Sei sulla pagina 1di 2

BP HSE COMMUNICATION – Lessons Learned Report

management did not generate a vibrant safety


Type of Incident: Major Incident – Electrical atmosphere on site in which everyone is aware of the
Incident: Electrocution and shock/burns Project commitment to the highest possible HS
from contact with 3,000+V DC standards and in which they are encouraged and
overhead line empowered to challenge and if necessary stop work
Business/Performance • CLC8.2 Inadequate leadership – standards not
Unit: Azerbaijan – Oil Exports enforced. The foreman failed to exercise supervisory
Country: Georgia control, and across the whole site there was a shortfall
Region: Europe in competent safety supervision
Business Stream: Upstream • CLC8.4 Inadequate identification of worksite hazards.
Location of Incident: Pump Station PSG2, Georgia The team did not understand the likely severity of
Date of Incident: 25 February 2004 contact with the line, nor the likelihood the pole would
Email: ashdowse@bp.com touch the line while they were raising it. This reflects
them coming from a culture which is risk tolerant and
Brief Account of Incident: A team of four Georgian where electricity is not well understood
labourers and their foreman working for a major sub- • CLC8.5 Inadequate management of change. The
contractor to the BTC Project were erecting steel poles foreman had been promoted to that role but this
to form “goal post” style warning markers about 30m change did not trigger him receiving the necessary
either side of an uncontrolled crossing at a railway line. supervisory skills training (also 7.4)
Above the line ran 10KV electricity cables on pylons, • CLC11.1 Inadequate work planning. The work control
and at a lower level the cable carrying the electric system (permits and JSAs) was not followed.
locomotive supply line at approximately 3,000V DC. Furthermore, routine low skill tasks were not
The latter was at about 5.7m above ground level. The effectively designed planned and resourced leading to
work scope involved digging four holes and cementing the work team having inadequate information and
in place vertical scaffold poles each 6m in length. materials
Bunting was to be stretched between them.
Golden Rules:
Pre-planning of the work by the sub-contractor was very • General – risk assessment. The JSA did refer to the
informal, and the associated job safety analysis and cables but it is likely this was not communicated
toolbox talk by the foreman were of limited quality. seriously, if at all, by the foreman to his team. There
was no perceived reason to worry unduly about the
Investigation has concluded that because of uncertainty cables which were high in the air and under which site
about the length of the final pole, two of the labourers vehicles were moving regularly
raised it to the vertical position almost underneath the • Permit to Work – no site general work permit was
locomotive supply line, presumably to check it was long issued
enough for its purpose. It touched the live line. They • Management of Change – promotion of the foreman
both suffered electric shock, burns and subsequent did not trigger his additional supervisory skills training
respiratory/cardiac arrest. Both received attention from as required by the training programme and contract
their colleagues and one was kept alive until the site
Doctor arrived and took over; it is believed he will make Resultant Actions:
a full recovery. The other could not be revived and was • Supervisors are not simply people who have shown
pronounced dead at the scene of the incident. they can do the technical work well – they need to
have leader qualities and accept accountability. The
Potential Outcome: This would probably have been a supervisory training programme is to be adjusted to
double fatality but for the skills of the local first-aiders focus on the leadership role and will be extended to all
and Doctor. existing supervisors and future recruits and promotees
• In a short-term project using local labour unused to a
What Went Wrong: disciplined working environment, getting “safety
• CLC8.2 Inadequate Management Leadership - weak completely in the line” is unrealistic and must be
site “safety climate”. The style and activities of supplemented by effective professional supervision.
The numbers of site safety supervisors will therefore View looking towards crossing. Locomotive supply line
be increased is lowest line above guard hut. In the foreground to the
• Effective planning of work limits uncertainty in the left can be seen one of the erected poles.
work scope and methodology and obviates the need
for additional activity not envisaged or planned and
which may carry unconsidered risks. Planning
processes are to be reviewed to ensure that even
simple tasks have an appropriate method statement
• All work, however simple, needs to have some
permission associated with it to allow an opportunity
for reflection on risks it might carry. The permit
system and JSA process is to be revised to make it
fit for purpose and to inject rigour into its
application
• No amount of commitment to HSE will deliver HSE
excellence unless the entire management team
demonstrates that commitment visibly,
enthusiastically, continuously and consistently to the
workforce. A strategy is to be implemented which
will increase the overall visibility of management
and their desire to pace safety alongside project
schedule

Key Message: In a short-term project environment in


a location having to use local and unskilled labour,
reliance cannot be placed exclusively on “safety in the
line”. It is essential to bolster this with extensive close
specialist safety supervision by personnel who are
willing to intervene in a constructive manner and
whose authority is respected by the workforce and
management alike, the latter giving them their
unqualified support.

View of crossing. Locomotive supply line is above


right hand rail.

Potrebbero piacerti anche