Project No. Project Title Facilities INFORMATION Tag no. System/Subsystem No.
INSPECTION / TEST OK N/A P/L No
1 Ensure ITR M44-A has been completed and signed off 2 Charge damper per manufacturer's specification and according to specifications. 3 Record recommended pre-charge pressure in bar g
4 Carry out manufacturers’ recommended Pre-commissioning procedure and
test 5 Record any exceptions found
COMMENT(S) AND ADDITIONAL INFORMATION:
COMPLETED BY VERIFIED BY ACCEPTED BY
Designation Contractor Representative PMT Inspector Commissioning Engineer Company Name Signature Date