Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
J
TransCanada
Revision
Project Project
Prepared Cp,cked by Approved/ Pages
No. ii pproved Approved Remarks
by /Date I ate Date Revised
y/Cate l)y/Date
.
- I A.\. J , I . � I A(JY),
0
�
-=--=::J._. ..rcrera � G. Makar
' " ,, (
G. Mak.a\ I' ,
1
I
'I
too0J 0
-
Issued
Approval
for
Reference Documents:
- API STD 2000, Venting Atmospheric and Low Pressure Storage Tanks
- Provincial/State & Federal Occupational Health & Safety Act and Regulations
Definitions:
Contractor The party that supplies the equipment, materials and services to
Geotechnical Engineer The party that supplies the services to confirm the determination of
hvdrotest activities.
Owner's Project
TransCanada's project manager
Manager
Test Report Final document prepared by the Contractor with data recorded
before, durina and after the test, as well as final test results.
documents.
Hydrostatic Test Final document issued by the tank Manufacturer to the Owner which
1. SCOPE
1.1 General
This document describes procedures for testing of new tanks that have been built in
accordance with the requirements of API STD 650, and testing of existing tanks that have
This document is intended to be used as a general specification across the Company for
the testing of atmospheric storage tanks. For specific project data, the Owner's
Responsible Engineer shall provide the information requested in Appendix A, at the end
of this document.
Alternative testing in accordance with API STD 650 shall be permitted only when practical
access to water is not available. The Owner's Responsible Engineer and Project Manager
2. PUR POSE
The primary purpose of the hydrostatic test for atmospheric storage tanks is to confirm the
overall integrity of the tank and particularly the integrity of the shell.
a. Confirm the toughness properties of the steel plates against brittle fracture,
b. Test the foundation for proper support of the tank, (applicable to new tank
construction),
c. Confirm that the floating roof travels freely during normal filling/emptying operation,
The hydrostatic test shall be performed in accordance with the requirements of the latest
Page 5 of 24
Specification for Tank
Rev.a
Hvdrotest
�).)
General
TransCanada
c. API STD 2000, Venting Atmospheric and Low Pressure Storage Tanks
3.2 Codes
3.3.1 Canada
Petroleum Products
Confined Spaces
4 PRE-HYDROTEST PREPARATION
4.1 Safety
The Contractor shall comply with Owner's HSE Safety Requirements, Specifically, the
a. The work areas shall be designated "fenced off" or "outside the operating plant".
These areas shall limit the mobility of personnel that will be allowed into the immediate
area surrounding the tanks during the test. Requirements for work permits shall be
b. Only personnel approved by the Contractor to perform the test and by the Owner's
off' areas during the test. All other support personnel participating in the test shall
Page 6 of 24
Specification for Tank
Rev.O
Hvdrotest
�).)
General
TransCanada
remain outside the designated areas. Personnel required to perform the test shall be
c. The Contractor shall supply all personnel with industry standard fire-retardant
d. All safety personnel (i.e. fire watch, confined space entry guards, traffic controllers,
etc.) shall be supplied by the Contractor. Such personnel shall be dedicated, qualified
e. If applicable, all personnel entering an operating plant or terminal site will require valid
H2S training (H 2 S Alive). The Contractor's Safety Program shall include an H2S
awareness component
f. All diesel engines shall be equipped with positive air shut off devices.
g. The Contractor shall develop a site tank hydrates! emergency response plan. Such
plan shall be reviewed and approved by the Owner prior to commencing with the
hydrates!.
h. The Contractor shall develop a Job Safety Analysis (JSA). Such analysis shall be
i. Since the tank area is still under construction, it is not necessary to have a complete
has not been completed prior to the test, The Contractor shall identify in the ERP
measures shall include a clear definition of the water path towards the site drainage
collection point(s), so no personnel, equipment or facilities are put at risk on the site.
j. The Contractor shall be aware of and follow confined space rules for tank entry based
Unless otherwise specified, the Owner will determine the source of water and will ensure
Sources of water include nearby rivers, lakes and related facilities. The Owner will ensure
that all required permits, agreements, schedules and logistics are in place before
The Owner will specify the test water quality. Potable water is preferred for hydro-testing;
however, this does not preclude the use of condensate, reverse osmosis water, well
Page 7 of 24
Specification for Tank
Rev.a
Hvdrotest
��
General
TransCanada
Sea or brine water may only be used if there is no other water source available. Sea or
brine water shall not be used as a test medium unless it has been approved by the
Owner. When used, the test shall be performed in such a way that the water is not in the
tank for more than 1 4 days. If water is to be in the tank for a duration that exceeds 14
days, an oxygen scavenger and a biocide must be added, as well as caustic to raise the
pH level. After the test is finished, the tank shall be emptied, completely rinsed with clean
The water temperature must be above the freezing point in order to prevent issues such
as low temperature brittle fracture and freeze damage. Issues such as suspended solids,
residuals left in the tank after emptying must be evaluated by the Owner depending on the
type and quality of the water used in the test. For carbon and low-alloy steel tanks, the
tank metal temperature during hydrostatic testing shall not be colder than the design
metal temperature.
Equipment and piping used to transfer the water from the source to the discharge point
must be adequate for the test conditions considering pump power, suction and discharge
When a l u m i n u m or stainless steel floating roofs are used, the requirements of API STD
650, H . 6 . 6 . 3 and S . 4 . 1 0 shall be complied with, in order to prevent severe pitting, cracking
or rusting.
4.3 Installation
After all lines, pumps and instruments are connected, the Owner's Representative must
authorize the system to be energized to start filling the water transfer line. At this point,
the test valves on the inlet to the tanks shall be closed so the system can be gradually
pressurized in order to confirm that there are no leaks in the water transfer line(s).
Once it has been confirmed that there are no leaks in the transfer line, the tank valve(s)
may be opened and the water transfer into the tank can commence. Flow rates shall
gradually be increased to the maximum rates and fill shall continue as indicated in Table
3.
4.4 Miscellaneous
Based on the specific needs of the project, the following activities may be performed prior
During normal project execution, internal tank coating or liner application shall be
performed after hydrostatic testing, however, if approved by the Owner, internal tank
Page 8 of 24
Specification for Tank
Rev.a
Hydrotest
((�
General
TransCanada
coating may be applied prior to hydrotest provided that the following activities are
completed:
a. The Contractor has obtained approval in writing from the Owner to perform a hydrotest
b. The tank Manufacturer has completed alternative testing to the shell portion of the
c. After the hydrotest has been completed and the tank has been drained and cleaned,
the Manufacturer will conduct a visual inspection to the coated areas to ensure that no
damage has occurred. If any repairs are necessary, they shall be completed prior to
During normal project execution, external tank painting shall only be performed after the
hydrostatic testing has been completed. If approved, however, by the Owner, external
tank painting may be applied to the tank prior to hydrotest under the following conditions:
a. The Contractor has obtained approval in writing from the Owner to perform a hydrotest
b. Only those parts of the tank that are not critical for the identification of leaks or
;. piping attached to the tank that has been previously tested ( i . e . foam piping),
;. top and outer side of pontoons on external floating roofs, provided they have been
c. Testing of the floating roof and the fixed roof is still required and shall be carried out in
Page 9 of 24
Specification for Tank
Rev.a
Hydrotest
�))
General
TransCanada
5 HYDROTEST PROCEDURE
5.1 General
Each tank to be hydrotested shall be filled with water to the lesser of the following levels:
b. To 50 mm (2 i n . ) above the weld connecting the roof plate or compression ring with
c. To a level lower than specified above when restricted by overflow slots, an internal
d. To a level of seawater producing a bottom shell hoop stress equal to that produced by
The tanks shall be inspected frequently during the filling operation, and any welded joints
above the test-water level shall be examined in accordance with any of the alternative
The test shall be conducted before permanent external piping is connected to the tank.
Attachments to the shell located at least 1 m (3 ft) above the water level, and roof
appurtenances may be welded during the filling of the tank. After completion of the hydro
Hydrostatic testing shall be performed only when ambient temperatures are above 0°C
(32°F) and/or when the tank foundation is unfrozen. However, under special
circumstances, testing may be performed under ambient temperatures below 0°C (32°F)
or when the tank foundation is frozen or partially frozen provided the following activities
are completed:
test under low temperature conditions. The engineering assessment will consider all
risks associated with low ambient temperature testing and will investigate the effect of
Page 1 0 of 24
Specification for Tank
Rev.O
Hvdrotest
(().)
General
TransCanada
Only if recommended by the engineering assessment, the Owner may authorize the
5.2 Monitoring
The water level shall be monitored by using both a flow meter(s) installed in the water
line(s) to determine the volume passing through and into the tank, and by using a
weighted tape or some other standard float and tape gauging system to be installed on
designated for thermowell connections. Caution must be exercised to prevent the water
Water level and temperature shall be monitored frequently during the test. Level and
temperature readings shall be taken and recorded at the same time as the settlement
readings are taken. Water temperature shall also be monitored and recorded during the
hold periods.
Any new tank constructed for the Owner in accordance with API STD 650 or any existing
tank that has been subject to a major alteration or repair as per the API STD 653, shall be
hydrostatically tested in accordance with the requirements of API STD 650, this
Specification and the Scope of Work developed for the specific hydrostatic test.
Alternative testing shall only be allowed when access to sufficient water is not available.
The Contractor s h a l l , at least two weeks prior to the start of the test, submit the following
c. List of equipment and instruments (i.e. pumps, flow meters, quality control equipment,
5.3.1 Settlement
a. The Owner's Responsible Engineer shall coordinate with the Geotechnical Engineer,
the Owner's Representative and the Contractor's Responsible Engineer, all aspects
Page 1 1 of 24
Specification for Tank
Rev.a
Hvdrotest
(())
General
TransCanada
b. The Geotechnical Engineer shall provide the maximum expected settlement based on
c. The Contractor shall establish and mark the locations for settlement readings as
» A permanent benchmark point to be used for test reference. Its elevation and
location shall be recorded in the test report. The permanent benchmark point and
shall be located at least 1 Y, times the tank diameter away from the tank
Diametrical Line
1 0 m ( 3 2 ft) --3>
/ Shell Settlement
Bottom Settlement
Reading Location
<E- 3 m ( 1 0 ft)
» Shell settlement reading locations shall be clearly and permanently marked on the
annular plate or the shell and shall be equally spaced around the periphery of the
Page 1 2 of 24
Specification for Tank
Rev.a
Hvdrotest
�))
General
TransCanada
Tank Diameter
N
m ft
46 to 69 1 5 0 to 225 24
69 to 99 225 to 325 32
intervals of 3 m ( 1 0 ft) on diametrical lines across the tank. The diametrical lines
Table 2.
l
Number of
Tank Diameter
Diametrical
m ft Lines
Up to 46 Up to 1 5 0 8
d. The Contractor shall measure and record shell settlement elevations and horizontal
J.. When the tank has been filled to Y. the test height (+/- 600 mm [24 in]). The water
level shall be maintained at this height for a minimum of two hours while
J.. When the tank has been filled to Y, the test height ( +/- 600 mm [24 in]). The water
level shall be maintained at this height for a minimum of two hours while
Page 1 3 of 24
Specification for Tank
Rev.a
Hydrotest
1'� General
TransCanada
� When the tank has been filled to :Y. the test height ( +/- 600 mm [24 in]). The water
level shall be maintained at this height for a minimum of two hours while
� When the tank has been filled to the maximum test height. The water level shall be
completed. Settlement readings shall be taken every 15 minutes for the first two
hours and then every hour thereafter until the end of this hold period.
e. The Contractor shall measure and record internal bottom settlement elevation
readings as follows:
f. The Contractor shall measure and record the maximum and minimum a n n u l a r space
� At the end of the 24 hour holding period with the water level at the maximum test
height. If possible, the wiper seals should not be installed prior to hydrates! in
the duration of the test for evaluation against the expected settlement indicated in the
Geotechnical Report.
Any differential settlement greater than 13 mm (1.5 in) per 10 m (32 ft) of tank
Geotechnical Engineer for further review and recommendation. Filling of the tank shall
be stopped until approval to continue testing has been given by the Geotechnical
criterion for repairs shall be in accordance with API STD 653, Appendix B.
Page 1 4 of 24
Specification for Tank
Rev.O
Hvdrotest
(('�
General
TransCanada
a. Unless otherwise specified by the tank Manufacturer and approved by the Owner, the
maximum fill and discharge rates shall be determined in accordance with Table 3
below.
)> Note: For tanks with an I F R or EFR, the maximum filling rate shall be 250 mm/hr
3
( 1 0 in/hr) or 842 m /hr (5,298 bbl/hr) until the floating roof is afloat. Thereafter, the
b. The Contractor shall remove any materials and debris from the tank before and after
the test.
c. The Contractor shall ensure that all nozzles used during the test are properly attached
to the temporary piping that has been installed to transport the test medium into/out of
the tank.
d. The Contractor shall ensure that all nozzles not used during the test are properly
e. The Contractor shall confirm that all tank accessories that are required during testing
of the tank and the floating roof, are installed and in good working condition.
Maximum Maximum
22 mm (7/8 in) and Thicker Middle Third of the Tank 300 (12) 1 , 0 1 0 (6,358)
f. Once all equipmenUinstruments are installed and all the required connections are in
place and after approval has been received from the Owner's Representative to
)> The tank Manufacturer shall confirm that there is adequate venting of the tank
Page 1 5 of 24
Specification for Tank
Rev.O
Hvdrotest
�.?)
General
TransCanada
;:. The Contractor shall confirm that the floating roof travels freely up and down the
tank and shall inspect the operation of the mechanical shoe, the rollers and seals,
as applicable.
This shall be accomplished by visually inspecting the floating roof and the seals at
each holding point while settlement readings are taken. At each inspection point,
the Contractor shall confirm that the roof is level, the seals are in their proper
position and that there are no seals, wipers, cables or rollers hanging up or
;:. At each hold point, while settlement readings are taken, the Owner's
Representative and the tank Manufacturer's Representative shall inspect all the
welds on the tank, searching for leaks, excessive deformation or areas with
unusual settlement.
h. Once the holding time at the maximum test height has expired, and after approval
from the Owner's and Manufacturer's Representatives has been received, the
Contractor may initiate tank draining activities and transfer the water to the next tank
i. Unless otherwise specified by the tank Manufacturer and approved by the Owner, the
discharge/transfer rates shall not exceed those indicated in Table 3 for the section of
;:. Note: For tanks with an IFR or EFR, when the floating roof is approaching its
j. The Contractor shall remove any sediment or debris from the tank after the test and
shall completely wash and dry all the internal surfaces of the tank, including floating
roof legs, columns, internal piping, etc. to prevent damage in the event that the
k. Wetted surfaces shall be washed with potable water if non-potable water was used for
the test and shall be completely dried. Hot air drying shall not be used. Confined
Space rules for tank entry based on 29 CFR 1910.14 b) and the Owner's safe work
I. The Contractor, as directed by the tank Manufacturer, shall replace and/or prepare all
remove the blind flanges from all nozzles and manholes, replace the gaskets with new
ones, and install blind flanges on nozzles designated as "spare" in accordance with
the tank drawings. All other nozzles designated for process use shall be left prepared
Page 1 6 of 24
Specification for Tank
Rev.O
Hvdrotest
(())
General
TransCanada
Tanks constructed with either an EFR or an IFR shall be given a floatation test in
accordance with the requirements of the API STD 650, Appendices C or H, respectively.
Unless otherwise directed by the Owner, this test is a mandatory requirement that shall be
completed even if the tank is not hydrotested. In most cases water shall be used as the
test medium, although for some type of IFRs, product can be used instead of water.
Unless the tank is not to be hydrotested, the floatation test shall be performed while the
tank is being filled with water for the hydrostatic test, as follows:
The EFR shall be given a floatation test while the tank is being filled with water. During the
test, the upper side of the roof shall be examined for leaks. The appearance of a wet spot
In order to conduct the test, the Contractor shall fill the tank to a level sufficient for the roof
to float. At this level, the filling operation shall be stopped and the Owner's Field
Representative and the tank Manufacturer's Representative will inspect all the welds on
the roof, searching for leaks, excessive deformation or areas with unusual d a m p i n g .
If any indications of leaks are found, the tank Manufacturer shall identify the problem
areas and repair them accordingly. Once the repair of all areas is finished, visual
inspection shall be carried out to confirm that no more leaks are present. Once confirmed,
The following internal floating roofs shall be given a floatation test with water:
e. Hybrid Type.
The following internal floating roofs shall be given a floatation test with water or product, at
Page 1 7 of 24
Specification for Tank
Rev.O
Hvdrotest
((�
General
TransCanada
During this test, the roof and all accessible compartments shall be checked to confirm that
they are free from leaks. The appearance of a damp spot on the upper side of the part in
During initial fill the IFR shall be checked to confirm that it travels freely to its full height.
The peripheral seal shall be checked for proper operation throughout the entire travel of
In order to conduct the test, the Contractor shall fill the tank to a level sufficient for the roof
to float. At this level, the filling operation shall be stopped and the Owner's Field
Representative and the tank Manufacturer's Representative shall inspect all the welds or
joints in the roof, searching for leaks, excessive deformation or areas with unusual
damping.
If any indications of leaks are found, the Tank Manufacturer shall identify the problem
areas and repair them accordingly. Once the repair of all areas is finished, visual
inspection shall be carried out to confirm that no more leaks are present. Once confirmed,
The tank Manufacturer shall confirm adequate venting of the tank prior to water
discharge.
A back-up pump unit complete with internal suction piping directed to the tank sump,
complete with a dedicated temporary discharge pipeline back to the water source, or a
temporary by-pass arrangement on the main fill line near the water pump, shall be set up
for emergency drain in case of a leak, foundation failure or floating roof malfunction.
Unless otherwise specified in the "Project Specific Requirements, the Owner will furnish
all necessary permits for obtaining water and for water disposal and will ensure that the
discharge point meets the conditions required by the appropriate authorities in terms of
The Contractor shall be responsible for all water analysis and testing. Water testing prior
to removing water from the source shall be completed and a water sample obtained. Prior
The Contractor shall obtain approval from the Owner or from the Owner's representative
prior to removing water from the source before hydrotesting and prior to disposal of any
Page 1 8 of 24
Specification for Tank
Rev.a
Hvdrotest
�))
General
TransCanada
6 DOCUMENTATION
All settlement measurements and hydrates! conditions, including date, source of water,
quality of water, water temperature, test pressure, holding times, maximum test level and
the test results shall be recorded in a formal test report as completed and submitted by
the Contractor within 24 hours of the test or as otherwise specified by the Owner.
The Contractor shall supply copies of the test report in accordance with the project
The Owner will maintain a copy of the test report on site for future reference, while other
copies will be filed with the project records and document control as necessary.
Page 1 9 of 24
Specification for Tank
Rev.a
Hvdrotest
��
General
TransCanada
Appendix A :
Definitions:
PROJECT NAME
LOCATION
Owner
Title:
Location:
Ph:
Email:
Title:
Location:
Ph:
Email:
Engineer
Title:
Location:
Ph:
Email:
Manufacturer
Manufacturer's Name:
Representative
Title:
Location:
Ph:
Email:
Contractor's Responsible
Engineer
Page 20 of 24
Specification for Tank
Rev.a
Hvdrotest
((�
General
TransCanada
A.1. SCOPE
General
A.2. SCHEDULE
General
Regulations
Source of Water
Page 21 of 24
Specification for Tank
Rev.a
Hvdrotest
(())
General
TransCanada
Internal Coating
External Painting
A.5. HYDROTEST P R O C E D U R E
General
Monitoring
Test Procedure
Roof
Water Disposal
Page 22 of 24
Specification for Tank
Rev.a
Hvdrotest
(('))
General
TransCanada
TRANSCANADA PIPELINES
Location: !Contract I:
lcontractor:
Tank Number:
[aate:
_!!!:!.:.....
1. Temilnal Loeat!on
Elevation
{Please COOl'O.nale 1311� test 10 m!Olflltle the frequency alld \'Q.\Jme or these di$Cha<9f5 )
m3 (bbl) ml (bbl)
1st tank to be tested
m3 \bbl) m3 (bbl)
2nd tank to be tested
ml(bbl) ml(bbl)
3rd tank to be Cested
ml(bbl)
3. Total volume ol water to be discharged?
4. Are you aware of other hydrostatic tank tests that are planned
Oo you have all the pennits In plate for use of water? YES D HO D
8. Olscharge rate:
m3(bb1)
1st tank to be emptied
m3(bbl)
2nd tank to ba emptied
m3(bbl)
3rd tank to be emp\lW
9. Do you have a\l the permits In place for discharge of water? YES O HO D
13. Does the term!nal have access to a sanitary sewer line? YES D NO D
If yes, please give the name of the utility company and name and phone number of contact person
Rrvl,J,on Hl<IOI)'
,.. Dalo I I .I
RIV. I Duct!�
°'"'�
' '
" ·-�
'
T
'"·
•
'
'
'
"
I
• '
'
' '
I I
'
I I
•
I I I I
Page 23 of 24
Specification for Tank
Rev.O
Hydrotest
�))
General
TransCanada
TRANSCANADA PIPELINES
Location: I contract#:
Rev.
1. Report No.
2. Test Pressure
3. Test Data
Test Medium
Source of Waler
Water Quality
Holding Time
Temperature
Shell • C (°F)
Water 'C('F)
4. Test Result
5. Remarks
Rovislon Hls!ory
" "
'
•
' '
•
'
Page 24 of 24