to the Appendix

This appendix contains the following sections:


z Introduction to Labels
z Engineering Labels for External Cables of Alarm Box
z Engineering Labels for Ethernet Cables
z Engineering Labels for Optical Fibers
z Engineering Labels for Trunk Cables
z Engineering Labels for Subscriber Cables
z Engineering Labels for Power Cables

B.2 Introduction to Labels

B.2.1 Functions of Engineering Labels

Engineering labels are affixed to both ends of various cables to identify the physical
positions of cables on different devices. Labels facilitate correct and orderly
connection of cables, and easy maintenance after the installation.

Note:
If there is special requirement from the customer for the description method of the
labels, the labels shall be printed accordingly. However, this must be stated in the
self-check report.

B.2.2 Label Material Specifications

The label material is polyester (PET) with UL and CSA certifications. The material
specifications are shown as follows:

Applicable ambient
Color Thickness Printing method
temperature
Chalk white 0.09 mm -29 °C – 149 °C Laser

Huawei Technologies Proprietary

B-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

B.2.3 Type and Shape of Labels

I. Introduction to label types

There are two types of engineering labels, specialized for signal cables and power
cables respectively. Power cables include AC power cables and DC power cables
(excluding the power cable that connects the distribution cabinet and the cabinet).
Signal cables include external cables of alarm box, Ethernet cables, optical fibers,
trunk cables and subscriber cables (excluding the antenna feeders).

II. Labels for signal cables

The label for signal cables is L-shaped with fixed dimensions, as shown in Figure B-1
(expressed in mm).

84.0
7.5
7.0
5.5

5.5

11.0 10.0

11.0 TO:
(2)
1.5
(2)
(1)
0.6
5.5
5.5 1.0
(1)
7.0
7.5
37.0
2.0

(1) Dividing line (2) Cut dotted line


Figure B-1 Label for signal cables

The dividing lines on the label help to specify more clearly the position of a cable. For
example, there is one between the cabinet number and the frame number and
another one between the frame number and the slot number. The dividing line is
1.5 mm ×0.6 mm in size with the color of PONTONE 656c (light blue).

The cut dotted line helps to fold the label when affixing it to the cable, and its size is
1.0 mm ×2.0 mm.

There is a mark “TO:” (upside down in the figure) at the lower right corner of the label.
The mark is used to identify the opposite end of the cable on which the label is affixed.

Huawei Technologies Proprietary

B-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

III. Labels for power cables

The labels for power cables must be attached to the identification plate on the cable
ties that are bundled to the cable. The identification plate has an embossment of
0.2 mm ×0.6 mm around (symmetric on both sides), and the area in the middle is for
affixing the label, as shown in Figure B-2 (expressed in mm):

10
26.2 R1.0
TO:
12.2 11

(2) 25
0.6

(1) 1.5

100
0.6
(3)

(1) Cable tie (2) Label (3) Dividing line on the label
Figure B-2 Label for power cables

B.2.4 Printing Labels

I. Introduction to label printing

The contents can be printed or written on the labels. Printing is recommended for the
sake of high efficiency and eye-pleasant layout.

II. Template for printing

The Word-format template is available for label printout. You can download the
template from http://tech-support.huawei.com/asp/comm/index.asp (path:
//support/technical document/project management/installation and
maintenance/document/others), or get the template from Huawei local office.

When using the template, you can directly modify the contents on the template, and
the following must be observed:
z The settings of centered characters, direction, and fonts must not be changed.
z When there are too many characters to be filled in, zoom out the characters, but
make sure the printouts are clear and legible.

Huawei Technologies Proprietary

B-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

III. Cells merging on the template

To merge the cells, you need first recover the table structure (if gridlines are displayed,
you can start from Step 3 directly).
1) Select the menu item [Edit/Select All].
2) Select the menu item [Format/Borders and Shading/Borders]. Select Box and
click <OK>.
3) Drag the mouse to select the cells to be merged and select the menu item
[Table/Merge Cells].
If two merged cells are still not enough to accommodate the characters, use multiple
lines.

IV. Requirements for the printer

To print the labels, laser jet printer must be used, although there is no restriction on
the model of the printer. Before printing the label, set up the page and try the printing
on ordinary blank paper (both sides are blank):
1) Cover the blank paper onto the whole page of label paper, and check whether the
page setup conforms to the requirement.
2) Make sure the printer properties, such as "paper size" and “direction”, have been
set correctly.
3) If the warning prompt as shown in Figure B-3 appears before printing, click
<Ignore> to continue the printing.

Figure B-3 Warning prompt before printing

If the printout confoms to the requiremnt, print it to label paper. If the printout does not
conform, adjust the page setup and try the printing again, until the correct printout is
produced. The method of adjusting the page setup is as follows:
1) Select the menu item [File/Page Setup].
2) Select the Margins tab page.
3) Select Left for Gutter Position.
4) Set Header and Footer as 0, and adjust the values of Top, Bottom, Left, and
Right.
After the page setup has been made correct, save it for future use. This page setup is
only necessary in the first time you use the template to print the labels.

Huawei Technologies Proprietary

B-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

V. Requirements for feeding the printer

Different from the ordinary paper, the label paper is composed of two pages. No
matter what model of printer you are using, feed in the labels one after another by
hand. Never use the auto-feed mode in order to avoid jamming the labels. Different
models of printers may have different feeding modes, make sure to feed in the labels
correctly.

VI. Requirements for printed labels

Make sure the printed labels satisfy the following requirements:


z All the printouts must be on the label, and nothing must be printed on the bottom
page of the label.
z Contents in the cells must be aligned in the center. In a single-line printout, the
dividing lines and the mark “TO” must not be covered by the printed characters.
z When the cells are merged and the printouts are made in multiple lines, avoid
covering the mark “TO” when printing the texts by using the space bar to move
the printing contents to the next line.

B.2.5 Writing Labels

Use the black oiliness markers delivered together with the device to write the labels.

In special cases, black ball-pens are allowed, although not recommended. When
writing with the ball-pen, take care not to leave the oil on the label, which may
contaminate the label and blur the words..

Note:
The delivered marker has two nibs. Make sure to use the smaller nib to write on the
labels.

For the sake of easy recognition and good looking, the font in handwriting must be
close to the standard typeface as much as possible. Table B-1 shows the standard
typeface.

Huawei Technologies Proprietary

B-5
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Table B-1 Standard typeface for handwriting

0 1 2 3 4 5 6 7 8

9 A B C D E F G H
I J K L M N O P Q
R S T U V W X Y Z

Write the characters in proper size, and the direction is as shown in Figure B-4:

TO:

Figure B-4 Writing direction of the label

B.2.6 Affixing Labels

I. Affixing label to signal cable

After printing or writing the label, remove the label from the bottom page and affix it to
the signal cable, or the identification plate of the power cable.

The steps to affix a label to a signal cable are shown in Figure B-5, Figure B-6 and
Figure B-7. The finished labels must be on the right or top of the cables, according to
different cabling methods. The left part of the figures shows the method to affix the
label when the cable is laid vertically, while the right part of the figures shows the
method to affix the label when the cable is laid horizontally.

The label is affixed 2 cm from the connector on the signal cable. In special cases, for
example, to avoid cable bent or affecting other cables, other positions are allowed to
affix the labels.

The steps to affix a label to a signal cable are as follows:


1) Stick the label to the proper position on the cable, fold the narrow part of the label
according to the directions shown in Figure B-5.

Huawei Technologies Proprietary

B-6
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Cable

Stick side Fold down

Fold to right Cable

Stick side

Figure B-5 Sticking the label onto proper position of the signal cable

The lengh of the narrow part is based on an external cable diameter of 2.6mm, after
this part has been stuck to the back of the label, it may not overlap the entire printed
part.
2) Fold the printed part along the dotted line according to the directions shown in
Figure B-6.

Cable Cable

Stick side

Stick side

Fold up

Fold to right

Figure B-6 Folding up the label

3) After the printed part of the label has been folded up, the narrow part of the label
must be covered completely, as shown in Figure B-7.

Huawei Technologies Proprietary

B-7
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Cable

Cable

TO:
A03 33 33 33 33

TO:
A03 33 33 33 33
Figure B-7 Appearance of affixed labels on signal cables

II. Affixing label to power cable

Remove the label from the bottom page, then affix it to the identification plate on the
cable tie. The label must be stuck to the rectangular flute, and must be stuck to only
one side of the identification plate. Make sure to affix the labels on the same side of
the identification plates. The cable ties are bundled at 2cm from the connectors, and
other positions are allowed in special circumstances.

Cable ties must be bundled on both ends of a cable. After the bundling, the finished
identification plate must be on top of the cable in horizontal cabling, or on the right
side of the cable in vertical cabling. Make sure the label is facing out, as shown in
Figure B-8.

Cable
TO:
B03

TO:
B03 -48V2
-48V2

Cable

Figure B-8 Appearance of affixed labels on power cables

Huawei Technologies Proprietary

B-8
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

B.2.7 Information Carried on Labels

I. Information for power cables

Labels for power cables are only affixed on one side of the identification plates. On the
labels, there is information (the part after the mark “TO:”) about the location of the
device on the other end of the cable, like the location of control cabinet, distribution
cabinet or power socket.

II. Information for signal cables

The two sides of the label affixed on the signal cable carry information about the
location of the ports connected to both ends of the cable, as shown in Figure B-9.

The information is given like this:


z Area 1 contains the location information of local end of the cable.
z Area 2 (with the mark "TO:") contains the location information of the opposite end
of the cable.
z Area 3 has been folded up inside the label.

Area 1 Area 3

Area 2 TO:

Figure B-9 Printed parts on the label for signal cables

Seen from the cabling end of the equipment, the text part of the label is on the right
side of the cable. The side with “TO:” that is facing outside carries the location
information of the opposite end; and the other side carries the location information of
the local end. Therefore, the information in Area 1 at one end is the same as the
information in Area 2 at the other end of the cable, and vice versa. In other words, the
local information at one end is called the opposite information at the other end.

B.2.8 Remarks

The following remarks are made for attentions.


z When printing/writing and affixing labels, pay attention to keep the labels clean.
z Because the label paper is made of moistureproof and waterproof material,
ink-jet printers and ink pens are forbidden for printing and writing labels.
z Labels must be affixed with good order in alignment.

Huawei Technologies Proprietary

B-9
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

z Cable ties must be bundled in the same position of power cables, with
identification plates on the same side.
z The positions of “up”, “down”, “right” or “left” are all based on the viewpoint of the
engineering person who is working on the label.

B.3 Engineering Labels for External Cables of Alarm Box

The external cables of alarm box are connected with the first subscriber cabinet of
each row (used for power distribution). Labels pasted on the first cabinet of each row
indicate which equipment is using the access terminal. Labels are not needed on the
equipment side unless there is special requirement. In this case, only Area 2 of the
label is filled in.

Table B-2 shows the information on the labels of alarm box external cables.

Table B-2 Information on labels affixed to the external cables of alarm box

Content Meaning Example


M: The cabinet rows from front to back are
MN: serial numbered from A to Z.
number of the
N: The cabinet columns from left to right are
MN cabinet in the
numbered from 01 to 99.
equipment
room For example, A01 indicates a cabinet at Row A,
Column 01.

Note:
Generally, the above numbering method is enough to identify the position of a specific
cabinet. If cabinets are installed in a back-to-back manner, the facing direction of the
cabinet must be specified, the numbering method like MNO is used. Here, “O” means
the direction of the cabinet, which can be “A” or “B”. On the cable labels described
below, this numbering method is used, unless otherwise stated.

The label on the alarm cable carries simple information, and only part of the text area
needs to be filled in. It is recommended to keep the whole length of the label instead of
cutting out the blank area.

Figure B-10 shows a label on the alarm cable, on which “A01” indicates that the alarm
cable is connected from the first cabinet to the cabinet at Row A, Column 01 in the
equipment room.

Huawei Technologies Proprietary

B-10
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Figure B-10 Example of the label on the alarm cable

B.4 Engineering Labels for Ethernet Cables

B.4.1 Introduction to the Labels

These labels are affixed to the Ethernet cables that connect the boards in the frames,
or on the cables that connect HUBs and servers or agents of the value-added service
(VAS) products.

B.4.2 Label Information Meanings

I. Introduction to information on labels

Table B-3 shows the information on both sides of the labels affixed to the Ethernet
cables that connect the boards in the frames.

Table B-3 Information on labels affixed to the Ethernet cables

Content Meaning Example


MN: Cabinet
For example, A01
number

B: Frame Numbered in top-down order with two digits, for


number example, 01
MN-B-C-D
C: Physical slot Numbered in top-down and left-right order with
number two digits, for example, 01

D: Ethernet port Numbered in top-down and left-right order with


number two digits, for example, 01

Huawei Technologies Proprietary

B-11
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Content Meaning Example


MN: Cabinet
For example, B02
number

Valid location number of the terminal device


onsite. If the cable is connected to a router in a
MN-Z cabinet, the serial numbers of the cabinet, the
Z: Location frame and the Ethernet interface of the router must
number be specified, for example, B02-03-12. If the cable
is connected to the Network Management Station
(NMS), specific location of the NMS must be
given.

In VAS products, the information provided on the labels is different, subject to different
devices that the Ethernet cables are connecting.

II. Labels for Ethernet cable that connects HUB and server

The information provided on the labels includes:


z The label at the HUB end indicates the number of the frame and cabinet where
the HUB locates, and the serial number on the HUB.
z The label at the server end indicates the number of the frame and cabinet where
the server locates. In case it is a stand-alone server, specific position of the
server should be provided.

III. Labels for Ethernet cable that connects HUB and agent

The information provided on the labels includes:


z The label at the agent end contains the serial number of the Ethernet port. The
definitions of the cabinet number and frame number are the same as those
described in Table B-3 above.
z If it is a stand-alone HUB without any cabinet or frame, the label contains specific
location information that identifies the HUB.
z The label contains the serial number of the HUB, the network port number of the
agent and the location of the stand-alone server according to actual connection.

B.4.3 Label Example

Figure B-11 shows the label on the Etherent cable:

Huawei Technologies Proprietary

B-12
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Figure B-11 Example of the label on the Ethernet cable

“A01-03-10-05” indicates that on the local end of the Ethernet cable is connected with
Ethernet Port 05, Slot 10, Frame 03 of the cabinet at Row A, Column 01 in the
equipment room.

“B02-03-12” indicates that the opposite end of the Ethernet cable is connected with
Ethernet Port 12, Frame 03 of the cabinet at Row B, Column 02 in the equipment
room.

B.5 Engineering Labels for Optical Fibers

B.5.1 Introduction to the Labels

These labels are affixed to the optical fibers that connect the optical interfaces on the
boards in a frame, or on the device boxes. There are two types of labels for optical
fibers: one is for the fiber that connects the optical interfaces on two devices, the other
is for the fiber that connects the device and the optical distribution frame (ODF).

B.5.2 Labels for Fiber that Connects Two Devices

I. Label information meanings

Table B-4 shows the information on both sides of the labels affixed to the optical fiber
that connects two devices.

Huawei Technologies Proprietary

B-13
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Table B-4 Information on labels affixed to the fiber between two devices

Content Meaning Example


MN: cabinet number For example, A01
Numbered in top-down order
B: frame number
with two digits, for example, 01
Numbered in top-down and
C: physical slot number left-right order with two digits,
for example, 01
MN-B-C-D-R/T
Numbered in top-down and
D: optical interface number left-right order with two digits,
for example, 05
R: optical receiving interface
T: optical transmitting
interface
MN: cabinet number The meanings are the same as
above. When the local device
B: frame number and the opposite end device are
C: physical slot number not in the same equipment
room, MN can be the name of
MN-B-C-D-R/T D: optical interface number the equipment room.

R: optical receiving interface


T: optical transmitting
interface

II. Label example

Figure B-12 shows the label on the optical fiber between two devices:

Figure B-12 Example of the label on the optical fiber between two devices

“A01-01-05-05-R” indicates that the local end of the optical fiber is connected with
Optical Receiving Interface 05 on Slot 5, Frame 01 in the cabinet at Row A, Column
01 in the equipment room.

Huawei Technologies Proprietary

B-14
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

“G01-01-01-01-T” indicates that the opposite end of the optical fiber is connected with
Optical Transmitting Interface 01 on Slot 01, Frame 01 in the cabinet at Row G,
Column 01 in the equipment room

B.5.3 Labels for Fiber that Connects the Device and the ODF

I. Label information meanings

Table B-5 shows the information on both sides of the labels affixed to the optical fiber
that connects the device and the ODF.

Table B-5 Information on labels affixed to the fiber between the device and the ODF

Content Meaning Example


MN: cabinet number For example, A01

Numbered in bottom-up order with


B: frame number
two digits, for example, 01
Numbered in top-down and
C: physical slot number left-right order with two digits, for
example, 01.
MN-B-C-D-R/T Numbered in top-down and
D: optical interface
left-right order with two digits, for
number
example, 05
R: optical receiving
interface
T: optical transmitting
interface

Numbered in the same rule as that


MN: row number and of the cabinets, for example, G01
column number of ODF indicates an ODF at Row G,
Column 01

B: row number of the


terminal device Range from 01 to 99, for example,
ODF-MN-B-C-R/
T C: column number of the 01-01
terminal device
R: optical receiving
interface
T: optical transmitting
interface

II. Label example

Figure B-13 shows the label on the optical fiber between the device and the ODF.

Huawei Technologies Proprietary

B-15
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Figure B-13 Example of the label on the optical fiber between the device and the
ODF

“ODF-G01-01-01-R” indicates that the local end of the optical fiber is connected with
the optical receiving terminal at Row 01, Column 01 of the ODF at Row G, Column 01
in the equipment room.

“A01-01-05-05-R” indicates that the opposite end of the optical fiber is connected with
Optical Receiving Interface 5 on Slot 05, frame 01 in the cabinet at Row A, Column 01
in the equipment room.

B.6 Engineering Labels for Trunk Cables

B.6.1 Introduction to the Labels

There are two types of labels for trunk cables. One type is used for the trunk cable
connecting two devices, such as the trunk board and built-in transmission unit, or two
trunk boards. The other type is used for connecting the device and the digital
distribution frame (DDF).

The trunk cables include 75Ω/120Ω E1 cables, 120Ω T1 cables, 34M, 45M, 140M,
155M cables and 120-to-75Ω trunk cables, as well as clock cables.

B.6.2 Labels for Trunk Cable that Connects Two Devices

I. Label information meanings

Table B-6 shows the information on both sides of the labels affixed to the trunk cable
that connects two devices.

Huawei Technologies Proprietary

B-16
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Table B-6 Information on labels affixed to the trunk cable between two devices

Content Meaning Example


MN: cabinet number For example, A01
Numbered in bottom-up order with
B: frame number
two digits, for example, 01

Numbered in top-down and left-right


C: physical slot number
order with two digits, for example, 01
MN-B-C-D-R/T Numbered in top-down and left-right
D: cable number
order with two digits, for example, 12
R: optical receiving
interface
T: optical transmitting
interface
MN-B-C-D-R/T Same as above Same as above

II. Label example

Figure B-14 shows the label on the trunk cable between two devices:

Figure B-14 Example of the label on the trunk cable between two devices

“G01-01-05-12-T” indicates that the local end of the trunk cable is connected with the
transmitting terminal of Trunk Cable 12 on Slot 05, Frame 01 in the cabinet at Row G,
Column 01 in the equipment room.

“D02-01-01-10-R” indicates that the opposite end of the trunk cable is connected with
the receiving terminal of Trunk Cable 10 on Slot 01, Frame 01 in cabinet at Row D,
Column 02 in the equipment room

B.6.3 Labels for Trunk Cable that Connects the Device and the DDF

I. Label information meanings

Table B-7 shows the information on both sides of the labels affixed to the trunk cable
that connects the device and the DDF.

Huawei Technologies Proprietary

B-17
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Table B-7 Information on labels affixed to the trunk cable between the device and the
DDF

Content Meaning Example


MN: cabinet number For example, A01

Numbered in bottom-up order with


B: frame number
two digits, for example, 01
Numbered in top-down and
C: physical slot number left-right order with two digits, for
example, 01
MN-B-C-D-R/T Numbered in top-down and
D: cable number left-right order with two digits, for
example, 05

R: optical receiving
interface
T: optical transmitting
interface

Numbered in the same rule as that


MN: row number and of the cabinets, for example, G01
column number of the DDF indicates a DDF at Row G, Column
01.

B: row number of the


terminal Range from 01 to 99, foe example:
C: column number of the 01-01.
DDF-MN-B-C- terminal
D/R/T
There is such a mark in DDF:
D: direction A or B
A: indicating the DDF terminals are
R: optical receiving connected to the optical network
interface equipment
T: optical transmitting B: indicating the DDF terminals are
interface connected to the switching
equipment

II. Label example

Figure B-15 shows the label on the trunk cable between the device and the DDF:

Huawei Technologies Proprietary

B-18
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Figure B-15 Example of the label on the trunk cable between the device and the DDF

“A01-03-01-01-R” indicates that local end of the trunk cable is connected with the
receiving terminal of Trunk Cable 01 in Slot 01, Frame 03 of the cabinet at Row A,
Column 01 in the equipment room.

“DDF-G01-01-01-AR” indicates that the opposite end of the trunk cable is connected
with the receiving terminal of Direction A (connected to optical network equipment) at
Row 01, Column 01 of the DDF at Row G and Column 01 in the equipment room.

B.7 Engineering Labels for Subscriber Cables

B.7.1 Introduction to the Labels

The labels are affixed to both ends of the subscriber cables to identify the position of
the cables on the device side and the main distribution frame (MDF) side.

B.7.2 Label Information Meanings

Table B-8 shows the information on both sides of the labels affixed to the subscriber
cables.

Table B-8 Information on labels affixed to the subscriber cables

Content Meaning Example


MN: cabinet number For example, A01
Numbered in bottom-up order with
B: frame number
two digits, for example, 03
Numbered in top-bottom and
MN-B-C-D C: physical slot number left-right order in two digits, for
example, 01
Numbered in top-bottom and
D: cable number left-right order with two digits, for
example, 01

Huawei Technologies Proprietary

B-19
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Content Meaning Example


Numbered in the same rule as that
MN: row number and column of the cabinets, for example, G01
number of MDF means the MDF of Row G and
MDF-MN- Column 01
B-C
B: row number of the terminal
Range from 01 to 99, for example:
C: column number of the 01-01
terminal

B.7.3 Label Example

Figure B-16 shows the label on the subscriber cable.

TO:

Figure B-16 Example of the label on the subscriber cable

“A01-03-01-01” indicates that local end of the subscriber cable is connected with
Terminal 01 on Slot 1, Frame 03 of the cabinet at Row A, Column 01 in the equipment
room.

“MDF-G01-01-01” indicates that the opposite end of the label is connected with the
terminal at Row 01, Column 01 of the MDF at Row G, Column 01 in the equipment
room.

B.8 Engineering Labels for Power Cables

B.8.1 Labels for DC Power Cables

I. Introduction to the labels

The labels are affixed to the DC cables that provide power for the cabinets, and the
protection grounding cables, including the -48V, PGND, and BGND cables. The labels
for DC power cables are affixed to one side of the identification plates on cable ties.

Huawei Technologies Proprietary

B-20
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

II. Label information meanings

Table B-9 shows the information carried on the labels for the DC power cables:

Table B-9 Information on labels affixed to the DC power cables

Content Meaning
MN(BC)--48V1 MN(BC): BC is written right under MN.

MN(BC)--48V2 On the equipment cabinet side, only MN is used to identify the


cabinet.
MN(BC)-BGND
On the power cabinet side, MN identifies the row and column
number of the power distribution equipment like the control
cabinet and distribution cabinet, BC identifies the row and
MN(BC)-PGND column number of the -48V connecter (if there is no row
number or column number, or the connecter can be identified
without them, BC can be omitted). BGND and PGND have no
row and column number for identification.

The label only carries location information about the opposite equipment, the control
cabinet or the distribution cabinet, while information of the local end is not necessary.
Table B-9 lists the information of two -48V power supplies on the label. The
information for other DC voltages (such as 24V, 60V) should be given in similar
methods.

III. Label example

Make sure that labels are affixed in correction direction. That is, after the cable ties
are bundled onto the cable, the identification plates with the labels should face up,
and the text on the labels in the same cabinet should be in the same direction, as
shown in Figure B-17.

TO:
TO:
A01 -48V2
B03 -48V2
B08

(1) (2)

Figure B-17 Example of the labels on the DC power cable

In Figure B-17, (1) indicates the label on the equipment cabinet side, which carries the
information about the position of the cable on the power distribution cabinet. (2)

Huawei Technologies Proprietary

B-21
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

indicates the label on the distribution cabinet side, which carries the information about
the position of the cable on the equipment cabinet side.

On the equipment cabinet side, the label marked “A01/B08--48V2” on the cable
indicates that the cable is -48V2 DC supply, which is from the 8th connecter on the
second row of -48V bus bar in the cabinet at Row A, and Column 1 in the equipment
room.

On the distribution cabinet side, the label marked “B03--48V2” indicates that the cable
is -48V2 DC supply, which is from the equipment cabinet at Row B, Column 03 in the
equipment room.

Note:
z In the power distribution cabinet (or the first power cabinet of a row in the
transmission equipment room), every terminal on the -48V terminal block has a
numeric identification, like “08” in “A01/B08--48V2” in the above example.
z PGND and BGND are copper bars, on which all the terminals are connected. In
this case, it is only necessary to specify the row and column of the power
distribution cabinet. For example, “A01-BGND” means that the power cable is a
BGND cable that connects to the BGND copper bar of the power distribution
cabinet at Row A, Column 01 in the equipment room.

B.8.2 Labels for AC Power Cables

I. Introduction to the labels

The labels are affixed to the AC cables that provide power for the cabinets, and the
protection grounding cables, including the POWER, PGND, and BGND cables. The
220V AC cables and related PGND and BGND cables are covered with insulating
sheath, so the labels only need to contain the words of “AC" and the cabinet number.
The labels for AC power cables are affixed to one side of the identification plates on
cable ties.

II. Label information meanings

Table B-10 shows the information carried on the labels for the AC power cables.

Huawei Technologies Proprietary

B-22
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix B Engineering Labels for Cables

Table B-10 Information on labels affixed to the AC power cables

Content Meaning
MN: serial number of the cabinet or the socket where the power is led in
The location of the socket is marked out according to onsite situation. If
MN-AC the sockets can be identified by row number and column number, they
can be numbered following the same rule for the cabinets. If the sockets
cannot be identified by rows and columns, specify the detailed locations
to avoid confusing with other sockets.

The label only carries location information about the opposite equipment and the
power socket, while information of the local end is not necessary.

III. Label example

Make sure that labels are affixed in correction direction. That is, after the cable ties
are bundled onto the cable, the identification plates with the labels should face up,
and the text on the labels in the same cabinet should be in the same direction, as
shown in Figure B-18:

TO: TO:
A01 AC B01 AC

(1) (2)

Figure B-18 Example of the labels on the AC power cable

In Figure B-18, (1) indicates the label on the equipment cabinet side, which carries the
information about the position of the cable on the power socket. (2) indicates the label
on the power socket side, which carries the information about the position of the cable
on the equipment cabinet side.

On the equipment cabinet side, the label marked “A01-AC” indicates that the power
cable is connected to the socket of Row A Column 01 in the equipment room.

On the power socket side, the label marked “B01-AC” indicates that the power cable
is connected to the equipment cabinet at Row B, Column 01 in the equipment room.

Huawei Technologies Proprietary

B-23
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

Appendix C Assembling Cable Connectors

C.1 Introduction to the Appendix


This appendix contains the following sections:

C.2 Assembling Power Cable Connector


C.2.1 Introduction to Assembly Procedure

Note:
The method applies to the assembly of bare pressure terminals and 50–240 mm2
power cables.

Figure C-1 shows the procedure for assembling bare pressure terminals and a single
cable.

Start

Cut cable

Mount heat-
shrinkable tube

Strip cable

Crimp cable

Shrink heat-
shrinkable tube

Check cable

Stick label

End

Figure C-1 Assembling bare pressure terminal and a single cable

Huawei Technologies Proprietary

C-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

C.2.2 Assembling Power Cable Connector

I. Cutting cable

To cut the cable, do as follows:


1) Place and roll the cable coils on the support, as shown in Figure C-2.
2) Measure and cut off a segment of the cable according to the cable layout of the
project design.

(1 )

(1 )

(1) Rolling direction


Figure C-2 Cutting a cable

II. Mounting heat-shrinkable tube

To mount heat-shrinkable tube, do as follows:


1) Cut off the power cable with an arm saw.
Because the power cable comprises many core wires, and the wire pairs are fairly fine
and soft, a denticulate arm saw (with the denticulate diameter of 0.8 mm) is
recommended. If available, use wire clippers (model KT35) to cut the power cable.
2) Mount the heat-shrinkable tube onto the cable from the end stripped.

III. Stripping cable

Generally, special stripping tool or electrical knife is recommended. The AM35 wire
stripper is recommended for round cables.
To strip the cable, do as follows:
1) Measure the cable length to be stripped.

Huawei Technologies Proprietary

C-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

The stripped cable length depends on the length of the crimping sleeve behind the bare
pressure terminal. For the JG bare pressure terminal commonly used by Huawei, the
length of stripped cable is calculated using the formula:
L1=L2 + (2~3 mm)
where L1 is the stripped cable length and L2 the length of the effective crimping area of
the JG terminal, as shown in Figure C-3.
2) Remove the multi-strand core wires at the insulation layer of the terminal end, and
strand them tightly. The stranding direction should be the same as the original
merging direction of the core wires.

(1)

(1) Crimping sleeve


Figure C-3 Stripping cable

Note:
When stripping cable, check with care whether the cable core wires have been
seriously oxidized or corroded. If so, cut off the oxidized or corroded segment.

IV. Crimping cable

To crimp the cable, do as follows:


1) Crimp the cable with special crimping pliers or special molds.
2) Try to insert the core wires into the wire inlets of the terminal crimping sleeve until
they cannot be pushed further. Thus the core wires should protrude 2–3 mm from
the terminal, as shown in Figure C-4.
3) Before crimping the wiring terminal, place the cable in the connection position so
that the contact surface of the wiring terminal is parallel to the power bus. If they
are not parallel, hold the end of the terminal with pliers to adjust it.
4) During crimping, use the mold with right cross section. The molding dies
corresponding to the 4 types of power cables are shown in Figure C-5.
5) Ensure correct crimping position, as shown in Figure C-6.

Huawei Technologies Proprietary

C-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

(2)

(1)

(1) Bare pressure terminal (2) Heat-shrinkable tube


Figure C-4 Connecting core wire with terminal crimping sleeve

(1)
(2)

50mm2 95mm2 120mm2 240mm2

(1) Bearing device (2) Compressing device


Figure C-5 Molding dies related to power cables

200

150-325

Figure C-6 Crimping cable

Huawei Technologies Proprietary

C-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

V. Shrinking heat-shrinkable tube

As stipulated in the cable design drawings, mount the heat-shrinkable tube onto the
position where the terminal and the cable are joined, and blow the tube with a heat gun
until the tube shrinks and wraps up tightly, as shown in Figure C-7.

(1) Shrank heat-shrinkable tube


Figure C-7 Shrinking heat-shrinkable tube

Note:
The heat-shrinkable tube on the cable should wrap up the whole crimping sleeve of the
bare pressure terminal, including the joint between the terminal and the cable.

VI. Checking cable

Table C-1 shows the normal tensile strength of the ready-made cables.

Table C-1 Tensile strength standard of ready-made cables

Cable Tensile strength


2
50 mm 1 KN
2
95 mm 2 KN
2
120 mm 2.5 KN
2
240 mm 5 KN

The cable with an oxidized terminal surface and damaged cable sheath is substandard.

VII. Labeling

Attach labels (provided with the goods) to both ends of the power cable. For details,
refer to Appendix B "Engineering Labels for Cables".

Huawei Technologies Proprietary

C-5
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

C.2.3 Application of Crimping Tool

I. Introduction to crimping tool

The crimping tools of different types are used for different purposes. The application of
the crimping tool SS-325 (usually used by Huawei) for large-section power cable
terminals is illustrated in Figure C-8.

(1) Fixing handle (2) Hydraulic head (3) Hand level (4) Fixing rod (5) Hydraulic switch
Figure C-8 SS325 parts

II. Using crimping tool

Note:
Improper installation of the fixed handle, the pressing and stressed components will
reduce the life cycle of the crimping tool.

The steps for using crimping tool are as follows:


1) Select the crimping component as required.
2) Assemble the compressing device, bearing device and fixing handle for the
crimping tool.
3) Release the fixing handle and place the tool in right place.
4) Turn on the hydraulic switch to put the compressing device into the in-service state,
and lift the hand level.
5) Place the cable to be crimped.
6) Push down the hand level to crimp the cable.
7) Check that the cable is well crimped.
After the crimping, a black line will appear at the hydraulic switch indicating that the
crimping is finished normally (as for the tool of type SS0325, there is no such a line).

Huawei Technologies Proprietary

C-6
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

Caution:

If the black line does not appear after the crimping, stop using the tool and have it
repaired.

8) Turn off the hydraulic switch.


Turn off the hydraulic switch after the operation and take out the crimping components.

III. Maintenance and storage

It is required to regularly oil the crimping components, hydraulic switch and the tool
body.
After using the tool, place it in a cool and ventilated place unreachable for children.
Meanwhile, avoid direct sunshine.

IV. Filling and replacing oil

The oil in the tool should be replaced completely every two years, and the oil can be
purchased in related authorized shop.

Caution:

z Wear gloves when filling oil. Eye contact or skin contact of the oil may cause
inflammation.
z The oil is inedible. Put it in the place unreachable for children.
z In the case of eye contact, wash eyes with clean water within 15 minutes and seek
medical assistance as soon as possible.
z In the case of skin contact, wash the area thoroughly with clean water.
z Dispose it according to the requirements of the related law for environmental
protection.

The steps for filling and replace oil are as follows:


1) Turn off the hydraulic switch.
2) Screw off the fixing rod to expose the oil-embolus.
3) Put the oil-embolus upward, and screw off the oil plug.
4) Fill in oil with a little oil can.
5) After a while, tap the tool against something hard to expel the air inside it, and then
fill oil again. Repeat above steps till the pot is full.

Huawei Technologies Proprietary

C-7
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

C.3 Assembling RJ45 Connector


C.3.1 Introduction to Assembly Procedure

Note:
The method applies to the assembly of RJ45 connector with straight through network
cable and crossover network cable.

Figure C-9 shows the procedure for assembling an RJ45 connector.

Start

Strip cable

Weld pin

Crimp outer
connector

Check cable

Stick label

End

Figure C-9 Flowchart of assembling RJ45 connector

C.3.2 Assembling RJ45 Connector

I. Stripping and cutting cable

The length of the stripped segment on either cable is "L + (2–3 mm)", as shown in
Figure C-10. The meaning of "L" is shown in Figure C-12, while "2–3 mm" represents
the length reserved for wire cutting and sorting.

Figure C-10 Length of stripped cable segment

Huawei Technologies Proprietary

C-8
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

Caution:

z When stripping the cable, make sure that the end of the sheath is neatly stripped
and the cutting angle is vertical to the cable.
z For the shielded cable, avoid damaging the shield layer when stripping the
protection layer. After the protection layer is stripped, fold the shielding layer
backwards to the root of the cable sheath, as shown in Figure C-11.
z The core wires, especially for the round communication cables, should be cut neatly.
Before cutting, spread the core wires evenly apart and cut them neatly with the
cutting tool, as shown in Figure C-12.
z The structure and dimensions of the truncated cable should be in accordance with
the requirements shown in Figure C-12. That is, the core wire should be equal to "L"
in length.

(1) Folded shielding layer


Figure C-11 Folded shielded cable

Figure C-12 Bare wires of a cable

II. Inserting cable

The requirements are as follows:


z The 8-core flat telephone line should be inserted from the tail of the RJ45
connector, till the point A of the connector engages the casing of power cable.
z Each core wire should be inserted along the cable trough to the head of the
connector, and all the core wires should be flush with the head of the connector, as
shown in Figure C-13.

Huawei Technologies Proprietary

C-9
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

1) The round communication cable should be inserted into the connector in the same
way as 8-core flat telephone line. The core wire end should be flush so that it is
easy to be put in position.
2) The shielded cable can be inserted in the shielded RJ45 connector in the same
way described above, with the folded shielding layer attaching the built-in
shielding piece at the tail of the RJ45 connector and butting against point A of the
connector. See Figure C-13.

(1)

(2)
(8)

(3)
(7)

(4)
(5)
(6)

(1) Shielding piece (2) External shielding piece (3) Cable insertion direction
(4) Built-in shielding piece (5) Point A (6) Locking piece
(7) Core wires flushing with cable end (8) Metal cutter
Figure C-13 RJ45 connector

Note:
The cable should be inserted in the order specified in the cable design drawings.
Figure C-14 and Figure C-15 illustrate the wires of crossover cable and straight through
cable.

Huawei Technologies Proprietary

C-10
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8

Brown
Blue

Orange
Brown and white
Blue and white

Orange and white


Orange and white

Brown
Orange

Blue

Green
Brown and white
Green and white

Blue and white


Green and white
Green

RJ45 RJ45

1 3
2 6
3 1
4 4
5 5
6 2
7 7
8 8

Figure C-14 Wire sequence of crossover cable

Huawei Technologies Proprietary

C-11
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8

Green
Brown and white
Brown
Brown

Orange and white

Blue and white


Green

Orange
Green and white
Blue

Brown and white

Blue
Orange and white
Orange
Green and white

Blue and white

RJ45 RJ45

1 1
2 2
3 3
4 4
5 5
6 6
7 7
8 8

Figure C-15 Wire sequence of straight through cable

III. Crimping cable

Note:
z Before crimping, the RJ45 connector should be placed in the corresponding slot of
the crimping pliers.
z The connector should be fully crimped. After the crimping, the metal cutter should
be lower than the top surface of the RJ45 connector.
z When crimping an RJ45 connector onto a shielded cable, make sure that metal
cutters in the connector are crimped in position and that the built-in shielding piece
of the connector securely contacts the shielding layer of the cable.

After the cable is inserted in place, crimp the connector using the RJ45 crimping pliers.
Figure C-16 shows a cable with an RJ45 connector.

Huawei Technologies Proprietary

C-12
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

Figure C-16 A ready-made RJ45 connector

IV. Inspecting cable

The inspection items include:


z Inspect the appearances of all the connectors carefully. The connectors with shell
breakage or evident crack, locking piece breakage or crack, or improper cable
insertion should be discarded.
z Inspect all the cables carefully. The sequence of the wires should be in line with
the design requirements.
z Carry out continuity check on all cables. The continuity ratio should be 100%. No
short circuit should be found between cables.

Note:
For the shielded cable assembled with shielded RJ45 connector, continuity check
should be performed between the shielding shell of the connector and the shielding
layer of the cable.

V. Labeling

Attach the ready-made labels to both ends of the cable. For details, refer to Appendix B
"Engineering Labels for Cables".

C.4 Assembling SMB Connector


C.4.1 Introduction to Assembly Procedure

Note:
The method applies to the assembly of SMB connector with external clock cable and
trunk cable.

Figure C-17 shows the procedure for assembling SMB connector.

Huawei Technologies Proprietary

C-13
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

Start

Mount heat-
shrinkable tube
and crimp sleeve

Strip cable

Weld pin

Crimp outer
conductor

Shrink heat-
shrinkable tube

Inspect cable

End

Figure C-17 Procedure for assembling SMB connector

C.4.2 Assembling SMB Connector

I. Mounting heat-shrinkable tube and crimping sleeve

Figure C-18 illustrates how to mount the heat-shrinkable tube and crimp it.

(1) (2)

(1) Heat-shrinkable tube (2) Crimping sleeve


Figure C-18 Mounting heat-shrinkable tube and crimping sleeve

II. Stripping cable

Strip off the shielding layer and the inner insulation layer of the cable with a wire stripper.
The shielding layer and the inner insulation layer should not be damaged. The cable
sheath and the end surface of the inner insulation layer should be cut neatly and
smoothly. The specification of the stripped length is shown in Figure C-19 (Unit: mm).

Huawei Technologies Proprietary

C-14
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

(1) (2 )

4.5
(3)

2 .3

(4 )
11

(1) Sheath (2) Inner insulation layer (3) Inner conductor (4) Shielding layer
Figure C-19 Stripping cable

III. Welding pin

Caution:

z During the welding, the inner insulation layer should not be scalded.
z Try not to let the soldering tin flow out to the exterior face of the pin while welding. In
the case of outflow, the tin must be cleaned up lest it should affect the next step.

Use the solder to weld the pin with the inner conductor of the cable together. The
temperature of the melting point should be above 125°C.
When welding, insert the inner conductor of the cable into the central hole at the rear of
the pin until the boss at the pin end contacts the inner conductor of the cable, as shown
in Figure C-20.

(1) Inner insulation layer (2) Boss


Figure C-20 Welding pin

Huawei Technologies Proprietary

C-15
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

IV. Crimping outer conductor

Caution:

z Before crimping, the SMB connector to be crimped should be checked. If the


shielded cables lay nakedly outside the crimping tube, the cable should be trimmed
with scissors.
z When crimping, the SMB connector should be placed in the right place to match with
the molding-die of the crimping pliers.

The steps for crimping outer conductor are as follows:


1) Place the knurled cylinder of the SMB connector between the inner insulation layer
and the shielding layer of the cable.
2) Make the shielding layer attach evenly to the knurled cylinder.
3) Have the needle lug butted against the inner insulation core of the connector. See
Figure C-21.
(1 )

(2 )

(3 )

(4 )

(1) Shielding layer covering the knurled cylinder evenly


(2) Inner insulation core of the connector
(3) Pin (4) Coaxial connector
Figure C-21 Crimping an SMB connector onto a coaxial cable

4) Push the crimping tube to cover the shielded cable entirely.


5) Crimp with the SMB crimping pliers.

V. Shrinking heat-shrinkable tube

Put the heat-shrinkable tube at the joint of the terminal and the cable, and blow the tube
using a heat gun until the tube shrinks and wraps up tightly. See Figure C-22.

Huawei Technologies Proprietary

C-16
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Appendix C Assembling Cable Connectors

(1 )

(1) Shrinking
Figure C-22 Shrinking heat-shrinkable tube

VI. Inspecting cable

The inspection items include:


z Use a multimeter to check the continuity between the connector pin and the inner
conductor of the coaxial cable and that between the outer shell of the connector
and the shielding layer of the coaxial cable.
z Use a multimeter to check that the inner and the outer conductor are not
short-circuited.
z Apply proper force (about 60 N) to pull the inner contact pin outward, there should
be no obvious displacement for the inner contact pin.
z Check that there is no shielded cable laying naked outside or no contact pins out
of position.

Huawei Technologies Proprietary

C-17
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

Appendix D Requirements for Equipment


Operating Environment

D.1 Observed Standards

This document is based on the standards of the People’s Republic of China. If the
on-site situation is inconsistent with the document, refer to the local standards and
regulations

D.2 Requirements for Equipment Room

D.2.1 Site Requirements

The communication equipment should run in a favorable environment. Its equipment


room should be located at a place free from high temperature, dust, toxic gases,
explosive materials or instable voltage, and away from great vibrations, strong noise
or power transformer stations. During project designing, such factors as hydrographic,
geological, seismic, power supply and transportation factors should be taken into
consideration to select the site in line with the engineering and environmental
requirements for the communication equipment.

The construction, structure, heating and ventilation, power supply, lighting, and
firefighting designs of the communications equipment room are done by specialized
construction designers and the environment design requirements of the switch should
be strictly followed. The communication equipment room shall be designed in
accordance with the industrial, environmental protection, fire-fighting and civil defense
requirements, as well as the current standards/regulations of the local country or
region and the requirements of special technical process for building construction
design.

Site requirements are as follows:


z The site should be kept away from pollution sources. For sources of heavy
pollution such as the smeltery and coal mine, keep a distance of 5 km. For
sources of medium pollution such as the chemical, rubber and galvanization
industries, keep a distance of 3.7 km. For sources of light pollution such as food
and tanner industries, keep a distance of 2 km. If these sources of pollution
cannot be avoided, the equipment room must be in the perennial upwind

Huawei Technologies Proprietary

D-1
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

direction of the pollution sources. In addition, quality equipment room or


protection product must be adopted.
z The ventilation port for air exchange of the equipment room must be kept away
from the exhaust of city waste pipes, big cesspools and sewage treatment tanks.
The equipment room should be kept in the positive pressure state lest the
corrosive gases enter the equipment room and erode components and circuit
boards.
z The equipment room should be kept away from the industrial and heating boilers.
z It is best to locate the equipment room in or above the second floor. If this
requirement cannot be satisfied, the ground for equipment installation in the
equipment room shall be at least 600 mm above the maximum flood level in the
local record.
z The equipment room should be kept away from livestock farms. If this
requirement cannot be satisfied, it should be located in the perennial upwind
direction of the livestock farms.
z The equipment room should be kept 3.7 km away from the seaside or salt lake. If
this requirement cannot be satisfied, the equipment room should be airtight with
cooling facilities. In addition, the alkalized soil cannot be used as the construction
material. Otherwise, the equipment applicable in atrocious environment must be
adopted.
z The old livestock room or the chemical fertilizer warehouse cannot be used as
the equipment room.
z The equipment room should be solid enough to withstand wind and downpour.
z The equipment room should be kept away from the road or sand field with dusts
flying around. If this requirement cannot be satisfied, the windows and doors of
the equipment room should be kept away from the sources of pollution

D.2.2 Equipment Room Composition

The equipment room is used to install switching equipment, communication


transmission devices, power supply devices, and other auxiliary devices. To facilitate
maintenance and management, it is required to install them in different room.
Figure D-1 shows the layout of equipment room.

Huawei Technologies Proprietary

D-2
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

Control room Diesel generator

Transmission Power distribution


Switching room Battery room
room room

Communication cable Power


and optical fiber transformation
room
Power cable

Figure D-1 Equipment room layout

The overall layout principles are as follows:


z The equipment room layout meets the requirements for laying communication
cables, power cables, and maintenance.
z Make the cable routes as short as possible, for the convenience of maintenance,
and for the purpose of reducing line cost and communication faults, and
improving work efficiency.

D.2.3 Building Requirements

Table D-1 shows the requirements for the building specifications of the equipment
room.

Table D-1 Requirements for building specifications of the equipment room

Item Specification
Area The equipment room can hold the whole equipment.
The indoor minimum height is the net height under beam or
Net height
air pipe. The net heath must not be less than 3 meters.

It is required that the floor is semi-conducting and dust-free.


Generally, it is required to pave ESD-preventive floor. The
floor blocks must be paved securely, and the error per square
meter must not be more than 2 mm. If there is not raised floor,
it is required to use static-conducing material (size to
Indoor floor 7 10
impedance ratio is 1.0 x 10 – 1.0 x 10 Ω). The
static-conducting material or raised floor must be well
connected to grounding device through current-limited
resistance and connection cable. The impedance of current
limit resistance is 1 MΩ.

Huawei Technologies Proprietary

D-3
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

Item Specification
Floor load bearing 2
More than 400 kg/m
capacity
The door is 2 meters high and 1 meter wide. It is OK to use
one door panel. It is required to seal the door and window by
Door and window
dust-proof rubber tape, and use double-layer windows and
seal them.
It is possible to paste wall paper or paint lusterless paint on
Wall surface
the wall, but chalked paint is not recommended.
Groove is used to lay cables. It must be clean inside. The
reserved length, width, the number of holes, the hole positions
Indoor groove
and hole size must comply with the requirements for the
layout of optical synchronous transmission devices.

The power supply pipe, drainage pipe and rain pipe must not
Water supply and pass through the equipment room, and fire extinguisher
drainage should be equipped where it is easy to find and access, such
as corridor or staircase, instead of in the equipment room.

The installation place must be separated from the door of the


Partition in equipment room. The partition panel will be helpful to prevent
equipment room some dust. The partition is shown in
Figure D-2.
Air conditioner The outlet air of the air conditioner must not directly point to
position the equipment.
In the equipment room, specific measures must be taken to
Other
prevent epiphyte and mildew, as well as rodent animals, such
requirements
as mouse.

(1)

(2)

(3)

(1) Air conditioner (2) Equipment (3) Partition panel


Figure D-2 Partition in equipment room

Huawei Technologies Proprietary

D-4
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

D.2.4 Humidity and Temperature Requirements

To ensure that the equipment operates in good condition, the humidity and
temperature must be kept within a certain range in the equipment room. Table D-2
shows the specific requirements.

Table D-2 Humidity and temperature requirements

Temperature Relative humidity


Long term Short term Long term Short term
+5 °C – +40 °C -5°C – +55°C 5% – 85% 5% – 95%
Note:
The measurement points of temperature and humidity refer to the values measured
1.5 m above the floor and 0.4 m away from the front side of the cabinet when there
are no protection panels in the front and back of the cabinet.
Short term means that the consecutive working duration is not more than 48 hours
and that the accumulated working duration of a year is not more than 15 days.

To meet the above requirements, the following measures must be taken in the
equipment room:
z The temperature control facility is equipped in the equipment room.
z Humidifier can be used in dry areas. It is also possible to use wet mop to mop
the floor to keep the humidity.
z In areas with high humidity, desiccating machine can be used.

D.2.5 Air Cleanness Requirements

The dust accumulated on the equipment might cause static attached, which might
cause metal connectors or metal contacts in bad contact. This will affect the life of the
equipment, and bring the equipment with faults.

In the equipment room, there must not exist explosive, conducing,


magnetic-conductive, or erosive dust. Table D-3 shows the requirements on dust
density.

Table D-3 Dust particle limit in the equipment room

Mechanically active
Unit Content
material
4
≤3×10 . (There is no visible dust on desk
Dust particle particle/m³
within 3 days)

Note: Dust particle: diameter ≥5 µm

Huawei Technologies Proprietary

D-5
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

To meet the above requirements, the following measures must be taken in the
equipment room:
z Dust-free materials must be used on the floor, walls, and ceiling.
z Door screen and window screen must be used for the doors and windows toward
outdoors. The windows must have dust-proof function.
z The equipment room and dust filter of the equipment must be cleaned
periodically (every 3 months).
z People entering the equipment room must wear ESD-preventive shoes,
ESD-preventive suits, and ESD-preventive wrist straps.

D.2.6 Erosive Gas Condition Requirements

Besides dust-proof measures, erosive gas proof measures must be taken in the
equipment room to prevent such gases as SO2, H2S, and NH3. Table D-4 shows the
requirements on the density of erosive gases.

Table D-4 Erosive gas density limit

Chemically active
Unit Content
material
SO2 mg/m³ ≤0.20
H2S mg/m³ ≤0.006
NH3 mg/m³ ≤0.05

Cl2 mg/m³ ≤0.01

To meet the above requirements, the following measures must be taken in the
equipment room:
z The equipment room must be far away from the areas with high density of
erosive gases, such as chemical plants.
z The air inlet must be against the pollution sources.
z The storage batteries must be placed separately in an independent room.
z It is required to ask professional company to inspect the environment
periodically.

D.2.7 Electromagnetic Requirements

Table D-5 shows the electromagnetic requirements.

Huawei Technologies Proprietary

D-6
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

Table D-5 Electromagnetic range

Environment electromagnetic Parameter


Frequency (Hz) 50 to 20 000
Low-frequency magnetic field
Ampl. A/m (rms) 10 to 0.025

Amplitude-modulation Frequency (MHz) 0.009 – 1000


radio-frequency electric field Ampl. V/m (rms) 3

Pulse-modulation radio-frequency Frequency (GHz) 1–20


electric field Ampl. (V/m (peak)) 3

The following measures can be taken to suppress the interference signals:


z The equipment must be far away from transformer, high-voltage electricity
transmission lines, and high-current devices. For example, there is no AC
transformer within 20 square meters, or high-voltage electricity transmission lines
within 50 square meters.
z The equipment must be far away from high-power broadcast transmitter, for
example, there is no high-power broadcast transmitter within 500 square meters.
z If there is mobile communication transmitter in the equipment building, the
interference must comply with related requirements, and shielding measures
must be taken to prevent the interference.
z In the equipment room, it is prohibited to use wireless handy set near the
equipment.

D.2.8 ESD-Preventive Requirements

The absolute voltage of electrostatic must be less than 1000 V.

To meet the above requirement, the following measures must be taken in the
equipment room:
z All operators must be trained in ESD-preventive knowledge.
z The humidity must be kept within a certain range, for example, above 60%RH, to
reduce the effect by electrostatic.
z The equipment room must have ESD-preventive floor, and people entering the
equipment room must wear ESD-preventive shoes, ESD-preventive suits, and
ESD-preventive wrist straps.

D.2.9 Lightning Protection Requirements

Table D-6 shows the lightning protection requirements.

Huawei Technologies Proprietary

D-7
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

Table D-6 Lightning protection requirements

Item Description
It is better that the equipment building is of reinforced concrete
structure.
Building The equipment building must have lightning arrester.
requirements
The ground for lightning arrester of the equipment building and
the protection ground of the equipment room share the same
group of grounding bodies.
The communication office has dedicated power transformer. The
power cables must have metal bushing or insulation bushing,
and are led in to the office through metal pipe under ground. The
metal bushing or metal pipe must be grounded at both ends. The
AC power length under group must be not less than 15 meters.
supply system
adopts TN-S The three phase lines at the low-voltage side of the AC
power supply transformer in the communication office must have separate
gapless zinc oxide lightning protector. The shell of the
transformer, the AC neutral line at the low-voltage side, and the
metal bushing of the power cable connected to transformer shell
must be grounded nearby.
It is not allowed to lead in or out the AC or DC power cables
to/from communication office in overhead way.
After low-voltage power cables are led into the equipment room,
lightning protector must be installed for the power cables in the
AC voltage regulator and AC switchboard, and the lightning
protector must be grounded nearby.
Lightning
protector for In the city, it is recommended to use power lightning protector
incoming with nominal discharge current of more than 20 kA. In the
power cable suburbs with more lightning dangers, it is recommended to use
power lightning protector with strike through-flow of more than
60 kA. In mountains or higher buildings in the city, it is
recommended to use power lightning protector with strike
through-flow of more than 100 kA.
The length of grounding cable for power lightning protector must
be less than 1 meter.

The DC working ground of the communication office (positive of


–48V or negative of 24V) must be connected to the indoor
grounding bus nearby, and the grounding cable must satisfy the
DC power requirements for the maximum load of the equipment.
distribution
grounding The power supply devices for the communication office must
have DC working grounding cable connected to the grounding
bus in the communication building or the protection grounding
bar in the equipment room.

Huawei Technologies Proprietary

D-8
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

Item Description
The communication equipment and auxiliary devices, such as
mobile base station, transmission device, switching device,
power supply device, and cable distribution rack, must be well
grounded. Their protection grounds must be connected to the
grounding bar in the equipment room.
Equipotential
connection The working ground and protection ground of the communication
equipment in the equipment room share the same ground net.
The cabling rack, suspension metal bracket, cabinet or shell,
metal air vent and metal doors and windows must be well
grounded.

It is prohibited to connect the neutral line of AC power cable to


protection ground of the communication equipment.
Grounding
requirements It is prohibited to use fuse or switch on the grounding cables.
All grounding cables must be as short and straight as possible.
The grounding impedance is less than 1 ohm.
The upper part of the grounding body must be more than 0.7 m
Grounding
from the ground. In cold areas, the grounding body must be
impedance
buried under frozen soil layer.
requirements
It is required to measure the grounding impedance periodically,
to ensure the validity of grounding.
In the communication office, signal cables must be laid
underground.
The communication cables must have metal bushing or be laid in
Signal cable
metal pipe when they are led in or out of the communication
layout
office.
requirements
The grounding cable for lightning protector must be as short as
possible, and unused wires in the cables must be well grounded
in the equipment room.

The grounding bus can be realized in grounding ring mode or


grounding bar mode.
The grounding cable must not be aluminum. When different
kinds of metals are connected, correct measures must be taken
Grounding bus
to prevent couple corrosion.
requirement
The grounding bus cable is made of copper bar with sectional
2
area of not less than 120 mm or zinc-coated steel with the same
impedance. The grounding bus cable must be insulated from the
steel of the building.
Grounding The grounding lead-in cable must not be longer than 30 meters,
lead-in cable and it is recommended to use zinc-coated steel with sectional
requirement area of 40mm x 4mm or 50mm x 5mm as the material.

Huawei Technologies Proprietary

D-9
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

D.3 Requirements for Power Supply

D.3.1 Requirements for AC Power Supply

I. Generic requirements on AC power supply

Adopt the centralized AC power supply model of mains, uninterrupted power supply
(UPS), and a reserved diesel generator.

Ensure simplicity in cable connection, security in operation, flexibility in scheduling,


and convenience in maintenance.

Adopt three-phase and five-wire, or monophase three-wire AC power for low-voltage


power supply system.

Table D-7 lists the nominal voltage and rated frequency of low-voltage power supply
system.

Table D-7 Specifications of AC voltage and frequency

Nominal voltage Rate frequency


110/127//220/380 V 50 Hz

Adopt UPS for the backup AC power supply. Keep it the same phase with mains. Set
the switching time between mains and UPS less than 10 ms; otherwise, the product
will reboot or reset itself.

Ensure that the equipment runs well below nominal current; never in the threshold of
failure.

Use a separate AC power supply protection unit for a piece of separate equipment.
The current to trigger the protection should be greater than the

When designing the DC power supply system, consider the maximum static and
dynamic load of the system. Always keep sufficient room for the two thresholds.

Choose the model of the power cables by the maximum load of power supply.

The diesel generator set of the office automatically functions in case of power failure,
automatically supply when the mains is insufficient, and automatically stops
functioning when power restores. It can be tested and controlled remotely in standard
interface and communication protocols.

II. Power supply specifications of AC-powered equipment

Here are the power supply specifications of AC-powered equipment:

Huawei Technologies Proprietary

D-10
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

z Voltage fluctuation of communications equipment: –10% – +5% of rated voltage.


z Voltage fluctuation of power supply equipment and important buildings:–15% –
+10% of rated voltage.
z Frequency fluctuation:–4% – +4%.
z Aberration rate of voltage sine wave: ≤5%.

III. Specifications of power cables

Here are the specifications of the power cables:


z Use the neutral line of the same cross-sectional area as the live line.
z Select the DC power feeder on long-term load.
z Use fire-resistant AC cables.

D.3.2 Suggestions on AC Power Supply

When the voltage of mains power supply is not stable, use the voltage regulator in
any of the following conditions:
z Powered by mains, the voltage fluctuation of communications equipment
exceeds the rated threshold (–10% – +5% of rated voltage).
z Powered by mains, the voltage exceeds the rated voltage fluctuation of
communications equipment.
z Not directly powered by mains, the voltage fluctuation exceeds the rated
threshold (–15% – +10% of rated voltage).
z The voltage exceeds the rated AC voltage fluctuation of DC power supply
equipment.
z Use UPS or inverter to prevent interruption or surge of power supply.
z Use a diesel generator set when the mains is faulty. The capacity of the
generator set should 1.5 to 2 times of the capacity of UPS.
z Use two groups of storage batteries in parallel.
z Use one group of UPS storage batteries. The batteries can be working in parallel
or serial connection.
z Use main inverter based on the maximum power. Keep a backup one.

D.3.3 Requirements for DC Power Supply

Ensure stable power supply. Close the power supply equipment to the
communications equipment to minimize the feeder line. The voltage level between
battery and the equipment should be less than 3.2 V.

When there are more than two switching systems, use two or multiple independent
power supply systems.

Set up multiple independent power supply systems for important communication


centers, each of which powers a separate equipment room. For ordinary offices,

Huawei Technologies Proprietary

D-11
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

adopt the model of a centralized power supply room plus a battery room. For
small-capacity offices, adopt the centralized power supply model. Always prevent the
boards from the erosive chemicals given out from batteries.

Table D-8 specifies the requirements on DC power supply.

Table D-8 DC power supply specifications

Item Specifications
Voltage fluctuation of
–40V–57V
–48-V input end

Anti-surge current Should be 1.5 times greater than the rated load current
capability capability.

When the AC input voltage range is from 85% to 110%


of the rated value, and the load current is from 5% to
Voltage stability 100% of the rated value, the output voltage of the
current stabilizer is an integral value between –56.4 and
–46.0V. The variance is less than equal to 1%.

Voltage surge at Less than equal to the integral value of DC output value
power-on and power-off ±5%

Peek-to-peek noise
≤200mV
voltage

The recovery time is less than 200 ms. The exceeding


Dynamic response amount should not be more or less than 5% of the rated
DC output voltage.

D.3.4 Suggestions on DC Power Supply

z Use the distributed power supply model. Scatter the power supply systems to
multiple sites.
z Adopt standard DC power supply system. The output voltage of the power
supply equipment should meet the requirement of the communications
equipment.
z Enhance the reliability of the power supply system. Optimize the capacity of the
storage batteries. In small-capacity offices, when it is difficult to maintain the
reliability of the power supply system, expand the capacity of the storage
batteries.
z The total configuration of high-frequency switch rectifier should meet the load
power of communication and the recharging power of the storage batteries.
Adopt the redundant configuration model for the rectifier module. Use a standby
rectifier for less than ten active ones; and add one rectifier for every additional
ten active ones.

Huawei Technologies Proprietary

D-12
Hardware Installation Manual Appendix D Requirements for Equipment
U-SYS SoftX3000 SoftSwitch System Operating Environment

z Equip the storage batteries in two or multiple groups. The total capacity is
determined by the power feeding duration. Ensure at least one hour of power
supply capability for the storage battery group.

Huawei Technologies Proprietary

D-13
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Index

Index

cabling rack, 6-15, A-1


A cabling trough, 6-15, A-4
alarm cable, B-10 captive fastener, 4-7
alarm sound switch, 9-4 captive screw, 4-6
alarm system, 8-2 centralized power supply, D-11
anti-tilt angle, 4-7 channel-section connecting piece, A-9
arm saw, C-2 channel-section steel, A-8
check equipment room conditions
B auxiliary devices, 2-5
back cabling mode, 6-8 building, 2-4
backhaul ground, 5-3 environment, 2-4
baffle ring, A-18 grounding, 2-5
binding bar, 6-3 other faclities, 2-6
BITS, 6-16 power supply, 2-4
blank filler panel, 4-5 procedure, 2-4
board allocation, 1-2 climbing ladder, A-12
clock cable, 6-12
C coaxial cable, C-17

cabinet combined cabinets, 3-21

checking cabinet, 9-1 connect signal cable

cabinet base, 7-6 internal signal cable, 6-1

cabinet configuration, 4-1 connector and socket

integrated configuration cabinet, 4-1 check, 9-2

MRS cabinet, 4-3 cord end terminal, 5-5, 5-15

service processing cabinet, 4-2 crimping plier, C-3, C-12

cable crimping sleeve, C-2, C-14

cable route, D-3 crimping tool, C-6

crimping cable, C-3 cross stay, A-8

cutting cable, C-1 cruciform screw, 5-8

stripping cable, C-2, C-14 crystal connector, 6-7

cable bushing, A-19


cable coil, C-1
D
cable connector, C-1 DC power distribution cabinet, 5-16, 5-18
cable distribution DC switchboard, 5-16, 5-18
checking cable distribution, 9-1 DDF, 6-14
cable tie, B-3 digital distribution frame, B-3
cable-through clip, A-3 distributed power supply model, D-12
cabling ladder, A-7, A-10 downward cabling, 5-16

Huawei Technologies Proprietary


i-1
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Index

downward cabling mode, 6-15 install cabinet fittings


dryer bag, 9-3 back door, 7-4
D-shape connector, 6-10 cabinet side panels, 7-4
door lintels, 7-2
E ESD-preventive floor holders, 7-1

electrical performance check, 9-3 front door, 7-4

emergency workstation, 6-8 protection grounding cable for door, 7-6

enclosure frame, 7-3 install cabinet on cement floor

end cover, A-19 fix cabinet, 3-20

environmental protection, C-7 introduction, 3-14

ESD-preventive plastic bag, 2-9 level cabinet, 3-19

Ethernet cable, B-10 plan cabinet position, 3-15

expansion bolt, 3-6, 3-19 test insulation, 3-21

external network cable, 6-17 install cabinet on ESD-preventive floor


fix cabinet, 3-11
F install holder fixing components, 3-10
install support and side rails, 3-6
fix cabinet
introduction, 3-1
fix bottom of cabinet, 3-11
level cabinet, 3-10
fix top of combined cabinet, 3-12
plan support position, 3-2
flat column, 7-4
test insulation, 3-13
floor holder, 3-10
install cable for BAM
floor holder fixing component, 3-10
power cable, 5-6

G install cable for frame


power cable, 5-5
ground supporting mode, A-7
install cable for hard disk array
grounding
power cable, 5-7
grounding bus, D-9
install cable for iGWB
grounding lead-in cable, D-9
power cable, 5-6
grounding bus cable, 5-5
install cable for KVMS
guide rail, 4-5
power cable, 5-8
install cable for LAN switch
H
power cable, 5-9
heat gun, C-5
install cable for MRS
heat-shrinkable tube, 5-18, C-2, C-14
power cable, 5-10
holder fixing component, 7-1
install cables between cabinet
horizontal ruler, 3-11, 3-19
protection grounding cable, 5-13
hydraulic switch, C-6
install cables for BAM
protection grounding cable, 5-12
I
install cables for cabinet
install cabinet power cable, 5-14
on cement floor, 3-14 protection grounding cable, 5-14
on ESD-preventive floor, 3-1

Huawei Technologies Proprietary


i-2
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Index

install cables for frame install power cables


protection grounding cable, 5-12 notes, 5-5
install cables for iGWB procedure, 5-3
protection grounding cable, 5-12 install protection grounding cable
install cables for KVMS between cabinet, 5-13
protection grounding cable, 5-12 for BAM, 5-12
install cables for LAN switch for frame, 5-12
protection grounding cable, 5-12 for iGWB, 5-12
install cables for MRS for KVMS, 5-12
protection grounding cable, 5-13 for LAN switch, 5-12
install data cable for MRS, 5-13
between iGWB server, 6-9 install serial port cable
install FE signal cable between iGWB server, 6-9
between HSCI and SIUI, 6-8 install signal cable
install internal component data cable, 6-9
BAM, 4-6 external signal cable, 6-14
hard disk array, 4-6 FE signal cable, 6-8
iGWB, 4-6 mode, 6-4
KVMS, 4-7 requirement, 6-3
LAN switch, 4-7 serial port cable, 6-9
MRS, 4-7 straight through network cable, 6-6
note, 4-5 install support and side rails
procedure, 4-5 adjust support height, 3-7
requirement, 4-6 assemble supports and slide, 3-7
install internal signal cable fix supports, 3-8
procedure, 6-5 install expansion bolt, 3-6
install peripheral install through network cable
alarm box, 8-2 between BAM and LAN switch, 6-7
grounding requirement, 8-3 between HSCI and LAN switch, 6-8
lay cable, 8-3 between iGWB and LAN switch, 6-7
terminal equipment, 8-1 between LAN switches, 6-6
install power bus cables, 5-18 insulation plate, 3-19
fix OT terminal, 5-20 internal component, 4-1
make OT terminal, 5-20
requirement, 5-21 K
install power cable knurled cylinder, C-16
for BAM, 5-6
for frame, 5-5, 5-6 L
for hard disk array, 5-7
label paper, B-4
for KVMS, 5-8
level cabinet
for LAN switch, 5-9
install insulation plate, 3-10
for MRS, 5-10
position cabinet, 3-10

Huawei Technologies Proprietary


i-3
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Index

lightning arrester, D-7 three-phase and five-wire, D-9


lightning protection ground, 5-16 preinstallation
lightning protector, D-8 prepare tools and meters, 2-3
line drawing template, 3-4, 3-17 pre-installation task
organize installation team, 2-1
M prepare auxiliary devices, 2-2

main distribution frame, B-6 prepare technical document, 2-1

mount angle, 4-5 primary power supply, 5-19

MRS chassis, 9-5 project service mode, 2-1


proof
N erosive gas proof, D-6
ESD-preventive requirement, D-7
N68-22 cabinet, 3-1
protection ground, 5-3
negative line bank, 5-16
protection grounding bar, 5-5
network cable
protection grounding system, 5-3
straight through network cable, 6-8
network port, 6-3
Q
O quake-proof support, A-16

optical distribution frame, B-12


R
optical fiber, B-1, B-12
OSTA, 1-1 RJ45 connector, C-8
OT terminal, 5-5 rodent-proof net, 6-4

P S
packing list, 2-6 serial port cable, 6-11
panel fastener, 4-6 server/switcher cable
percussion drill, 3-5, 3-18 display cable, 6-10
plan cabinet position keyboard cable, 6-10
determine cabinet position, 3-15 mouse cable, 6-10
drill hole, 3-18 shielded cable, C-10
mark hole, 3-15 shockproof support, A-7, A-16
plan support position shuffle pin, 7-5
determine cabinet positions, 3-2 signal cable
drill hole, 3-5 classification, 6-1
mark installation holes, 3-3 silica-gel drier, 2-9
positive line bank, 5-16 site requirement, D-1
power bus cable, 5-18 SMB connector, 6-16, C-13
power distribution cabinet, B-9 storage battery, D-6
power distribution frame subscriber cable, B-1, B-6
ALARM switch, 9-5 supervision and debugging mode, 2-2
power supply system, 5-1, D-9 supervision and service mode, 2-2
monophase three-wire, D-9 suspension mounting mode, A-7

Huawei Technologies Proprietary


i-4
Hardware Installation Manual
U-SYS SoftX3000 SoftSwitch System Index

T upward cabling, 5-17


upward cabling mode, 6-15, A-1
triangular support, A-7
UT terminal, 5-6
trunk cable, 6-14, B-1, B-3

U V
vacuum cleaner, 3-6, 3-19
universal alarm box, 8-2
unpack
W
cardboard box, 2-9
requirement, 2-6 wire bushing, 6-5

wooden crate, 2-7 wire clipper, C-2


wire stripper, C-14

i.

Huawei Technologies Proprietary


i-5

Potrebbero piacerti anche