Sei sulla pagina 1di 152

STATUS OF PROJECTS

CY 2017 CONSTRUCTION PROGRAM


Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location d) Contractor d) Start Date C
(Scope of Work/Physical Target)
e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P

1 Project I.D : a) 1,000.00 a) by Contract P


Contract I.D : 17MH0008 b) 1,000.00 b) 20-Dec-16 R
Construction of Senior Citizen Building, c) c) A
Brgy. Bugso, Sen. Ninoy Aquino, Sultan Kudarat d) d) S
e) e)
f) 55 C.D f) Failure of on December 15, 2016. Re-bid scheduled on January 24, 2017.
g) 1 pr g)
2 Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0019 b) 1,000.00 b) 20-Dec-16 R
Construction of Baranggay Hall, Brgy. Poblacion, c) c) A
Sen. Ninoy Aquino, Sultan Kudarat d) d) S
e) e)
f) 55 C.D f) Failure of on December 15, 2016. Re-bid scheduled on January 24, 2017.
g) 1 pr g)
3 Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0020 b) 1,000.00 b) 20-Dec-16 R
Construction of Baranggay Hall, Brgy. Sewod, c) c) A
Sen. Ninoy Aquino, Sultan Kudarat d) d) S
e) e)
f) 55 C.D f) Failure of on December 15, 2016. Re-bid scheduled on January 24, 2017.
g) 1 pr g)
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location d) Contractor d) Start Date C
(Scope of Work/Physical Target)
e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
Page 5 of 9

21.Project I.D : a) 1,000.00 a) by Contract P


Contract I.D : 17MH0021 b) 1,000.00 b) 13-Dec-16 R
Construction of Day Care Centers, Brgy. Sitio c) c) A
Lower Alas-as,Masiag, Bagumbayan, d) JARGON CONSTRUCTION AN d) S
Sultan Kudarat e) 971,000.00 e)
f) 55 C.D f) Contract Documents on Process.
g) 1pr g)
22.Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0022 b) 1,000.00 b) 13-Dec-16 R
Construction of Day Care Centers, Brgy. Bai c) c) A
Saripinang, Bagumbayan, Sultan Kudarat d) JARGON CONSTRUCTION AN d) S
e) 971,000.00 e)
f) 55 C.D f) Contract Documents on Process.
g) 1pr g)
23.Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0023 b) 1,000.00 b) 13-Dec-16 R
Construction of Day Care Centers, Purok I c) c) A
Brgy. Biwang, Bagumbayan, Sultan Kudarat d) JARGON CONSTRUCTION AN d) S
e) 960,300.00 e)
f) 55 C.D f) Contract Documents on Process.
g) 1pr g)
24.Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0024 b) 1,000.00 b) 13-Dec-16 R
Construction of Day Care Centers, Brgy. Sta. c) c) A
Clara, Kalamansig, Sultan Kudarat d) TRI-VERT CONSTRUCTION &d) S
e) 967,558.38 e)
f) 55 C.D f) Contract Documents on Process.
g) 1pr g)
Page 6 of 9
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location d) Contractor d) Start Date C
(Scope of Work/Physical Target)
e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
25.Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0025 b) 1,000.00 b) 13-Dec-16 R
Construction of Day Care Centers, Brgy. Limulan, c) c) A
Kalamansig, Sultan Kudarat d) TRI-VERT CONSTRUCTION &d) S
e) 967,558.38 e)
f) 55 C.D f) Contract Documents on Process.
g) 1pr g)
26.Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0026 b) 1,000.00 b) 13-Dec-16 R
Construction of Day Care Centers, Brgy. c) c) A
Christianuevo, Lebak, Sultan Kudarat d) CS CONSTRUCTION & SUPPL d) S
e) 985,000.00 e)
f) 55 C.D f) Contract Documents on Process.
g) 1pr g)
27.Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0027 b) 1,000.00 b) 13-Dec-16 R
Construction of Day Care Centers, c) c) A
Brgy. Keytodac, Lebak, Sultan Kudarat d) JARGON CONSTRUCTION AN d) S
e) 980,300.00 e)
f) 55 C.D f) Contract Documents on Process.
g) 1pr g)
28.Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0028 b) 1,000.00 b) 13-Dec-16 R
Construction of Day Care Centers, Brgy. Bolebak, c) c) A
Lebak, Sultan Kudarat d) JARGON CONSTRUCTION AN d) S
e) 980,300.00 e)
f) 55 C.D f) Contract Documents on Process.
g) 1pr g)
Page 7 of 9
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location d) Contractor d) Start Date C
(Scope of Work/Physical Target)
e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
29.Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0029 b) 1,000.00 b) 20-Dec-16 R
Construction of Day Care Centers, Brgy. c) c) A
Pamantingan, Esperanza, Sultan Kudarat d) CURVE-LINE CONSTRUCTIO d) S
e) 985,922.70 e)
f) 55 C.D f) Contract Documents on Process.
g) 1pr g)
30.Project I.D : a) 1,000.00 a) by Contract P
Contract I.D : 17MH0030 b) 1,000.00 b) 20-Dec-16 R
Construction of Day Care Centers, Brgy. Gapok, c) c) A
Sen. Ninoy Aquino, Sultan Kudarat d) COFEJOK CONST. & SUPPL d) S
e) 988,000.00 e)
f) 55 C.D f) Contract Documents on Process.
g) 1pr g)
31.Project I.D : a) 5,000.00 a) by Contract P
Contract I.D : 17MH0031 b) 5,000.00 b) 8-Dec-16 R
Construction of Covered Court, Sitio. Cataan, c) c) A
Brgy. Bai Saripinang, Bagumbayan, d) PEARL CONSTRUCTION & SUd) S
Sultan Kudarat e) 4,402,200.00 e)
f) 120 C.D f) Contract Documents on Process.
g) 1pr g)
32.Project I.D : a) 5,000.00 a) by Contract P
Contract I.D : 17MH0032 b) 5,000.00 b) 8-Dec-16 R
Construction of Covered Court, Brgy. Poblacion, c) c) A
Esperanza, Sultan Kudarat d) CURVE-LINE CONSTRUCTIO d) S
e) 4,275,488.70 e)
f) 120 C.D f) Contract Documents on Process.
g) 1pr g)
Page 8 of 9
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location d) Contractor d) Start Date C
(Scope of Work/Physical Target)
e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
33.Project I.D : a) 5,000.00 a) by Contract P
Contract I.D : 17MH0033 b) 5,000.00 b) 8-Dec-16 R
Construction of Covered Court, (Municipal High c) c) A
School), Brgy. Poblacion, Palimbang, d) CS CONSTRUCTION & SUPPL d) S
Sultan Kudarat e) 4,576,750.00 e)
f) 120 C.D f) Contract Documents on Process.
g) 1pr g)
34.Project I.D : a) 5,000.00 a) by Contract P
Contract I.D : 17MH0034 b) 5,000.00 b) 8-Dec-16 R
Construction of Covered Court, Brgy. Poblacion, c) c) A
Kalamansig, Sultan Kudarat d) ROBETH GEN. MDSE. CONST.d) S
e) 4,704,525.52 e)
f) 120 C.D f) Contract Documents on Process.
g) 1pr g)
50,000.00 Page 9 of 9

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA LOIDA L. LEAL, MPA MAMINTAL T. TAHA, MPS


Engineer II Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2016 CONSTRUCTION PROGRAM
FY 2015 Carry-over - Basic Education Facilities Fund (Elementary and Junior High Schools) Batch 3
#REF!

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Year 2016
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope d) Contractor d) Start Date C
of Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO # : SR2015-06-004611 dated June 11, 2015
1. Project I.D : 1205-15-S-00065 a) 2,952.59 a) By Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 15MH0066 b) 2,952.59 b) 21-Jul-15 R 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
NEW CALINOG ES, LEBAK c) 01-Jul-15 c) 17-Aug-15 A 52.00 54.00 70.00 73.00 76.00 77.00 78.00 79.10 79.25 79.31 79.32 100.00
d) MINROCK MULTI-BUILDERS d) 24-Aug-15 S -48.00 -46.00 -30.00 -27.00 -24.00 -23.00 -22.00 -20.90 -20.75 -20.69 -20.68 -
e) 2,867,619.86 e) 21-Dec-15
f) 120 f) 21-Jan-16 Completed on December 15, 2016.
cjp g) 1sty 3cl (toilet attached) g) L. P. Santos
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

#REF! LOIDA L. LEAL, MPA MAMINTAL T. TAHA, MPS


Engineer II Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
CY 2016 Construction/ Improvement of Access Roads leading to Airports, Seaports, and Declared Tourism Destinations - To Declared Tourism
Destinations
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-04-008059 Dated: April 06, 2017
1. Project I.D : P00030282MN a) 3,942.19 a) By Contract P - - - - - - - 41.54 100.00 100.00 100.00 100.00
Contract I.D : 17MH0059 b) 3,942.19 b) 20-Jun-17 R - - - - - - - 41.54 100.00 100.00 100.00 100.00
Concreting of Jct. National Highway c) c) 31-Jul-17 A - - - - - - - 55.00 91.00 100.00
Leading to Marguez Hotspring Brgy. d) FPJ CONST. & SUPPLY d) 6-Aug-17 S - - - - - - - 13.46 -9.00 -
Marguez, Esperanza, Sultan Kudarat e) 3,567,048.65 e) 15-Sep-17
f) 41 C.D f)
Completed on October 15, 2017.
g) g)

Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA ELISEO L. OTOC, MPA MAMINTAL T. TAHA, Ph.D.


Engineer II Assistant District Engineer/ District Engineer
Concurrent Chief, Construction Section
STATUS OF PROJECTS
FY 2016 CONSTRUCTION PROGRAM
Water Supply and Sanitation for Poverty Areas and Tourism Priority Sites
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year =2018 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-03-007050 Dated: March 21, 2017
1. Project I.D : P00035151MN_CW1 a) 48,015.00 a) By Contract P 41.90 55.24 70.00 84.29 99.05 100.00 100.00 12.38 27.14
Contract I.D : 17MH0076 b) 48,015.00 b) 28-Sep-17 R 20.24 36.62 59.40 72.71 86.47 99.80 100.00 8.81 9.63
Construction of Various Water Supply, c) c) 30-Oct-17 A 33.52 40.00 56.00 68.00 83.00 95.00 3.00 20.00 20.50
Kalamansig, Sultan Kudarat d) HERVELYN INTERTRADINGd) 05-Nov-17 S 13.28 3.38 -3.40 -4.71 -3.47 -4.80 3.00 11.19 10.87
BUILDERS CORPORATION e) 02-Jun-18
e) 45,822,622.21 f) 02-Jul-18
f) 210 C.D. g) H.D. Alangca On-going, project delayed due to clearing of right of way.
g)
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2016 CONSTRUCTION PROGRAM
BASIC EDUCATIONAL FACILITIES FUND BATCH 9
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2016-04-006281 Dated: April 12, 2016
1. Project I.D : P00074352MN a) 20,887.50 a) By Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 16MH0031 b) 20,887.50 b) 19-Jul-16 R 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
New Panay National High School, Esperanza, c) c) 10-Aug-16 A 91.97 91.98 91.99 92.00 92.06 92.07
Sultan Kudarat d) FFJJ CONSTRUCTION d) 16-Aug-16 S -8.03 -8.02 -8.01 -8.00 -7.94 -7.93
e) 20,653,990.09 e) 08-Mar-17
f) 205 C.D f) 07-May-17 On-going, project completion delayed due to unfavorable weather prevailing in the area.
g) 3 Storey -15 CL g) L. P. Santos Remaining works will be subjected to liquidated damages.
2. Project I.D : P00074353MN a) 16,740.00 a) By Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 16MH0027 b) 16,740.00 b) 19-Jul-16 R 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kalamansig National High School, Kalamansig, c) c) 10-Aug-16 A 94.31 94.32 94.32 94.33 94.35 94.36
Sultan Kudarat d) FFJJ CONSTRUCTION d) 16-Aug-16 S -5.69 -5.68 -5.68 -5.67 -5.65 -5.64
e) 15,822,496.81 e) 21-Feb-17
f) 190 CD f) 23-Mar-17 On-going, project completion delayed due to unfavorable weather prevailing in the area.
g) 3 Storey -12 CL g) A.A. BRANZUELA Remaining works will be subjected to liquidated damages.
3. Project I.D : P00074356MN a) 33,480.00 a) By Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 16MH0026 b) 33,480.00 b) 19-Jul-16 R 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Lebak Legislated National High School, Lebak, c) c) 10-Aug-16 A 92.77 92.78 92.78 92.79 92.81 92.82
Sultan Kudarat d) FFJJ CONSTRUCTION d) 16-Aug-16 S -7.23 -7.22 -7.22 -7.21 -7.19 -7.18
e) 33,124,729.04 e) 21-Feb-17
f) 190 CD f) 23-Mar-17 On-going, project completion delayed due to unfavorable weather prevailing in the area.
g) 2 units,3 Storey-12CL g) A.A. BRANZUELA Remaining works will be subjected to liquidated damages.
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2016 CONSTRUCTION PROGRAM
CY 2016 Basic Educational Facilities Fund - Technical and Vocational Facilities/Workshop Building for Senior High School Batch 10
#REF!

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2016
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2016-04-006319 Dated: April 12, 2016
1. Project I.D : P00074623MN_CW1 a) 2,688.70 a) by Contract P - - - - - - 11.00 30.00 74.00 97.00 100.00 100.00
Contract I.D : 16MH0029 b) 2,688.70 b) 21-Jun-16 R - - - - - - 11.00 30.00 74.00 97.00 100.00 100.00
Kalamansig National High School, Kalamansig, c) c) 11-Jul-16 A - - - - - - 5.10 31.30 85.00 98.00 100.00
Sultan Kudarat d) Jargon Const. & Supply d) 17-Jul-16 S - - - - - - -5.90 1.30 11.00 1.00 -
e) 2,621,886.00 e) 13-Nov-16
f) 120 CD f) 13-Dec-16 Completed on November 30, 2016.
g) 1 pr g) A. A. Branzuela
2. Project I.D : P00074624MN_CW1 a) 2,688.70 a) by Contract P - - - - - - 18.24 30.60 78.63 96.05 100.00 100.00
Contract I.D : 16MH0032 b) 2,688.70 b) 21-Jun-16 R - - - - - - 18.24 27.71 36.60 79.19 96.05 100.00
New Panay National High School, Esperanza, c) c) 12-Jul-16 A - - - - - - 10.00 45.00 80.00 86.00 97.00 100.00
Sultan Kudarat d) Megaline Builders & Supply d) 18-Jul-16 S - - - - - - -8.24 17.29 43.40 6.81 0.95 -
e) 2,646,136.69 e) 14-Nov-16
f) 120 CD f) 14-Dec-16 Completed on December 9, 2016.
g) 1 pr g) L. P. Santos
5,310.59 Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA LOIDA L. LEAL, MPA MAMINTAL T. TAHA, MPS


Engineer II Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
CY 2016 Local Infrastructure Program
#REF!

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
1. Project I.D : P00054971MN a) 10,000.00 a) By Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 16MH0022 b) 10,000.00 b) 14-Jun-16 R 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Completion of Municipal Gymnasium Lebak, c) c) 1-Jul-16 A 98.00 98.70 99.00 100.00
Sultan Kudarat, 2nd LD d) JV CONSTECH d) 7-Jul-16 S -2.00 -1.30 -1.00 -
e) 9,555,644.63 e) 2-Jan-17
f) 180 f) 1-Feb-17 Completed on April 15, 2017
g) 1 pr g) R.C. Guardiano, Jr.
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA ELISEO L. OTOC, MPA MAMINTAL T. TAHA, MPS


Engineer II Assistant District Engineer/ District Engineer
Concurrent Chief, Construction Section
STATUS OF PROJECTS
FY 2016 CONSTRUCTION PROGRAM
Construction of Flood Control (Ala River Basin)
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2016-06-008736 Dated: June 24, 2016
1. Project I.D : P00022778MN_CW1 a) 40,000.00 a) by Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 16MH0045 b) 40,000.00 b) 6-Dec-16 R 100.00 100.00 100.00 100.00 100.00 100.00 95.91 100.00 100.00 100.00 100.00 100.00
Construction of Flood Control (Ala River Basin), c) c) 5-Jan-17 A 94.11 94.50 100.00 90.65 91.50 92.50 92.87 94.00 94.10
K 0+000 - K 0+200 Sec. 1 K 0+000 - K 0+798.5 d) THREE W BUILDERS, INC / d) 11-Jan-17 S -5.89 -5.50 - -5.26 -8.50 -7.50 -7.13 -6.00 -5.90
Sec. 2, Daladap, Esperanza, Sultan Kudarat ROBETH GEN. MDSE. e) 17-Jul-17
CONST. SUPPLY (JV) f) 30-Sep-17
e) 36,592,800.00 Completed on March 22, 2018.
f) 188 C.D
JL g) g) L.P Santos
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2016 CONSTRUCTION PROGRAM
National Secondary Road
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
1. Project I.D : P00005587MN a) 30,000.00 a) By Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 15MH0143 b) 30,000.00 b) 5-Jan-16 R 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Awang-Upi-Lebak-Kalamansig-Palimbang- c) c) 21-Mar-16 A 98.14 98.16 100.00 97.90 97.95 97.97 98.00 98.10 98.13
Sarangani Road (Km. 1948+486 - d) SUNSTONE CONST./ d) 27-Mar-16 S -1.86 -1.84 0.00 -2.10 -2.05 -2.03 -2.00 -1.90 -1.87
Km. 1949+870) J-ONE BUILDERS (JV) e) 22-Jul-16
e) 27,508,018.49 f) 21-Aug-16
f) 118 g) A. A. Branzuela Completed on March 22, 2018.
g) 1.37750 Km
Page 1 of 1
PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2016 CONSTRUCTION PROGRAM
Replacement of Bridges (Temporary to Permanent)..
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
1. Project I.D : P00002380MN a) 45,000.00 a) By Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 16MH0033 b) 45,000.00 b) 13-Sep-16 R 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Sebayor Br. 3 (B01146MN) along Awang-Upi- c) c) 28-Sep-16 A 95.84 95.90 95.91 95.92 95.94 95.95
Kalamansig-Palimbang-Sarangani Road d) FFJJ Construction d) 04-Oct-16 S -4.16 -4.10 -4.09 -4.08 -4.06 -4.05
(Completion) e) 36,574,450.49 e) 29-Mar-17
On-going, project completion delayed due to unfavorable weather prevailing in the area.
f) 177 f) 13-May-17
Remaining works will be subjected to liquidated damages.
g) 40 Ln.m. g) R.C. Guardiano, Jr.
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
OVER-ALL STATUS
IMPLEMENTED CARRY-OVER PROJECTS
FY 2016 Carry Over CONSTRUCTION PROGRAM
Sultan Kudarat 2nd District Engineering Office
As of June 30, 2018

PRE-CONSTRUCTION CONSTRUCTION
PROGRAM TOTAL NO.
NUMBER OF PROJECTS NO. OF PROJECTS STATUS
FUND SOURCE AMOUNT OF
(Php'000) PROJECTS COM- ON- ADVER CONTRACT ACTUAL COM- ON- PLANNED ACTUAL SLIPPAG
NYS BID NTP NYS
PLETED GOING -TIZED APPROVED % ACC PLETED GOING % TARGET % ACC E%

DPWH REGULAR INFRASTRUCTURE


Replacement of Bridges (Temporary to
63,000.00 2 2 - - 2 2 2 2 100.00 1 1 - 100.00 97.10 -2.90
Permanent)..
Road Upgrading (unpaved to paved) - National
82,800.00 3 3 - - 3 3 3 3 100.00 3 - - 100.00 100.00 -
Secondary Roads
Construction/ Improvement of Access Roads leading
to Airports, Seaports, and Declared Tourism
40,000.00 1 1 - - 1 1 1 1 100.00 1 - - 100.00 100.00 -
Destinations - To Declared Tourism Destinations

Construction of Flood Control (Ala River Basin) 40,000.00 1 1 - - 1 1 1 1 100.00 1 - - 100.00 100.00 -
Local Infrastructure Program 50,000.00 18 18 - - 18 18 18 18 100.00 18 - - 100.00 100.00 -
Construction of Rain Water Collector System
3,400.00 1 1 - - 1 1 1 1 100.00 1 - - 100.00 100.00 -
(CWRCS)
Construction of Solid Management Maaterials
152.791 1 1 - - 1 1 1 1 100.00 1 - - 100.00 100.00 -
Recovery Facilities (SM-MRF)
Construction/ Improvement of Access Roads leading
to Airports, Seaports, and Declared Tourism
3,942.188 1 1 - - 1 1 1 1 100.00 1 - - 100.00 100.00 -
Destinations - To Declared Tourism Destinations

Water Supply and Sanitation for Poverty Areas


48,015.00 1 1 - - 1 1 1 1 100.00 - 1 - 99.80 95.00 -4.80
and Tourism Priority Sites
SUB-TOTAL 331,309.98 29 29 - - 29 29 29 29 100.00 27 2 - 99.97 98.72 -1.25
DPWH OUTSIDE INFRASTRUCTURE
Farm to Market Road 50,000.00 7 7 - - 7 7 7 7 100.00 7 - - 100.00 100.00 -
Basic Educational Facilities Fund BATCH 9 95,619.63 5 5 - - 5 5 5 5 100.00 2 3 - 100.00 94.76 -5.24
BEFF - Technical and Vocational
Facilities/Workshop Building for the Senior High 5,377.40 2 2 - - 2 2 2 2 100.00 2 - - 100.00 100.00 -
School Batch 10
HFEP-Health Facilities Enhancement Program 9,300.00 5 5 - - 5 5 5 5 100.00 5 - - 100.00 100.00 -
SUB-TOTAL 160,297.03 19 19 - - 19 19 19 19 100.00 16 3 - 100.00 96.87 -3.13
TOTAL 491,607.01 48 48 - - 48 48 48 48 100.00 43 5 - 99.98 98.12 -1.86
438,207.01 Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:


CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.
Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 11)
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE


a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-14723 Dated: November 29, 2017
1. Project I.D : P00181178MN a) 2,794.73 a) By Contract P 1.55 23.28 76.85 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MHG0207 b) 2,794.73 b) 27-Dec-17 R 1.55 23.28 76.85 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Completion of School Building, c) 18-Dec-17 c) 19-Jan-18 A 8.25 45.00 80.00 95.62 100.00
Esperanza NHS, Esperanza, Sultan Kudarat d) Cofejok Const. & Supply Corp d) 25-Jan-18 S 6.70 21.72 3.15 -4.38 -
e) 2,747,805.70 e) 19-Apr-18
f) 85 C.D. f) 19-May-18 Completed on May 15, 2018.
g) 3STY12CL g) SANTOS L.P.
2,794.73 Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 10)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope d) Contractor d) Start Date C
of Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-11-014712 Dated: November 29, 2017
1. Project I.D : P00181015MN a) 2,896.56 a) By Contract P 4.73 32.03 81.88 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0290 b) 2,896.56 b) 20-Dec-17 R 4.73 32.03 81.88 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
S'Daf Panamin Primary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 37.95 78.00 95.65 98.00 98.06
Bagumbayan, Sultan Kudarat d) ALBANOR CONST d) 25-Jan-18 S 3.53 5.92 -3.88 -4.35 -2.00 -1.94
e) 2,850,168.53 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1STY2CL w/ Toilet g) COLOMA J.A.E.
2. Project I.D : P00181016MN a) 2,896.56 a) By Contract P 4.88 46.90 91.83 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0291 b) 2,896.56 b) 20-Dec-17 R 4.88 46.90 91.83 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Legodon Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 38.00 88.00 96.35 96.50 96.53
Esperanza, Sultan Kudarat d) ALBANOR CONST d) 25-Jan-18 S 3.38 -8.90 -3.83 -3.65 -3.50 -3.47
e) 2,850,168.53 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1STY2CL w/ Toilet g) GUARDIANO R.C.
3. Project I.D : P00181017MN a) 2,866.63 a) By Contract P 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0292 b) 2,866.63 b) 20-Dec-17 R 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Artemio L. Martin Elementary c) 18-Dec-17 c) 19-Jan-18 A 8.28 47.00 83.25 96.65 96.80 96.83
School, Kalamansig, d) JV CONSTECH d) 25-Jan-18 S 0.04 5.82 5.60 -3.35 -3.20 -3.17
Sultan Kudarat e) 2,802,162.10 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1STY2CL w/ Toilet g) DURUIN P.S.
4. Project I.D : P00181018MN a) 2,866.63 a) By Contract P 4.10 46.10 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0293 b) 2,866.63 b) 20-Dec-17 R 4.10 4.10 47.50 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Datu Malayat Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.28 44.00 87.00 96.65 98.20 100.00
Kalamansig, Sultan Kudarat d) JV CONSTECH d) 25-Jan-18 S 4.18 39.90 39.50 6.65 -1.80 -
e) 2,802,527.80 e) 19-Apr-18
f) 85 C.D. f) 19-May-18 Completed on June 15, 2018.
g) 1STY2CL w/ Toilet g) CADUNGOG M.P..
Page 1 of 7
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 10)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope d) Contractor d) Start Date C
of Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-11-014712 Dated: November 29, 2017
5. Project I.D : P00181019MN a) 2,866.63 a) By Contract P 7.15 45.95 86.52 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0294 b) 2,866.63 b) 20-Dec-17 R 7.15 45.95 86.52 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Don Modesto Buenaflor Sr. c) 18-Dec-17 c) 19-Jan-18 A 8.28 50.00 90.25 97.00 97.20 97.85
Elementary School, d) JV CONSTECH d) 25-Jan-18 S 1.13 4.05 3.73 -3.00 -2.80 -2.15
Kalamansig, Sultan Kudarat e) 2,803,746.80 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1STY2CL w/ Toilet g) ALANGCA H.D.
6. Project I.D : P00181020MN a) 2,986.33 a) By Contract P 4.20 46.40 89.70 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0295 b) 2,986.33 b) 20-Dec-17 R 4.20 46.40 89.70 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Datu Ito Andong Memorial c) 18-Dec-17 c) 19-Jan-18 A 8.28 8.28 86.45 97.00 97.20 97.23
Elementary School, d) JV CONSTECH d) 25-Jan-18 S 4.08 -38.12 -3.25 -3.00 -2.80 -2.77
Kalamansig, Sultan Kudarat e) 2,948,979.18 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For revision of project scheduled
f) 85 C.D. f) 19-May-18
implementation.
g) 1STY2CL w/ Toilet g) GUARDIANO R.C.
7. Project I.D : P00181021MN a) 4,278.03 a) By Contract P 4.19 25.14 63.97 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0296 b) 4,278.03 b) 20-Dec-17 R 4.19 25.14 63.97 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Sewal Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 36.45 61.00 97.00 97.20 97.25
Sen. Ninoy Aquino, Sultan Kudarat d) DALANON CONST REF SUPPL d) 25-Jan-18 S 4.07 11.31 -2.97 -3.00 -2.80 -2.75
e) 4,203,296.10 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1STY3CL w/ Toilet g) COLOMA J.A.E.
8. Project I.D : P00181022MN a) 2,896.56 a) By Contract P 5.92 33.49 83.07 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0297 b) 2,896.56 b) 20-Dec-17 R 5.92 33.49 83.07 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Lagubang Elemenary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 36.85 80.00 97.00 97.20 97.23
Sen. Ninoy Aquino, Sultan Kudarat d) DALANON CONST REF SUPPL d) 25-Jan-18 S 2.34 3.36 -3.07 -3.00 -2.80 -2.77
e) 2,845,957.37 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f) 19-May-18
damages.
g) 1STY2CL w/ Toilet g) COLOMA J.A.E.
Page 2 of 7
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 10)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope d) Contractor d) Start Date C
of Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-11-014712 Dated: November 29, 2017
9. Project I.D : P00181023MN a) 2,986.33 a) By Contract P 6.10 47.50 87.30 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0298 b) 2,986.33 b) 20-Dec-17 R 6.10 6.10 49.20 87.30 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Elem Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 36.79 84.69 92.00 93.25 100.00
Lebak, Sultan Kudarat d) BARRIST BUILDERS AND CO d) 25-Jan-18 S 2.16 30.69 35.49 4.70 -6.75 -
e) 2,900,812.16 e) 19-Apr-18
f) 85 C.D. f) 19-May-18 Completed on June 15, 2018.
g) 1STY2CL w/ Toilet g) CADUNGOG M.P..
10. Project I.D : P00181024MN a) 2,966.38 a) By Contract P 4.28 46.01 89.36 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0299 b) 2,966.38 b) 20-Dec-17 R 4.28 46.01 89.36 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Tibong-Tibong Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 45.50 86.35 96.85 97.10 100.00
Lebak, Sultan Kudarat d) JV CONSTECH d) 25-Jan-18 S 3.98 -0.51 -3.01 -3.15 -2.90 -
e) 2,926,325.08 e) 19-Apr-18
f) 85 C.D. f) Completed on June 15, 2018.
g) 1STY2CL w/ Toilet g) CADUNGOG M.P..
11. Project I.D : P00181025MN a) 2,875.11 a) By Contract P 4.98 31.25 84.12 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0300 b) 2,875.11 b) 20-Dec-17 R 4.98 31.25 84.12 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Isuko Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 31.35 75.35 96.85 97.00 97.05
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 25-Jan-18 S 3.28 0.10 -8.77 -3.15 -3.00 -2.95
e) 2,855,000.00 e) 19-Apr-18
On-going, project delayed due to peace and order problem in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1STY2CL w/ Toilet g) COLOMA J.A.E.
12. Project I.D : P00181026MN a) 2,946.43 a) By Contract P 6.22 48.34 93.87 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0301 b) 2,946.43 b) 20-Dec-17 R 6.22 48.34 93.87 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Dona Catalina Memorial Elementary Sc) 18-Dec-17 c) 19-Jan-18 A 8.26 36.81 74.35 96.85 97.00 97.05
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 25-Jan-18 S 2.04 -11.53 -19.52 -3.15 -3.00 -2.95
e) 2,931,360.00 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f) 19-May-18
damages.
g) 1STY2CL w/ Toilet g) MANGATONG, R.
Page 3 of 7
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 10)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope d) Contractor d) Start Date C
of Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-11-014712 Dated: November 29, 2017
13. Project I.D : P00181027MN a) 2,896.56 a) By Contract P 6.20 37.70 83.10 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0302 b) 2,896.56 b) 20-Dec-17 R 6.20 37.70 83.10 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Maguid Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 38.00 75.35 96.75 97.00 97.05
Palimbang, Sultan Kudarat d) ILON MULTIBUILDERS CO. d) 25-Jan-18 S 2.06 0.30 -7.75 -3.25 -3.00 -2.95
e) 2,849,221.96 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f) 19-May-18
damages.
g) 1STY2CL w/ Toilet g) GUIAMEL M.D.
14. Project I.D : P00181028MN a) 2,896.56 a) By Contract P 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0303 b) 2,896.56 b) 21-Dec-17 R 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Malisbong Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 31.45 31.45 31.45 31.45 31.45
Palimbang, Sultan Kudarat d) BAMEC DEVELOPERS d) 25-Jan-18 S 0.02 -9.73 -46.20 -68.55 -68.55 -68.55
e) 2,860,297.00 e) 19-Apr-18
f) 85 C.D. f) Recision Documents on process.
g) 1STY2CL w/ Toilet g) MANGATONG, R.
15. Project I.D : P00181029MN a) 2,896.56 a) By Contract P 5.97 46.62 86.97 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0304 b) 2,896.56 b) 21-Dec-17 R 5.97 5.97 48.44 86.97 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
St. Andrew's Mission ES - Annex, c) 18-Dec-17 c) 19-Jan-18 A 8.26 42.00 84.35 96.85 97.00 97.04
Kalamansig, Sultan Kudarat d) BARRIST BUILDERS AND CO d) 25-Jan-18 S 2.29 36.03 35.91 9.88 -3.00 -2.96
e) 2,800,764.17 e) 19-Apr-18
Project delayed due to inaccesible road leading to project site cause of bad weather prevailing in the
f) 85 C.D. f) 19-May-18
area.
g) 1STY2CL w/ Toilet g) GUARDIANO R.C.
16. Project I.D : P00181030MN a) 2,916.51 a) By Contract P 6.12 37.49 83.15 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0305 b) 2,916.51 b) 21-Dec-17 R 6.12 37.49 83.15 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Tibuhol Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 36.85 75.00 96.85 96.90 97.01
Palimbang, Sultan Kudarat d) ILON MULTIBUILDERS CO. d) 25-Jan-18 S 2.14 -0.64 -8.15 -3.15 -3.10 -2.99
e) 2,900,187.58 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f) 19-May-18
damages.
g) 1STY2CL w/ Toilet g) GUIAMEL M.D.
Page 4 of 7
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 10)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope d) Contractor d) Start Date C
of Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-11-014712 Dated: November 29, 2017
17. Project I.D : P00181031MN a) 2,926.48 a) By Contract P 5.88 33.30 83.17 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0306 b) 2,926.48 b) 21-Dec-17 R 5.88 33.30 83.17 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kisaday Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 38.65 80.35 96.75 97.00 97.11
Sen. Ninoy Aquino, Sultan Kudarat d) DALANON CONST REF SUPPL d) 25-Jan-18 S 2.38 5.35 -2.82 -3.25 -3.00 -2.89
e) 2,860,763.88 e) 19-Apr-18
On-going, project delayed due to inaccessible road leading to the jobsite. For revision of project
f) 85 C.D. f) 19-May-18
scheduled implementation.
g) 1STY2CL w/ Toilet g) COLOMA J.A.E.
18. Project I.D : P00181032MN a) 2,896.56 a) By Contract P 9.8 53.34 89.63 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0307 b) 2,896.56 b) 21-Dec-17 R 9.8 53.34 89.63 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Lifi-lifian Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 31.62 87.25 97.25 97.50 97.81
Esperanza, Sultan Kudarat d) CS CONST. & SUPPLY d) 25-Jan-18 S -1.54 -21.72 -2.38 -2.75 -2.50 -2.19
e) 2,883,791.00 e) 19-Apr-18
On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1STY2CL w/ Toilet g) SANTOS L.P.
19. Project I.D : P00181033MN a) 2,926.48 a) By Contract P 5.88 33.30 83.17 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0308 b) 2,926.48 b) 21-Dec-17 R 5.88 33.30 83.17 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Basag Elementary School - Tinalon A c) 18-Dec-17 c) 19-Jan-18 A 8.26 31.65 81.00 97.25 97.30 97.31
Sen. Ninoy Aquino, Sultan Kudarat d) DALANON CONST REF SUPPL d) 25-Jan-18 S 2.38 -1.65 -2.17 -2.75 -2.70 -2.69
e) 2,860,763.88 e) 19-Apr-18
On-going, project delayed due to inaccessible road leading to the jobsite. For revision of project
f) 85 C.D. f) 19-May-18
scheduled implementation.
g) 1STY2CL w/ Toilet g) COLOMA J.A.E.
20. Project I.D : P00181034MN a) 2,866.63 a) By Contract P 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0309 b) 2,866.63 b) 21-Dec-17 R 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Manobo Village Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 38.00 75.00 97.25 97.50 97.56
Sen. Ninoy Aquino, Sultan Kudarat d) COFEJOK CONST. & SUPPLY d) 25-Jan-18 S 0.02 -3.18 -2.65 -2.75 -2.50 -2.44
e) 2,839,446.82 e) 19-Apr-18
On-going, project delayed due to bad weather condition prevailing in the area. For imposition of
f) 85 C.D. f) 19-May-18
liquidated damages.
g) 1STY2CL w/ Toilet g) COLOMA J.A.E.
Page 5 of 7
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 10)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope d) Contractor d) Start Date C
of Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-11-014712 Dated: November 29, 2017
21. Project I.D : P00181035MN a) 2,896.56 a) By Contract P 7.98 47.05 88.96 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0310 b) 2,896.56 b) 21-Dec-17 R 7.98 47.05 88.96 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kabanalian Elementary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 35.00 86.45 97.25 98.00 100.00
Esperanza, Sultan Kudarat d) ALBANOR CONST d) 25-Jan-18 S 0.28 -12.05 -2.51 -2.75 -2.00 -
e) 2,797,523.24 e) 19-Apr-18
f) 85 C.D. f) Completed on June 20, 2018.
g) 1STY2CL w/ Toilet g) SANTOS L.P.
22. Project I.D : P00181036MN a) 2,896.56 a) By Contract P 4.10 46.60 90.10 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0311 b) 2,896.56 b) 21-Dec-17 R 4.10 46.60 90.10 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Maat Primary School, Kalamansig, c) 18-Dec-17 c) 19-Jan-18 A 8.26 45.00 88.00 97.35 98.15 100.00
Sultan Kudarat d) JV CONSTECH d) 25-Jan-18 S 4.16 -1.60 -2.10 -2.65 -1.85 -
e) 2,860,235.98 e) 19-Apr-18
f) 85 C.D. f) Completed on June 15, 2018.
g) 1STY2CL w/ Toilet g) CADUNGOG M.P..
23. Project I.D : P00181037MN a) 2,896.56 a) By Contract P 5.50 32.37 84.42 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0312 b) 2,896.56 b) 21-Dec-17 R 5.50 32.37 84.42 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Lageten Primary School, c) 18-Dec-17 c) 19-Jan-18 A 8.26 31.35 75.35 97.35 97.50 97.52
Sen. Ninoy Aquino, Sultan Kudarat d) CS CONST. & SUPPLY d) 25-Jan-18 S 2.76 -1.02 -9.07 -2.65 -2.50 -2.48
e) 2,884,296.00 e) 19-Apr-18
On-going, project delayed due to inaccessible road leading to the jobsite. For revision of project
f) 85 C.D. f) 19-May-18
scheduled implementation.
g) 1STY2CL w/ Toilet g) COLOMA J.A.E.
24. Project I.D : P00181038MN a) 2,896.56 a) By Contract P 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0313 b) 2,896.56 b) 21-Dec-17 R 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Mamansual Adbul National High Schooc) 18-Dec-17 c) 19-Jan-18 A 8.26 31.65 31.65 31.65 31.65 31.65
Palimbang Annex, Palimbang, Sultan d) BAMEC DEVELOPERS d) 25-Jan-18 S 0.02 -9.53 -46.00 -68.35 -68.35 -68.35
e) 2,860,297.00 e) 19-Apr-18
f) 85 C.D. f) Recision Documents on process.
g) 1STY2CL w/ Toilet g) GUIAMEL M.D. (MR)
Page 6 of 7
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 10)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope d) Contractor d) Start Date C
of Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-11-014712 Dated: November 29, 2017
25. Project I.D : P00181039MN a) 2,866.63 a) By Contract P 5.34 37.56 89.27 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0314 b) 2,866.63 b) 21-Dec-17 R 0.00 6.16 47.53 86.39 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Purikay National High School, c) 18-Dec-17 c) 19-Jan-18 A 9.00 36.85 57.00 92.35 98.25 98.49
Lebak, Sultan Kudarat d) ROBETH GEN. MDSE CONST. d) 25-Jan-18 S 9.00 30.69 9.47 5.96 -1.75 -1.51
e) 2,815,124.57 e) 19-Apr-18
f) 85 C.D. f) 19-May-18 On-going, for imposition of liquidated damages.
g) 1STY2CL w/ Toilet g) ALANGCA H.D.
26. Project I.D : P00181040MN a) 2,916.51 a) By Contract P 4.00 39.10 85.40 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0315 b) 2,916.51 b) 21-Dec-17 R 4.00 39.10 85.40 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Tapudi Integrated School, Lebak, c) 18-Dec-17 c) 19-Jan-18 A 8.28 45.00 87.00 98.50 100.00
Sultan Kudarat d) ROBETH GEN. MDSE CONST. d) 25-Jan-18 S 4.28 5.90 1.60 -1.50 -
e) 2,864,103.72 e) 19-Apr-18
f) 85 C.D. f) Completed on May 15, 2018.
g) 1STY2CL w/ Toilet g) GUARDIANO R.C.
76,919.86 Page 7 of 7

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
1. Project I.D : P00183543MN a) 2,866.63 a) By Contract P 10.22 47.00 92.31 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0218 b) 2,866.63 b) 5-Dec-17 R 10.22 47.00 92.31 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kapaya Elementary School, Bagumbayan c) 20-Nov-17 c) 15-Jan-18 A 13.00 41.23 78.00 96.00 96.08 100.00
Sultan Kudarat d) COFEJOK CONST & SUPPLY d) 21-Jan-18 S 2.78 -5.77 -14.31 -4.00 -3.92 -
e) 2,854,130.14 e) 15-Apr-18
f) 85 C.D f) Completed on June 15, 2018.
g) 1 stry- 2CL g) DURUIN P.S.
2. Project I.D : P00183544MN a) 4,130.05 a) By Contract P 6.46 50.25 81.95 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0219 b) 4,130.05 b) 5-Dec-17 R 6.46 50.25 81.95 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Busok Elementary School, Bagumbayan c) 20-Nov-17 c) 19-Jan-18 A 7.45 27.25 78.85 96.35 96.42 96.53
Sultan Kudarat d) DALANON CONST. REF SUPPLd) 25-Jan-18 S 0.99 -23.00 -3.10 -3.65 -3.58 -3.47
e) 4,057,900.33 e) 29-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 95 C.D. f)
damages.
g) 1 stry- 3CL g) SANTOS L.P.
3. Project I.D : P00183545MN a) 4,130.05 a) By Contract P 12.15 56.11 85.08 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0220 b) 4,130.05 b) 5-Dec-17 R 12.15 56.11 85.08 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Tuka Elementary School, Bagumbayan c) 20-Nov-17 c) 15-Jan-18 A 11.60 31.62 81.00 96.35 96.40 96.45
Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 21-Jan-18 S -0.55 -24.49 -4.08 -3.65 -3.60 -3.55
e) 3,956,143.85 e) 25-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 95 C.D. f)
damages.
g) 1 stry- 3CL g) SANTOS L.P.
4. Project I.D : P00183546MN a) 2,886.58 a) By Contract P 8.78 42.01 92.37 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0221 b) 2,886.58 b) 5-Dec-17 R 8.78 42.01 92.37 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Chua Elementary School, Bagumbayan c) 20-Nov-17 c) 15-Jan-18 A 13.00 47.00 78.00 96.35 97.00 100.00
Sultan Kudarat d) ROBETH GEN MDSE. CONST. d) 21-Jan-18 S 4.22 4.99 -14.37 -3.65 -3.00 -
e) 2,834,716.23 e) 15-Apr-18
f) 85 C.D. f) 15-May-18 Completed on June 16, 2018.
g) 1 stry- 2CL w/ toilet g) DURUIN P.S.
Page 1 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
5. Project I.D : P00183547MN a) 2,866.63 a) By Contract P 11.83 63.78 89.39 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0222 b) 2,866.63 b) 5-Dec-17 R 11.83 63.78 89.39 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Numo Elementary School, Esperanza c) 20-Nov-17 c) 15-Jan-18 A 13.00 42.00 85.00 97.00 97.02 97.11
Sultan Kudarat d) CEK CONT. & WATER SUPPL d) 21-Jan-18 S 1.17 -21.78 -4.39 -3.00 -2.98 -2.89
e) 2,810,616.71 e) 15-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1 stry- 2CL w/ toilet g) SANTOS L.P.
6. Project I.D : P00183548MN a) 2,866.63 a) By Contract P 11.91 63.86 89.41 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0223 b) 2,866.63 b) 5-Dec-17 R 11.91 63.86 89.41 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Sagasa Elementary School, Esperanza c) 20-Nov-17 c) 15-Jan-18 A 13.00 42.12 85.00 97.00 97.02 97.06
Sultan Kudarat d) CEK CONT. & WATER SUPPL d) 21-Jan-18 S 1.09 -21.74 -4.41 -3.00 -2.98 -2.94
e) 2,816,888.68 e) 15-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1 stry- 2CL w/ toilet g) SANTOS L.P.
7. Project I.D : P00183549MN a) 2,866.63 a) By Contract P 10.00 50.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0224 b) 2,866.63 b) 5-Dec-17 R 10.00 50.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Hinalaan Elementary School, Kalamansig c) 20-Nov-17 c) 15-Jan-18 A 13.20 47.00 92.00 97.00 98.55 100.00
Sultan Kudarat d) JARGON CONST. & SUPPLY d) 21-Jan-18 S 3.20 -3.00 2.00 -3.00 -1.45 -
e) 2,830,867.09 e) 15-Apr-18
f) 85 C.D. f) Completed on June 1, 2018.
g) 1 stry- 2CL w/ toilet g) GUARDIANO R.C.
8. Project I.D : P00183550MN a) 2,866.63 a) By Contract P 10.00 50.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0225 b) 2,866.63 b) 5-Dec-17 R 10.00 50.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Roquildo D. Talapian Sr. Memorial Elementaryc) 20-Nov-17 c) 15-Jan-18 A 13.00 41.00 88.00 97.00 98.20 98.27
School, Kalamansig, Sultan Kudarat d) JARGON CONST. & SUPPLY d) 21-Jan-18 S 3.00 -9.00 -2.00 -3.00 -1.80 -1.73
e) 2,830,866.99 e) 15-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1 stry- 2CL w/ toilet g) CADUNGOG M.P
Page 2 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
9. Project I.D : P00183551MN a) 2,866.63 a) By Contract P 8.80 35.66 87.79 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0226 b) 2,866.63 b) 5-Dec-17 R 8.80 35.66 87.79 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Malegdeg Elementary School, Sen. Ninoy c) 20-Nov-17 c) 15-Jan-18 A 13.00 36.15 78.00 97.00 97.10 97.16
Aquino, Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 21-Jan-18 S 4.20 0.49 -9.79 -3.00 -2.90 -2.84
e) 2,788,389.57 e) 15-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1 stry- 2CL w/ toilet g) COLOMA J.A.E.
10. Project I.D : P00183552MN a) 2,901.54 a) By Contract P 8.34 45.63 90.83 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0227 b) 2,901.54 b) 5-Dec-17 R 8.34 45.63 90.83 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Babato Elementary School, Lebak, c) 20-Nov-17 c) 19-Jan-18 A 8.45 36.45 82.00 96.00 96.09 96.14
Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 25-Jan-18 S 0.11 -9.18 -8.83 -4.00 -3.91 -3.86
e) 2,888,615.00 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1 stry- 2CL w/ toilet g) MANGATONG R.
11. Project I.D : P00183553MN a) 2,896.56 a) By Contract P 12.94 45.88 82.35 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0228 b) 2,896.56 b) 5-Dec-17 R 12.94 45.88 82.35 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bolebak Integrated School, Lebak c) 20-Nov-17 c) 15-Jan-18 A 13.00 48.77 83.00 98.00 98.10 100.00
Sultan Kudarat d) ROBETH GEN MDSE. CONST. d) 21-Jan-18 S 0.06 2.89 0.65 -2.00 -1.90 -
e) 2,844,512.06 e) 15-Apr-18
f) 85 C.D. f) Completed on June 15, 2018.
g) 1 stry- 2CL g) ALANGCA H.D.
12. Project I.D : P00183554MN a) 5,998.22 a) By Contract P 4.82 29.29 54.46 79.47 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0229 b) 5,998.22 b) 5-Dec-17 R 4.82 29.29 54.46 79.47 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Pakil Elementary School, Lebak, c) 20-Nov-17 c) 15-Jan-18 A 9.25 35.00 60.00 87.00 95.20 100.00
Sultan Kudarat d) JV CONSTECH d) 21-Jan-18 S 4.43 5.71 5.54 7.53 -4.80 -
e) 5,893,283.68 e) 20-May-18
f) 120 C.D. f) Completed on June 15, 2018.
g) 1 stry- 5CL g) ALANGCA H.D.
Page 3 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
13. Project I.D : P00183555MN a) 2,866.63 a) By Contract P 9.63 49.29 90.62 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0230 b) 2,866.63 b) 5-Dec-17 R 9.63 49.29 90.62 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Gestosani Elementary School, Lebak, c) 20-Nov-17 c) 15-Jan-18 A 13.00 52.00 92.00 98.50 99.05 100.00
Sultan Kudarat d) JV CONSTECH d) 21-Jan-18 S 3.37 2.71 1.38 -1.50 -0.95 -
e) 2,816,546.30 e) 15-Apr-18
f) 85 C.D. f) 15-May-18 Completed on June 1, 2018.
g) 1 stry- 2CL w/ toilet g) ALANGCA H.D.
14. Project I.D : P00183556MN a) 2,866.63 a) By Contract P 13.67 49.55 91.63 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0231 b) 2,866.63 b) 5-Dec-17 R 13.67 49.55 91.63 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Guintales Elementary School, Lebak, c) 20-Nov-17 c) 15-Jan-18 A 13.00 49.21 92.00 98.25 99.02 99.07
Sultan Kudarat d) DALANON CONST. REF SUPPLd) 21-Jan-18 S -0.67 -0.34 0.37 -1.75 -0.98 -0.93
e) 2,802,257.88 e) 15-Apr-18
Substantially completed, project delayed due to bad weather prevailing in the area. For imposition
f) 85 C.D. f)
of liquidated damages.
g) 1 stry- 2CL w/ toilet g) ALANGCA H.D.
15. Project I.D : P00183557MN a) 2,866.63 a) By Contract P 45.88 82.35 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0232 b) 2,866.63 b) 5-Dec-17 R 12.94 45.88 82.35 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Pasandalan Elementary SchooL, Lebak, c) 20-Nov-17 c) 15-Jan-18 A 13.50 50.00 84.00 100.00
Sultan Kudarat d) JARGON CONST. & SUPPLY d) 21-Jan-18 S 0.56 4.12 1.65 -
e) 2,643,241.64 e) 15-Apr-18
f) 85 C.D. f) Completed on April 30, 2018.
g) 1 stry- 2CL w/ toilet g) ALANGCA H.D.
16. Project I.D : P00183558MN a) 2,866.63 a) By Contract P 9.59 45.53 91.19 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0233 b) 2,866.63 b) 6-Dec-17 R 9.59 45.53 91.19 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Salaman Central Elementary School, c) 20-Nov-17 c) 15-Jan-18 A 13.50 50.00 93.00 100.00
Lebak, Sultan Kudarat d) JARGON CONST. & SUPPLY d) 21-Jan-18 S 3.91 4.47 1.81 -
e) 2,830,867.09 e) 15-Apr-18
f) 85 C.D. f) Completed on April 30, 2018.
g) 1 stry- 2CL w/ toilet g) ALANGCA H.D.
Page 4 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
17. Project I.D : P00183559MN a) 2,966.38 a) By Contract P 9.52 37.11 87.19 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0234 b) 2,966.38 b) 6-Dec-17 R 9.52 37.11 87.19 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Baluan Elementary School, Palimbang c) 20-Nov-17 c) 15-Jan-18 A 12.98 41.65 84.00 96.35 96.52 96.76
Sultan Kudarat d) DALANON CONST. REF SUPPLd) 21-Jan-18 S 3.46 4.54 -3.19 -3.65 -3.48 -3.24
e) 2,899,767.88 e) 15-Apr-18
On-going, project delayed due to bad weather condition prevailing in the area. For imposition of
f) 85 C.D. f) 15-May-18
liquidated damages.
g) 1 stry- 2CL w/ toilet g) COLOMA J.A.E.
18. Project I.D : P00183560MN a) 2,936.46 a) By Contract P 11.00 54.00 95.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0235 b) 2,936.46 b) 6-Dec-17 R 11.00 54.00 95.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Dionisio Cagadoc Sr. Memorial ES, Palimbang c) 20-Nov-17 c) 15-Jan-18 A 12.98 41.53 80.00 95.00 95.20 95.24
Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 21-Jan-18 S 1.98 -12.47 -15.00 -5.00 -4.80 -4.76
e) 2,880,433.36 e) 15-Apr-18
f) 85 C.D. f) 15-May-18 On-going, calibrated action issued to the contractor. For imposition of liquidated damages.
g) 1 stry- 2CL w/ toilet g) MANGATONG R.
19. Project I.D : P00183561MN a) 6,058.07 a) By Contract P 9.17 32.50 58.33 83.33 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0236 b) 6,058.07 b) 6-Dec-17 R 9.17 32.50 58.33 83.33 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Imam Adil Memorial Elem. School, Palimbang, c) 20-Nov-17 c) 15-Jan-18 A 9.24 22.65 55.00 79.00 90.25 90.56
Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 21-Jan-18 S 0.07 -9.85 -3.33 -4.33 -9.75 -9.44
e) 5,922,600.00 e) 20-May-18
f) 120 C.D. f) 19-Jun-18 On-going, calibrated action issued to the contractor. For revision of implementation scheduled.
g) 1stry- 5CL w/ toilet g) MANGATONG R.
20. Project I.D : P00183562MN a) 3,016.26 a) By Contract P 9.30 35.47 88.09 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0237 b) 3,016.26 b) 6-Dec-17 R 9.30 35.47 88.09 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kilbog Elementary School, Palimbang, c) 20-Nov-17 c) 15-Jan-18 A 13.00 36.00 78.00 97.00 97.04 97.08
Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 21-Jan-18 S 3.70 0.53 -10.09 -3.00 -2.96 -2.92
e) 3,000,000.00 e) 15-Apr-18
On-going, project delayed due to inaccessible road leading in the project area. For imposition of
f) 85 C.D. f) 15-May-18
liquidated damages.
g) 1 stry- 2CL w/ toilet g) COLOMA J.A.E.
Page 5 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
21. Project I.D : P00183563MN a) 6,675.15 a) By Contract P 10.95 43.42 74.76 92.05 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0238 b) 6,675.15 b) 6-Dec-17 R 10.95 43.42 74.76 92.05 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bagumbayan National High School, c) 20-Nov-17 c) 15-Jan-18 A 9.20 28.16 70.00 90.00 94.20 100.00
Bagumbayan, Sultan Kudarat d) BLIMEX CONST & SUPPLY d) 21-Jan-18 S -1.75 -15.26 -4.76 -2.05 -5.80 -
e) 6,654,419.14 e) 20-May-18
f) 120 C.D. f) Completed on June 15, 2018.
g) 1stry- 5CL w/ toilet g) SANTOS L.P.
22. Project I.D : P00183564MN a) 6,675.15 a) By Contract P 9.61 51.55 70.23 89.09 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0239 b) 6,675.15 b) 6-Dec-17 R 9.61 51.55 70.23 89.09 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bagumbayan National High School, c) 20-Nov-17 c) 15-Jan-18 A 9.45 35.00 66.00 87.00 92.40 92.52
Bagumbayan, Sultan Kudarat d) ILON MULTIBUILDERS CO. d) 21-Jan-18 S -0.16 -16.55 -4.23 -2.09 -7.60 -7.48
e) 6,552,991.94 e) 20-May-18
f) 120 C.D. f) On-going, calibrated action issued to the contractor.
g) 1 pr-2 units g) SANTOS L.P.
23. Project I.D : P00183565MN a) 5,279.23 a) By Contract P 17.19 51.81 80.13 98.23 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0240 b) 5,279.23 b) 6-Dec-17 R 17.19 51.81 80.13 98.23 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bagumbayan NHS, Bagumbayan, c) 20-Nov-17 c) 15-Jan-18 A 10.55 38.00 76.95 95.00 97.20 100.00
Sultan Kudarat d) PALMARES GEN MDSE d) 21-Jan-18 S -6.64 -13.81 -3.18 -3.23 -2.80 -
e) 5,253,022.86 e) 5-May-18
f) 105 C.D. f) Completed on June 20, 2018.
g) 1stry- 4CL w/ toilet g) SANTOS L.P.
24. Project I.D : P00183566MN a) 4,110.10 a) By Contract P 9.08 46.45 77.09 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0241 b) 4,110.10 b) 6-Dec-17 R 9.08 46.45 77.09 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kapaya National High School, Bagumbayan, c) 20-Nov-17 c) 15-Jan-18 A 11.75 41.12 78.00 100.00
Sultan Kudarat d) SOPHIA CONST & SUPPLY d) 21-Jan-18 S 2.67 -5.33 0.91 -
e) 4,084,568.42 e) 25-Apr-18
f) 95 C.D f) Completed on April 17, 2018.
g) 1stry- 3CL g) DURUIN P.S.
Page 6 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
25. Project I.D : P00183567MN a) 2,866.63 a) By Contract P 8.84 42.30 92.32 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0242 b) 2,866.63 b) 6-Dec-17 R 8.84 42.30 92.32 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Masiag National High School - Bagumbayan c) 20-Nov-17 c) 15-Jan-18 A 13.00 46.00 78.00 96.35 96.38 97.02
Annex, Bagumbayan, Sultan Kudarat d) ROBETH GEN MDSE. CONST. d) 21-Jan-18 S 4.16 3.70 -14.32 -3.65 -3.62 -2.98
e) 2,815,124.57 e) 15-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D f)
damages.
g) 1stry- 2CL g) DURUIN P.S.
26. Project I.D : P00183568MN a) 5,259.28 a) By Contract P 15.81 45.32 79.55 98.37 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0262 b) 5,259.28 b) 11-Dec-17 R 15.81 45.32 79.55 98.37 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bai Saripinang National High School, c) 20-Nov-17 c) 16-Jan-18 A 9.85 38.00 75.00 96.00 97.05 100.00
Bagumbayan, Sultan Kudarat d) ROBETH GEN MDSE. CONST. d) 22-Jan-18 S -5.96 -7.32 -4.55 -2.37 -2.95 -
e) 5,203,919.30 e) 6-May-18
f) 105 C.D. f) Completed on June 20, 2018.
g) 1stry- 4CL g) SANTOS L.P.
27. Project I.D : P00183569MN a) 2,886.58 a) By Contract P 12.48 63.42 91.21 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0263 b) 2,886.58 b) 12-Dec-17 R 0.00 10.44 65.02 91.21 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bai Saripinang NHS, Bagumbayan, c) 20-Nov-17 c) 16-Jan-18 A 12.00 35.00 83.00 96.00 96.25 96.57
Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 22-Jan-18 S 12.00 24.56 17.98 4.79 -3.75 -3.43
e) 2,792,966.41 e) 16-Apr-18
On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of
f) 85 C.D f) 16-May-18
liquidated damages.
g) 1 stry- 2CL w/ toilet g) SANTOS L.P.
28. Project I.D : P00183570MN a) 2,866.63 a) By Contract P 9.06 44.24 91.04 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0264 b) 2,866.63 b) 12-Dec-17 R 9.06 44.24 91.04 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
E. Arcano Memorial, National High School, c) 20-Nov-17 c) 16-Jan-18 A 12.00 50.00 92.00 98.00 98.55 100.00
Lebak, Sultan Kudarat d) JARGON CONST. & SUPPLY d) 22-Jan-18 S 2.94 5.76 0.96 -2.00 -1.45 -
e) 2,830,866.99 e) 16-Apr-18
f) 85 C.D f) 1-May-18 Completed on June 18, 2018.
g) 1 stry- 2CL g) ALANGCA H.D.
Page 7 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
29. Project I.D : P00183571MN a) 3,269.15 a) By Contract P 3.92 21.86 59.64 91.66 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0265 b) 3,269.15 b) 12-Dec-17 R 3.92 21.86 59.64 91.66 100.00 100.00 100.00 100.00 100.00 100.00 100.00
E. Arcano Memorial, National High School, c) 20-Nov-17 c) 16-Jan-18 A 9.95 40.00 60.00 95.00 98.03 100.00
Lebak, Sultan Kudarat d) JARGON CONST. & SUPPLY d) 22-Jan-18 S 6.03 18.14 0.36 3.34 -1.97 -
e) 3,223,244.23 e) 06-May-18
f) 105 C.D. f) 21-May-18 Completed on June 18, 2018.
g) 1 pr g) ALANGCA H.D.
30. Project I.D : P00183572MN a) 2,886.58 a) By Contract P 13.35 60.19 91.03 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0266 b) 2,886.58 b) 12-Dec-17 R 13.35 60.19 91.03 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Busok National High School, Bagumbayan, c) 20-Nov-17 c) 16-Jan-18 A 12.00 35.00 87.00 97.00 97.35 97.41
Sultan Kudarat d) DALANON CONST. REF SUPPLd) 22-Jan-18 S -1.35 -25.19 -4.03 -3.00 -2.65 -2.59
e) 2,821,759.88 e) 16-Apr-18
On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of
f) 85 C.D f)
liquidated damages.
g) 1stry- 2CL g) SANTOS L.P.
31. Project I.D : P00183573MN a) 6,695.10 a) By Contract P 8.53 46.41 75.01 92.42 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0267 b) 6,695.10 b) 12-Dec-17 R 8.53 46.41 75.01 92.42 97.83 100.00 100.00 100.00 100.00 100.00 100.00
Busok National High School, Bagumbayan, c) 20-Nov-17 c) 16-Jan-18 A 8.50 32.00 71.00 90.00 95.25 95.62
Sultan Kudarat d) FPJ CONST & SUPPLY d) 22-Jan-18 S -0.03 -14.41 -4.01 -2.42 -2.58 -4.38
e) 6,610,764.66 e) 21-May-18
f) 120 C.D. f) On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of
g) 1stry- 5CL g) SANTOS L.P. liquidated damages.
32. Project I.D : P00183574MN a) 3,283.84 a) By Contract P 8.41 50.37 71.44 97.56 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0268 b) 3,283.84 b) 12-Dec-17 R 0.00 8.41 55.47 71.44 97.81 100.00 100.00 100.00 100.00 100.00 100.00
Busok National High School, Bagumbayan, c) 20-Nov-17 c) 16-Jan-18 A 9.75 26.32 67.00 95.00 98.00 100.00
Sultan Kudarat d) SOPHIA CONST & SUPPLY d) 22-Jan-18 S 9.75 17.91 11.53 23.56 0.19 -
e) 3,200,648.82 e) 06-May-18
f) 105 C.D. f) 05-Jun-18 Completed on June 5, 2018.
g) 1 pr g) SANTOS L.P.
Page 8 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
33. Project I.D : P00183575MN a) 13,055.89 a) By Contract P 9.77 45.63 71.22 96.28 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0269 b) 13,055.89 b) 12-Dec-17 R 0.00 7.83 46.55 71.22 96.47 100.00 100.00 100.00 100.00 100.00 100.00
Esperanza National High School, Esperanza, c) 20-Nov-17 c) 16-Jan-18 A 9.75 32.00 70.00 93.00 96.50 96.62
Sultan Kudarat d) DALANON CONST. REF SUPPLd) 22-Jan-18 S 9.75 24.17 23.45 21.78 0.03 -3.38
e) 12,827,825.68 e) 06-May-18
f) 105 C.D. f) 05-Jun-18 On-going, for imposition of liquidated damages.
g) 1 pr g) SANTOS L.P.
34 Project I.D : P00183576MN a) 3,263.89 a) By Contract P 7.00 32.67 59.87 91.22 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0270 b) 3,263.89 b) 12-Dec-17 R 7.00 32.67 59.87 91.22 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kalamansig National High School, Kalamansig c) 20-Nov-17 c) 16-Jan-18 A 9.65 38.26 62.00 93.00 98.12 100.00
Sultan Kudarat d) ISULAN ECT CONST & GEN Md) 22-Jan-18 S 2.65 5.59 2.13 1.78 -1.88 -
e) 3,158,038.67 e) 06-May-18
f) 105 C.D. f) 21-May-18 Completed on June 16, 2018.
g) 1 pr g) ALANGCA H.D.
35. Project I.D : P00183577MN a) 4,130.05 a) By Contract P 10.53 40.00 72.63 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0271 b) 4,130.05 b) 12-Dec-17 R 10.53 40.00 72.63 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Sangay National High School, Kalamansig, c) 20-Nov-17 c) 16-Jan-18 A 10.75 42.00 74.00 98.00 98.22 98.23
Sultan Kudarat d) JV CONSTECH d) 22-Jan-18 S 0.22 2.00 1.37 -2.00 -1.78 -1.77
e) 4,070,274.45 e) 26-Apr-18
f) 95 C.D f) On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
g) 1 stry- 3CL g) GUARDIANO R.C.
damages.
36. Project I.D : P00183578MN a) 3,315.42 a) By Contract P 3.41 31.41 65.71 96.37 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0272 b) 3,315.42 b) 12-Dec-17 R 0.00 2.00 33.00 75.00 96.00 100.00 100.00 100.00 100.00 100.00 100.00
Sangay National High School, Kalamansig, c) 20-Nov-17 c) 16-Jan-18 A 9.65 38.00 68.00 92.00 96.20 96.51
Sultan Kudarat d) JV CONSTECH d) 22-Jan-18 S 9.65 36.00 35.00 17.00 0.20 -3.49
e) 3,278,316.61 e) 06-May-18
f) 105 C.D. f) 05-Jun-18 On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
g) 1 pr g) GUARDIANO R.C.
damages.
Page 9 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
37. Project I.D : P00183579MN a) 2,926.48 a) By Contract P 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0273 b) 2,926.48 b) 12-Dec-17 R 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Datu Wasay National High School, c) 20-Nov-17 c) 19-Jan-18 A 8.50 32.00 74.00 96.35 96.38 96.40
Kalamansig, Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 25-Jan-18 S 0.26 -9.18 -3.65 -3.65 -3.62 -3.60
e) 2,869,435.62 e) 19-Apr-18
f) 85 C.D. f) On-going, project delayed due to peace and order problem in the area. For imposition of liquidated
g) 1stry - 2CL g) COLOMA J.A.E.
damages.
38. Project I.D : P00183580MN a) 3,397.42 a) By Contract P 4.14 18.34 47.86 91.88 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0274 b) 3,397.42 b) 12-Dec-17 R 4.14 18.34 47.86 91.88 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Datu Wasay National High School, c) 20-Nov-17 c) 19-Jan-18 A 6.75 23.88 58.00 92.00 92.05 92.07
Kalamansig, Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 25-Jan-18 S 2.61 5.54 10.14 0.12 -7.95 -7.93
e) 3,361,389.13 e) 09-May-18
f) 105 C.D. f) On-going, calibrated action issued to the contractor. For imposition of liquidated damages.
g) 1 pr g) COLOMA J.A.E.
39. Project I.D : P00183581MN a) 2,946.43 a) By Contract P 11.76 44.71 81.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0275 b) 2,946.43 b) 12-Dec-17 R 11.76 44.71 81.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Langgal National High School, SNA, c) 20-Nov-17 c) 16-Jan-18 A 11.85 40.00 78.00 94.25 96.10 96.16
Sultan Kudarat d) ROBETH GEN MDSE. CONST. d) 22-Jan-18 S 0.09 -4.71 -3.18 -5.75 -3.90 -3.84
e) 2,843,252.24 e) 16-Apr-18
f) 85 C.D. f) 16-May-18 On-going, project delayed due to inaccessible road leading to the jobsite. For revision of project
g) 1stry - 2CL g) COLOMA J.A.E.
scheduled implementation.
40. Project I.D : P00183582MN a) 3,848.04 a) By Contract P 10.97 29.72 60.10 94.46 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0276 b) 3,848.04 b) 12-Dec-17 R 10.97 29.72 60.10 94.46 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Langgal National High School, SNA, c) 20-Nov-17 c) 16-Jan-18 A 9.65 26.45 62.00 92.35 92.40 92.47
Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 22-Jan-18 S -1.32 -3.27 1.90 -2.11 -7.60 -7.53
e) 3,780,809.11 e) 06-May-18
f) 105 C.D. f) 05-Jun-18 On-going, project delayed due to inaccessible road leading to the jobsite. For revision of project
g) 1 pr g) COLOMA J.A.E.
scheduled implementation.
Page 10 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
41. Project I.D : P00183583MN a) 6,695.10 a) By Contract P 9.52 36.19 65.71 94.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0277 b) 6,695.10 b) 12-Dec-17 R 9.52 36.19 65.71 94.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Gapok National High School- Langgal Annex, c) 20-Nov-17 c) 16-Jan-18 A 9.65 31.78 62.00 95.00 95.05 95.08
SNA, Sultan Kudarat d) CURVELINE CONSTRUCTION d) 22-Jan-18 S 0.13 -4.41 -3.71 0.71 -4.95 -4.92
e) 6,646,636.92 e) 6-May-18
f) 120 C.D. f) On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
g) 1stry - 5cl g) DURUIN P.S.
damages.
42. Project I.D : P00183584MN a) 3,317.61 a) By Contract P 2.20 22.64 51.32 91.97 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0278 b) 3,317.61 b) 13-Dec-17 R 2.20 22.64 51.32 91.97 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Gapok National High School- Langgal Annex, c) 20-Nov-17 c) 19-Jan-18 A 6.70 29.41 47.00 95.00 95.05 95.10
SNA, Sultan Kudarat d) ROBETH GEN MDSE. CONST. d) 25-Jan-18 S 4.50 6.77 -4.32 3.03 -4.95 -4.90
e) 3,257,999.27 e) 9-May-18
f) 105 C.D. f) On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
g) 1 pr g) DURUIN P.S.
damages.
43. Project I.D : P00183585MN a) 4,150.00 a) By Contract P 7.37 36.84 69.47 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0279 b) 4,150.00 b) 13-Dec-17 R 2.61 10.39 32.53 84.11 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Senator Ninoy Aquino National High School, c) 20-Nov-17 c) 19-Jan-18 A 7.45 37.00 71.00 95.65 100.00
SNA, Sultan Kudarat d) ISULAN ECT CONST & GEN Md) 25-Jan-18 S 4.84 26.61 38.47 11.54 -
e) 4,134,595.78 e) 29-Apr-18
f) 95 C.D f) 19-May-18 Completed on May 15, 2018.
g) 1 stry- 3CL g) COLOMA J.A.E.
44. Project I.D : P00183586MN a) 6,715.05 a) By Contract P 6.67 33.33 62.86 91.43 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0280 b) 6,715.05 b) 13-Dec-17 R 2.89 16.83 33.65 67.74 84.43 100.00 100.00 100.00 100.00 100.00 100.00
Senator Ninoy Aquino National High School, c) 20-Nov-17 c) 19-Jan-18 A 6.72 34.25 64.00 93.00 100.00
SNA, Sultan Kudarat d) ISULAN ECT CONST & GEN Md) 25-Jan-18 S 3.83 17.42 30.35 25.26 15.57
e) 6,693,219.94 e) 9-May-18
f) 105 C.D. f) 29-May-18 Completed on May 15, 2018.
g) 1 pr g) COLOMA J.A.E.
Page 11 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
45. Project I.D : P00183587MN a) 2,866.63 a) By Contract P 5.07 41.84 88.11 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0281 b) 2,866.63 b) 13-Dec-17 R 0.00 2.96 43.57 88.11 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Lebak National High School, c) 20-Nov-17 c) 19-Jan-18 A 8.35 32.00 84.00 90.25 95.10 95.17
Lebak, Sultan Kudarat d) JARGON CONST. & SUPPLY d) 25-Jan-18 S 8.35 29.04 40.43 2.14 -4.90 -4.83
e) 2,830,866.99 e) 19-Apr-18
f) 85 C.D. f) 19-May-18 On-going, project delayed due to demolition of exisitng building.
g) 1stry - 2CL g) GUARDIANO R.C.
46. Project I.D : P00183588MN a) 3,263.97 a) By Contract P 4.00 31.30 74.60 92.30 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0282 b) 3,263.97 b) 13-Dec-17 R 4.00 31.30 74.60 92.30 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Lebak National High School, c) 20-Nov-17 c) 19-Jan-18 A 6.70 23.68 70.00 93.00 95.25 95.30
Lebak, Sultan Kudarat d) DALANON CONST. REF SUPPLd) 25-Jan-18 S 2.70 -7.62 -4.60 0.70 -4.75 -4.70
e) 3,222,446.26 e) 09-May-18
f) 105 C.D. f) On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
g) 1 pr g) GUARDIANO R.C.
damages.
47. Project I.D : P00183589MN a) 2,926.48 a) By Contract P 5.10 43.20 84.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0283 b) 2,926.48 b) 13-Dec-17 R 5.10 43.20 84.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Keytodac National High School, c) 20-Nov-17 c) 19-Jan-18 A 8.27 36.49 81.00 95.65 95.72 95.77
Lebak, Sultan Kudarat d) BARRIST BUILDERS & SUPPL d) 25-Jan-18 S 3.17 -6.71 -3.50 -4.35 -4.28 -4.23
e) 2,855,023.48 e) 19-Apr-18
f) 85 C.D. f) On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of
g) 1 stry- 2CL g) GUARDIANO R.C.
liquidated damages.
48. Project I.D : P00183590MN a) 6,735.00 a) By Contract P 2.30 35.30 69.60 96.10 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0284 b) 6,735.00 b) 13-Dec-17 R 2.30 35.30 69.60 96.10 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Keytodac National High School, c) 20-Nov-17 c) 19-Jan-18 A 6.70 28.63 67.85 92.12 95.22 95.26
Lebak, Sultan Kudarat d) BARRIST BUILDERS & SUPPL d) 25-Jan-18 S 4.40 -6.67 -1.75 -3.98 -4.78 -4.74
e) 6,616,302.71 e) 09-May-18
f) 105 C.D. f) On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of
g) 2 pr g) GUARDIANO R.C.
liquidated damages.
Page 12 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
49. Project I.D : P00183591MN a) 5,299.18 a) By Contract P 2.20 27.30 70.30 94.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0285 b) 5,299.18 b) 13-Dec-17 R 2.20 27.30 70.30 94.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Milbuk National High School, Palimbang c) 20-Nov-17 c) 19-Jan-18 A 6.70 28.96 58.00 88.00 95.32 95.82
Sultan Kudarat d) CA BETALAC CONST & GEN d) 25-Jan-18 S 4.50 1.66 -12.30 -6.50 -4.68 -4.18
e) 4,981,782.43 e) 09-May-18
f) 105 C.D. f) 08-Jun-18 On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
g) 1stry- 4CL g) GUIAMEL M.D.
damages.
50. Project I.D : P00183592MN a) 6,715.22 a) By Contract P 3.00 32.00 71.70 91.20 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0286 b) 6,715.22 b) 13-Dec-17 R 3.00 32.00 71.70 91.20 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Milbuk National High School, Palimbang c) 20-Nov-17 c) 19-Jan-18 A 6.70 29.00 58.00 88.25 90.20 90.25
Sultan Kudarat d) CEK CONST & SUPPLY d) 25-Jan-18 S 3.70 -3.00 -13.70 -2.95 -9.80 -9.75
e) 6,621,723.52 e) 09-May-18
f) 105 C.D. f) 08-Jun-18 On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
g) 1 pr g) GUIAMEL M.D.
damages.
51. Project I.D : P00183593MN a) 5,299.18 a) By Contract P 3.91 20.50 47.74 94.59 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0243 b) 5,299.18 b) 06-Dec-17 R 3.91 20.50 47.74 94.59 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Baluan Senior High School, Palimbang c) 20-Nov-17 c) 15-Jan-18 A 10.50 33.15 44.00 92.65 96.12 96.16
Sultan Kudarat d) JV CONSTECH d) 21-Jan-18 S 6.59 12.65 -3.74 -1.94 -3.88 -3.84
e) 5,206,087.22 e) 05-May-18
f) 105 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of
g) 1stry- 4CL g) COLOMA J.A.E.
liquidated damages.
52. Project I.D : P00183594MN a) 6,778.38 a) By Contract P 12.94 45.88 82.35 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0244 b) 6,778.38 b) 06-Dec-17 R 12.94 45.88 82.35 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Baluan Senior High School, Palimbang c) 20-Nov-17 c) 15-Jan-18 A 13.00 42.65 78.00 95.85 95.90 95.96
Sultan Kudarat d) COFEJOK CONST & SUPPLY d) 21-Jan-18 S 0.06 -3.23 -4.35 -4.15 -4.10 -4.04
e) 6,755,796.60 e) 15-Apr-18
f) 85 C.D. f) 15-May-18 On-going, project delayed due to bad weather condition prevailing in the area. For imposition of
g) 1 pr g) COLOMA J.A.E.
liquidated damages.
Page 13 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
53. Project I.D : P00183595MN a) 5,259.28 a) By Contract P 12.48 50.22 72.62 95.56 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0245 b) 5,259.28 b) 6-Dec-17 R 12.48 50.22 72.62 95.56 100.00 100.00 100.00 100.00 100.00 100.00 100.00
New Panay National High School, c) 20-Nov-17 c) 15-Jan-18 A 10.62 32.32 69.85 93.00 96.20 100.00
Esperanza, Sultan Kudarat d) ISULAN ECT CONST & GEN Md) 21-Jan-18 S -1.86 -17.90 -2.77 -2.56 -3.80 -
e) 5,088,714.58 e) 5-May-18
f) 105 C.D. f) Completed on June 20, 2018.
g) 1stry- 4CL g) SANTOS L.P.
54. Project I.D : P00183596MN a) 6,197.72 a) By Contract P 8.33 31.67 57.50 82.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0246 b) 6,197.72 b) 6-Dec-17 R 8.33 31.67 57.50 82.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Palimbang National High School, c) 20-Nov-17 c) 16-Jan-18 A 8.50 32.00 55.00 80.00 95.25 95.51
Palimbang, Sultan Kudarat d) ILON MULTIBUILDERS CO. d) 22-Jan-18 S 0.17 0.33 -2.50 -2.50 -4.75 -4.49
e) 6,162,269.24 e) 21-May-18
f) 120 C.D. f)
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
g) 1stry- 5CL w/ toilet g) MANGATONG R.
55. Project I.D : P00183597MN a) 2,906.53 a) By Contract P 9.50 41.60 87.40 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0247 b) 2,906.53 b) 6-Dec-17 R 9.50 41.60 87.40 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Palimbang National High School, c) 20-Nov-17 c) 16-Jan-18 A 11.80 45.00 77.00 96.50 96.70 96.75
Palimbang, Sultan Kudarat d) ILON MULTIBUILDERS CO. d) 22-Jan-18 S 2.30 3.40 -10.40 -3.50 -3.30 -3.25
e) 2,570,640.96 e) 16-Apr-18
f) 85 C.D f) 16-May-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
g) 1 stry- 2CL w/ toilet g) MANGATONG R.
56. Project I.D : P00183598MN a) 5,299.18 a) By Contract P 9.52 36.19 65.71 94.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0248 b) 5,299.18 b) 11-Dec-17 R 9.52 36.19 65.71 94.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Palimbang National High School, c) 20-Nov-17 c) 16-Jan-18 A 9.65 36.50 62.00 91.00 92.00 92.10
Palimbang, Sultan Kudarat d) ILON MULTIBUILDERS CO. d) 22-Jan-18 S 0.13 0.31 -3.71 -3.29 -8.00 -7.90
e) 5,181,429.09 e) 6-May-18
f) 105 C.D. f) 5-Jun-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
g) 1stry- 4CL g) GUIAMEL M.D.
Page 14 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
57. Project I.D : P00183599MN a) 10,068.66 a) By Contract P 6.67 33.33 62.86 91.43 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0249 b) 10,068.66 b) 11-Dec-17 R 6.67 33.33 62.86 91.43 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Palimbang National High School, c) 20-Nov-17 c) 19-Jan-18 A 6.85 29.33 60.00 88.00 90.65 90.75
Palimbang, Sultan Kudarat d) ILON MULTIBUILDERS CO. d) 25-Jan-18 S 0.18 -4.00 -2.86 -3.43 -9.35 -9.25
e) 9,083,207.17 e) 9-May-18
f) 105 C.D. f) 8-Jun-18 On-going, calibrated action issued to the contractor. For imposition of liquidated damages.
g) 1 pr g) MANGATONG R.
58. Project I.D : P00183600MN a) 2,866.63 a) By Contract P 8.21 44.16 90.09 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0250 b) 2,866.63 b) 11-Dec-17 R 8.21 44.16 90.09 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Salabaca National High School, Esperanza, c) 20-Nov-17 c) 19-Jan-18 A 8.26 37.25 86.95 96.00 97.05 100.00
Sultan Kudarat d) ISULAN ECT CONST & GEN Md) 25-Jan-18 S 0.05 -6.91 -3.14 -4.00 -2.95 -
e) 2,801,446.82 e) 19-Apr-18
f) 85 C.D. f) Completed on June 15, 2018.
g) 1stry - 2CL g) SANTOS L.P.
59. Project I.D : P00183601MN a) 2,866.63 a) By Contract P 7.30 45.97 86.39 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0251 b) 2,866.63 b) 11-Dec-17 R 0.00 6.16 47.53 86.39 96.62 100.00 100.00 100.00 100.00 100.00 100.00
Sta. Clara National High School, c) 20-Nov-17 c) 19-Jan-18 A 9.00 9.00 48.00 90.00 94.00 95.21
Kalamansig, Sultan Kudarat d) JV CONSTECH d) 25-Jan-18 S 9.00 2.84 0.47 3.61 -2.62 -4.79
e) 2,813,620.30 e) 19-Apr-18
f) 85 C.D. f) 3-Jun-18 On-going, project delayed due to bad weather prevailing in the area.
g) 1stry - 2CL g) ALANGCA H.D.
60. Project I.D : P00183602MN a) 3,263.89 a) By Contract P 4.55 23.49 61.89 95.89 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0252 b) 3,263.89 b) 11-Dec-17 R 0.00 2.95 24.38 61.85 96.62 98.31 100.00 100.00 100.00 100.00 100.00
Sta. Clara National High School, c) 20-Nov-17 c) 16-Jan-18 A 10.00 10.00 26.85 75.00 92.00 93.78
Kalamansig, Sultan Kudarat d) JV CONSTECH d) 22-Jan-18 S 10.00 7.05 2.47 13.15 -4.62 -4.53
e) 3,059,217.00 e) 6-May-18
f) 105 C.D. f) 20-Jun-18
On-going, project delayed due to bad weather prevailing in the area. For revision of
implementation scheduled due to variation order.
g) 1 pr g) ALANGCA H.D.
Page 15 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
61. Project I.D : P00183603MN a) 2,886.58 a) By Contract P 11.76 44.71 81.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0253 b) 2,886.58 b) 11-Dec-17 R 11.76 44.71 81.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Sewod National High School - Langgal Annex c) 20-Nov-17 c) 16-Jan-18 A 11.80 35.00 78.00 96.50 96.70 96.67
SNA, Sultan Kudarat d) CEK CONST & SUPPLY d) 22-Jan-18 S 0.04 -9.71 -3.18 -3.50 -3.30 -3.33
e) 2,847,929.97 e) 16-Apr-18
f) 85 C.D. f)
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
g) 1stry - 2CL g) DURUIN P.S.
62. Project I.D : P00183604MN a) 3,317.61 a) By Contract P 6.88 32.41 65.68 95.49 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0254 b) 3,317.61 b) 11-Dec-17 R 6.88 32.41 65.68 95.49 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Sewod National High School - Langgal Annex c) 20-Nov-17 c) 16-Jan-18 A 9.65 32.00 62.00 92.00 93.00 93.12
SNA, Sultan Kudarat d) CURVELINE CONSTRUCTION d) 22-Jan-18 S 2.77 -0.41 -3.68 -3.49 -7.00 -6.88
e) 3,209,979.90 e) 6-May-18
f) 105 C.D. f) On-going, calibrated action issued to the contractor. For imposition of liquidated damages.
g) 1 pr g) DURUIN P.S.
63. Project I.D : P00183605MN a) 5,733.26 a) By Contract P 9.32 56.24 92.01 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0255 b) 5,733.26 b) 11-Dec-17 R 9.32 56.24 92.01 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Biwang NHS- Bagumbayan Annex, c) 20-Nov-17 c) 19-Jan-18 A 12.00 47.00 93.00 97.65 100.00
Bagumbayan, Sultan Kudarat d) ROBETH GEN MDSE. CONST. d) 25-Jan-18 S 2.68 -9.24 0.99 -2.35 -
e) 5,630,252.89 e) 19-Apr-18
f) 85 C.D. f) Completed on May 15, 2018.
g) 2 Unit - 1stry - 2CL w/ tg) SANTOS L.P.
64. Project I.D : P00183606MN a) 4,218.18 a) By Contract P 10.53 40.00 72.63 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0256 b) 4,218.18 b) 11-Dec-17 R 10.53 40.00 72.63 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Biwang NHS- Bagumbayan Annex, c) 20-Nov-17 c) 16-Jan-18 A 10.65 35.95 68.00 96.35 100.00
Bagumbayan, Sultan Kudarat d) ISULAN ECT CONST & GEN Md) 22-Jan-18 S 0.12 -4.05 -4.63 -3.65 -
e) 4,122,605.69 e) 26-Apr-18
f) 95 C.D f) Completed on May 15, 2018.
g) 1stry - 3CL w/ toilet g) SANTOS L.P.
Page 16 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
65. Project I.D : P00183607MN a) 6,675.15 a) By Contract P 10.04 41.54 74.68 91.92 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0257 b) 6,675.15 b) 11-Dec-17 R 10.04 41.54 74.68 91.92 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Biwang NHS- Bagumbayan Annex, c) 20-Nov-17 c) 16-Jan-18 A 8.45 26.87 70.00 92.00 98.20 100.00
Bagumbayan, Sultan Kudarat d) BLIMEX CONST & SUPPLY d) 22-Jan-18 S -1.59 -14.67 -4.68 0.08 -1.80 -
e) 6,654,337.94 e) 21-May-18
f) 120 C.D. f) Completed on June 15, 2018.
g) 1 stry- 5CL g) SANTOS L.P.
66. Project I.D : P00183608MN a) 3,263.89 a) By Contract P 7.06 38.88 70.67 96.66 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0258 b) 3,263.89 b) 11-Dec-17 R 7.06 38.88 70.67 96.66 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Biwang NHS- Bagumbayan Annex, c) 20-Nov-17 c) 19-Jan-18 A 10.00 37.89 72.00 97.00 100.00
Bagumbayan, Sultan Kudarat d) ROBETH GEN MDSE. CONST. d) 25-Jan-18 S 2.94 -0.99 1.33 0.34 -
e) 3,205,246.46 e) 09-May-18
f) 105 C.D. f) Completed on May 24, 2018.
g) 1 pr g) SANTOS L.P.
67. Project I.D : P00183609MN a) 2,906.53 a) By Contract P 11.76 44.71 81.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0259 b) 2,906.53 b) 11-Dec-17 R 11.76 44.71 81.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Mangudadatu National High School- c) 20-Nov-17 c) 16-Jan-18 A 11.85 40.00 79.00 95.00 95.50 95.51
Villamonte Annex, Lebak, Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 22-Jan-18 S 0.09 -4.71 -2.18 -5.00 -4.50 -4.49
e) 2,869,435.62 e) 16-Apr-18
f) 85 C.D. f)
Project delayed due to inaccesible road leading to project site cause of bad weather prevailing in
the area. For imposition of liquidated damages.
g) 1stry - 2CL w/ toilet g) GUARDIANO R.C.
68. Project I.D : P001836010MN a) 2,886.58 a) By Contract P 11.76 44.71 81.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0260 b) 2,886.58 b) 11-Dec-17 R 11.76 44.71 81.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Mangudadatu National High School- c) 20-Nov-17 c) 16-Jan-18 A 11.85 39.89 77.00 95.00 95.50 95.52
Villamonte Annex, Lebak, Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 22-Jan-18 S 0.09 -4.82 -4.18 -5.00 -4.50 -4.48
e) 2,869,435.62 e) 16-Apr-18
f) 85 C.D. f)
Project delayed due to inaccesible road leading to project site cause of bad weather prevailing in
the area. For imposition of liquidated damages.
g) 1stry - 2CL w/ toilet g) GUARDIANO R.C.
Page 17 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 13)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-11-014193 Dated: November 09, 2017
69. Project I.D : P001836011MN a) 3,357.52 a) By Contract P 9.52 36.19 65.71 94.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0261 b) 3,357.52 b) 11-Dec-17 R 9.52 36.19 65.71 94.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Mangudadatu National High School- c) 20-Nov-17 c) 19-Jan-18 A 9.65 31.96 61.00 92.00 93.00 93.10
Villamonte Annex, Lebak, Sultan Kudarat d) CS CONSTRUCTION AND SUPd) 25-Jan-18 S 0.13 -4.23 -4.71 -2.29 -7.00 -6.90
e) 3,323,511.13 e) 09-May-18
f) 105 C.D. f) Project delayed due to inaccesible road leading to project site cause of bad weather prevailing in
g) 1 pr g) GUARDIANO R.C. the area. Calibrated action issued to the contractor, for imposition of liquidated damages.

290,959.15 Page 18 of 18

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

Completed on June 15, 2018.

100.00
100.00
A=70.49

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.

100.00
100.00
A=75.63

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.

100.00
100.00

Completed on June 16, 2018.

Page 1 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00
A=62.36

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.

100.00
100.00
A=64.42

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.

100.00
100.00
a=70.78

Completed on June 1, 2018.

100.00
100.00
a=69.82

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.

Page 2 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00
A=54.99

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.

100.00
100.00
a=28.08

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.

100.00
100.00
a=54.73

Completed on June 15, 2018.

100.00
100.00
a=55.04

Completed on June 15, 2018.

Page 3 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00
a=73.40

Completed on June 1, 2018.

100.00
100.00
a=58.50

Substantially completed, project delayed due to bad weather prevailing in the area. For imposition
of liquidated damages.

100.00
100.00
a=77.68

Completed on April 30, 2018.

100.00
100.00
a=74.87

Completed on April 30, 2018.

Page 4 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

On-going, project delayed due to bad weather condition prevailing in the area. For imposition of
liquidated damages.

100.00
100.00

On-going, calibrated action issued to the contractor. For imposition of liquidated damages.

100.00
100.00

On-going, calibrated action issued to the contractor. For revision of implementation scheduled.

100.00
100.00

On-going, project delayed due to inaccessible road leading in the project area. For imposition of
liquidated damages.

Page 5 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

Completed on June 15, 2018.

100.00
100.00

On-going, calibrated action issued to the contractor.

100.00
100.00

Completed on June 20, 2018.

100.00
100.00

Completed on April 17, 2018.

Page 6 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.

100.00
100.00

Completed on June 20, 2018.

100.00
100.00

On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of
liquidated damages.

100.00
100.00

Completed on June 18, 2018.

Page 7 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

Completed on June 18, 2018.

100.00
100.00

On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of
liquidated damages.

100.00
100.00

On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of
liquidated damages.
100.00
100.00

Completed on June 5, 2018.

Page 8 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

On-going, for imposition of liquidated damages.

100.00
100.00

Completed on June 16, 2018.

100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
Page 9 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

On-going, project delayed due to peace and order problem in the area. For imposition of liquidated
damages.
100.00
100.00

On-going, calibrated action issued to the contractor. For imposition of liquidated damages.

100.00
100.00

On-going, project delayed due to inaccessible road leading to the jobsite. For revision of project
scheduled implementation.
100.00
100.00

On-going, project delayed due to inaccessible road leading to the jobsite. For revision of project
scheduled implementation.
Page 10 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
100.00
100.00

Completed on May 15, 2018.

100.00
100.00

Completed on May 15, 2018.

Page 11 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

On-going, project delayed due to demolition of exisitng building.

100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
100.00
100.00
a=31.10

On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of
liquidated damages.
100.00
100.00

On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of
liquidated damages.
Page 12 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
100.00
100.00

On-going, project delayed due to bad weather condition prevailing in the area. For imposition of
liquidated damages.
100.00
100.00

On-going, project delayed due to bad weather condition prevailing in the area. For imposition of
liquidated damages.
Page 13 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

Completed on June 20, 2018.

100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
Page 14 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

On-going, calibrated action issued to the contractor. For imposition of liquidated damages.

100.00
100.00

Completed on June 15, 2018.

100.00
100.00

On-going, project delayed due to bad weather prevailing in the area.

100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For revision of
implementation scheduled due to variation order.
Page 15 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
damages.
100.00
100.00

On-going, calibrated action issued to the contractor. For imposition of liquidated damages.

100.00
100.00

Completed on May 15, 2018.

100.00
100.00

Completed on May 15, 2018.

Page 16 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

Completed on June 15, 2018.

100.00
100.00

Completed on May 24, 2018.

100.00
100.00

Project delayed due to inaccesible road leading to project site cause of bad weather prevailing in
the area. For imposition of liquidated damages.
100.00
100.00

Project delayed due to inaccesible road leading to project site cause of bad weather prevailing in
the area. For imposition of liquidated damages.
Page 17 of 18
TATUS OF PROJECTS
ONSTRUCTION PROGRAM
al Facilities Fund (BEFF - Batch 13)
As of June 30, 2018

CUMULATIVE ACCOMPLISHMENT IN PERCENT


Current Year = 2018

DEC

100.00
100.00

Project delayed due to inaccesible road leading to project site cause of bad weather prevailing in
the area. Calibrated action issued to the contractor, for imposition of liquidated damages.

Page 18 of 18
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
1. Project I.D : P00177379MN_CW1 a) 2,866.63 a) By Contract P 13.77 42.30 91.62 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0174 b) 2,866.63 b) 27-Nov-17 R 2.09 17.42 44.23 91.62 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Spur 2 Elementary School, Bagumbayan c) 06-Nov-17 c) 08-Jan-18 A 21.20 21.20 82.00 96.35 96.46 96.48
Sultan Kudarat d) FPJ CONSTRUCTION & SUPP d) 14-Jan-18 S 19.11 3.78 37.77 4.73 -3.54 -3.52
e) 2,773,171.38 e) 08-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f) 08-May-18
damages.
g) 1stry- 2CLw/ toilet g) COLOMA J.A.E
2. Project I.D : P00177380MN_CW1 a) 2,866.63 a) By Contract P 13.77 42.30 91.62 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0175 b) 2,866.63 b) 27-Nov-17 R 2.09 17.42 44.23 91.62 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Spur 2 Elementary School, Bagumbayan c) 06-Nov-17 c) 08-Jan-18 A 21.20 21.20 82.00 96.35 96.46 96.48
Sultan Kudarat d) FPJ CONSTRUCTION & SUPP d) 14-Jan-18 S 19.11 3.78 37.77 4.73 -3.54 -3.52
e) 2,773,171.38 e) 08-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f) 08-May-18
damages.
g) 1stry- 2CLw/ toilet g) COLOMA J.A.E
3. Project I.D : P00177381MN_CW1 a) 3,337.57 a) By Contract P 17.14 43.81 73.33 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0176 b) 3,337.57 b) 27-Nov-17 R 0.00 17.96 57.14 73.80 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bagumbayan National Highschool - A, c) 06-Nov-17 c) 08-Jan-18 A 17.20 47.65 69.00 96.35 96.42 96.84
Bagumbayan, Sultan Kudarat d) ILON MULTIBUILDERS COMP d) 14-Jan-18 S 17.20 29.69 11.86 22.55 -3.58 -3.16
e) 3,180,357.85 e) 28-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f) 28-May-18
damages.
g) 1 pr g) SANTOS L.P.
4. Project I.D : P00177382MN_CW1 a) 3,337.57 a) By Contract P 21.24 52.10 73.25 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0177 b) 3,337.57 b) 27-Nov-17 R 21.24 52.10 73.25 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bagumbayan National High School - (B) c) 06-Nov-17 c) 08-Jan-18 A 17.20 34.00 70.00 96.35 96.40 96.44
Bagumbayan, Sultan Kudarat d) DALANON CONST. REF SUPP d) 14-Jan-18 S -4.04 -18.10 -3.25 -3.65 -3.60 -3.56
e) 3,229,333.67 e) 28-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f)
damages.
g) 1 pr g) SANTOS L.P.
Page 1 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
5. Project I.D : P00177383MN_CW1 a) 3,263.89 a) By Contract P 21.53 52.18 73.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0178 b) 3,263.89 b) 27-Nov-17 R 21.53 52.18 73.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Biwang NHS-Bagumbayan Annex c) 06-Nov-17 c) 08-Jan-18 A 17.20 33.85 70.00 97.25 97.68 100.00
Bagumbayan, Sultan Kudarat d) BLIMEX CONSTRUCTION ANDd) 14-Jan-18 S -4.33 -18.33 -3.18 -2.75 -2.32 -
e) 3,251,709.97 e) 28-Apr-18
f) 105 C.D. f) Completed on June 15, 2018.
g) 1 pr g) SANTOS L.P.
6. Project I.D : P00177384MN_CW1 a) 3,283.84 a) By Contract P 14.02 57.06 81.15 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0179 b) 3,283.84 b) 27-Nov-17 R 14.02 57.06 81.15 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Busok National High School c) 06-Nov-17 c) 08-Jan-18 A 18.00 47.00 85.00 98.00 98.05 100.00
Bagumbayan, Sultan Kudarat d) MEGALINE BUILDERS AND S d) 14-Jan-18 S 3.98 -10.06 3.85 -2.00 -1.95 -
e) 3,209,722.81 e) 28-Apr-18
f) 105 C.D. f) Completed on June 20, 2018
g) 1 pr g) SANTOS L.P.
7. Project I.D : P00177385MN_CW1 a) 2,926.48 a) By Contract P 21.00 64.00 97.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0180 b) 2,926.48 b) 27-Nov-17 R 21.00 64.00 97.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bongo-Bongo Elementary School - (A) c) 06-Nov-17 c) 08-Jan-18 A 21.25 55.00 93.00 97.00 97.06 97.11
Esperanza, Sultan Kudarat d) DALANON CONST. REF SUPP d) 14-Jan-18 S 0.25 -9.00 -4.00 -3.00 -2.94 -2.89
e) 2,917,646.82 e) 08-Apr-18
On-going, project delayed due to inaccessible road leading to the project site. For imposition of
f) 85 C.D. f)
liquidated damages.
g) 1stry- 2CLw/ toilet g) GUARDIANO R.C.
8. Project I.D : P00177386MN_CW1 a) 2,926.48 a) By Contract P 21.00 64.00 97.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0181 b) 2,926.48 b) 27-Nov-17 R 21.00 64.00 97.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bongo-Bongo Elementary School - (B) c) 06-Nov-17 c) 08-Jan-18 A 21.25 55.00 93.25 97.00 97.05 97.08
Esperanza, Sultan Kudarat d) DALANON CONST. REF SUPP d) 14-Jan-18 S 0.25 -9.00 -3.75 -3.00 -2.95 -2.92
e) 2,917,646.82 e) 08-Apr-18
On-going, project delayed due to inaccessible road leading to the project site. For imposition of
f) 85 C.D. f)
liquidated damages.
g) 1stry- 2CLw/ toilet g) GUARDIANO R.C.
Page 2 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
9. Project I.D : P00177387MN_CW1 a) 2,866.63 a) By Contract P 20.95 57.48 95.85 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0182 b) 2,866.63 b) 27-Nov-17 R 0.00 17.51 59.20 95.85 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Salabaca National High School - (A) c) 06-Nov-17 c) 08-Jan-18 A 21.25 55.00 97.00 98.00 100.00
Esperanza, Sultan Kudarat d) CASTILLANES CONSTRUCTIOd) 14-Jan-18 S 21.25 37.49 37.80 2.15 -
e) 2,806,556.83 e) 08-Apr-18
f) 85 C.D. f) 08-May-18 Completed on May 4, 2018.
g) 1stry- 2CLw/ toilet g) SANTOS L.P.
10. Project I.D : P00177388MN_CW1 a) 2,866.63 a) By Contract P 21.74 66.06 96.63 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0183 b) 2,866.63 b) 27-Nov-17 R 0.00 18.29 66.82 96.63 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Salabaca National High School - (B) c) 06-Nov-17 c) 08-Jan-18 A 21.25 44.23 92.12 97.00 97.07 97.11
Esperanza, Sultan Kudarat d) H. ROYAL CONSTRUCTION d) 14-Jan-18 S 21.25 25.94 25.30 0.37 -2.93 -2.89
e) 2,816,513.30 e) 08-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f) 08-May-18
damages.
g) 1stry- 2CLw/ toilet g) SANTOS L.P.
11. Project I.D : P00177389MN_CW1 a) 3,263.97 a) By Contract P 12.88 32.38 73.20 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0184 b) 3,263.97 b) 27-Nov-17 R 12.88 32.38 73.20 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Esperanza National High School - (A) c) 06-Nov-17 c) 08-Jan-18 A 17.25 34.16 70.00 97.00 97.02 97.13
Esperanza, Sultan Kudarat d) ISULAN ECT CONST. &GEN. d) 14-Jan-18 S 4.37 1.78 -3.20 -3.00 -2.98 -2.87
e) 3,133,254.64 e) 28-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f)
damages.
g) 1 pr g) SANTOS L.P.
12. Project I.D : P00177390MN_CW1 a) 3,263.97 a) By Contract P 15.37 44.96 76.67 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0185 b) 3,263.97 b) 27-Nov-17 R 0.00 13.55 45.62 76.67 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Esperanza National High School - (B) c) 06-Nov-17 c) 08-Jan-18 A 17.50 34.16 72.00 96.00 96.05 97.02
Esperanza, Sultan Kudarat d) ROBETH GEN. MDSE CONST. d) 14-Jan-18 S 17.50 20.61 26.38 19.33 -3.95 -2.98
e) 3,206,917.09 e) 28-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f) 28-May-18
damages.
g) 1 pr g) SANTOS L.P.
Page 3 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
13. Project I.D : P00177391MN_CW1 a) 3,263.97 a) By Contract P 20.47 51.93 72.90 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0186 b) 3,263.97 b) 27-Nov-17 R 0.00 17.79 52.36 72.90 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Esperanza National High School - (C) c) 06-Nov-17 c) 08-Jan-18 A 17.20 34.16 68.45 97.00 97.05 97.07
Esperanza, Sultan Kudarat d) CURVELINE CONST. d) 14-Jan-18 S 17.20 16.37 16.09 24.10 -2.95 -2.93
e) 3,200,315.82 e) 28-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f) 28-May-18
damages.
g) 1 pr g) SANTOS L.P.
14. Project I.D : P00177392MN_CW1 a) 3,263.97 a) By Contract P 20.07 52.22 77.11 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0187 b) 3,263.97 b) 27-Nov-17 R 20.07 52.22 77.11 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Esperanza National High School - (D) c) 06-Nov-17 c) 08-Jan-18 A 17.20 47.00 80.00 97.85 97.92 100.00
Esperanza, Sultan Kudarat d) PALMARES GEN. MERCHANDId) 14-Jan-18 S -2.87 -5.22 2.89 -2.15 -2.08 -
e) 3,247,000.43 e) 28-Apr-18
f) 105 C.D. f) Completed on June 20, 2018
g) 1 pr g) SANTOS L.P.
15. Project I.D : P00177393MN_CW1 a) 2,866.63 a) By Contract P 14.46 48.76 94.23 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0188 b) 2,866.63 b) 27-Nov-17 R 14.46 48.76 94.23 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Pag-asa Elementary School - (A) c) 06-Nov-17 c) 10-Jan-18 A 19.20 56.00 95.00 98.85 99.20 100.00
Kalamansig, Sultan Kudarat d) ROBETH GEN. MDSE CONST. d) 16-Jan-18 S 4.74 7.24 0.77 -1.15 -0.80 -
e) 2,816,554.48 e) 10-Apr-18
f) 85 C.D. f) 10-May-18 Completed on June 1, 2018.
g) 1stry- 2CLw/ toilet g) ALANGCA H.D.
16. Project I.D : P00177394MN_CW1 a) 2,866.63 a) By Contract P 14.46 48.76 94.23 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0189 b) 2,866.63 b) R 14.46 48.76 94.23 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Pag-asa Elementary School - (B) c) 06-Nov-17 c) 10-Jan-18 A 19.25 54.00 96.00 99.00 99.20 100.00
Kalamansig, Sultan Kudarat d) ROBETH GEN. MDSE CONST. d) 16-Jan-18 S 4.79 5.24 1.77 -1.00 -0.80 -
e) 2,816,554.48 e) 10-Apr-18
f) 85 C.D. f) 10-May-18 Completed on June 1, 2018.
g) 1stry- 2CLw/ toilet g) ALANGCA H.D.
Page 4 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
17. Project I.D : P00177395MN_CW1 a) 2,926.48 a) By Contract P 14.20 59.40 94.40 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0190 b) 2,926.48 b) 29-Nov-17 R 14.20 59.40 94.40 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Sangay National High School c) 06-Nov-17 c) 10-Jan-18 A 19.25 53.00 90.00 97.00 97.55 97.57
Kalamansig, Sultan Kudarat d) JV CONSTECH d) 16-Jan-18 S 5.05 -6.40 -4.40 -3.00 -2.45 -2.43
e) 2,874,413.56 e) 10-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1stry- 2CLw/ toilet g) GUARDIANO R.C.
18. Project I.D : P00177396MN_CW1 a) 3,397.42 a) By Contract P 6.67 33.33 62.86 91.43 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0191 b) 3,397.42 b) R 6.67 33.33 62.86 91.43 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Datu Wasay National High School c) 06-Nov-17 c) 19-Jan-18 A 6.95 23.65 58.00 89.00 90.75 90.78
Kalamansig, Sultan Kudarat d) CS CONST. & SUPPLY d) 25-Jan-18 S 0.28 -9.68 -4.86 -2.43 -9.25 -9.22
e) 3,361,389.13 e) 09-May-18
f) 105 C.D. f) On-going, calibrated action issued to the contractor. For imposition of liquidated damages.
g) 1 pr g) COLOMA J.A.E
19. Project I.D : P00177397MN_CW1 a) 3,263.89 a) By Contract P 9.36 24.85 71.33 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0192 b) 3,263.89 b) 29-Nov-17 R 9.36 24.85 71.33 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kalamansig National High School c) 06-Nov-17 c) 10-Jan-18 A 16.20 43.00 75.00 98.25 99.02 100.00
Kalamansig, Sultan Kudarat d) JARGON CONST & SUPPLY d) 16-Jan-18 S 6.84 18.15 3.67 -1.75 -0.98 -
e) 3,172,528.97 e) 30-Apr-18
f) 105 C.D. f) 30-May-18 Completed on June 1, 2018.
g) 1 pr g) ALANGCA H.D.
20. Project I.D : P00177398MN_CW1 a) 3,315.42 a) By Contract P 7.43 41.13 80.22 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0193 b) 3,315.42 b) 29-Nov-17 R 0.00 6.00 42.00 79.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Sangay National High School c) 06-Nov-17 c) 10-Jan-18 A 16.20 43.00 68.00 90.00 92.00 92.51
Kalamansig, Sultan Kudarat d) JV CONSTECH d) 16-Jan-18 S 16.20 37.00 26.00 11.00 -8.00 -7.49
e) 3,274,576.93 e) 30-Apr-18
Substantially completed, project delayed due to bad weather prevailing in the area. For revision of
f) 105 C.D. f) 30-May-18
implementation scheduled.
g) 1 pr g) GUARDIANO R.C.
Page 5 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
21. Project I.D : P00177399MN_CW1 a) 3,263.89 a) By Contract P 4.73 23.61 61.85 95.72 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0194 b) 3,263.89 b) 29-Nov-17 R 0.00 2.95 24.38 61.85 96.62 98.31 100.00 100.00 100.00 100.00 100.00 100.00
Sta. Clara National High School c) 06-Nov-17 c) 15-Jan-18 A 11.10 11.10 30.00 70.00 92.00 94.53
Kalamansig, Sultan Kudarat d) JV CONSTECH d) 21-Jan-18 S 11.10 8.15 5.62 8.15 -4.62 -3.78
e) 3,215,000.00 e) 05-May-18
On-going, project delayed due to bad weather prevailing in the area. For revision of project
f) 105 C.D. f) 19-Jun-18
scheduled implementation due to variation order.
g) 1 pr g) ALANGCA H.D.
22. Project I.D : P00177400MN_CW1 a) 2,896.56 a) By Contract P 10.00 50.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0195 b) 2,896.56 b) 29-Nov-17 R 10.00 50.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Capilan Elementary School - (A) c) 06-Nov-17 c) 15-Jan-18 A 13.00 42.00 85.95 96.00 96.05 96.06
Lebak, Sultan Kudarat d) JARGON CONST & SUPPLY d) 21-Jan-18 S 3.00 -8.00 -4.05 -4.00 -3.95 -3.94
e) 2,790,242.55 e) 15-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1stry- 2CLw/ toilet g) GUARDIANO R.C.
23. Project I.D : P00177401MN_CW1 a) 2,896.56 a) By Contract P 3.97 45.66 90.13 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0196 b) 2,896.56 b) 12-Dec-17 R 3.97 45.66 90.13 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Capilan Elementary School - (B) c) 06-Nov-17 c) 19-Jan-18 A 8.95 37.95 86.59 97.00 97.60 97.66
Lebak, Sultan Kudarat d) JV CONSTECH d) 25-Jan-18 S 4.98 -7.71 -3.54 -3.00 -2.40 -2.34
e) 2,845,962.16 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1stry- 2CLw/ toilet g) GUARDIANO R.C.
24. Project I.D : P00177402MN_CW1 a) 2,866.63 a) By Contract P 8.00 46.00 92.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0197 b) 2,866.63 b) 29-Nov-17 R 8.00 46.00 92.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Tran National High School c) 06-Nov-17 c) 15-Jan-18 A 13.50 30.00 83.65 96.25 98.02 98.50
Lebak, Sultan Kudarat d) ROBETH GEN. MDSE CONST. d) 21-Jan-18 S 5.50 -16.00 -8.35 -3.75 -1.98 -1.50
e) 2,811,554.48 e) 15-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1stry- 2CLw/ toilet g) GUARDIANO R.C.
Page 6 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
25. Project I.D : P00177403MN_CW1 a) 3,269.15 a) By Contract P 4.45 23.45 61.92 95.99 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0198 b) 3,269.15 b) 04-Dec-17 R 4.45 23.45 61.92 95.99 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
E. Arcano Mem. National High School c) 06-Nov-17 c) 15-Jan-18 A 10.65 27.00 58.00 92.00 95.22 95.23
Lebak, Sultan Kudarat d) JV CONSTECH d) 21-Jan-18 S 6.20 3.55 -3.92 -3.99 -4.78 -4.77
e) 3,221,851.72 e) 05-May-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f)
damages.
g) 1 pr g) MANGATONG R.
26. Project I.D : P00177404MN_CW1 a) 3,367.50 a) By Contract P 6.95 36.46 74.50 91.24 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0199 b) 3,367.50 b) 04-Dec-17 R 6.95 36.46 74.50 91.24 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Keytodac National High School - (A) c) 06-Nov-17 c) 15-Jan-18 A 10.55 33.16 70.00 88.00 95.05 95.06
Lebak, Sultan Kudarat d) CS CONST. & SUPPLY d) 21-Jan-18 S 3.60 -3.30 -4.50 -3.24 -4.95 -4.94
e) 3,325,163.17 e) 05-May-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f) 02-Jun-18
damages.
g) 1 pr g) GUARDIANO R.C.
27. Project I.D : P00177405MN_CW1 a) 3,367.50 a) By Contract P 6.95 36.46 74.50 91.24 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0200 b) 3,367.50 b) 04-Dec-17 R 6.95 36.46 74.50 82.87 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Keytodac National High School - (B) c) 06-Nov-17 c) 15-Jan-18 A 10.55 33.16 70.00 79.00 95.04 95.06
Lebak, Sultan Kudarat d) CS CONST. & SUPPLY d) 21-Jan-18 S 3.60 -3.30 -4.50 -3.87 -4.96 -4.94
e) 3,325,142.11 e) 05-May-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f) 02-Jun-18
damages.
g) 1 pr g) GUARDIANO R.C.
28. Project I.D : P00177406MN_CW1 a) 3,263.97 a) By Contract P 6.80 36.30 76.30 91.40 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0201 b) 3,263.97 b) 04-Dec-17 R 6.80 36.30 76.30 91.40 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Lebak National High School c) 06-Nov-17 c) 15-Jan-18 A 10.65 33.00 72.00 87.00 94.82 94.85
Lebak, Sultan Kudarat d) DALANON CONST. REF SUPP d) 21-Jan-18 S 3.85 -3.30 -4.30 -4.40 -5.18 -5.15
e) 3,158,119.52 e) 05-May-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f)
damages.
g) 1 pr g) GUARDIANO R.C.
Page 7 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
29. Project I.D : P00177407MN_CW1 a) 3,357.52 a) By Contract P 9.52 36.19 65.71 94.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0202 b) 3,357.52 b) 04-Dec-17 R 9.52 36.19 65.71 94.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Mangudadatu National High School- c) 06-Nov-17 c) 16-Jan-18 A 9.75 31.65 62.00 92.00 92.12 92.16
Villamonte Annex, Lebak, Sultan Kudarat d) CS CONST. & SUPPLY d) 22-Jan-18 S 0.23 -4.54 -3.71 -2.29 -7.88 -7.84
e) 3,323,511.13 e) 06-May-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f)
damages.
g) 1 pr g) GUARDIANO R.C.
30. Project I.D : P00177408MN_CW1 a) 2,875.11 a) By Contract P 7.56 33.67 87.03 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0203 b) 2,875.11 b) 04-Dec-17 R 7.56 33.67 87.03 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Isuko Elementary School c) 06-Nov-17 c) 16-Jan-18 A 11.98 40.00 78.00 96.00 96.04 96.11
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 22-Jan-18 S 4.42 6.33 -9.03 -4.00 -3.96 -3.89
e) 2,854,500.00 e) 16-Apr-18
On-going, project delayed due to inaccessible road leading to the jobsite. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1stry- 2CLw/ toilet g) COLOMA J.A.E
31. Project I.D : P00177409MN_CW1 a) 3,389.19 a) By Contract P 11.85 29.15 62.94 95.54 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0204 b) 3,389.19 b) 04-Dec-17 R 11.85 29.15 62.94 95.54 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Baluan Senior High School - (A) c) 06-Nov-17 c) 15-Jan-18 A 10.85 33.85 58.95 92.00 94.22 94.26
Palimbang, Sultan Kudarat d) DALANON CONST. REF SUPP d) 21-Jan-18 S -1.00 4.70 -3.99 -3.54 -5.78 -5.74
e) 3,340,693.32 e) 05-May-18
f) 105 C.D. f) 04-Jun-18 On-going, calibrated action issued to the contractor. For imposition of liquidated damages.
g) 1 pr g) COLOMA J.A.E
32. Project I.D : P00177410MN_CW1 a) 3,389.19 a) By Contract P 11.85 29.15 62.94 95.54 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0205 b) 3,389.19 b) 04-Dec-17 R 11.85 29.15 62.94 95.54 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Baluan Senior High School - (B) c) 06-Nov-17 c) 15-Jan-18 A 10.85 33.15 59.00 93.00 94.37 94.39
Palimbang, Sultan Kudarat d) DALANON CONST. REF SUPP d) 21-Jan-18 S -1.00 4.00 -3.94 -2.54 -5.63 -5.61
e) 3,340,693.32 e) 05-May-18
f) 105 C.D. f) 04-Jun-18 On-going, calibrated action issued to the contractor. For imposition of liquidated damages.
g) 1 pr g) COLOMA J.A.E
Page 8 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
33. Project I.D : P00177411MN_CW1 a) 3,357.61 a) By Contract P 10.00 40.00 80.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0206 b) 3,357.61 b) 04-Dec-17 R 10.00 40.00 80.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Milbuk National High School - (A) c) 06-Nov-17 c) 15-Jan-18 A 10.85 34.00 62.95 88.25 95.22 96.26
Palimbang, Sultan Kudarat d) CEK CONSTRUCTION & SUPP d) 21-Jan-18 S 0.85 -6.00 -17.05 -1.75 -4.78 -3.74
e) 2,947,474.40 e) 05-May-18
On-going, project delayed because of large volume of excavation. For imposition of liquidated
f) 105 C.D. f)
damages.
g) 1 pr g) GUIAMEL M.D.
34. Project I.D : P00177412MN_CW1 a) 3,357.61 a) By Contract P 10.00 40.00 80.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0207 b) 3,357.61 b) 04-Dec-17 R 10.00 40.00 80.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Milbuk National High School - (B) c) 06-Nov-17 c) 15-Jan-18 A 10.85 33.52 62.95 87.35 95.27 95.29
Palimbang, Sultan Kudarat d) CEK CONSTRUCTION & SUPP d) 21-Jan-18 S 0.85 -6.48 -17.05 -2.65 -4.73 -4.71
e) 2,947,474.40 e) 05-May-18
On-going, project delayed because of large volume of excavation. For imposition of liquidated
f) 105 C.D. f) 04-Jun-18
damages.
g) 1 pr g) GUIAMEL M.D.
35. Project I.D : P00177413MN_CW1 a) 3,382.82 a) By Contract P 5.00 26.80 68.20 96.70 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0208 b) 3,382.82 b) R 5.00 26.80 68.20 96.70 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Palimbang National High School - (A) c) 06-Nov-17 c) 16-Jan-18 A 9.85 38.00 62.35 92.35 92.38 92.41
Palimbang, Sultan Kudarat d) ILON MULTIBUILDERS COMP d) 22-Jan-18 S 4.85 11.20 -5.85 -4.35 -7.62 -7.59
e) 3,294,371.28 e) 06-May-18
On-going, project delayed due to bad weather prevailing in the area. For revision of project
f) 105 C.D. f) 05-Jun-18
scheduled implementation.
g) 1 pr g) MANGATONG R.
36. Project I.D : P00177414MN_CW1 a) 3,342.92 a) By Contract P 6.00 36.00 77.00 97.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0209 b) 3,342.92 b) R 6.00 36.00 77.00 97.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Palimbang National High School - (B) c) 06-Nov-17 c) 16-Jan-18 A 9.87 38.00 62.35 93.65 95.17 95.26
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 22-Jan-18 S 3.87 2.00 -14.65 -3.35 -4.83 -4.74
e) 3,267,798.64 e) 06-May-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f) 05-Jun-18
damages.
g) 1 pr g) GUIAMEL M.D.
Page 9 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
37. Project I.D : P00177415MN_CW1 a) 3,342.92 a) By Contract P 6.00 36.00 77.00 97.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0210 b) 3,342.92 b) R 6.00 36.00 77.00 97.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Palimbang National High School - (C) c) 06-Nov-17 c) 16-Jan-18 A 9.75 38.15 62.00 93.00 95.17 96.01
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 22-Jan-18 S 3.75 2.15 -15.00 -4.00 -4.83 -3.99
e) 3,267,798.64 e) 06-May-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f) 05-Jun-18
damages.
g) 1 pr g) GUIAMEL M.D.
38. Project I.D : P00177416MN_CW1 a) 2,885.08 a) By Contract P 10.00 52.30 94.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0211 b) 2,885.08 b) R 10.00 52.30 94.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kraan ES - (A) c) 06-Nov-17 c) 16-Jan-18 A 11.85 42.00 78.00 96.35 96.38 96.41
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 22-Jan-18 S 1.85 -10.30 -16.60 -3.65 -3.62 -3.59
e) 2,820,292.57 e) 16-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f) 16-May-18
damages.
g) 1stry- 2CLw/ toilet g) GUIAMEL M.D.
39. Project I.D : P00177417MN_CW1 a) 2,885.08 a) By Contract P 10.00 52.30 94.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0212 b) 2,885.08 b) R 10.00 52.30 94.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kraan ES - (B) c) 06-Nov-17 c) 16-Jan-18 A 11.85 42.35 78.00 97.00 97.05 97.11
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 22-Jan-18 S 1.85 -9.95 -16.60 -3.00 -2.95 -2.89
e) 2,820,292.15 e) 16-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f) 16-May-18
damages.
g) 1stry- 2CLw/ toilet g) GUIAMEL M.D.
40. Project I.D : P00177418MN_CW1 a) 3,317.61 a) By Contract P 5.86 27.14 61.13 92.25 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0213 b) 3,317.61 b) R 5.86 27.14 61.13 92.25 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Gapok National High School - Langgal c) 06-Nov-17 c) 16-Jan-18 A 9.87 33.42 62.00 94.00 98.40 98.92
Annex, Sen. Ninoy Aquino, Sultan Kudarat d) PALMARES GEN. MERCHANDId) 22-Jan-18 S 4.01 6.28 0.87 1.75 -1.60 -1.08
e) 3,753,039.96 e) 06-May-18
On-going, delayed due to demolition of dilapidated building. For revision of implementation
f) 105 C.D. f) 05-Jun-18
scheduled.
g) 1 pr g) DURUIN P.S.
Page 10 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
41. Project I.D : P00177419MN_CW1 a) 3,848.04 a) By Contract P 9.52 36.19 65.71 94.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0214 b) 3,848.04 b) R 9.52 36.19 65.71 94.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Langgal National High School c) 06-Nov-17 c) 16-Jan-18 A 9.85 33.25 62.00 92.00 94.33 94.36
Sen. Ninoy Aquino, Sultan Kudarat d) COFEJOK CONST. & SUPPLY d) 22-Jan-18 S 0.33 -2.94 -3.71 -2.29 -5.67 -5.64
e) 3,753,039.96 e) 06-May-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f) 05-Jun-18
damages.
g) 1 pr g) COLOMA J.A.E
42. Project I.D : P00177420MN_CW1 a) 3,357.52 a) By Contract 7.39 21.56 54.18 95.46 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0215 b) 3,357.52 b) R 1.18 9.71 25.07 62.16 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Senator Ninoy Aquino National High School-A c) 06-Nov-17 c) 16-Jan-18 A 10.20 33.00 52.00 93.00 94.35 100.00
Sen. Ninoy Aquino, Sultan Kudarat d) ROBETH GEN. MDSE CONST. d) 22-Jan-18 S 9.02 23.29 26.93 30.84 -5.65 -
e) 3,297,159.32 e) 06-May-18
f) 105 C.D. f) 29-May-18 Completed on June 1, 2018.
g) 1 pr g) COLOMA J.A.E
43. Project I.D : P00177421MN_CW1 a) 3,357.52 a) By Contract P 7.39 21.56 54.18 95.46 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0216 b) 3,357.52 b) R 1.18 9.71 25.07 62.16 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Senator Ninoy Aquino National High School - ( c) 06-Nov-17 c) 16-Jan-18 A 10.18 33.00 52.00 93.00 95.00 100.00
Sen. Ninoy Aquino, Sultan Kudarat d) ROBETH GEN. MDSE CONST. d) 22-Jan-18 S 9.00 23.29 26.93 30.84 -5.00 -
e) 3,297,159.32 e) 06-May-18
f) 105 C.D. f) 29-May-18 Completed on June 1, 2018.
g) 1 pr g) COLOMA J.A.E
Page 11 of 12
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 7)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-10-013589 Dated: October 23, 2017
44. Project I.D : P00177422MN_CW1 a) 3,317.61 a) By Contract P 5.86 27.15 61.13 92.25 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0217 b) 3,317.61 b) R 5.86 27.15 61.13 92.25 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Sewod National High School-Langgal Annex c) 06-Nov-17 c) 16-Jan-18 A 9.65 40.00 58.00 93.00 98.30 98.76
Sen. Ninoy Aquino, Sultan Kudarat d) PALMARES GEN. MERCHANDId) 22-Jan-18 S 3.79 12.85 -3.13 0.75 -1.70 -1.24
e) 3,270,603.64 e) 06-May-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f)
damages.
g) 1 pr g) DURUIN P.S.
140,189.85 Page 12 of 12

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 5)
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE


a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: 2017-09-12972 Dated: September 29, 2017
1. Project I.D : P00174555MN_CW1 a) 2,731.41 a) By Contract P 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0172 b) 2,731.41 b) 13-Dec-17 R 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kubo Banday Elementary School, c) 12-Oct-17 c) 19-Jan-18 A 8.35 34.69 73.00 94.00 94.10 94.15
Kalamansig, Sultan Kudarat d) CS CONSTRUCTION & SUPPL d) 25-Jan-18 S 0.11 -6.49 -4.65 -6.00 -5.90 -5.85
e) 2,671,915.01 e) 19-Apr-18
Project delayed due to inaccesible road leading to project site cause of bad weather prevailing in the
f) 85 C.D. f)
area. Calibrated issued to contractor. For imposition of liquidated damages.
g) 1stry- 2CL g) DURUIN P.S.
2. Project I.D : P00174556MN_CW1 a) 2,731.41 a) By Contract P 11.76 44.71 81.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0173 b) 2,731.41 b) 13-Dec-17 R 11.76 44.71 81.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kubo Banday Elementary School, c) 12-Oct-17 c) 16-Jan-18 A 11.85 37.00 76.95 94.75 94.78 94.79
Kalamansig, Sultan Kudarat d) CS CONSTRUCTION & SUPPL d) 22-Jan-18 S 0.09 -7.71 -4.23 -5.25 -5.22 -5.21
e) 2,671,915.01 e) 16-Apr-18
Project delayed due to inaccesible road leading to project site cause of bad weather prevailing in the
f) 85 C.D. f)
area. Calibrated issued to contractor. For imposition of liquidated damages.
g) 1stry- 2CL g) DURUIN P.S.
3. Project I.D : P00174557MN_CW1 a) 2,731.41 a) By Contract P 5.73 47.14 87.12 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0167 b) 2,731.41 b) 20-Dec-17 R 5.73 5.73 48.94 87.12 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Saint Andrews Mission School-Main, c) 12-Oct-17 c) 19-Jan-18 A 8.44 43.25 83.00 97.00 97.10 97.16
Kalamansig, Sultan Kudarat d) BARRIST BUILDERS & CONSTd) 25-Jan-18 S 2.71 37.52 34.06 9.88 -2.90 -2.84
e) 2,683,953.27 e) 19-Apr-18
Project delayed due to inaccesible road leading to project site cause of bad weather prevailing in the
f) 85 C.D. f) 19-May-18
area. For imposition of liquidated damages.
g) 1stry- 2CL g) GUARDIANO, R.C.
8,194.22553 Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
1. Project I.D : P00174310MN-CW1 a) 5,100.03 a) By Contract P 21.90 48.57 78.10 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0138 b) 5,100.03 b) 27-Nov-17 R 21.90 48.57 78.10 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Salumping Elementary School, Esperanza, c) 12-Oct-17 c) 03-Jan-18 A 22.00 44.63 74.00 97.00 97.05 97.07
Sultan Kudarat d) ILON MULTIBUILDERS COMPA d) 09-Jan-18 S 0.10 -3.94 -4.10 -3.00 -2.95 -2.93
e) 4,764,681.62 e) 23-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 105 C.D. f)
damages.
g) 1 stry- 4CL g) GUARDIANO R.C.
2. Project I.D : P00174311MN-CW1 a) 3,824.98 a) By Contract P 39.08 73.93 92.99 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0139 b) 3,824.98 b) 27-Nov-17 R 39.08 73.93 92.99 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Daladap Elementary School, Esperanza, c) 12-Oct-17 c) 03-Jan-18 A 24.25 49.53 93.25 97.00 98.10 100.00
Sultan Kudarat d) CS CONSTRUCTION AND SUPPd) 09-Jan-18 S -14.83 -24.40 0.26 -3.00 -1.90 -
e) 3,758,905.87 e) 13-Apr-18
f) 95 C.D. f) Completed on June 20, 2018
JL g) 1 stry- 3CL g) SANTOS L. P.
3. Project I.D : P00174312MN-CW1 a) 3,824.98 a) By Contract P 38.83 72.96 93.14 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0140 b) 3,824.98 b) 27-Nov-17 R 38.83 72.96 93.14 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
New Panay Elementary School, Esperanza, c) 12-Oct-17 c) 03-Jan-18 A 24.25 50.62 90.00 97.00 97.20 97.32
Sultan Kudarat d) FPJ CONSTRUCTION & SUPPL d) 09-Jan-18 S -14.58 -22.34 -3.14 -3.00 -2.80 -2.68
e) 3,735,612.64 e) 13-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 95 C.D. f)
damages.
g) 1 stry- 3CL g) SANTOS L. P.
Page 1 of 11
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
4. Project I.D : P00174313MN-CW1 a) 2,731.41 a) By Contract P 9.35 60.43 89.61 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0141 b) 2,731.41 b) 06-Dec-17 R 9.35 33.98 61.39 89.61 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Ugis Elementary School, Esperanza, c) 12-Oct-17 c) 15-Jan-18 A 13.00 41.35 85.00 96.35 96.40 96.42
Sultan Kudarat d) ILON MULTIBUILDERS COMPA d) 21-Jan-18 S 3.65 7.37 23.61 6.74 -3.60 -3.58
e) 2,690,462.79 e) 15-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f) 15-May-18
damages.
g) 1 stry- 2CL g) SANTOS L. P.
5. Project I.D : P00174314MN-CW1 a) 3,824.98 a) By Contract P 11.68 51.31 83.88 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0142 b) 3,824.98 b) 06-Dec-17 R 11.68 51.31 83.88 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kanalan Elementary School, Esperanza, c) 12-Oct-17 c) 15-Jan-18 A 11.75 36.63 80.00 96.85 96.90 96.91
Sultan Kudarat d) ILON MULTIBUILDERS COMPA d) 21-Jan-18 S 0.07 -14.68 -3.88 -3.15 -3.10 -3.09
e) 3,777,735.47 e) 25-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 95 C.D. f)
damages.
g) 1 stry- 3CL g) SANTOS L. P.
6. Project I.D : P00174315MN-CW1 a) 2,731.41 a) By Contract P 36.77 77.04 97.61 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0143 b) 2,731.41 b) 27-Nov-17 R 36.77 77.04 97.61 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Tiger Elementary School, Esperanza, c) 12-Oct-17 c) 03-Jan-18 A 27.23 55.35 93.00 98.00 98.20 100.00
Sultan Kudarat d) DALANON CONST. REF SUPPLYd) 09-Jan-18 S -9.54 -21.69 -4.61 -2.00 -1.80 -
e) 2,721,562.90 e) 03-Apr-18
f) 85 C.D. f) Completed on June 20, 2018
g) 1 stry- 2CL g) SANTOS L. P.
Page 2 of 11
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
7. Project I.D : P00174316MN-CW1 a) 3,824.98 a) By Contract P 24.21 53.68 86.32 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0144 b) 3,824.98 b) 27-Nov-17 R 24.21 53.68 86.32 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Abang Elementary School, Esperanza, c) 12-Oct-17 c) 03-Jan-18 A 24.65 49.13 82.00 97.00 98.25 98.27
Sultan Kudarat d) DALANON CONST. REF SUPPLYd) 09-Jan-18 S 0.44 -4.55 -4.32 -3.00 -1.75 -1.73
e) 3,813,892.51 e) 13-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 95 C.D. f)
damages.
g) 1 stry- 3CL g) GUARDIANO R.C.
8. Project I.D : P00174317MN-CW1 a) 3,824.98 a) By Contract P 11.68 51.31 83.88 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0145 b) 3,824.98 b) 06-Dec-17 R 11.68 51.31 83.88 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Datu Gambangan Saliling Primary School, c) 12-Oct-17 c) 15-Jan-18 A 11.75 36.62 80.00 96.35 96.50 96.52
Esperanza, Sultan Kudarat d) ILON MULTIBUILDERS COMPA d) 21-Jan-18 S 0.07 -14.69 -3.88 -3.65 -3.50 -3.48
e) 3,777,735.47 e) 25-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 95 C.D. f)
damages.
g) 1 stry- 3CL g) SANTOS L. P.
9. Project I.D : P00174318MN-CW1 a) 3,824.98 a) By Contract P 40.15 74.45 93.56 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0146 b) 3,824.98 b) 27-Nov-17 R 40.15 74.45 93.56 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
SultaN Sinanggayan Integrated School, c) 12-Oct-17 c) 03-Jan-18 A 24.35 50.00 94.50 100.00
Esperanza, Sultan Kudarat d) CURVELINE CONST. d) 09-Jan-18 S -15.80 -24.45 0.94 -
e) 3,734,084.58 e) 13-Apr-18
f) 95 C.D. f) Completed on April 17, 2018.
g) 1 stry- 3CL g) SANTOS L. P.
Page 3 of 11
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
10. Project I.D : P00174319MN-CW1 a) 2,731.41 a) By Contract P 6.30 29.13 85.91 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0147 b) 2,731.41 b) 06-Dec-17 R 6.30 29.13 85.91 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Datu Wasay Elementary School, c) 12-Oct-17 c) 15-Jan-18 A 13.00 41.00 78.00 95.85 95.90 95.95
Kalamansig, Sultan Kudarat d) ILON MULTIBUILDERS COMPA d) 21-Jan-18 S 6.70 11.87 -7.91 -4.15 -4.10 -4.05
e) 2,690,462.79 e) 15-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1 stry- 2CL g) COLOMA J.A.E.
11. Project I.D : P00174320MN-CW1 a) 2,731.41 a) By Contract P 19.63 54.94 97.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0148 b) 2,731.41 b) 28-Nov-17 R 19.63 54.94 97.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Nalilidan Elementary School, c) 12-Oct-17 c) 08-Jan-18 A 27.00 62.00 97.80 98.90 98.96 98.98
Kalamansig, Sultan Kudarat d) ROBETH GEN. MDSE CONST d) 14-Jan-18 S 7.37 7.06 0.20 -1.10 -1.04 -1.02
e) 2,683,064.90 e) 08-Apr-18
Substantially completed, project delayed due to bad weather prevailing in the area. For imposition of
f) 85 C.D. f)
liquidated damages.
g) 1 stry- 2CL g) ALANGCA H.D.
12. Project I.D : P00174321MN-CW1 a) 2,731.41 a) By Contract P 25.88 58.82 95.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0149 b) 2,731.41 b) 28-Nov-17 R 25.88 58.82 95.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Francisco Baluyot Concha Memorial Elem. c) 12-Oct-17 c) 03-Jan-18 A 26.00 54.00 91.00 96.00 96.55 100.00
Kalamansig, Sultan Kudarat d) BARRIST BUILDERS & CONST. d) 09-Jan-18 S 0.12 -4.82 -4.29 -4.00 -3.45 -
e) 2,682,214.47 e) 03-Apr-18
f) 85 C.D. f) Completed on June 30, 2018.
g) 1 stry- 2CL g) DURUIN P.S
Page 4 of 11
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
13. Project I.D : P00174322MN-CW1 a) 2,731.41 a) By Contract P 5.07 40.86 87.81 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0150 b) 2,731.41 b) 28-Nov-17 R 5.07 40.86 87.81 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Tapudi Elementary School, c) 12-Oct-17 c) 03-Jan-18 A 27.20 60.46 90.00 99.50 100.00
Lebak, Sultan Kudarat d) JARGON CONST. & SUPPLY d) 09-Jan-18 S 22.13 19.60 2.19 -0.50 -
e) 2,640,101.46 e) 03-Apr-18
f) 85 C.D. f) Completed on May 13, 2018.
g) 1 stry- 2CL g) GUARDIANO R.C.
14. Project I.D : P00174323MN-CW1 a) 2,731.41 a) By Contract P 26.01 69.50 99.43 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0151 b) 2,731.41 b) 28-Nov-17 R 26.01 69.50 99.43 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
S.A. Balabagan Elementary School, c) 12-Oct-17 c) 04-Jan-18 A 26.00 54.00 95.00 97.00 97.05 97.11
Lebak, Sultan Kudarat d) BARRIST BUILDERS & CONST. d) 10-Jan-18 S -0.01 -15.50 -4.43 -3.00 -2.95 -2.89
e) 2,710,101.25 e) 04-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1 stry- 2CL g) GUARDIANO R.C.
15. Project I.D : P00174324MN-CW1 a) 2,731.41 a) By Contract P 26.00 69.50 99.40 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0152 b) 2,731.41 b) 28-Nov-17 R 26.00 58.82 99.40 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Salangsang Elementary School, c) 12-Oct-17 c) 04-Jan-18 A 26.00 54.15 95.00 97.35 97.40 97.43
Lebak, Sultan Kudarat d) BARRIST BUILDERS & CONST. d) 10-Jan-18 S 0.00 -4.67 -4.40 -2.65 -2.60 -2.57
e) 2,705,141.83 e) 04-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1 stry- 2CL g) GUARDIANO R.C.
Page 5 of 11
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
16. Project I.D : P00174325MN-CW1 a) 2,731.41 a) By Contract P 21.18 54.12 90.59 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0153 b) 2,731.41 b) 05-Dec-17 R 21.18 54.12 90.59 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Villamonte Elementary School, c) 12-Oct-17 c) 08-Jan-18 A 21.25 49.78 85.65 95.65 95.70 95.73
Lebak, Sultan Kudarat d) ILON MULTIBUILDERS COMPA d) 14-Jan-18 S 0.07 -4.34 -4.94 -4.35 -4.30 -4.27
e) 2,690,462.79 e) 08-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D. f)
damages.
g) 1 stry- 2CL g) MANGATONG R.
17. Project I.D : P00174326MN-CW1 a) 3,824.98 a) By Contract P 24.48 52.22 93.76 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0154 b) 3,824.98 b) 28-Nov-17 R 24.48 52.22 93.76 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Ampad-Guiabar Memorial Elementary c) 12-Oct-17 c) 04-Jan-18 A 24.00 55.00 95.00 98.25 98.65 100.00
School, Lebak, Sultan Kudarat d) JV CONSTECH d) 10-Jan-18 S -0.48 2.78 1.24 -1.75 -1.35 -
e) 3,700,912.27 e) 14-Apr-18
f) 95 C.D. f) 29-May-18 Completed on June 1, 2018.
g) 1 stry- 3CL g) ALANGCA H.D.
18. Project I.D : P00174327MN-CW1 a) 5,100.03 a) By Contract P 19.33 52.13 85.31 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0155 b) 5,100.03 b) 28-Nov-17 R 19.33 52.13 85.31 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
B. Difuntorum Sr. MES, Lebak, c) 12-Oct-17 c) 04-Jan-18 A 21.00 55.00 87.00 98.00 98.62 100.00
Sultan Kudarat d) ROBETH GEN. MDSE CONST d) 10-Jan-18 S 1.67 2.87 1.69 -2.00 -1.38 -
e) 5,010,807.95 e) 24-Apr-18
f) 105 C.D. f) Completed on June 1, 2018.
g) 1 stry- 4CL g) ALANGCA H.D.
Page 6 of 11
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
19. Project I.D : P00174328MN-CW1 a) 2,731.41 a) By Contract P 6.54 44.85 86.26 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0156 b) 2,731.41 b) 28-Nov-17 R 6.54 44.85 86.26 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Pakil Elementary School, Lebak, c) 12-Oct-17 c) 04-Jan-18 A 26.50 50.00 90.00 98.25 98.79 100.00
Sultan Kudarat d) JV CONSTECH d) 10-Jan-18 S 19.96 5.15 3.74 -1.75 -1.21 -
e) 2,642,098.10 e) 04-Apr-18
f) 85 C.D f) 04-May-18 Completed on June 1, 2018.
g) 1stry- 2CL g) ALANGCA H.D.
20. Project I.D : P00174330MN-CW1 a) 3,824.98 a) By Contract P 23.16 52.63 85.26 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0157 b) 3,824.98 b) 28-Nov-17 R 3.50 20.40 60.40 95.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Bitogen Primary School, Lebak, c) 12-Oct-17 c) 04-Jan-18 A 23.25 23.40 75.00 90.25 95.25 95.30
Sultan Kudarat d) DALANON CONST. REF SUPPLYd) 10-Jan-18 S 19.75 3.00 14.60 -4.75 -4.75 -4.70
e) 3,736,392.51 e) 14-Apr-18
f) 95 C.D. f) 14-May-18 On-going, calibrated issued to contractor . For imposition of liquidated damages.
g) 1stry - 3CL w/ toilet g) GUARDIANO R.C.
21. Project I.D : P00174332MN-CW1 a) 2,731.41 a) By Contract P 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0158 b) 2,731.41 b) R 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Datu Manggong Primary School, Lebak, c) 12-Oct-17 c) 19-Jan-18 A 8.50 9.00 74.00 92.00 93.25 93.40
Sultan Kudarat d) CS CONSTRUCTION AND SUPPd) 25-Jan-18 S 0.26 -32.18 -3.65 -8.00 -6.75 -6.60
e) 2,718,182.00 e) 19-Apr-18
f) 85 C.D f) On-going, calibrated action issued to contractor. For imposition of liquidated damages.
g) 1stry- 2CL g) GUARDIANO R.C.
Page 7 of 11
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
22. Project I.D : P00174333MN-CW1 a) 2,731.41 a) By Contract P 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0159 b) 2,731.41 b) 12-Dec-18 R 8.24 41.18 77.65 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Mangudadatu NHS, Villamonte Annex, Lebak,c) 12-Oct-17 c) 19-Jan-18 A 8.50 36.95 74.00 95.85 95.88 95.91
Sultan Kudarat d) ILON MULTIBUILDERS COMPA d)25-Jan-18 S 0.26 -4.23 -3.65 -4.15 -4.12 -4.09
e) 2,708,522.17 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D f)
damages.
g) 1stry- 2CL g) GUARDIANO R.C.
23. Project I.D : P00174334MN-CW1 a) 2,731.41 a) By Contract P 19.62 39.00 80.89 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0160 b) 2,731.41 b) 22-Dec-17 R 19.62 39.00 80.89 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Datu Sipot Elementary School, Palimbang c) 12-Oct-17 c) 19-Jan-18 A 8.48 31.85 74.00 90.65 95.25 95.31
Sultan Kudarat d) CS CONSTRUCTION AND SUPPd) 25-Jan-18 S -11.14 -7.15 -6.89 -9.35 -4.75 -4.69
e) 2,719,616.00 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For revision of scheduled
f) 85 C.D f) 19-May-18
implementation.
g) 1stry- 2CL g) COLOMA J.A.E.
24. Project I.D : P00174335MN-CW1 a) 2,731.41 a) By Contract P 5.19 46.29 93.11 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0161 b) 2,731.41 b) 12-Dec-18 R 5.19 46.29 93.11 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kiponget Elementary School, Palimbang c) 12-Oct-17 c) 19-Jan-18 A 8.50 31.45 74.00 95.85 95.92 95.96
Sultan Kudarat d) CS CONSTRUCTION AND SUPPd) 25-Jan-18 S 3.31 -14.84 -19.11 -4.15 -4.08 -4.04
e) 2,697,399.79 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D f) 19-May-18
damages.
g) 1stry- 2CL g) MANGATONG R.
Page 8 of 11
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
25. Project I.D : P00174336MN-CW1 a) 2,731.41 a) By Contract P 16.46 45.07 94.35 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0162 b) 2,731.41 b) 28-Nov-17 R 16.46 45.07 94.35 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Kiadsam Elementary School, Sen. Ninoy c) 12-Oct-17 c) 08-Jan-18 A 21.85 51.00 90.00 96.35 96.38 96.41
Aquino, Sultan Kudarat d) CEK CONST. & WATER SUPPL d) 14-Jan-18 S 5.39 5.93 -4.35 -3.65 -3.62 -3.59
e) 2,657,598.38 e) 08-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D f) 08-May-18
damages.
g) 1stry- 2CL g) COLOMA J.A.E.
26. Project I.D : P00174337MN-CW1 a) 2,731.41 a) By Contract P 16.47 45.09 94.35 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0163 b) 2,731.41 b) 28-Nov-17 R 16.47 45.09 94.35 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Midtungok Elementary School, Sen. Ninoy c) 12-Oct-17 c) 08-Jan-18 A 21.82 51.00 90.00 96.35 96.40 96.43
Aquino, Sultan Kudarat d) CEK CONST. & WATER SUPPL d) 14-Jan-18 S 5.35 5.91 -4.35 -3.65 -3.60 -3.57
e) 2,656,318.38 e) 08-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D f) 08-May-18
damages.
g) 1stry- 2CL g) COLOMA J.A.E.
27. Project I.D : P00174338MN-CW1 a) 2,731.41 a) By Contract P 21.18 54.12 90.59 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0164 b) 2,731.41 b) 28-Nov-17 R 0.00 13.23 43.32 93.11 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Matanao Elementary School, Sen. Ninoy c) 12-Oct-17 c) 08-Jan-18 A 21.68 44.65 85.95 92.65 94.90 94.92
Aquino, Sultan Kudarat d) PEARL CONST. & SUPPLY d) 14-Jan-18 S 21.68 31.42 42.63 -0.46 -5.10 -5.08
e) 2,714,562.90 e) 08-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D f) 08-May-18
damages.
g) 1stry- 2CL g) COLOMA J.A.E.
Page 9 of 11
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
28. Project I.D : P00174339MN-CW1 a) 3,824.98 a) By Contract P 18.95 48.42 81.05 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0165 b) 3,824.98 b) 28-Nov-17 R 18.95 48.42 81.05 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Tamangan Elementary School, Sen. Ninoy c) 12-Oct-17 c) 08-Jan-18 A 19.00 45.00 78.00 95.65 97.10 97.21
Aquino, Sultan Kudarat d) COFEJOK CONST. & SUPPLY d) 14-Jan-18 S 0.05 -3.42 -3.05 -4.35 -2.90 -2.79
e) 3,810,273.47 e) 18-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 95 C.D f) 18-May-18
damages.
g) 1stry- 3CL g) COLOMA J.A.E.
29. Project I.D : P00174340MN-CW1 a) 3,824.98 a) By Contract P 18.95 48.42 81.05 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0166 b) 3,824.98 b) 28-Nov-17 R 18.95 48.42 81.05 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Sen. Ninoy Aquino NHS, Sen. Ninoy Aquino, c) 12-Oct-17 c) 08-Jan-18 A 19.00 45.00 78.00 95.85 98.05 100.00
Sultan Kudarat d) PEARL CONST. & SUPPLY d) 14-Jan-18 S 0.05 -3.42 -3.05 -4.15 -1.95 -
e) 3,805,392.51 e) 18-Apr-18
f) 95 C.D f) 18-May-18 Completed on June 1, 2018.
g) 1stry- 3CL g) COLOMA J.A.E.
30. Project I.D : P00174308MN-CW1 a) 2,731.41 a) By Contract P 7.50 54.62 88.79 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0168 b) 2,731.41 b) 12-Dec-17 R 7.50 54.62 88.79 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Laquicon Elementary School, Bagumbayan, c) 12-Oct-17 c) 19-Jan-18 A 8.45 37.19 86.00 95.65 95.78 95.82
Sultan Kudarat d) ILON MULTIBUILDERS COMPA d) 25-Jan-18 S 0.95 -17.43 -2.79 -4.35 -4.22 -4.18
e) 2,703,442.17 e) 19-Apr-18
On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
f) 85 C.D f)
damages.
g) 1stry- 2CL g) SANTOS L. P.
Page 10 of 11
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 4)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2017-09-012902 Dated: September 27, 2017
31. Project I.D : P00174309MN-CW1 a) 2,731.41 a) By Contract P 7.49 54.52 88.62 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0169 b) 2,731.41 b) 12-Dec-17 R 7.49 54.52 88.62 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Laquicon Elementary School, Bagumbayan, c) 12-Oct-17 c) 19-Jan-18 A 8.45 36.95 86.45 95.25 95.30 95.37
Sultan Kudarat d) ILON MULTIBUILDERS COMPA d) 25-Jan-18 S 0.96 -17.57 -2.17 -4.75 -4.70 -4.63
e) 2,708,522.17 e) 19-Apr-18
f) 85 C.D f) On-going, project delayed due to bad weather prevailing in the area. For imposition of liquidated
g) 1stry- 2CL g) SANTOS L. P.
damages.
32. Project I.D : P00174329MN-CW1 a) 2,731.41 a) By Contract P 5.50 40.06 88.53 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0170 b) 2,731.41 b) R 8.24 41.18 88.53 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Pigel Elementary School, Lebak, Sultan c) 12-Oct-17 c) 19-Jan-18 A 8.45 36.65 50.00 95.65 95.68 95.70
Kudarat d) ILON MULTIBUILDERS COMPA d) 25-Jan-18 S 0.21 -4.53 -38.53 -4.35 -4.32 -4.30
e) 2,700,902.17 e) 19-Apr-18
f) 85 C.D f) Project delayed due to inacessible road leading to the project area. For imposition of liquidated
g) 1stry - 2CL w/ toilet g) MANGATONG R.
damages.
33. Project I.D : P00174330MN-CW1 a) 2,731.41 a) By Contract P 5.58 46.97 89.08 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0171 b) 2,731.41 b) R 8.24 41.18 89.08 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Pigel Elementary School, Lebak, Sultan c) 12-Oct-17 c) 19-Jan-18 A 8.45 36.65 50.00 95.65 95.68 95.70
Kudarat d) ILON MULTIBUILDERS COMPA d) 25-Jan-18 S 0.21 -4.53 -39.08 -4.35 -4.32 -4.30
e) 2,700,902.17 e) 19-Apr-18
Project delayed due to inacessible road leading to the project area. For imposition of liquidated
f) 85 C.D. f)
g) 1stry - 2CL w/ toilet g)
damages.
MANGATONG R.
105,809.435 Page 11 of 11

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
CY 2017 CONSTRUCTION PROGRAM
CY 2017 Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE


a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-07-011064 Dated: July 28, 2017
1. Project I.D : P00170477MN_CW1 a) 1,250.00 a) By Contract P 57.78 100.00
Contract I.D : 17MH0075 b) 1,250.00 b) 26-Sep-17 R 57.78 100.00
Construction and Completion of school bldg. c) 14-Aug-17 c) 30-Oct-17 A 5.00 62.82 100.00
in the Elementary and Secondary, d) CURVELINE CONST. d) 5-Nov-17 S 5.00 5.04 -
Esperanza NHS, Esperanza, Sultan Kudarat e) 1,227,683.06 e) 19-Dec-17
f) 45 C.D. f)
Completed on December 19, 2017.
CJ
g) 1 unit 3 stry, 12 CL g) L. P. Santos
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Department of Agrarian Reform (DAR) Projects
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE


a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
1. Project I.D : P00199018MN_CW1 a) 38,668.00 a) By Contract P 38.94 78.77 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 8.15 23.13
Contract I.D : 17MH0077 b) b) 10-Oct-17 R 23.61 37.30 80.22 100.00 100.00 100.00 100.00 100.00 100.00 100.00 8.15 8.58
Rehab/Const/Improv of Masiag-Kanulay Farm c) c) 07-Nov-17 A 27.00 32.00 76.00 92.00 93.25 93.56 10.00 18.65
to Market Road (FMR), Bagumbayan, d) COFEJOK CONST. & SUPPLY d) 13-Nov-17 S 3.39 -5.30 -4.22 -8.00 -6.75 -6.44 1.85 10.07
Sultan Kudarat e) 34,549,923.90 e) 15-Mar-18
On-going, project delayed due to bad weather prevailing in the area. Calibrated action
f) 123 C.D. f) 14-Apr-18
issued to the contractor. For imposition of liquidated damages.
g) g) J.A.E. Coloma
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
1. Project I.D : P00131112MN_CW1 a) 75.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 75.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Bagumbayan Central Elem. School, e) 72,412.71 e) 18-Dec-17
Roxas Street f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
2. Project I.D : P00131113MN_CW1 a) 45.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 45.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Dorin Elem. School, Purok Campo Sarmiento, e) 43,358.63 e) 18-Dec-17
Bagumbyan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
3. Project I.D : P00131114MN_CW1 a) 45.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 45.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Venus Elem. School, Purok San Roque e) 43,360.36 e) 18-Dec-17
Bagumbyan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
4. Project I.D : P00131115MN_CW1 a) 75.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 75.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Bai Saripinang Central Elem. School, e) 72,225.74 e) 18-Dec-17
Purok San Vicente, Bagumbyan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 1 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
5. Project I.D : P00131116MN_CW1 a) 105.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 105.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Dawing Elem. School, Sitio Lower Dawing, e) 101,546.36 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
6. Project I.D : P00131117MN_CW1 a) 145.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 145.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Biwang Elem. School, Purok 4, Bagumbayan e) 139,619.09 e) 18-Dec-17
f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
7. Project I.D : P00131118MN_CW1 a) 135.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 135.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Moises (Malingawon) Elem. School, Purok 6, e) 130,074.73 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
8. Project I.D : P00131119MN_CW1 a) 75.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 75.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Busok Elem. School, Purok Maligaya e) 72,231.72 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 2 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
9. Project I.D : P00131120MN_CW1 a) 75.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 75.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Chua Elem. School, Proper Chua, e) 72,386.26 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
10.Project I.D : P00131121MN_CW1 a) 145.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 145.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Daguma Elem. School, Purok 6, Bagumbayan e) 140,047.89 e) 18-Dec-17
f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
11.Project I.D : P00131122MN_CW1 a) 300.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 300.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Daluga Elem. School, Purok 1, e) 289,230.11 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
12.Project I.D : P00131123MN_CW1 a) 270.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 270.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Sia-an Primary School, Sitio Sia-an e) 260,233.50 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 3 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
13.Project I.D : P00131124MN_CW1 a) 380.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 380.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Kabulanan Elem. School, Purok Rose e) 323,976.09 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
14.Project I.D : P00131125MN_CW1 a) 330.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 330.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Kanulay Elem. School, Purok Orchids e) 308,100.32 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
15.Project I.D : P00131126MN_CW1 a) 75.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 75.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Kapaya Elem. School, Purok Pag-asa, e) 72,256.18 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
16.Project I.D : P00131127MN_CW1 a) 175.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 175.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Don Jose Buencamino Elem. School, e) 168,651.53 e) 18-Dec-17
Sitio Kabulanan, Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 4 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
17.Project I.D : P00131128MN_CW1 a) 145.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 145.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Kinayao Elem. School, Block II e) 139,917.08 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
18.Project I.D : P00131129MN_CW1 a) 75.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 75.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Masiag Elem. School, Purok Paghedait e) 72,213.83 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
19.Project I.D : P00131130MN_CW1 a) 270.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 270.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Nalum Elem. School, Sitio Nalum e) 260,067.36 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
20.Project I.D : P00131131MN_CW1 a) 105.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 105.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
San Vicente Elem. School, e) 101,307.14 e) 18-Dec-17
Sitio San Vicente, Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 5 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
21.Project I.D : P00131132MN_CW1 a) 330.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 330.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Campo 3 Elem. School, Sitio Campo 3 e) 308,348.14 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
22.Project I.D : P00131133MN_CW1 a) 270.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 270.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Kipuso Primary School, Sitio Kipuso e) 260,027.09 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
23.Project I.D : P00131134MN_CW1 a) 270.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 270.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Lower Alas Primary School, Sitio Lower Alas e) 260,351.13 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
24.Project I.D : P00131135MN_CW1 a) 270.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 270.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Upper Alas Primary School, Sitio Upperr Alas e) 260,027.09 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 6 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
25.Project I.D : P00131136MN_CW1 a) 330.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 330.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Dante Elem. School, Purok Orchids e) 305,667.60 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
26.Project I.D : P00131137MN_CW1 a) 330.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 330.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
New Datal Village Primary School, e) 308,242.73 e) 18-Dec-17
Sitio New Datal Village, Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
27.Project I.D : P00131138MN_CW1 a) 330.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 330.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Sto.niño Elem. School, Proper Sto.niño e) 308,323.27 e) 18-Dec-17
f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
28.Project I.D : P00131139MN_CW1 a) 270.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 270.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Tulali Elem. School, Sitio Tulali e) 260,027.09 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 7 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
29.Project I.D : P00131140MN_CW1 a) 75.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 75.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Sison Elem. School, Purok Santan e) 72,301.38 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
30.Project I.D : P00131141MN_CW1 a) 130.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 130.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
South Sepaka Elem. School, e) 125,336.00 e) 18-Dec-17
Purok Sambag, Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
31.Project I.D : P00131142MN_CW1 a) 270.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 270.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Sumilil Elem. School, Purok Pag asa e) 260,312.57 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
32.Project I.D : P00131143MN_CW1 a) 270.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 270.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Seguya Elem. School, Sitio Seguya e) 260,372.74 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 8 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
33.Project I.D : P00131144MN_CW1 a) 105.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 105.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Titulok Elem. School, Purok 1 e) 101,294.86 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
34.Project I.D : P00131145MN_CW1 a) 105.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 105.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Spur 2 Primary School, Sitio Spur 2 e) 101,104.26 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
35.Project I.D : P00131146MN_CW1 a) 105.00 a) By Contract P - - - - - - - 4.47 23.26 56.13 92.12 100.00
Contract I.D : 17MH0061 b) 105.00 b) 11-Jul-17 R - - - - - - - 4.47 23.26 56.13 92.12 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 10.00 35.00 80.00 95.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 5.53 11.74 23.87 2.88 -
Tuka Elem. School, Purok Islam e) 101,308.93 e) 18-Dec-17
Bagumbayan f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
36.Project I.D : P00131147MN_CW1 a) 75.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 75.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Palimbang Elem. School, Poblacion e) 72,143.42 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 9 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
37.Project I.D : P00131148MN_CW1 a) 75.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 75.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Palimbang National High School, e) 72,162.83 e) 18-Dec-17
Poblacion, Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
38.Project I.D : P00131149MN_CW1 a) 75.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 75.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Badiangon Elem. School, Badiangon e) 71,940.07 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
39.Project I.D : P00131150MN_CW1 a) 105.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 105.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Baliango Elem. School, Baliango e) 101,054.90 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
40.Project I.D : P00131151MN_CW1 a) 105.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 105.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Balwan Elem. School, Balwan e) 101,054.90 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 10 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
41.Project I.D : P00131153MN_CW1 a) 270.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 270.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Baranayan Primary School, Baranayan e) 260,434.86 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
42 Project I.D : P00131154MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Barongis Primary School, Barongis e) 129,933.70 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
43 Project I.D : P00131156MN_CW1 a) 330.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 330.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Butril Primary School, Butril, Palimbang e) 308,783.05 e) 18-Dec-17
f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
44 Project I.D : P00131157MN_CW1 a) 330.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 330.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Colobe Primary School, Colobe (Tagadtal) e) 308,783.05 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 11 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
45 Project I.D : P00131158MN_CW1 a) 380.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 380.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Domolol Primary School, Domolol e) 325,542.20 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
46 Project I.D : P00131160MN_CW1 a) 270.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 270.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Kalibuhan Primary School, Kalibuhan, e) 260,356.94 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
47 Project I.D : P00131161MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Kanipaan Elem. School, Kanipaan e) 129,928.51 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
48 Project I.D : P00131162MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Kisek Primary School, Kisek e) 129,938.44 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 12 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
49 Project I.D : P00131164MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Kiponget Primary School, Kiponget, e) 130,039.54 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
50 Project I.D : P00131165MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Kulong-Kulong Primary School, Kulong-Kulong e) 129,938.44 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
51 Project I.D : P00131166MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Kraan Elem. School, Kraan, Palimbang e) 129,928.51 e) 18-Dec-17
f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
52 Project I.D : P00131169MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Ligao Brgy. Hall, Ligao, Palimbang e) 130,279.66 e) 18-Dec-17
f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 13 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
53 Project I.D : P00131171MN_CW1 a) 330.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 330.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Lopoken Primary School, Lopoken e) 318,628.03 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
54 Project I.D : P00131173MN_CW1 a) 330.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 330.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Maguid Primary School, Maguid, e) 318,628.03 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
55 Project I.D : P00131174MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Malatunol Primary School, Malatunol, e) 129,927.51 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
56 Project I.D : P00131175MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Malisbong Elem. School, Malisbong, e) 129,928.51 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 14 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
57 Project I.D : P00131176MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Medol Brgy. Hall, Medol, Palimbang e) 129,928.51 e) 18-Dec-17
f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
58 Project I.D : P00131177MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Milbuk Elem. School, Milbuk, e) 129,928.51 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
59 Project I.D : P00131178MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Mina Elem. School, Mina, Palimbang e) 129,944.45 e) 18-Dec-17
f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
60 Project I.D : P00131179MN_CW1 a) 330.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 330.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Molon Primary School, Molon, e) 318,110.67 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 15 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
61 Project I.D : P00131180MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Namat Masla School, Namat Masla, e) 130,572.53 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
62 Project I.D : P00131181MN_CW1 a) 330.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 330.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Napnapon Brgy. Hall, Napnapon e) 317,848.56 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
63 Project I.D : P00131183MN_CW1 a) 330.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 330.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Tibuhol Primary School, Tibuhol, e) 317,640.58 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
64 Project I.D : P00131185MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Wasag Primary School, Wasag, e) 129,986.59 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 16 of 17
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Construction of Accessible Polling Places (APP) Exclusively for Persons with Disabilities (PWDs) and Senior Citizens (SC)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-02-004034 Dated: February 10, 2017
65 Project I.D : P00131186MN_CW1 a) 135.00 a) By Contract P - - - - - - - 5.20 27.08 56.25 87.11 100.00
Contract I.D : 17MH0062 b) 135.00 b) 11-Jul-17 R - - - - - - - 5.20 27.08 56.25 87.11 100.00
Construction of pathways and ramps with c) 27-Feb-17 c) 15-Aug-17 A - - - - - - - 9.50 36.00 85.00 93.00 100.00
railings for physically challenged persons at d) JV CONSTECH d) 21-Aug-17 S - - - - - - - 4.30 8.92 28.75 5.89 -
Datu Maguiales Brgy. Hall, Datu Maguiales e) 129,986.12 e) 18-Dec-17
Palimbang f) 120 C.D f) Completed on December 15, 2017.
g) g) H.D. Alangca
Page 17 of 17

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Department of Agrarian Reform (DAR) Projects
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE


a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
1. Project I.D : P00099112MN_CW1 a) 48,100.00 a) By Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 16MH0050 b) 48,100.00 b) 20-Dec-16 R 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Rehab of Bugso - Kamison - Matanao - Gapok c) c) 12-Jan-17 A 96.35 96.42 97.00 97.50 98.20 98.26
Sen. Ninoy Aquino, Sultan Kudarat d) JARGON CONSTRUCTION AN d) 18-Jan-17 S -3.65 -3.58 -3.00 -2.50 -1.80 -1.74
e) 35,552,045.26 e) 14-Aug-17
Substantially Completed, project delayed due to bad weather condition prevailling in the area.
f) 209 C.D f) 13-Oct-17
Remaining works will be subjected to liquidated damages.
CJ g) g) R.C. GUARDIANO
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Department of Agriculture (DA) Proposed Projects
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-03-006549 Dated: March 16, 2017
1. Project I.D : P00166115MN_CW1 a) 8,000.00 a) By Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0056 b) 8,000.00 b) 06-Jun-17 R 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Concreting of Sitio Barurao to Logpond FMR c) 10-Apr-17 c) 27-Jun-17 A 97.13 97.32 97.32 97.33 97.41 97.41
Brgy. Butril, Palimbang, Sultan Kudarat d) RNS CONST. ENGINEERING d) 03-Jul-17 S -2.87 -2.68 -2.68 -2.67 -2.59 -2.59
e) 7,601,672.13 e) 01-Sep-17
f) 61 C.D f) 01-Oct-17 On-going, for imposition of liquidated damages.
g) 0.800 km g) M.D. Guiamel
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
Water Supply and Sanitation for Poverty Areas and Tourism Priority Sites
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location d) Contractor d) Start Date C
(Scope of Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-03-007050 Dated: March 21, 2017
1. Project I.D : a) 48,015.00 a) by Contract P
Contract I.D : b) 48,015.00 b) R
Construction of Various Water Supply Projects c) 10-Apr-17 c) A
at Kalamansig,Sultan Kudarat d) d) S
e) e)
f) f)
g) g)

Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA ELISEO L. OTOC, MPA MAMINTAL T. TAHA, MPS


Engineer II Assistant District Engineer District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Construction of Rain Water Collector System (CWRCS)
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2017-03-005521 Dated: March 3, 2017
1. Project I.D : a) 3,366.00 a) by Contract P 100.00 100.00 100.00 100.00 100.00 13.33 39.17 65.00 90.00 100.00 100.00 100.00
Contract I.D : 17MH0049 b) 3,366.00 b) 4-May-17 R 100.00 100.00 100.00 100.00 100.00 1.59 33.38 34.81 57.28 87.08 100.00 100.00
Construction of Rain Water Collector c) 20-Mar-17 c) 9-Jun-17 A 97.35 98.23 100.00 - - 16.00 40.00 66.00 86.00 91.00 91.20 93.10
System (CWRCS) d) CS Construction & Supply d) 15-Jun-17 S -2.65 -1.77 - - - 14.41 6.62 31.19 28.72 3.92 -8.80 -6.90
e) 3,184,000.00 e) 12-Oct-17
1. D. Moises ES, Bagumbayan f) 120 CD f) 11-Nov-17
2. Don Jose Buencamino ES, Bagumbayan g) 1 pr g) J.A.E. Coloma
3. Dorin ES Campo Sarmiento, Bagumbayan
4. Legodon ES, Esperanza
5. Tiger ES, Esperanza
6. Salumping ES, Esperanza
7. Cadiz ES, Brgy. Cadiz, Kalamansig
8. Datu Wasay Sitio Napleco, Kalamansig
9. Hinalaan ES, Kalamansig Completed on March 05, 2018.
10. Kalibuhan ES, Palimbang
11. Kanipaan ES, Palimbang
12. Kiponget ES, Palimbang
13. Malisbong ES, Palimbang
14. Midtungok ES, SNA
15. Nati ES, SNA
16. Bugso ES, SNA
17. Matanao ES, SNA
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Construction of Flood Control (Ala River Basin)
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P

1. Project I.D : P00121790MN-CW1 a) 40,000.00 a) by Contract P 100.00 100.00 100.00 100.00 20.74 36.70 53.19 69.68 85.64 100.00 100.00 100.00
Contract I.D : 17MH0035 b) 40,000.00 b) 8-Dec-16 R 100.00 100.00 100.00 100.00 1.64 28.30 67.12 78.20 87.08 95.24 100.00 100.00
Construction of Flood Control (Ala River Basin), c) c) 17-Apr-17 A 92.45 96.49 100.00 25.00 32.00 54.00 70.00 79.00 87.60 91.98 92.39
K0+000-K0+380, Esperanza, Sultan Kudarat d) THREE W BUILDERS, INC / d) 23-Apr-17 S -7.55 -3.51 - 23.36 3.70 -13.12 -8.20 -8.08 -7.64 -8.02 -7.61
ROBETH GEN. MDSE. e) 27-Oct-17
CONST. SUPPLY (JV) f) 10-Jan-18
e) 36,187,500.59 g) L.P. SANTOS Completed on March 12, 2018.
f) 188 C.D
RV g) 380 l.m
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
FY 2017 CONSTRUCTION PROGRAM
Replacement of Bridges (Temporary to Permanent)..
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
1. Project I.D : P00112001MN-CW1 a) 40,000.00 a) By Contract P 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 17MH0041 b) 40,000.00 b) 29-Dec-16 R 95.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Replacement of Bridge from Temporary to c) c) 09-Jun-17 A 90.91 95.33 95.34 95.34 95.36 95.38
Permanent, Balonglong Br. (B00331MN) d) CS CONSTRUCTION & SUPPL d) 15-Jun-17 S -4.69 -4.67 -4.66 -4.66 -4.64 -4.62
along Awang-Upi-Lebak-Kalamansig- e) 36,761,229.12 e) 18-Jan-18
Palimbang-Sarangani Rd K 2015+636 - f) 218 C.D f) 17-Feb-18 On-going, project delayed due to bad weather prevailing in the area.
RM K 2015+957 (PCCP=273m), Palimbang, SK. g) 381.60 sq.m g) M.D. Guiamel
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
OVER-ALL STATUS
FY 2017 Carry Over CONSTRUCTION PROGRAM
Sultan Kudarat 2nd District Engineering Office
As of June 30, 2018

PRE-CONSTRUCTION CONSTRUCTION
PROGRAM TOTAL NO.
NUMBER OF PROJECTS NO. OF PROJECTS STATUS
FUND SOURCE AMOUNT OF
PROJECTS COM- ON- ADVER CONTRACT ACTUAL COM- ON- PLANNED ACTUAL SLIPPAGE
(Php'000) PLETED GOING
NYS
-TIZED
BID
APPROVED
NTP
% ACC PLETED GOING
NYS
% TARGET % ACC %
DPWH REGULAR INFRASTRUCTURE
Replacement of Bridges (Temporary to Permanent).. 40,000.00 1 1 - - 1 1 1 1 100.00 - 1 - 100.00 95.38 -4.62
Road Upgrading (unpaved to paved) - National
89,799.00 3 3 - - 3 3 3 3 100.00 3 - - 100.00 100.00 -
Secondary Roads

Construction/ Improvement of Access Roads leading


to Airports, Seaports, and Declared Tourism 17,868.35 2 2 - - 2 2 2 2 100.00 2 - - 100.00 100.00 -
Destinations - To Declared Tourism Destinations

Construction of Flood Control (Ala River Basin) 40,000.00 1 1 - - 1 1 1 1 100.00 1 - - 100.00 100.00 -
Local Infrastructure Program 50,000.00 34 34 - - 34 34 34 34 100.00 34 - - 100.00 100.00 -
Construction of Rain Water Collector System
3,400.00 1 1 - - 1 1 1 1 100.00 1 - - 100.00 100.00 -
(CWRCS)
Construction/Repair/Rehabilitation/ Improvement of
27,034.92 1 1 - - 1 1 1 1 100.00 1 - - 100.00 100.00 -
Various Infrastructure
Sub-total 268,102.27 43 43 - - 43 43 43 43 100.00 42 1 - 100.00 99.31 -0.69
DPWH OUTSIDE INFRASTRUCTURE
MinSAAD-DAR (1st Released) 48,100.00 1 1 - - 1 1 1 1 100.00 - 1 - 100.00 98.26 -1.74
MinSAAD-DAR (2nd Released) 37,314.62 1 1 - - 1 1 1 1 100.00 - 1 - 100.00 93.56 -6.44
Department of Agriculture (DA) 40,000.00 5 5 - - 5 5 5 5 100.00 4 1 - 100.00 99.48 -0.52
Const./Rehab. of Accessibility Facilities for Physically
16,410.00 98 98 - - 98 98 98 98 100.00 98 - - 100.00 100.00 -
Challenged Persons
CY 2017 BEFF - Batch 1 1,250.00 1 1 - - 1 1 1 1 100.00 1 - - 100.00 100.00 -
CY 2017 BEFF - Batch 4 105,809.43 33 33 - - 33 33 33 33 100.00 9 24 - 100.00 97.45 -2.55
CY 2017 BEFF - Batch 5 8,194.23 3 3 - - 3 3 3 3 100.00 - 3 - 100.00 95.37 -4.63
CY 2017 BEFF - Batch 7 140,189.85 44 44 - - 44 44 44 44 100.00 9 35 - 99.96 96.62 -3.34
CY 2017 BEFF - Batch 13 290,959.15 69 69 - - 69 69 69 69 100.00 24 45 - 99.98 96.72 -3.26
CY 2017 BEFF - Batch 10 76,919.86 26 26 - - 26 26 26 26 100.00 6 20 - 100.00 92.98 -7.02
CY 2017 BEFF - Batch 11 2,794.73 1 1 - - 1 1 1 1 100.00 1 - - 100.00 100.00 -
Sub-total 767,941.87 282 282 - - 282 282 282 282 100.00 152 130 - 99.99 96.59 -3.40
TOTAL 1,036,044.14 325 325 - - 325 325 325 325 100.00 194 131 - 99.99 97.29 -2.70
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
1. Project I.D : P00272788MN-CW1 a) 33,966.98 a) By Contract P
Contract I.D : 18MH0104 b) 33,966.98 b) 25-Jun-18 R
Datu Guiabar Pilot School, Kalamansig c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 205 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 3 stry- 15CL g) ALANGCA, H.D.
2. Project I.D : P00272789MN-CW1 a) 22,494.37 a) By Contract P
Contract I.D : 18MH0105 b) 22,494.37 b) 25-Jun-18 R
Salangsang Elementary School, Lebak c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 175 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- 10CL g) DURUIN, P.S.
3. Project I.D : P00272790MN-CW1 a) 10,235.63 a) By Contract P
Contract I.D : 18MH0106 b) 10,235.63 b) 25-Jun-18 R
Bagumbayan NHS, Bagumbayan c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) COLOMA, J.A.E.
Page 1 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
4. Project I.D : P00272791MN-CW1 a) 10,175.93 a) By Contract P
Contract I.D : 18MH0107 b) 10,175.93 b) 25-Jun-18 R
Kapaya NHS, Bagumbyan, c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) COLOMA, J.A.E.
5. Project I.D : P00272792MN-CW1 a) 10,255.53 a) By Contract P
Contract I.D : 18MH0108 b) 10,255.53 b) R
Masiag NHS-Bagumbayan Annex, c) 29-May-18 c) A
Bagumbayan, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bidding re-scheduled on July 05, 2018 due to revision of Plans and POW.
g) 2 stry- ICT Lab. g) COLOMA, J.A.E.
6. Project I.D : P00272793MN-CW1 a) 10,275.43 a) By Contract P
Contract I.D : 18MH0109 b) 10,275.43 b) 25-Jun-18 R
Bai Saripinang NHS, Bagumbayan c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) SANTOS, L.P.
Page 2 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
7. Project I.D : P00272794MN-CW1 a) 10,175.93 a) By Contract P
Contract I.D : 18MH0110 b) 10,175.93 b) R
E. Arcaño Memorial NHS, Lebak, c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bidding re-scheduled on July 05, 2018 due to revision of Plans and POW.
g) 2 stry- ICT Lab. g) ALANGCA, H.D.
8. Project I.D : P00272795MN-CW1 a) 10,215.73 a) By Contract P
Contract I.D : 18MH0111 b) 10,215.73 b) 25-Jun-18 R
Busok NHS, Bagumbayan, c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) COLOMA, J.A.E.
9. Project I.D : P00272796MN-CW1 a) 10,175.93 a) By Contract P
Contract I.D : 18MH0112 b) 10,175.93 b) 25-Jun-18 R
Esperanza NHS, Esperanza c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) SANTOS, L.P.
Page 3 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
10. Project I.D : P00272797MN-CW1 a) 25,119.96 a) By Contract P
Contract I.D : 18MH0113 b) 25,119.96 b) 25-Jun-18 R
Esperanza NHS, Esperanza c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 140 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 units, 2 stry- 6CL g) SANTOS, L.P.
11. Project I.D : P00272798MN-CW1 a) 36,123.49 a) By Contract P
Contract I.D : 18MH0114 b) 36,123.49 b) 25-Jun-18 R
Esperanza NHS, Esperanza c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 195 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 4 stry- 12CL g) SANTOS, L.P.
12. Project I.D : P00272799MN-CW1 a) 10,175.93 a) By Contract P
Contract I.D : 18MH0115 b) 10,175.93 b) 25-Jun-18 R
Kalamansig NHS, Kalamansig c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) ALANGCA, H.D.
Page 4 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
13. Project I.D : P00272800MN-CW1 a) 25,436.05 a) By Contract P
Contract I.D : 18MH0116 b) 25,436.05 b) 25-Jun-18 R
Kalamansig NHS, Kalamansig c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 3 stry- 9 CL g) ALANGCA, H.D.
14. Project I.D : P00272801MN-CW1 a) 10,255.53 a) By Contract P
Contract I.D : 18MH0117 b) 10,255.53 b) 25-Jun-18 R
Sangay NHS, Kalamansig c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) CADUNGOG, M.P.
15. Project I.D : P00272802MN-CW1 a) 10,235.63 a) By Contract P
Contract I.D : 18MH0118 b) 10,235.63 b) 25-Jun-18 R
Datu Wasay NHS, Kalamansig c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) GUARDIANO, R.C.
Page 5 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
16. Project I.D : P00272803MN-CW1 a) 10,335.13 a) By Contract P
Contract I.D : 18MH0119 b) 10,335.13 b) 25-Jun-18 R
Langgal NHS, Sen. Ninoy Aquino, c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) COLOMA, J.A.E.
17. Project I.D : P00272804MN-CW1 a) 10,215.73 a) By Contract P
Contract I.D : 18MH0120 b) 10,215.73 b) 25-Jun-18 R
Gapok NHS-Langgal Annex, c) 29-May-18 c) A
Sen. Ninoy Aquino, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) COLOMA, J.A.E.
18. Project I.D : P00272805MN-CW1 a) 10,215.73 a) By Contract P
Contract I.D : 18MH0121 b) 10,215.73 b) 25-Jun-18 R
Sen. Ninoy Aquino NHS, c) 29-May-18 c) A
Sen. Ninoy Aquino, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) COLOMA, J.A.E.
Page 6 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
19. Project I.D : P00272806MN-CW1 a) 10,215.73 a) By Contract P
Contract I.D : 18MH0122 b) 10,215.73 b) 25-Jun-18 R
Lebak NHS, Lebak, Sultan Kudarat c) 29-May-18 c) A
d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) ALANGCA, H.D.
20. Project I.D : P00272807MN-CW1 a) 10,295.33 a) By Contract P
Contract I.D : 18MH0123 b) 10,295.33 b) 25-Jun-18 R
Keytodac NHS, Lebak, Sultan Kudarat c) 29-May-18 c) A
d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) GUARDIANO, R.C.
21. Project I.D : P00272808MN-CW1 a) 10,215.73 a) By Contract P
Contract I.D : 18MH0124 b) 10,215.73 b) 25-Jun-18 R
Lebak Legislated NHS, Lebak, c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) ALANGCA, H.D.
Page 7 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
22. Project I.D : P00272809MN-CW1 a) 12,559.98 a) By Contract P
Contract I.D : 18MH0125 b) 12,559.98 b) 25-Jun-18 R
Lebak Legislated NHS, Lebak, c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 140 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry-6CL g) ALANGCA, H.D.
23. Project I.D : P00272810MN-CW1 a) 10,295.33 a) By Contract P
Contract I.D : 18MH0126 b) 10,295.33 b) 25-Jun-18 R
Milbuk National High School, c) 29-May-18 c) A
Palimbang, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) GUIAMEL, M.D.
24. Project I.D : P00272811MN-CW1 a) 10,295.33 a) By Contract P
Contract I.D : 18MH0127 b) 10,295.33 b) 25-Jun-18 R
Baluan Senior High School, c) 29-May-18 c) A
Palimbang, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) COLOMA, J.A.E.
Page 8 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
25. Project I.D : P00272812MN-CW1 a) 12,858.48 a) By Contract P
Contract I.D : 18MH0128 b) 12,858.48 b) 25-Jun-18 R
Baluan Senior High School, c) 29-May-18 c) A
Palimbang, Sultan Kudarat d) d) S
e) e)
f) 140 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- 6CL g) COLOMA, J.A.E.
26. Project I.D : P00272813MN-CW1 a) 10,175.93 a) By Contract P
Contract I.D : 18MH0129 b) 10,175.93 b) 25-Jun-18 R
New Panay NHS, Esperanza, c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) SANTOS, L.P.
27. Project I.D : P00272814MN-CW1 a) 10,295.33 a) By Contract P
Contract I.D : 18MH0130 b) 10,295.33 b) 25-Jun-18 R
Palimbang National High School, c) 29-May-18 c) A
Palimbang, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 25, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) GUIAMEL, M.D.
Page 9 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
28. Project I.D : P00272815MN-CW1 a) 10,175.93 a) By Contract P
Contract I.D : 18MH0131 b) 10,175.93 b) 26-Jun-18 R
Purikay National High School, c) 29-May-18 c) A
Lebak, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 26, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) ALANGCA, H.D.
29. Project I.D : P00272816MN-CW1 a) 10,175.93 a) By Contract P
Contract I.D : 18MH0132 b) 10,175.93 b) 26-Jun-18 R
Salabaca NHS, Esperanza, c) 29-May-18 c) A
Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 26, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) SANTOS, L.P.
30. Project I.D : P00272817MN-CW1 a) 10,175.93 a) By Contract P
Contract I.D : 18MH0133 b) 10,175.93 b) 26-Jun-18 R
Sta.Clara National High School, c) 29-May-18 c) A
Kalamansig, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 26, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) ALANGCA, H.D.
Page 10 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
31. Project I.D : P00272818MN-CW1 a) 10,175.93 a) By Contract P
Contract I.D : 18MH0134 b) 10,175.93 b) 26-Jun-18 R
Tran National High School, c) 29-May-18 c) A
Lebak, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 26, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) ALANGCA, H.D.
32. Project I.D : P00272819MN-CW1 a) 10,255.53 a) By Contract P
Contract I.D : 18MH0135 b) 10,255.53 b) 25-Jun-18 R
Sewod NHS-Langgal Annex, c) 29-May-18 c) A
Sen. Ninoy Aquino, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) For unlocking at Central Office.
g) 2 stry- ICT Lab. g) COLOMA, J.A.E.
33. Project I.D : P00272820MN-CW1 a) 10,175.93 a) By Contract P
Contract I.D : 18MH0136 b) 10,175.93 b) 26-Jun-18 R
Biwang NHS-Bagumbayan Annex, c) 29-May-18 c) A
Bagumbayan, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 26, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) COLOMA, J.A.E.
Page 11 of 12
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Basic Educational Facilities Fund (BEFF - Batch 1)
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #:SR2018-05-009295 Dated: May 10, 2018
34. Project I.D : P00272821MN-CW1 a) 10,235.63 a) By Contract P
Contract I.D : 18MH0137 b) 10,235.63 b) 26-Jun-18 R
Mangudadatu NHS-Villamonte Annex, c) 29-May-18 c) A
Lebak, Sultan Kudarat d) d) S
e) e)
f) 120 C.D. f) Bid-out on June 26, 2018. Post-qualification on-going.
g) 2 stry- ICT Lab. g) DURUIN, P.S.
444,662.6672200 Page 12 of 12

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Department of Agrarian Reform (DAR) Projects
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE


a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A FY = 2019 Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
1. Project I.D : a) 33,476.32 a) By Contract P 97.77 100.00 100.00 100.00 100.00 1.79 15.63 29.46 43.84 56.70 70.09
Contract I.D : 18MH0101 b) b) 01-Jun-18 R 97.77 100.00 100.00 100.00 100.00 1.79 15.63 29.46 43.84 56.70 70.09
Construction of Baluan Bridge, c) c) 21-Jun-18 A 2.50
Palimbang, Sultan Kudarat d) ST. GERRARD CONST. GEN. d) 27-Jun-18 S 0.71
e) 31,768,512.25 e) 05-Feb-19
f) 224 C.D. f) Notice to Proceed issued on June 21, 2018. On-going.
g) g) COLOMA, J.A.E.
FY = 2019 Current Year = 2018
1. Project I.D : a) 72,127.08 a) By Contract P 87.25 98.41 100.00 100.00 100.00 1.59 14.17 26.29 43.84 50.60 62.55
Contract I.D : 18MH0102 b) b) 01-Jun-18 R 87.25 98.41 100.00 100.00 100.00 1.59 14.17 26.29 43.84 50.60 62.55
Const/Rehab of Sitio Puting Bato-Sitio Tagpuan, c) c) 21-Jun-18 A 3.00
Kalibuhan-Sitio Tabaca-Sitio Lihek-Purok 3, d) LEGACY CONST. & SUPPLY d) 27-Jun-18 S 1.41
Baluan (Brgy. Kalibuhan-Brgy. Baluan) FMR, e) 68,435,156.48 e) 04-Mar-19
Palimbang, Sultan Kudarat f) 251 C.D. f) Notice to Proceed issued on June 21, 2018. On-going.
g) g) GUIAMEL, M.D.
105,603.40 Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
2018

DEC

83.93
83.93

2018
74.90
74.90

Page 1 of 1

AHA, Ph.D.
gineer
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Department of Agriculture (DA) Proposed Projects
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %
a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
SARO #: SR2018-03-007322 Dated: March 05, 2018
1. Project I.D : P00266238MN_CW1 a) 10,000.00 a) By Contract P - - - - 19.99 63.54 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0087 b) 10,000.00 b) 19-Apr-18 R - - - - 19.99 63.54 100.00 100.00 100.00 100.00 100.00 100.00
Concreting of Tuka-Busok FMR, Brgy. Tuka and c) c) 09-May-18 A - - - - 25.00 60.00
Brgy. Busok, Bagumbayan, Sultan Kudarat d) RAQI BUILDERS CONST. & S d) 15-May-18 S - - - - 5.01 -3.54
e) 9,651,500.00 e) 22-Jul-18
f) 69 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) 1 km g) COLOMA, J.A.E
SARO #: SR2018-03-007320 Dated: March 05, 2018
2. Project I.D : P00266239MN_CW1 a) 10,000.00 a) By Contract P - - - - 24.64 68.12 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0088 b) 10,000.00 b) 19-Apr-18 R - - - - 24.64 68.12 100.00 100.00 100.00 100.00 100.00 100.00
Concreting of Keytodac- New Calinog FMR, c) c) 09-May-18 A - - - - 25.00 64.00
Brgy. Keytodac, Lebak, Sultan Kudarat d) MUST ENTERPRISES d) 15-May-18 S - - - - 0.36 -4.12
e) 9,657,797.76 e) 22-Jul-18
f) 69 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) 1 km g) DURUIN, P.S.
SARO #: SR2018-03-007321 Dated: March 05, 2018
3. Project I.D : P00266237MN_CW1 a) 7,000.00 a) By Contract P - - - - 24.21 79.58 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0089 b) 7,000.00 b) 19-Apr-18 R - - - - 24.21 79.58 100.00 100.00 100.00 100.00 100.00 100.00
Concreting of Purok Narra-Brgy. Poblacion FMR, c) c) 09-May-18 A - - - - 30.00 74.95
Brgy. Numo, Esperanza, Sultan Kudarat d) RAQI BUILDERS CONST. & S d) 15-May-18 S - - - - 5.79 -4.63
e) 6,756,050.00 e) 10-Jul-18
f) 57 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) 0.700 km g) SANTOS, L.P.
27,000.00 Page 1 of 1
PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
CY 2018 Construction of Rain Water Collector System (CWRCS)
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE


a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Y b) Date Bid A Current Year = 2018
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location
d) Contractor d) Start Date C
(Scope of Work/Physical Target)
e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P

1. Project I.D : a) 3,366.00 a) By Contract P - - - 21.67 46.67 72.50 98.33 100.00 100.00 100.00 100.00
Contract I.D : 18MH0058 b) 3,366.00 b) 10-Apr-18 R - - - 21.67 46.67 72.50 98.33 100.00 100.00 100.00 100.00
Construction of Rain Water Collection System c) c) 30-Apr-18 A - - - 5.00 22.00 47.00
(RWCS) d) JV CONSTECH d) 06-May-18 S - - - 5.00 0.33 0.33
1. Ugis ES, Esperanza 11. Buenaflores ES, SNA e) 3,281,000.00 e) 02-Sep-18
2. Sultan Sinanggayan IS, 12. Salangsang ES, Lebak f) 120 C.D. f)
Esperanza 13. Bululawan ES, Lebak g) 2.80 lane Km. g) DURUIN, P.S.
3. Numo ES, Esperanza 14. Mangudadatu NHS-
4. Pamantingan ES, Villamonte Annex, Lebak
5. Salumpipng NHS, 15. S.A. Balabagan ES, Lebak
6. Spur 2 ES, Bagumbayan 16. Salaman CES, Lebak On-going
7. San Vicente ES, 17. Pasandalan ES, Lebak
Bagumbayan
8. Kapaya ES, Bagumbayan
9. Gapok NHS, SNA
10. Malegdeg ES, SNA

Page 1 of 1

PREPARED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P

1. Project I.D : P00253471MN_CW1 a) 1,000.00 a) by Contract P - - 7.65 55.41 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0028 b) 1,000.00 b) 13-Feb-18 R - - 7.65 55.41 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Datu Guiabar Pilot School, Brgy. Poblacion, c) c) 22-Mar-18 A - - 8.00 70.00 100.00
Kalamansig, Sultan Kudarat d) JV CONSTECH d) 28-Mar-18 S - - 0.35 14.59 -
e) 986,274.51 e) 21-May-18
f) 55 C.D. f) Completed on May 21, 2018.
g) 1 CL g) ALANGCA, H.D.
2. Project I.D : P00253472MN_CW1 a) 1,000.00 a) by Contract P - - 7.65 55.41 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0030 b) 1,000.00 b) 13-Feb-18 R - - 7.65 55.41 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Barurao 2 Primary School - Pakil Elementary c) c) 22-Mar-18 A - - 8.25 70.00 96.00 97.55
School Annex, Brgy. Barurao 2, Lebak, d) JV CONSTECH d) 28-Mar-18 S - - 0.60 14.59 -4.00 -2.45
Sultan Kudarat e) 986,274.51 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
g) 1 CL g) ALANGCA, H.D. damages.
3. Project I.D : P00253473MN_CW1 a) 1,000.00 a) by Contract P - - 0.34 47.24 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0029 b) 1,000.00 b) 13-Feb-18 R - - 0.34 47.24 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
SNA National High School, Brgy. Kulaman, c) c) 22-Mar-18 A - - 7.50 60.00 95.25 95.28
Senator Ninoy Aquino, Sultan Kudarat d) ALBANOR CONSTRUCTION d) 28-Mar-18 S - - 7.16 12.76 -4.75 -4.72
e) 987,496.61 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) 1 CL g) COLOMA, J.A.E
4. Project I.D : P00253460MN_CW1 a) 1,000.00 a) by Contract P - - 4.98 51.72 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0027 b) 1,000.00 b) 13-Feb-18 R - - 4.97 51.72 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Capilan, c) c) 22-Mar-18 A - - 8.25 65.00 96.00 96.05
Lebak, Sultan Kudarat d) JV CONSTECH d) 28-Mar-18 S - - 3.28 13.28 -4.00 -3.95
e) 985,345.40 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
RA g) 1 CL g) GUARDIANO, R.C.
5. Project I.D : P00253461MN_CW1 a) 1,000.00 a) by Contract P - - 20.35 81.16 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0009 b) 1,000.00 b) 14-Dec-17 R - - 20.35 81.16 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Malatunol, c) c) 16-Mar-18 A - - 18.35 70.00 98.10 98.16
Palimbang, Sultan Kudarat d) FPJ CONST. & SUPPLY d) 22-Mar-18 S - - -2.00 -11.16 -1.90 -1.84
e) 989,216.41 e) 15-May-18
f) 55 C.D. f) On-going, for imposition of liquidated damages.
g) 1 CL g) MANGATONG, R.
Page 1 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
6. Project I.D : P00253462MN_CW1 a) 1,000.00 a) by Contract P - - 3.70 55.83 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0036 b) 1,000.00 b) 30-Jan-18 R - - 3.70 55.83 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Senior Citizen Building, Dukay, c) c) 22-Mar-18 A - - 8.00 60.00 96.00 96.06
Esperanza, Sultan Kudarat d) CS CONST. & SUPPLY d) 28-Mar-18 S - - 4.30 4.17 -4.00 -3.94
e) 980,668.81 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) 1 CL g) SANTOS, L.P.
7. Project I.D : P00253463MN_CW1 a) 1,000.00 a) by Contract P - - - 34.55 90.91 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0037 b) 1,000.00 b) 27-Mar-18 R - - - 34.55 90.91 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Senior Citizen Building, Poblacion 2, Lebak, c) c) 06-Apr-18 A - - - 40.00 92.00 92.05 - - - - - -
Sultan Kudarat d) JV CONSTECH d) 12-Apr-18 S - - - 5.45 1.09 -7.95 - - - - - -
e) 987,454.45 e) 05-Jun-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
g) 1 CL g) ALANGCA, H.D. damages.
8. Project I.D : P00253464MN_CW1 a) 1,000.00 a) by Contract P - - - 50.91 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0034 b) 1,000.00 b) 27-Feb-18 R - - - 50.91 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Senior Citizen Building, Gapok, c) c) 28-Mar-18 A - - 3.00 48.00 96.00 96.05
Senator Ninoy Aquino, Sultan Kudarat d) CS CONST. & SUPPLY d) 03-Apr-18 S - - 3.00 -2.91 -4.00 -3.95
e) 988,000.00 e) 27-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
g) 1 CL g) DURUIN, P.S. damages.
9. Project I.D : P00253466MN_CW1 a) 1,000.00 a) by Contract P - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0077 b) 1,000.00 b) 24-Apr-18 R - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Rehabilitation of Multi-purpose Building, c) c) 09-May-18 A - - - - 30.00 80.00 - - - - - -
Poblacion, Kalamansig, Sultan Kudarat d) JV CONSTECH d) 15-May-18 S - - - - 1.67 1.67 - - - - - -
e) 979,303.29 e) 13-Jul-18
f) 60 C.D. f) On-going
g) g) ALANGCA, H.D.
10. Project I.D : P00253467MN_CW1 a) 2,000.00 a) by Contract P - - 0.63 14.03 50.37 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0007 b) 2,000.00 b) 27-Dec-17 R - - 0.63 14.03 50.37 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Multi-purpose Building, c) c) 22-Mar-18 A - - 6.25 35.00 51.00 90.16
South Sepaka, Bagumbayan, Sultan Kudarat d) CS CONST. & SUPPLY d) 28-Mar-18 S - - 5.62 20.97 0.63 -9.84
e) 1,886,236.92 e) 25-Jun-18
f) 90 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) SANTOS, L.P.
Page 2 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
11. Project I.D : P00253468MN_CW1 a) 2,000.00 a) by Contract P - - 5.88 34.56 65.96 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D :18MH0006 b) 2,000.00 b) 14-Dec-17 R - - 5.88 34.56 65.96 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Multi-purpose Building, Mina, c) c) 12-Mar-18 A - - 18.70 46.00 79.00 90.73
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 18-Mar-18 S - - 12.82 11.44 13.04 -9.27
e) 1,886,500 e) 15-Jun-18
f) 90 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) MANGATONG, R.
12. Project I.D : P00253469MN_CW1 a) 700.00 a) by Contract P - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0074 b) 700.00 b) 19-Apr-18 R - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 09-May-18 A - - - - 30.00 80.00 - - - - - -
Poblacion 1, Lebak, Sultan Kudarat d) JV CONSTECH d) 15-May-18 S - - - - 1.67 1.67 - - - - - -
e) 681,322.12 e) 13-Jul-18
f) 60 C.D. f) On-going
g) g) ALANGCA, H.D.
13. Project I.D : P00253470MN_CW1 a) 1,000.00 a) by Contract P - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0071 b) 1,000.00 b) 19-Apr-18 R - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 09-May-18 A - - - - 30.00 70.00 - - - - - -
Poblacion, Palimbang, Sultan Kudarat d) JV CONSTECH d) 15-May-18 S - - - - 1.67 -8.33 - - - - - -
e) 988,000.00 e) 13-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) MANGATONG, R.
14. Project I.D : P00253474MN_CW1 a) 1,000.00 a) by Contract P - - 3.57 55.73 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0025 b) 1,000.00 b) 13-Feb-18 R - - 3.57 55.73 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Sison, c) c) 22-Mar-18 A - - 7.65 60.00 96.00 96.21
Bagumbayan, Sultan Kudarat d) CS CONST. & SUPPLY d) 28-Mar-18 S - - 4.08 4.27 -4.00 -3.79
e) 987,946.00 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) SANTOS, L.P.
15. Project I.D : P00255352MN_CW1 a) 1,000.00 a) by Contract P - - 5.70 84.26 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0011 b) 1,000.00 b) 08-Feb-17 R - - 5.70 84.26 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Marguez, c) c) 12-Mar-18 A - - 25.75 76.35 95.50 95.61
Esperanza, Sultan Kudarat d) ALBANOR CONSTRUCTION d) 18-Mar-18 S - - 20.05 -7.91 -4.50 -4.39
e) 984,500.00 e) 11-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) SANTOS, L.P.
Page 3 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
16. Project I.D : P00253475MN_CW1 a) 1,000.00 a) by Contract P - - 25.45 80.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0043 b) 1,000.00 b) 30-Jan-18 R - - 25.45 80.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Kangkong, c) c) 12-Mar-18 A - - 26.00 77.00 95.90 100.00
Esperanza, Sultan Kudarat d) ALBANOR CONSTRUCTION d) 18-Mar-18 S - - 0.55 -3.00 -4.10 -
e) 986,000.00 e) 11-May-18
f) 55 C.D. f) Completed on June 20, 2018.
g) g) SANTOS, L.P.
17. Project I.D : P00253476MN_CW1 a) 1,000.00 a) by Contract P - - 12.62 81.77 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0024 b) 1,000.00 b) 18-Dec-17 R - - 12.62 81.77 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Daladap, c) c) 12-Mar-18 A - - 26.00 78.00 95.80 100.00
Esperanza, Sultan Kudarat d) ALBANOR CONSTRUCTION d) 18-Mar-18 S - - 13.38 -3.77 -4.20 -
e) 965,966.26 e) 11-May-18
f) 55 C.D. f) Completed on June 20, 2018.
g) g) SANTOS, L.P.
18. Project I.D : P00253477MN_CW1 a) 1,000.00 a) by Contract P - - 0.40 57.20 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0023 b) 1,000.00 b) 20-Feb-18 R - - 0.40 57.20 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Salumping, c) c) 22-Mar-18 A - - 8.00 60.00 95.85 95.88
Esperanza, Sultan Kudarat d) ALBANOR CONSTRUCTION d) 28-Mar-18 S - - 7.60 2.80 -4.15 -4.12
e) 988,500.00 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) CADUNGOG, M.P.
19. Project I.D : P00253478MN_CW1 a) 1,000.00 a) by Contract P - - 8.78 74.10 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0022 b) 1,000.00 b) 18-Dec-17 R - - 8.78 74.10 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Saliao, c) c) 16-Mar-18 A - - 18.95 71.25 95.69 95.80
Esperanza, Sultan Kudarat d) ALBANOR CONSTRUCTION d) 22-Mar-18 S - - 10.17 -2.85 -4.31 -4.20
e) 975,266.26 e) 15-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) SANTOS, L.P.
20. Project I.D : P00253479MN_CW1 a) 1,000.00 a) by Contract P - - 12.33 81.98 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0021 b) 1,000.00 b) 18-Dec-17 R - - 12.33 81.98 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Laguinding, c) c) 12-Mar-18 A - - 18.85 72.00 95.80 100.00
Esperanza, Sultan Kudarat d) CS CONST. & SUPPLY d) 18-Mar-18 S - - 6.52 -9.98 -4.20 -
e) 981,854.86 e) 11-May-18
f) 55 C.D. f) Completed on June 20, 2018.
g) g) SANTOS, L.P.
Page 4 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
21. Project I.D : P00255350MN_CW1 a) 1,000.00 a) by Contract P - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0082 b) 1,000.00 b) 24-Apr-18 R - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction MPB (Brgy. Hall), Legodon, c) c) 09-May-18 A - - - - 25.00 70.00 - - - - - -
Esperanza, Sultan Kudarat d) ALBANOR CONSTRUCTION d) 15-May-18 S - - - - -3.33 -8.33 - - - - - -
e) 987,500.00 e) 08-Jul-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) GUARDIANO, R.C.
22. Project I.D : P00253480MN_CW1 a) 1,000.00 a) by Contract P - - 0.52 55.47 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0013 b) 1,000.00 b) 08-Feb-18 R - - 0.52 55.47 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Magsaysay, c) c) 22-Mar-18 A - - 7.50 60.00 95.25 100.00
Esperanza, Sultan Kudarat d) ALBANOR CONSTRUCTION d) 28-Mar-18 S - - 6.98 4.53 -4.75 -
e) 985,000.00 e) 21-May-18
f) 55 C.D. f) Completed on June 20, 2018.
g) g) SANTOS, L.P.
23. Project I.D : P00253481MN_CW1 a) 1,000.00 a) by Contract P - - 6.19 53.22 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0014 b) 1,000.00 b) 08-Feb-18 R - - 6.19 53.22 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Pag-asa, c) c) 22-Mar-18 A - - 7.95 15.00 90.25 90.31
Kalamansig, Sultan Kudarat d) JV CONSTECH d) 28-Mar-18 S - - 1.76 -38.22 -9.75 -9.69
e) 985,547.65 e) 21-May-18
f) 55 C.D. f) 05-Jun-18 On-going, project delayed due to demolition of existing dilapidated building. For revision of scheduled project
implementation.
g) g) ALANGCA, H.D.
24. Project I.D : P00253482MN_CW1 a) 1,000.00 a) by Contract P - - - - - 36.36 92.73 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0080 b) 1,000.00 b) 09-May-18 R - - - - - 36.36 92.73 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Barurao I, c) c) 05-Jun-18 A - - - - 5.00 40.00 - - - - - -
Lebak, Sultan Kudarat d) ROBETH GEN. MDSE. d) 11-Jun-18 S - - - - 5.00 3.64 - - - - - -
e) 955,349.77 e) 04-Aug-18
f) 55 C.D. f) On-going.
g) g) ALANGCA, H.D.
25. Project I.D : P00255351MN_CW1 a) 1,000.00 a) by Contract P - - 6.19 53.22 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0010 b) 1,000.00 b) 08-Feb-18 R - - 6.19 53.22 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Christianuevo, c) c) 22-Mar-18 A - - 8.25 60.00 91.25 92.02
Lebak, Sultan Kudarat d) JV CONSTECH d) 28-Mar-18 S - - 2.06 6.78 -8.75 -7.98
e) 985,547.65 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) ALANGCA, H.D.
Page 5 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
26. Project I.D : P00253483MN_CW1 a) 1,000.00 a) by Contract P - - 4.98 51.72 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0015 b) 1,000.00 b) 08-Feb-18 R - - 4.98 51.72 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Bululawan, c) c) 22-Mar-18 A - - 8.25 60.00 91.50 92.92
Lebak, Sultan Kudarat d) JV CONSTECH d) 28-Mar-18 S - - 3.27 8.28 -8.50 -7.08
e) 985,333.12 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) ALANGCA, H.D.
27. Project I.D : P00253484MN_CW1 a) 1,000.00 a) by Contract P - - 5.90 60.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0016 b) 1,000.00 b) 13-Feb-18 R - - 5.90 60.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Kanipaan, c) c) 22-Mar-18 A - - 8.25 60.00 95.35 95.46
Palimbang, Sultan Kudarat d) ILON MULTIBUILDERS CO. d) 28-Mar-18 S - - 2.35 -0.60 -4.65 -4.54
e) 982,329.99 e) 21-May-18
f) 55 C.D. f) 20-Jun-18 On-going, project delayed due to bad weather condition prevailing in the area. For revision of implementation
scheduled.
g) g) GUIAMEL, M.D.
28. Project I.D : P00255353MN_CW1 a) 1,000.00 a) by Contract P - - 5.90 60.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0017 b) 1,000.00 b) 13-Feb-18 R - - 5.90 60.60 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Poblacion, c) c) 22-Mar-18 A - - 7.35 60.00 95.45 95.51
Palimbang, Sultan Kudarat d) ILON MULTIBUILDERS CO. d) 28-Mar-18 S - - 1.45 -0.60 -4.55 -4.49
e) 982,329.99 e) 21-May-18
f) 55 C.D. f) 20-Jun-18 On-going, project delayed due to bad weather condition prevailing in the area. For revision of implementation
scheduled.
g) g) GUIAMEL, M.D.
29. Project I.D : P00253485MN_CW1 a) 1,000.00 a) by Contract P - - 4.51 65.20 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0018 b) 1,000.00 b) 13-Feb-18 R - - 4.51 65.20 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Kisek, c) c) 22-Mar-18 A - - 7.80 60.00 95.05 95.08
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 28-Mar-18 S - - 3.29 -5.20 -4.95 -4.92
e) 987,500.00 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) MANGATONG, R.
30. Project I.D : P00253486MN_CW1 a) 1,000.00 a) by Contract P - - 6.21 62.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0019 b) 1,000.00 b) 13-Feb-18 R - - 6.21 62.18 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Akol, c) c) 22-Mar-18 A - - 8.00 60.00 95.15 95.18
Palimbang, Sultan Kudarat d) ILON MULTIBUILDERS CO. d) 28-Mar-18 S - - 1.79 -2.18 -4.85 -4.82
e) 982,329.99 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) MANGATONG, R.
Page 6 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
31. Project I.D : P00253487MN_CW1 a) 1,000.00 a) by Contract P - - 26.70 87.07 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0026 b) 1,000.00 b) 13-Feb-18 R - - 26.70 87.07 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Langali, c) c) 12-Mar-18 A - - 27.00 76.00 95.50 95.53
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 18-Mar-18 S - - 0.30 -11.07 -4.50 -4.47
e) 987,986.58 e) 11-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) MANGATONG, R.
32. Project I.D : P00253488MN_CW1 a) 1,000.00 a) by Contract P - - 7.54 57.64 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0012 b) 1,000.00 b) 08-Feb-18 R - - 7.54 57.64 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Malegdeg, c) c) 16-Mar-18 A - - 19.00 70.00 95.80 95.83
Senator Ninoy Aquino, Sultan Kudarat d) CS CONST. & SUPPLY d) 22-Mar-18 S - - 11.46 12.36 -4.20 -4.17
e) 987,000.00 e) 15-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) COLOMA, J.A.E
33. Project I.D : P00253489MN_CW1 a) 1,000.00 a) by Contract P - - 1.84 44.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0020 b) 1,000.00 b) 13-Feb-18 R - - 1.84 44.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Buklod, c) c) 22-Mar-18 A - - 8.20 60.00 95.24 95.27
Senator Ninoy Aquino, Sultan Kudarat d) CS CONST. & SUPPLY d) 28-Mar-18 S - - 6.36 15.50 -4.76 -4.73
e) 988,000.00 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) COLOMA, J.A.E
34. Project I.D : P00255349MN_CW1 a) 1,000.00 a) by Contract P - - - - - 36.36 92.73 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0079 b) 1,000.00 b) 09-May-18 R - - - - - 36.36 92.73 100.00 100.00 100.00 100.00 100.00
Construction of MPB (Brgy. Hall), Bugso, c) c) 05-Jun-18 A - - - - 5.00 30.00 - - - - - -
Senator Ninoy Aquino, Sultan Kudarat d) COFEJOK CONST. & SUPPLY d) 11-Jun-18 S - - - - 5.00 -6.36 - - - - - -
e) 988,500.00 e) 04-Aug-18
f) 55 C.D. f) On-going, project dlayed due to bad weather condition prevailing in the area.
g) g) COLOMA, J.A.E
35. Project I.D : P00253490MN_CW1 a) 1,000.00 a) by Contract P - - 1.84 44.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0008 b) 1,000.00 b) 08-Feb-18 R - - 1.84 44.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Barangay Hall, Tacupis, c) c) 22-Mar-18 A - - 8.65 61.00 95.15 95.18
Senator Ninoy Aquino, Sultan Kudarat d) CS CONST. & SUPPLY d) 28-Mar-18 S - - 6.81 16.50 -4.85 -4.82
e) 988,000.00 e) 21-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) COLOMA, J.A.E
Page 7 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
36. Project I.D : P00253491MN_CW1 a) 1,000.00 a) by Contract P - - 12.80 81.93 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0035 b) 1,000.00 b) 30-Jan-18 R - - 12.80 81.93 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Senior Citizen Building, c) c) 12-Mar-18 A - - 26.00 78.00 95.80 100.00
Poblacion, Bagumbayan, Sultan Kudarat d) CS CONST. & SUPPLY d) 18-Mar-18 S - - 13.20 -3.93 -4.20 -
e) 982,935.83 e) 11-May-18
f) 55 C.D. f) Completed on June 20, 2018.
g) g) SANTOS, L.P.
37. Project I.D : P00253492MN_CW1 a) 1,000.00 a) by Contract P - - - 34.55 90.91 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0033 b) 1,000.00 b) 27-Mar-18 R - - - 34.55 90.91 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Senior Citizen Building, c) c) 06-Apr-18 A - - - 32.00 85.95 90.13 - - - - - -
Salangsang, Lebak, Sultan Kudarat d) JV CONSTECH d) 12-Apr-18 S - - - -2.55 -4.96 -9.87 - - - - - -
e) 987,523.28 e) 05-Jun-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) CADUNGOG, M.P.
38. Project I.D : P00253493MN_CW1 a) 2,000.00 a) by Contract P - - 0.68 14.53 50.71 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D :18MH0005 b) 2,000.00 b) 14-Dec-17 R - - 0.68 14.53 50.71 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Multipurpose Building, c) c) 22-Mar-18 A - - 7.00 37.00 52.00 90.26
Biwang National High School, Biwang, d) CS CONST. & SUPPLY d) 28-Mar-18 S - - 6.32 22.47 1.29 -9.74
Bagumbayan, Sultan Kudarat e) 1,885,170.07 e) 25-Jun-18
f) 90 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) SANTOS, L.P.
39. Project I.D : P00253494MN_CW1 a) 2,500.00 a) by Contract P - - 5.38 36.67 75.03 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0003 b) 2,500.00 b) 14-Dec-17 R - - 5.38 36.67 75.03 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Multipurpose Building, c) c) 16-Mar-18 A - - 14.32 50.00 65.00 90.95
Salaman, Lebak, Sultan Kudarat d) PHILTIL CONSTRUCTION d) 22-Mar-18 S - - 8.94 13.33 -10.03 -9.05
e) 2,364,052.86 e) 19-Jun-18
f) 90 C.D. f) On-going, for issuance of calibrated action.
g) g)
40. Project I.D : P00253495MN_CW1 a) 2,000.00 a) by Contract P - - 6.27 35.64 67.53 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0004 b) 2,000.00 b) 14-Dec-17 R - - 6.27 35.64 67.53 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Multipurpose Building, Cadiz, c) c) 16-Mar-18 A - - 14.32 50.00 63.00 90.18
Kalamansig, Sultan Kudarat d) JV CONSTECH d) 22-Mar-18 S - - 8.05 14.36 -4.53 -9.82
e) 1,906,333.25 e) 19-Jun-18
f) 90 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) ALANGCA, H.D.
Page 8 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
41. Project I.D : P00253496MN_CW1 a) 1,000.00 a) by Contract P - - - 50.91 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0032 b) 1,000.00 b) 30-Jan-18 R - - - 50.91 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Day Care Centers, Sewod, c) c) 28-Mar-18 A - - 3.00 48.00 95.65 95.69
Senator Ninoy Aquino, Sultan Kudarat d) CS CONST. & SUPPLY d) 03-Apr-18 S - - 3.00 -2.91 -4.35 -4.31
e) 988,000.00 e) 27-May-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For imposition of liquidated
damages.
g) g) DURUIN, P.S.
42. Project I.D : P00253497MN_CW1 a) 1,000.00 a) by Contract P - - - 50.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0031 b) 1,000.00 b) 27-Feb-18 R - - - 50.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Day Care Centers, Maguiales, c) c) 28-Mar-18 A - - 3.00 48.00 95.25 95.31
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 03-Apr-18 S - - 3.00 -2.00 -4.75 -4.69
e) 987,898.00 e) 27-May-18
f) 55 C.D. f) 26-Jun-18 On-going, project delayed due to bad weather condition prevailing in the area. For revision of implementation
scheduled.
g) g) GUIAMEL, M.D.
43. Project I.D : P00253499MN_CW1 a) 700.00 a) by Contract P - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0065 b) 700.00 b) 03-Apr-18 R - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 30-Apr-18 A - - - 3.00 39.00 84.00 - - - - - -
Kabulanan, Bagumbayan, Sultan Kudarat d) CS CONST. & SUPPLY d) 06-May-18 S - - - 3.00 -4.33 -9.33 - - - - - -
e) 670000 e) 04-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) COLOMA, J.A.E
44. Project I.D : P00253500MN_CW1 a) 800.00 a) by Contract P - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0072 b) 800.00 b) 19-Apr-18 R - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 09-May-18 A - - - - 24.00 69.00 - - - - - -
Kapaya, Bagumbayan, Sultan Kudarat d) COFEJOK CONST. & SUPPLY d) 15-May-18 S - - - - -4.33 -9.33 - - - - - -
e) 790,500.00 e) 13-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) DURUIN, P.S.
45. Project I.D : P00253501MN_CW1 a) 700.00 a) by Contract P - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0066 b) 700.00 b) 03-Apr-18 R - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 30-Apr-18 A - - - 3.00 39.00 84.00 - - - - - -
Tuka, Bagumbayan, Sultan Kudarat d) COFEJOK CONST. & SUPPLY d) 06-May-18 S - - - 3.00 -4.33 -9.33 - - - - - -
e) 684500 e) 04-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) COLOMA, J.A.E
Page 9 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
46. Project I.D : P00253502MN_CW1 a) 1,000.00 a) by Contract P - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0067 b) 1,000.00 b) 19-Apr-18 R - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 09-May-18 A - - - - 30.00 69.00 - - - - - -
Paitan, Esperanza, Sultan Kudarat d) COFEJOK CONST. & SUPPLY d) 15-May-18 S - - - - 1.67 -9.33 - - - - - -
e) 988,500.00 e) 13-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) SANTOS, L.P.
47. Project I.D : P00253503MN_CW1 a) 700.00 a) by Contract P - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0064 b) 700.00 b) 03-Apr-18 R - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 30-Apr-18 A - - - 3.00 44.00 95.05 - - - - - -
Limulan, Kalamansig, Sultan Kudarat d) JV CONSTECH d) 06-May-18 S - - - 3.00 0.67 1.72 - - - - - -
e) 678,691.68 e) 04-Jul-18
f) 60 C.D. f) On-going
g) g) ALANGCA, H.D.
48. Project I.D : P00253504MN_CW1 a) 700.00 a) by Contract P - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0060 b) 700.00 b) 03-Apr-18 R - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 30-Apr-18 A - - - 3.00 39.00 95.02 - - - - - -
Basak, Lebak, Sultan Kudarat d) JV CONSTECH d) 06-May-18 S - - - 3.00 -4.33 1.69 - - - - - -
e) 679,248.01 e) 04-Jul-18
f) 60 C.D. f) On-going
g) g) GUARDIANO, R.C.
49. Project I.D : P00253505MN_CW1 a) 700.00 a) by Contract P - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0059 b) 700.00 b) 03-Apr-18 R - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 30-Apr-18 A - - - 3.00 38.95 85.00 - - - - - -
Taguisa, Lebak, Sultan Kudarat d) COFEJOK CONST. & SUPPLY d) 06-May-18 S - - - 3.00 -4.38 -8.33 - - - - - -
e) 684,500.00 e) 04-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) GUARDIANO, R.C.
50. Project I.D : P00253506MN_CW1 a) 700.00 a) by Contract P - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0062 b) 700.00 b) 03-Apr-18 R - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 30-Apr-18 A - - - 3.00 38.75 85.02 - - - - - -
Kalamongog, Lebak, Sultan Kudarat d) JV CONSTECH d) 06-May-18 S - - - 3.00 -4.58 -8.31 - - - - - -
e) 678,422.71 e) 04-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) GUARDIANO, R.C.
Page 10 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
51. Project I.D : P00253507MN_CW1 a) 700.00 a) by Contract P - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0061 b) 700.00 b) 03-Apr-18 R - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 30-Apr-18 A - - - 3.00 38.50 83.71 - - - - - -
Nuling, Lebak, d) COFEJOK CONST. & SUPPLY d) 06-May-18 S - - - 3.00 -4.83 -9.62 - - - - - -
e) 684,500.00 e) 04-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) GUARDIANO, R.C.
52. Project I.D : P00253508MN_CW1 a) 700.00 a) by Contract P - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0073 b) 700.00 b) 19-Apr-18 R - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Gymnasium, c) c) 09-May-18 A - - - - 30.00 75.00 - - - - - -
Pamantingan, Esperanza, Sultan Kudarat d) CURVELINE CONST. d) 15-May-18 S - - - - 1.67 -3.33 - - - - - -
e) 685,929.48 e) 13-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) SANTOS, L.P.
53. Project I.D : P00253509MN_CW1 a) 700.00 a) by Contract P - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0075 b) 700.00 b) 19-Apr-18 R - - - - 28.33 78.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Multipurpose c) c) 09-May-18 A - - - - 30.00 75.00 - - - - - -
Building, Villamor, Esperanza, Sultan Kudarat d) CURVELINE CONST. d) 15-May-18 S - - - - 1.67 -3.33 - - - - - -
e) 685,923.06 e) 13-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) SANTOS, L.P.
54. Project I.D : P00253510MN_CW1 a) 700.00 a) by Contract P - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0063 b) 700.00 b) 03-Apr-18 R - - - - 43.33 93.33 100.00 100.00 100.00 100.00 100.00 100.00
Construction (Completion) of Multipurpose c) c) 30-Apr-18 A - - - 3.00 45.00 89.00 - - - - - -
Building, Sta. Clara, Kalamansig, Sultan Kudarat d) JV CONSTECH d) 06-May-18 S - - - 3.00 1.67 -4.33 - - - - - -
e) 679,551.60 e) 04-Jul-18
f) 60 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) ALANGCA, H.D.
55. Project I.D : P00253511MN_CW1 a) 1,000.00 a) by Contract P - - - - - 36.36 92.73 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0078 b) 1,000.00 b) 09-May-18 R - - - - - 36.36 92.73 100.00 100.00 100.00 100.00 100.00
Rehabilitation of Barangay Hall, Dumolol, c) c) 05-Jun-18 A - - - - 5.00 32.00 - - - - - -
Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 11-Jun-18 S - - - - 5.00 -4.36 - - - - - -
e) 988,000.00 e) 04-Aug-18
f) 55 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) MANGATONG, R.
Page 11 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
56. Project I.D : P00253512MN_CW1 a) 700.00 a) by Contract P - - - - - 22.22 56.67 91.11 100.00 100.00 100.00 100.00
Contract I.D : 18MH0086 b) 700.00 b) 09-May-18 R - - - - - 22.22 56.67 91.11 100.00 100.00 100.00 100.00
Rehabilitation of Barangay Hall, Kadi, c) c) 05-Jun-18 A - - - - 5.00 25.00 - - - - - -
Senator Ninoy Aquino, Sultan Kudarat d) COFEJOK CONST. & SUPPLY d) 11-Jun-18 S - - - - 5.00 2.78 - - - - - -
e) 684500 e) 08-Sep-18
f) 90 C.D. f) On-going
g) g) COLOMA, J.A.E
57. Project I.D : P00257423MN_CW1 a) 3,000.00 a) by Contract P - - - - - 22.22 56.67 91.11 100.00 100.00 100.00 100.00
Contract I.D : 18MH0084 b) 3,000.00 b) 09-May-18 R - - - - - 22.22 56.67 91.11 100.00 100.00 100.00 100.00
Construction of Multipurpose Building, c) c) 05-Jun-18 A - - - - 5.00 25.00 - - - - - -
Sitio Sindiolo, Brgy. Kisek, Palimbang, d) CS CONST. & SUPPLY d) 11-Jun-18 S - - - - 5.00 2.78 - - - - - -
Sultan Kudarat e) 2,968,183.09 e) 08-Sep-18
f) 90 C.D. f) On-going
g) g)
58. Project I.D : P00255354MN_CW1 a) 1,000.00 a) by Contract P - - - - - 22.22 56.67 91.11 100.00 100.00 100.00 100.00
Contract I.D : 18MH0076 b) 1,000.00 b) 09-May-18 R - - - - - 22.22 56.67 91.11 100.00 100.00 100.00 100.00
Construction of MPB (Barangay Hall), Keytodac c) c) 05-Jun-18 A - - - - 5.00 25.00 - - - - - -
Lebak, Sultan Kudarat d) JV CONSTECH d) 11-Jun-18 S - - - - 5.00 2.78 - - - - - -
e) 983,143.50 e) 04-Aug-18
f) 55 C.D. f) On-going
g) g) GUARDIANO, R.C.
59. Project I.D : P00257424MN_CW1 a) 2,000.00 a) by Contract P - - - - - - 32.22 66.67 100.00 100.00 100.00 100.00
Contract I.D : 18MH0083 b) 2,000.00 b) 07-Jun-18 R - - - - - 32.22 66.67 100.00 100.00 100.00 100.00
Construction of New Municipal Hall, Palimbang, c) c) 27-Jun-18 A - - - - - 3.00 - - - - - -
Sultan Kudarat d) CS CONST. & SUPPLY d) 03-Jul-18 S - - - - - 3.00 - - - - - -
e) 1,979,000.00 e) 30-Sep-18
f) 90 C.D. f) Notice to proceed just issued on June 27, 2018. Contractor started at their own risk.
g) g)
60. Project I.D : P00257425MN_CW1 a) 5,000.00 a) by Contract P - - - - - 10.48 40.00 69.52 100.00 100.00 100.00 100.00
Contract I.D : 18MH0081 b) 5,000.00 b) 24-May-18 R - - - - - 10.48 40.00 69.52 100.00 100.00 100.00 100.00
Construction of a Multi-purpose Building, Sultan c) c) 14-Jun-18 A - - - - - 11.00 - - - - - -
Kudarat Capitol Extension Area, Brgy. Tigbuan, d) JV CONSTECH d) 20-Jun-18 S - - - - - 0.52 - - - - - -
Lebak, Sultan Kudarat e) 4,802,179.14 e) 17-Sep-18
f) 105 C.D. f) On-going
g) g) ALANGCA, H.D.
Page 12 of 13
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Local Infrastructure Program
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
61. Project I.D : P00253465MN_CW1 a) 10,300.00 a) By Contract P - - - 20.10 80.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0047 b) 10,300.00 b) 20-Feb-18 R - - - 20.10 80.29 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Roads, Poblacion, Bagumbayan, c) c) 28-Mar-18 A - - 3.00 37.00 80.00 90.26
Sultan Kudarat d) COFEJOK CONST. & SUPPLY d) 03-Apr-18 S - - 3.00 16.90 -0.29 -9.74
e) 9,589,300.00 e) 11-Jun-18
f) 70 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) g) COLOMA, J.A.E
LOCAL BRIDGES
62. Project I.D : P00253498MN_CW1 a) 1,000.00 a) By Contract P - - - - - - 32.22 66.67 100.00 100.00 100.00 100.00
Contract I.D : 18MH0085 b) 1,000.00 b) 15-May-18 R - - - - - - 32.22 66.67 100.00 100.00 100.00 100.00
Construction of Footbridge, Kinayao, Bagumbayanc) c) 27-Jun-18 A - - - - - - - - - - - -
Sultan Kudarat d) CS CONST. & SUPPLY d) 03-Jul-18 S - - - - - - - - - - - -
e) 988,499.98 e) 30-Sep-18
f) 90 C.D. f) Notice to proceed just issued on June 27, 2018.
g) g) SANTOS, L.P.
80,000.00 Page 13 of 13

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
Construction/Improvement of Access Roads leading to Declared Tourism
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE


a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P

1. Project I.D : P00230235MN_CW1 a) 49,500.00 a) By Contract P - - 0.70 24.60 34.80 49.79 64.03 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0041 b) 49,500.00 b) 30-Jan-18 R - - 0.70 24.60 34.80 49.79 64.03 100.00 100.00 100.00 100.00 100.00
NRJ leading to Marguez Hotspring, c) c) 22-Mar-18 A - - 6.50 17.00 35.00 50.00
Brgy. Marguez, Esperanza, Sultan Kudarat d) R. SEMILLA CONST. & MARKEd) 28-Mar-18 S - - 5.80 -7.60 0.20 0.21
e) 39,654,920.43 e) 23-Aug-18
f) 149 C.D. f) On-going
g) 2.80 lane Km. g) L.P.SANTOS
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
CY 2018 Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P

1. Project I.D : P00220943MN_CW1 a) 50,000.00 a) by Contract P - - 0.65 5.00 17.84 40.84 66.05 87.74 92.38 94.54 99.45 100.00
Contract I.D : 18MH0002 b) 50,000.00 b) 14-Dec-17 R - - 0.65 5.00 17.84 40.84 66.05 87.74 92.38 94.54 99.45 100.00
Construction of River Bank Protection/ c) c) 22-Mar-18 A - - 5.00 9.00 20.00 41.00
Flood Control at Brgy. Daladap, d) C.B. GARAY PHILWIDE BUIL d) 28-Mar-18 S - - 4.35 4.00 2.16 0.16
Esperanza, Sultan Kudarat e) 46,385,847.64 e) 02-Dec-18
f) 250 C.D. f) On-going
g) 380 ln.m g) L.P. SANTOS
2. Project I.D : P00220960MN_CW1 a) 50,000.00 a) by Contract P - - - 7.60 20.00 32.00 44.40 56.80 68.80 81.20 93.20 100.00
Contract I.D : 18MH0048 b) 50,000.00 b) 27-Mar-18 R - - - 7.60 20.00 32.00 44.40 56.80 68.80 81.20 93.20 100.00
Construction of River Bank Protection/ c) c) 06-Apr-18 A - - - 5.50 21.00 24.00
Flood Control at Brgy. Badiangon, d) LEGACY CONST. CORP. d) 12-Apr-18 S - - - -2.10 1.00 -8.00
Palimbang, Sultan Kudarat e) 46,488,126.00 e) 17-Dec-18
K0+000-K0+480 f) 250 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) 380 ln.m g) M.D. GUIAMEL
3. Project I.D : P00220961MN_CW1 a) 50,000.00 a) by Contract P - - 1.95 10.65 28.29 48.94 72.49 89.30 93.55 96.43 100.00 100.00
Contract I.D : 18MH0001 b) 50,000.00 b) 14-Dec-17 R - - 1.95 10.65 28.29 48.94 72.49 89.30 93.55 96.43 100.00 100.00
Construction of River Bank Protection/ c) c) 12-Mar-18 A - - 6.00 14.50 35.00 44.00
Flood Control Brgy. Biwang, Bagumbayan, d) JARGON CONSTRUCTION & Sd) 18-Mar-18 S - - 4.05 3.85 6.71 -4.94
Sultan Kudarat e) 47,285,046.91 e) 22-Nov-18
f) 250 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) 380 ln.m g) R.C. GUARDIANO
4. Project I.D : P00220962MN_CW1 a) 50,000.00 a) by Contract P - - 1.98 16.83 32.18 47.03 62.38 77.72 95.57 100.00 100.00 100.00
Contract I.D : 18MH0040 b) 50,000.00 b) 30-Jan-18 R - - 1.98 16.83 32.18 47.03 62.38 77.72 95.57 100.00 100.00 100.00
Construction of Sea Wall Protection, c) c) 22-Mar-18 A - - 5.00 12.95 27.65 48.01
Brgy. Milbuk, Palimbang, Sultan Kudarat d) CS CONST. & SUPPLY d) 28-Mar-18 S - - 3.02 -3.88 -4.53 0.98
e) 46,520,000.00 e) 15-Oct-18
f) 202 C.D. f) On-going
g) 1,400 ln.m g) M.D. GUIAMEL
5. Project I.D : P00221063MN_CW1 a) 15,000.00 a) by Contract P - - - 22.58 47.58 71.77 96.77 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0045 b) 15,000.00 b) 20-Feb-18 R - - - 22.58 47.58 71.77 96.77 100.00 100.00 100.00 100.00 100.00
Construction of Sea Wall Protection, c) c) 28-Mar-18 A - - 5.00 25.00 45.00 70.86
Brgy. Sta. Clara, Kalamansig, Sultan Kudarat d) CS CONST. & SUPPLY & JV C d) 03-Apr-18 S - - 5.00 2.42 -2.58 -0.91
e) 14,406,379.79 e) 04-Aug-18
f) 124 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) 425 ln.m g) H.D. ALANGCA
Page 1 of 2
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
CY 2018 Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
6. Project I.D : P00221070MN_CW1 a) 50,000.00 a) by Contract P - - - 9.41 24.75 39.60 54.95 70.30 85.15 100.00 100.00 100.00
Contract I.D : 18MH0050 b) 50,000.00 b) 27-Mar-18 R - - - 9.41 24.75 39.60 54.95 70.30 85.15 100.00 100.00 100.00
Construction of Sea Wall Protection, c) c) 06-Apr-18 A - - - 7.00 20.00 30.25
Brgy. Baranayan, Palimbang, Sultan Kudarat d) LEGACY CONST. CORP. d) 12-Apr-18 S - - - -2.41 -4.75 -9.35
e) 46,453,551.01 e) 30-Oct-18
f) 202 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For revision of
implementation scheduled.
g) 1,400 ln.m g) M.D. GUIAMEL
7. Project I.D : P00221798MN_CW1 a) 5,700.00 a) by Contract P - - - 29.23 76.92 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0049 b) 5,700.00 b) 27-Mar-18 R - - - 29.23 76.92 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Rehabilitation of River Bank Protection along c) c) 06-Apr-18 A - - - 25.65 72.00 90.21
Awang-Upi-Lebak-Kalamansig-Palimbang- d) ABU CONSTRUCTION d) 12-Apr-18 S - - - -3.58 -4.92 -9.79
Saranggani Road-K2019+380-K2019+558, e) 5,469,385.23 e) 15-Jun-18
Sultan Kudarat f) 65 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For revision of
g) g) M.D. GUIAMEL implementation scheduled.
270,700.00 Page 2 of 2

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
CY 2018 Network Development - Secondary Roads
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location
d) Contractor d) Start Date C
(Scope of Work/Physical Target)
e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
ROAD WIDENING
1. Project I.D : P00200759MN_CW1 a) 50,000.00 a) By Contract P 8.10 22.38 37.14 51.90 66.19 80.95 95.24 100.00
Contract I.D : 18MH0070 b) 50,000.00 b) 19-Apr-18 R 8.10 22.38 37.14 51.90 66.19 80.95 95.24 100.00
Awang-Upi-Kalamansig-Palimbang- c) c) 09-May-18 A 20.00 30.00
Sarangani Rd - K1941+348 - K1941+824, d) SOPHIA CONST. & JV CONSTd) 15-May-18 S 11.90 7.62
K1942+070-K1942+946, K1943+155- e) 47,775,850.30 e) 10-Dec-18
K1943+289 f) 210 C.D. f) On-going
g) 2.972 lane Km. g) DURUIN, P.S.
2. Project I.D : P00200760MN_CW1 a) 50,000.00 a) By Contract P - - - 1.54 27.97 37.07 52.72 74.06 84.36 100.00 100.00 100.00
Contract I.D : 18MH0046 b) 50,000.00 b) 20-Feb-18 R - - - 1.54 27.97 37.07 52.72 74.06 84.36 100.00 100.00 100.00
Isulan Jct-Ninoy Aquino Rd - c) c) 28-Mar-18 A - - 3.00 12.00 24.00 35.00
K1775+(-601) - K1775+274, d) LEGACY CONST. CORP d) 03-Apr-18 S - - 3.00 10.46 -3.97 -2.07
K1785+(-755 ) - K1785+253 e) 46,452,450.80 e) 29-Oct-18
f) 210 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) 3.326 lane Km. g) L.P. SANTOS
3. Project I.D : P00200761MN_CW1 a) 50,000.00 a) By Contract P - - 0.37 1.44 34.74 41.21 60.11 80.26 89.91 100.00 100.00 100.00
Contract I.D : 18MH0039 b) 50,000.00 b) 30-Jan-18 R - - 0.37 1.44 34.74 41.21 60.11 80.26 89.91 100.00 100.00 100.00
Isulan Jct-Ninoy Aquino Rd - c) c) 22-Mar-18 A - - 5.00 12.00 30.00 51.36
K1793+000 -K1794+578 d) LEGACY CONST. CORP/JANM d) 28-Mar-18 S - - 4.63 10.56 -4.74 10.15
e) 46,500,898.17 e) 23-Oct-18
f) 210 C.D. f) On-going
g) 3.162 lane Km. g) R.C. GUARDIANO
Page 1 of 3
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
CY 2018 Network Development - Secondary Roads
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location
d) Contractor d) Start Date C
(Scope of Work/Physical Target)
e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
PAVING OF UNPAVED ROADS
4. Project I.D : P00201506MN_CW1 a) 19,000.00 a) By Contract P - - 2.45 26.74 63.94 98.06 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0038 b) 19,000.00 b) 30-Jan-18 R - - 2.45 26.74 63.94 98.06 100.00 100.00 100.00 100.00 100.00 100.00
SNA-Lebak-Kalamansig Rd c) c) 16-Mar-18 A - - 10.00 47.00 64.87 95.00
K1905+185 - K1905+686, d) ROBETH GEN. MDSE. CONST.d) 22-Mar-18 S - - 7.55 20.26 0.93 -3.06
K1905+695 - K1905+734 e) 17,982,390.90 e) 02-Jul-18
On-going, project delayed due to bad weather condition prevailing in the area. For revision of implementation
f) 103 C.D. f)
scheduled.
g) 1.080 lane km. g)
H.D. ALANGCA
PREVENTIVE MAINTENANCE
5. Project I.D : P00200058MN_CW1 a) 42,456.00 a) By Contract P 10.64 27.13 43.62 59.57 76.06 92.02 100.00
Contract I.D : 18MH0068 b) 42,456.00 b) 09-May-18 R 10.64 27.13 43.62 59.57 76.06 92.02 100.00
Preventive Maintenance Awang-Upi- c) c) 05-Jun-18 A 5.00 30.00
Lebak-Kalamansig-Palimbang-Sarangani d) JARGON CONST. & SUPPLY d) 11-Jun-18 S 5.00 19.36
Rd- K1942 + 000 - K1943 + 046, K1943+ e) 39,526,092.36 e) 15-Dec-18
055.45 -K1944 + 400, K1945 + 411.12 - f) 188 C.D. f)
K1946 + 000, K1946 + 513.62 - K1946+ g) 9.994 lane km g) H.D. ALANGCA On-going.
665, K1947 + 147 - K1948 + 306, K1949+
2000 - K1949 + 2707
REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED RODS
6. Project I.D : P00200126MN_CW1 a) 15,119.00 a) By Contract P 14.17 39.17 65.00 90.83 100.00 100.00 100.00 100.00
Contract I.D : 18MH0069 b) 15,119.00 b) 19-Apr-18 R 14.17 39.17 65.00 90.83 100.00 100.00 100.00 100.00
Rehabilitation/ Reconstruction/ c) c) 09-May-18 A 20.00 45.00
Upgrading of Damaged Paved Roads d) ROBETH GEN. MDSE. CONST.d) 15-May-18 S 5.83 5.83
Awang-Upi-Lebak-Kalamansig-Palimbang- e) 14,068,959.83 e) 11-Sep-18
Sarangani Rd -K1946+000 - K1946+503 f) 120 C.D. f) On-going
g) 1.006 lane km g) H.D. ALANGCA
Page 2 of 3
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
CY 2018 Network Development - Secondary Roads
As of June 30, 2018
SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE
a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location
d) Contractor d) Start Date C
(Scope of Work/Physical Target)
e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
REHABILITATION/RECONSTRUCTION/OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE
7. Project I.D : P00200249MN_CW1 a) 5,000.00 a) By Contract P - - - 15.84 52.24 85.91 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0042 b) 5,000.00 b) 30-Jan-18 R - - - 15.84 52.24 85.91 100.00 100.00 100.00 100.00 100.00 100.00
Rehabilitation/ Reconstruction of c) c) 02-Apr-18 A - - - 20.00 50.00 81.00
Roads with Slips, Slope collapse and d) Pearl Const. & Supply d) 08-Apr-18 S - - - 4.16 -2.24 -4.91
Landslide Isulan Jct-Ninoy Aquino Rd - e) 4,753,000.00 e) 15-Jul-18
K1828 + 817 - K1828 + 865 f) 99 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area.
g) 144 sq.m g) COLOMA, J.A.E.
231,575.00 Page 3 of 3

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
CY 2018 Rehabilitation/Major Repair of Permanent Bridges
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P

1. Project I.D : P00200974MN_CW1 a) 39,870.00 a) by Contract P - - - 9.93 37.46 69.69 91.34 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0051 b) 39,870.00 b) 27-Mar-18 R - - - 9.93 37.46 69.69 80.43 100.00 100.00 100.00 100.00 100.00
Domolol Br. (B00159MN) along c) c) 06-Apr-18 A - - - 11.00 32.00 65.00
Awang-Upi-Lebak-Kalamansig-Palimbang d) ABU CONSTRUCTION d) 12-Apr-18 S - - - 1.07 -5.46 -4.69
-Sarangani Rd e) 38,076,105.83 e) 28-Aug-18
f) 139 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For revision of
g) g) MANGATONG, R. implementation scheduled.
2. Project I.D : P00200978MN_CW1 a) 12,650.00 a) by Contract P - - - 4.20 57.89 79.81 94.34 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0052 b) 12,650.00 b) 27-Mar-18 R - - - 4.20 57.89 79.81 94.34 100.00 100.00 100.00 100.00 100.00
San Roque Br. (B00396MN) Awang-Upi- c) c) 06-Apr-18 A - - - 12.00 37.00 75.00
Kalamansig-Palimbang-Sarangani-Rd d) ABU CONSTRUCTION d) 12-Apr-18 S - - - 7.80 -20.89 -4.81
e) 12,136,063.05 e) 09-Aug-18
f) 120 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For revision of
g) g) GUIAMEL, M.D. implementation scheduled.
3. Project I.D : P00200972MN_CW1 a) 9,930.00 a) by Contract P - - - 9.50 35.20 77.80 92.40 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0053 b) 9,930.00 b) 27-Mar-18 R - - - 9.50 35.20 77.80 92.40 100.00 100.00 100.00 100.00 100.00
Colubi Br. 1 (B00400MN) Awang-Upi- c) c) 06-Apr-18 A - - - 13.20 39.00 72.95
Kalamansig-Palimbang-Sarangani-Rd d) ABU CONSTRUCTION d) 12-Apr-18 S - - - 3.70 3.80 -4.85
e) 9,525,482.94 e) 03-Aug-18
f) 114 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For revision of
implementation scheduled.
g) g) GUIAMEL, M.D.
4. Project I.D : P00200973MN_CW1 a) 12,250.00 a) by Contract P - - - 4.00 58.00 87.00 99.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0054 b) 12,250.00 b) 27-Mar-18 R - - - 4.00 58.00 87.00 99.00 100.00 100.00 100.00 100.00 100.00
Colubi Br. 2 (B00401MN) Awang-Upi- c) c) 06-Apr-18 A - - - 12.85 37.95 82.12
Kalamansig-Palimbang-Sarangani-Rd d) ABU CONSTRUCTION d) 12-Apr-18 S - - - 8.85 -20.05 -4.88
e) 11,749,065.92 e) 08-Aug-18
f) 119 C.D, f) On-going, project delayed due to bad weather condition prevailing in the area. For revision of
implementation scheduled.
g) g) GUIAMEL, M.D.
5. Project I.D : P00200975MN_CW1 a) 50,000.00 a) by Contract P - - - - 7.58 38.68 52.39 68.69 77.50 95.15 99.54 100.00
Contract I.D : 18MH0055 b) 50,000.00 b) 10-Apr-18 R - - - - 7.58 38.68 52.39 68.69 77.50 95.15 99.54 100.00
Kraan Br.1 (B00402MN) Awang-Upi- c) c) 30-Apr-18 A - - - 5.00 12.00 33.75
Kalamansig-Palimbang-Sarangani-Rd d) ABU CONSTRUCTION d) 06-May-18 S - - - 5.00 4.42 -4.93
e) 48,138,809.94 e) 10-Dec-18
f) 219 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For revision of
g) g) GUIAMEL, M.D. implementation scheduled.
Page 1 of 2
STATUS OF PROJECTS
CY 2018 CONSTRUCTION PROGRAM
CY 2018 Rehabilitation/Major Repair of Permanent Bridges
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2018
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of d) Contractor d) Start Date C
Work/Physical Target) e) Contract Amount e) Exp. Compl. Date O FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
6. Project I.D : P00200977MN_CW1 a) 46,400.00 a) by Contract P - - - - 12.38 26.67 41.43 56.19 70.48 85.24 99.52 100.00
Contract I.D : 18MH0056 b) 46,400.00 b) 12-Apr-18 R - - - - 12.38 26.67 41.43 56.19 70.48 85.24 99.52 100.00
Salaman Br (B00624MN) Awang-Upi- c) c) 30-Apr-18 A - - - 5.00 20.00 35.00
Kalamansig-Palimbang-Sarangani-Rd d) ABU CONSTRUCTION / JV COd) 06-May-18 S - - - 5.00 7.62 8.33
e) 44,554,933.59 e) 01-Dec-18
f) 210 C.D. f) On-going
g) g) H.D. ALANGCA
7. Project I.D : P00200976MN_CW1 a) 9,450.00 a) by Contract P - - - - 23.01 49.56 76.99 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0057 b) 9,450.00 b) 10-Apr-18 R - - - - 23.01 49.56 76.99 100.00 100.00 100.00 100.00 100.00
Marigaeg Br (B00625MN) Awang-Upi- c) c) 30-Apr-18 A - - - 5.00 25.00 52.00
Kalamansig-Palimbang-Sarangani-Rd d) CS CONST. & SUPPLY & JV C d) 06-May-18 S - - - 5.00 1.99 2.44
e) 8,983,093.25 e) 26-Aug-18
f) 113 C.D. f) On-going
g) g) DURUIN P.S.
8. Project I.D : P00200979MN_CW1 a) 9,000.00 a) by Contract P - - - 11.36 57.40 87.54 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 18MH0044 b) 9,000.00 b) 20-Feb-18 R - - - 11.36 57.40 87.54 100.00 100.00 100.00 100.00 100.00 100.00
Sinandigan Br (B01628MN) Awang-Upi- c) c) 28-Mar-18 A - - 3.00 21.52 47.95 83.00
Kalamansig-Palimbang-Sarangani-Rd d) ABU CONSTRUCTION d) 03-Apr-18 S - - 3.00 10.16 -9.45 -4.54
e) 8,418,624.10 e) 23-Jul-18
f) 112 C.D. f) On-going, project delayed due to bad weather condition prevailing in the area. For revision of
g) g) MANGATONG, R. implementation scheduled.
189,550.00 Page 2 of 2

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2017 CONSTRUCTION PROGRAM
CY 2017 Local Roads and Bridges
As of June 30, 2018

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE


a) Allocation (P'000) a) Mode of Impl. % CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
c) Date SARO rec'd. c) Date NTP C
Name of Project/Location
d) Contractor d) Start Date C
(Scope of Work/Physical Target)
e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
LOCAL ROADS
1. Project I.D : a) 10,300.00 a) By Contract P
Contract I.D : b) 10,300.00 b) R
Construction of Roads, Poblacion, Bagumbayan, c) c) A
Sultan Kudarat d) d) S
e) e)
f) f)
g) g)
LOCAL BRIDGES
1. Project I.D : a) 1,000.00 a) By Contract P
Contract I.D : b) 1,000.00 b) R
Construction of Footbridge, Kinayao, Bagumbayan, c) c) A
Sultan Kudarat d) d) S
e) e)
f) f)
g) g)
11,300.00 Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
OVER-ALL STATUS
FY 2018 CONSTRUCTION PROGRAM
Sultan Kudarat 2nd District Engineering Office
As of June 30, 2018

PRE-CONSTRUCTION CONSTRUCTION
PROGRAM TOTAL NO.
FUND SOURCE AMOUNT OF NUMBER OF PROJECTS NO. OF PROJECTS STATUS
(Php'000) PROJECTS COM- ON- ADVER CONTRACT ACTUAL COM- ON- PLANNED ACTUAL SLIPPAGE
NYS BID NTP NYS
PLETED GOING -TIZED APPROVED % ACC PLETED GOING % TARGET % ACC %
DPWH REGULAR INFRASTRUCTURE

Rehabilitation/Major Repair of Permanent Bridges 189,550.00 8 8 - - 8 8 8 8 100.00 - 8 - 53.04 51.81 -1.23

Network Development - Secondary Roads 231,575.00 7 7 - - 7 7 7 7 100.00 - 7 - 36.14 43.10 6.96

Construction/Maintenance of Flood Mitigation


270,700.00 7 7 - - 7 7 7 7 100.00 - 7 - 44.58 40.41 -4.16
Structures and Drainage Systems

Construction/Improvement of Access Roads


49,500.00 1 1 - - 1 1 1 1 100.00 - 1 - 49.79 50.00 0.21
leading to Declared Tourism

Local Infrastructure Program 80,000.00 62 62 - - 62 62 62 62 100.00 6 56 - 81.36 76.63 -4.74

Construction of Rain Water Collector System


3,366.00 1 1 - - 1 1 1 1 100.00 - 1 - 46.67 47.00 0.33
(CWRCS)
Sub-total 824,691.00 86 86 - - 86 86 86 86 100.00 6 80 - 48.04 47.90 -0.14
DPWH OUTSIDE INFRASTRUCTURE
Department of Agriculture (DA) 27,000.00 3 3 - - 3 3 3 3 100.00 - 3 - 69.39 65.36 -4.04
Department of Agrarian Reform (DAR) 105,603.40 2 2 - - 2 2 2 2 100.00 - 2 - 1.65 2.84 1.19
CY 2017 BEFF - Batch 1 444,662.67 34 - 34 - 34 31 74.78 - - 34
Sub-total 577,266.07 39 5 34 - 39 36 5 5 78.02 - 5 34 3.55 3.58 0.03
TOTAL 1,401,957.07 125 91 34 - 125 122 91 91 93.14 6 85 34 29.72 29.65 -0.07

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA REYNALDO C. GUARDIANO JR. MAMINTAL T. TAHA, Ph.D.


Engineer II Acting Chief, Construction Section District Engineer
STATUS OF PROJECTS
CY 2016 CONSTRUCTION PROGRAM
CY 2016 Replacement of Bridges (Temporary to Permanent)..
#REF!

SULTAN KUDARAT 2nd DISTRICT ENGINEERING OFFICE %


a) Allocation (P'000) a) Mode of Impl. CUMULATIVE ACCOMPLISHMENT IN PERCENT
b) Programmed (This Yr) b) Date Bid A Current Year = 2017
Name of Project/Location c) Date SARO rec'd. c) Date NTP C
(Scope of Work/Physical d) Contractor d) Start Date C
Target) e) Contract Amount e) Exp. Compl. Date O JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
f) Contract Duration f) Rev. Expiry Date M
g) Physical Target g) Project Engineer P
1. Project I.D : 1205-14-H-00091 a) 3,042.65 a) By Contract P 44.03 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Contract I.D : 16MH0044 b) 3,042.65 b) 29-Nov-16 R 44.03 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Construction of Sebayor IV Bridge and c) c) 6-Jan-16 A
Approaches (K1959+120-K1959+215 and d) Tri-vert Construction d) 12-Jan-16 S
K1959+254-K1959+329) and Supply e) 18-Feb-16
Kalamansig, Sultan Kudarat e) 2,496,902.88 f) On-going, delayed due to bad weather. For revision of implementation schedule due to
f) 38 g) A.A. Branzuela suspension.
g)
Page 1 of 1

PREPARED BY: CHECKED BY: SUBMITTED BY:

CONNIE JANE T. PADILLA LOIDA L. LEAL, MPA MAMINTAL T. TAHA, MPS


Engineer II Chief, Construction Section District Engineer
month type % 25%, 50%, 85%, 100%
effectivity commulative periodic

2018 J 31 0 0 #DIV/0! #DIV/0! #DIV/0!


F 28 0 0 #DIV/0! #DIV/0! #DIV/0!
M 31 0 0 0.00 0.00 #DIV/0!
A 30 0 0 0.00 0.00 0.00
M 31 0 0 0.00 0.00 0.00
J 30 4 4 1.59 1.59 1.59
J 31 31 35 14.17 14.17 12.58
A 31 31 66 26.29 6.57 -7.60
S 30 30 96 43.84 19.73 13.15
O 31 31 127 50.60 #VALUE!
N 30 30 157 62.55 31.27 #VALUE!
D 31 31 188 74.90 56.18 24.90
J 2018 31 31 219 87.25 71.55 15.37
F 28 28 247 98.41 88.57 17.02
M 31 4 251 100.00 100.00 11.43
A 30 0 251 100.00 100.00 0.00
M 31 0 251 100.00 100.00 0.00
J 30 0 251 100.00 100.00 0.00
J 31 0 251 0.00 -100.00

251 #DIV/0! #DIV/0! #DIV/0!


251

# OF SETS FOR CONSOLIDATED 0.4342105263


15th 30th
region 5
records (deo/ro) 2
de 1 1
ade 1 1
chief 1 1
laloi 1 1
jane 1 1
pe 1 1
pds 1
qas 1 1
gso 1
auditor 1
budget 1
7 18
dbm c/o 1
budget
7 19

opt
# OF SETS FOR Project Monitoring System (PMS)
CONSOLIDATED

15th 30th
region 5 extra 5 copies of summary
de 1 1
ade 1 1
chief 1 1
laloi 1 1
jane 1 1
pe 1 1
pds 1
qas 1 1
gso 1
auditor 1
budget 1
7 16
dbm c/o
budget
1 quarterly

7 17

mutual
SUMMARY SUMMARY

CY 2015 BRIDGES CY 2015 BRIDGES

CY 2015 TOURISM CY 2015 TOURISM

CY 2015 LIP CY 2015 LIP

CY 2015 BEFF SHS-1B CY 2015 BEFF SHS-1B

CY 2015 BEFF SHS-2B CY 2015 BEFF SHS-2B

CY 2015 BEFF (E&JHS)-3B CY 2015 BEFF (E&JHS)-3B

CY 2015 DepEd BEFF (E&JHS)-6B CY 2015 DepEd BEFF (E&JHS)-6B

CY 2015 DepEd BEFF (E&JHS)-7B CY 2015 DepEd BEFF (E&JHS)-7B

CY 2015 DepEd BEFF-TechVoc CY 2015 DepEd BEFF-TechVoc

CY 2015 Fund 151 CY 2015 Fund 151

CY 2015 DA Fund CY 2015 DA Fund

CY 2015 R&M FC&DS CY 2015 R&M FC&DS

CY 2015 R&M N. Bldgs. CY 2015 R&M N. Bldgs.

FY 2014 BEFF -1B FY 2014 BEFF -1B

FY 2014 BEFF-4B FY 2014 BEFF-4B

FY 2014 RSBP-2B FY 2014 RSBP-2B

FY 2014 Trust Fund-DA FY 2014 Trust Fund-DA

FY 2014 MOOE FY 2014 MOOE

Potrebbero piacerti anche