0 valutazioniIl 0% ha trovato utile questo documento (0 voti)
15 visualizzazioni2 pagine
1) Four Georgian laborers and their foreman were erecting poles near high voltage lines when two laborers raised a pole into a live 3,000V line, suffering electric shock and burns. One laborer died.
2) The investigation found issues with safety leadership and climate, hazard identification, management of change, and work planning. The foreman lacked proper supervision skills.
3) Actions taken include improving supervisor training, increasing safety supervision for short term projects using local labor, and revising work permitting and planning processes to reduce uncertainty and ensure oversight of even simple tasks.
1) Four Georgian laborers and their foreman were erecting poles near high voltage lines when two laborers raised a pole into a live 3,000V line, suffering electric shock and burns. One laborer died.
2) The investigation found issues with safety leadership and climate, hazard identification, management of change, and work planning. The foreman lacked proper supervision skills.
3) Actions taken include improving supervisor training, increasing safety supervision for short term projects using local labor, and revising work permitting and planning processes to reduce uncertainty and ensure oversight of even simple tasks.
1) Four Georgian laborers and their foreman were erecting poles near high voltage lines when two laborers raised a pole into a live 3,000V line, suffering electric shock and burns. One laborer died.
2) The investigation found issues with safety leadership and climate, hazard identification, management of change, and work planning. The foreman lacked proper supervision skills.
3) Actions taken include improving supervisor training, increasing safety supervision for short term projects using local labor, and revising work permitting and planning processes to reduce uncertainty and ensure oversight of even simple tasks.
Type of Incident: Major Incident – Electrical atmosphere on site in which everyone is aware of the Incident: Electrocution and shock/burns Project commitment to the highest possible HS from contact with 3,000+V DC standards and in which they are encouraged and overhead line empowered to challenge and if necessary stop work Business/Performance • CLC8.2 Inadequate leadership – standards not Unit: Azerbaijan – Oil Exports enforced. The foreman failed to exercise supervisory Country: Georgia control, and across the whole site there was a shortfall Region: Europe in competent safety supervision Business Stream: Upstream • CLC8.4 Inadequate identification of worksite hazards. Location of Incident: Pump Station PSG2, Georgia The team did not understand the likely severity of Date of Incident: 25 February 2004 contact with the line, nor the likelihood the pole would Email: ashdowse@bp.com touch the line while they were raising it. This reflects them coming from a culture which is risk tolerant and Brief Account of Incident: A team of four Georgian where electricity is not well understood labourers and their foreman working for a major sub- • CLC8.5 Inadequate management of change. The contractor to the BTC Project were erecting steel poles foreman had been promoted to that role but this to form “goal post” style warning markers about 30m change did not trigger him receiving the necessary either side of an uncontrolled crossing at a railway line. supervisory skills training (also 7.4) Above the line ran 10KV electricity cables on pylons, • CLC11.1 Inadequate work planning. The work control and at a lower level the cable carrying the electric system (permits and JSAs) was not followed. locomotive supply line at approximately 3,000V DC. Furthermore, routine low skill tasks were not The latter was at about 5.7m above ground level. The effectively designed planned and resourced leading to work scope involved digging four holes and cementing the work team having inadequate information and in place vertical scaffold poles each 6m in length. materials Bunting was to be stretched between them. Golden Rules: Pre-planning of the work by the sub-contractor was very • General – risk assessment. The JSA did refer to the informal, and the associated job safety analysis and cables but it is likely this was not communicated toolbox talk by the foreman were of limited quality. seriously, if at all, by the foreman to his team. There was no perceived reason to worry unduly about the Investigation has concluded that because of uncertainty cables which were high in the air and under which site about the length of the final pole, two of the labourers vehicles were moving regularly raised it to the vertical position almost underneath the • Permit to Work – no site general work permit was locomotive supply line, presumably to check it was long issued enough for its purpose. It touched the live line. They • Management of Change – promotion of the foreman both suffered electric shock, burns and subsequent did not trigger his additional supervisory skills training respiratory/cardiac arrest. Both received attention from as required by the training programme and contract their colleagues and one was kept alive until the site Doctor arrived and took over; it is believed he will make Resultant Actions: a full recovery. The other could not be revived and was • Supervisors are not simply people who have shown pronounced dead at the scene of the incident. they can do the technical work well – they need to have leader qualities and accept accountability. The Potential Outcome: This would probably have been a supervisory training programme is to be adjusted to double fatality but for the skills of the local first-aiders focus on the leadership role and will be extended to all and Doctor. existing supervisors and future recruits and promotees • In a short-term project using local labour unused to a What Went Wrong: disciplined working environment, getting “safety • CLC8.2 Inadequate Management Leadership - weak completely in the line” is unrealistic and must be site “safety climate”. The style and activities of supplemented by effective professional supervision. The numbers of site safety supervisors will therefore View looking towards crossing. Locomotive supply line be increased is lowest line above guard hut. In the foreground to the • Effective planning of work limits uncertainty in the left can be seen one of the erected poles. work scope and methodology and obviates the need for additional activity not envisaged or planned and which may carry unconsidered risks. Planning processes are to be reviewed to ensure that even simple tasks have an appropriate method statement • All work, however simple, needs to have some permission associated with it to allow an opportunity for reflection on risks it might carry. The permit system and JSA process is to be revised to make it fit for purpose and to inject rigour into its application • No amount of commitment to HSE will deliver HSE excellence unless the entire management team demonstrates that commitment visibly, enthusiastically, continuously and consistently to the workforce. A strategy is to be implemented which will increase the overall visibility of management and their desire to pace safety alongside project schedule
Key Message: In a short-term project environment in
a location having to use local and unskilled labour, reliance cannot be placed exclusively on “safety in the line”. It is essential to bolster this with extensive close specialist safety supervision by personnel who are willing to intervene in a constructive manner and whose authority is respected by the workforce and management alike, the latter giving them their unqualified support.
Technical Analysis of Electrical Ground System in Hydroelectric Power Plant, On Normal Operation With Low Risk Factor - The Real Case Study HV 440 KV Sub-Station - Ilha Solteira Power Plant - Cesp