Sei sulla pagina 1di 5

2006 IEEE PES Transmission and Distribution Conference and Exposition Latin America, Venezuela

Limiting Distributed Generator Capacity Due to the


Voltage Stability Phenomena
R. B. Prada, L. F. Ferreira, and L. C. A. Ferreira

that a load is reaching its maximum, the objective of the


reinforcement function is to calculate adequate control actions
in order to increase the "distance" between the actual load to
the (new) maximum power flow. However, if it is detected
that a control action may have the reverse effect, the objective
of the reinforcement function is to move the operating point
from the lower half of the well-known SV curve (nicknamed
"nose curve") to its upper half. Appropriate voltage profile
changes and consequent loss reduction may achieve the
enhancement objective. If that procedure is not enough, active
generation rescheduling may be recommended.
However, operational preventive and corrective actions
should be necessary only in the event of unforeseen and
unplanned scenarios. The studies associated with the
connection of a new generator should guarantee that voltage is
kept under control for all power output and transfer levels as
well as for the base- and contingency-cases. It is not
Index Terms - Power flow, voltage collapse, voltage control, appropriate to make available generating sources that cannot
voltage security, voltage stability. be fully used for voltage control.

I. INTRODUCTION II. DETERMINING THE PHENOMENA EXISTENCE

Power systems are operated under increasingly loaded The problem addressed in this paper is the opposite
conditions. Open access, few new transmission lines, and relationship between the generator excitation voltage and the
increased energy consumption originate much greater levels of controlled voltage when near by transmission network is
power transfers. The system is operating near its limits in heavily loaded (see Appendix). In this case, the full capacity
order to achieve maximum economic benefit. of production / absorption of reactive power by the generator
Voltage instability has become a major threat for the may not be useful for keeping the bus voltage within pre-
operation of many systems and it is a factor leading to limit defined range. Due to opposite relationship, an increase in the
power transfers [1]. Voltage stability analysis, or more excitation voltage would lower the voltage. Automatic control
adequately, voltage security analysis, may be divided in two would keep acting, thus leading to still lower voltage. If the
aspects: the assessment function and, if necessary, the voltage becomes too low, angular stability may be at a threat.
reinforcement function. The voltage security assessment may Under-voltage relays would could come into action as well.
find results of two different types: i) the power flow arriving Voltage collapse is a possible consequence. The other
in a load bus is reaching its maximum, ii) the effect of voltage possibility is the excitation current hitting limits before the
control actions in a voltage-controlled bus may be opposite to voltage becomes too low thus interrupting the voltage decay
the expected one [2]-[3]. process.
The objective of the voltage security assessment is to point Although there are hundreds of papers in the literature
out critical buses and areas. Once the assessment has detected about voltage security assessment, none of them performs the
analysis of voltage-controlled buses except "the matrix [D']
1
method" [4] and the well-known "VQ curve method" [5]. On
The first two authors received financial support from CNPq, CAPES and the other hand, there are only about twenty papers on voltage
FAPERJ.
security reinforcement and none of them considers the voltage
R. B. Prada and L. F. Ferreira are with Department of Electrical Engineering, security reinforcement on voltage-controlled buses, although
Catholic University, Rio de Janeiro, 22453 900, Brazil, prada@ele.puc-rio.br / the necessity to do so has already been recognised as early as
nando@ele.puc-rio.br and L. C. A. Ferreira is with ONS, the Independent 1978 and 1980 [6]-[7]. To quote Tiranuchit and Thomas [8]:
Brazilian System Operator, Rio de Janeiro, Brazil, lclaudio@ons.org.br.
"The actual cases of blackouts characterised by voltage
1-4244-0288-3/06/$20.00 ©2006 IEEE

1
depressions reported in the literature indicate that standard the gradient vectors ’P and ’Q and it has being proved that
practice procedures such as transformer tap changing,
00  E  1800 in the upper part of the SV curve (the well-
capacitor switching, synchronous condenser adjustment, and
load shedding may aggravate an already unstable voltage known nicknamed "nose curve"), while 00 ! E ! 1800 in the
profile". Generators are to be included in the list of voltage lower half, where voltage control may have the reverse effect.
controlling devices. At the maximum, the gradient vectors are aligned and thus E
Quasi-static voltage control instability, as above described,
was verified in actual operating points of real life systems [9]. is equal to 0o or r 180o [4]. The Influence Index, defined as
Therefore, as already stated in [10], it is necessary to correlate II = (Mi / Mo - 1), translates the benefits of a reinforcement
the physical variable used to control voltage, such as the control action, where Mo and Mi are the margins before and
excitation current and the controlled voltage in generators. after the control is applied.
The objective is to determine whether the voltage control In order to verify the dynamic behaviour of the generator
action would have the expected steady-state effect or not. automatic voltage regulator, a time domain simulation is
The voltage security assessment method used in this paper performed.
is fully described in [4]. The assessment results are based on
III. NUMERICAL EXAMPLE
indexes Si , Sm , M, E and II where Si is the complex
This paper shows a real life numerical example with the
power injected into the network by the generator, and Sm is
unifilar diagram shown in Fig. 1. A new generator (M.
an estimate of the maximum complex power that could be Merchant connected to bus 3977) was connected to an
injected by the generator, calculated in the operating point existing transmission line which was already heavily load
under analysis. Therefore, M = ( Sm  Si ) / Sm is the complex (connected through a voltage step-up transformer between
power margin between the amount being injected and the buses 3977 and 3966 to the 345 KV transmission line between
estimated maximum (in per unit of Sm). E is the angle between buses 140 Adrianópolis and 147 Campos).

Fig. 1. Portion of the unifilar diagram of the Brazilian system used for tests

2
The voltage security assessment detects that the 276

relationship between the reactive power output and the


259
controlled voltage is opposite to the usual giving a strong
indication the voltage control is not working properly (the 242
negative signs in Table I).
225

TABLE I
VOLTAGE SECURITY ASSESSMENT RESULTS FOR THE 207

GENERATOR TERMINAL BUS (BASE-CASE)


190

Angle
Bus Volt- MVA Index 173
E (de- 0 6 12 19 25
number age (pu) margin (%) dQ/dV
grees) Time(seconds)
3977 1.057 -136.4 -196.9 -0.8 Fig. 4. Reactive power at the terminal bus (pu)

The time domain simulation confirms the static analysis. If the generator voltage control cannot work properly, a
When the reference voltage is changed to a larger value, remedial action would be to decrease the generator output
the excitation voltage is increased by the AVR (Fig. 2). and/or the transmission line (where the unit is connected
Unexpectedly, the controlled voltage decreases (Fig. 3). to) power flow.
The relationship between the reactive power output and the As an example, the active power flow across the
terminal voltage is opposite to the expected (Figs. 3 and 4). transmission line where the generator is connected to is
As the voltage control leads to a lower terminal voltage, the decrease by 7% through generation rescheduling but
automatic control would keep acting, thus leading to still maintaining the generator under analysis with its active
lower voltage. Voltage collapse is a possible consequence. output constant. As a consequence, the reactive power
It is also possible that the excitation current hits limits output decreases by 80%. The security assessment results
interrupting the voltage decay process. are shown in Table II. Generator voltage control is now
working properly as signs are positive.

TABLE II
2,2
VOLTAGE SECURITY ASSESSMENT RESULTS FOR THE
2,183
GENERATOR TERMINAL BUS (AFTER CONTROL ACTION)

2,165 Angle
Bus Volt- MVA Index
E (de-
2,147
number age (pu) margin (%) dQ/dV
grees)
2,129
3977 1.007 175.34 10.0 0.7

2,112
The time domain simulation confirms the static analysis.
2,094
When the reference voltage is changed to a smaller value,
0 6 12 19 25
the excitation voltage is decreased by the AVR (Fig. 5). As
Time(seconds) expected, the controlled voltage decreases (Fig. 6). The
Fig. 2. Generator excitation voltage (pu) relationship between the reactive power output and the
terminal voltage is as usual (Figs. 6 and 7).

1,057 1,04

1,052 1,017

1,047 0,994

1,042 0,971

1,037 0,948

1,032 0,925

1,027 0,902
0 6 12 19 25 0 6 12 19 25

Time (seconds) Time(seconds)


Fig. 3. Generator terminal voltage (pu) Fig. 5. Generator excitation voltage (pu)

3
The generator or compensator is modelled by a variable
1,007 voltage source Eg in the internal bus g behind the
synchronous reactance XS controlling the voltage V0 in the
0,998
terminal bus, as shown in Fig. 8. When the excitation
current hits its limits, the excitation voltage is fixed and the
0,989
voltage V0 is no longer controlled.
0,981

0,972

0,964

0,955
0 6 12 19 25

Time (seconds)
Fig. 6. Generator terminal voltage (pu) Fig. 8. Unifilar diagram of a synchronous generator or compensator
connected to the system

31,8
Solving a power flow algorithm with a sequence of
different values for the terminal voltage reference, the
17,5 corresponding values of the excitation voltage and the
reactive generation are recorded. These three sets of values
3,3
are used to plot the graphics Eg x Vt and Vt x Qg shown in
-10,9
Fig. 9.

-25,1

1.6 12
Eg x Vt
-39,4
Qg x Vt

-53,6
0 6 12 19 25

Time(seconds)
Fig. 7. Reactive power at the terminal bus (pu)
1.55 10

IV. CONCLUSION

The case dealt with in this paper was the opposite


relationship between the generator excitation voltage and
the controlled voltage when the transmission network 1.5 8
1.04 1.06 1.08 1.1 1.12 1.14 1.16 1.18 1.2
where the generator or compensator is connected to is
heavily loaded. In this case, the full capacity of production
/ absorption of reactive power by the generator may not be Fig. 9 Relationships between Eg, Vt and Qg
useful for keeping the bus voltage within pre-defined
range.
It was shown a real life example when a new generator The right side of the curves is the normal region of
presented inappropriate voltage control. It was necessary to operation where Eg, Vt and Qg move in the same direction.
reschedule active power generation in order to decrease the On the other hand, the left side is the region where Eg and
active and reactive power flow across the transmission line Vt move in opposite direction, as well as Qg and Vt. As the
where the generator was connected to. After the remedial minimum of the two curves do not coincide for the same
action, proper voltage control was recovered and the full Vt, there is a region, when 1.12 < Vt <1.14, where Eg and
MW capacity of the new generator could be used. If there Vt vary in the same direction whereas Qg and Vt vary in
was no remedial action, the only possibility would be to opposite direction.
reduce the new generator output. The success of the numerical exercise in obtaining both
sides of the curves will depend on the relationship between
V. APPENDIX the synchronous reactance and the system Thevenin
impedance as seen by the generator terminal bus. In most
A very simple numerical experiment demonstrates the cases only the right side, i.e. the usual region will appear
regular and the opposite relationships between the even if the limits on Vt, Eg and Qg are slightly relaxed.
excitation and the terminal voltages as well as between the
reactive generated power and the terminal voltage.

4
VI. REFERENCES VII. BIOGRAPHIES

[1] Th. Van Cutsem, "Voltage instability: phenomena, countermeasures, Ricardo B. Prada was born in 1951, obtained
and analysis methods", Proc. IEEE, Vol. 88, No. 2, pp. 208-227, Diploma in Electrical Engineering (1975) and
February 2000. M.Sc. in Power Systems (1977) both from
[2] R. B. Prada, B. J. Cory and R. Navarro-Perez, "Assessment of steady Catholic University of Rio de Janeiro, Brazil,
state voltage collapse critical conditions", in Proc.10th Power Ph.D. in Electrical Engineering (1980) from
Systems Computation Conference, 1990, Graz, Austria, pp. 1189- Imperial College of Science and Technology,
1195. London, U.K. He is Associate Professor at
[3] R. B. Prada, A. C. Zambroni, X. Vieira Filho, A. G. Massaud and J. Department of Electrical Engineering, Catholic
C. C. Oliveira, "Voltage stability: phenomena characterisation based University of Rio de Janeiro, Rua Marquês de São
on reactive control effects and system critical areas identification", in Vicente, 225, Rio de Janeiro, RJ, Brazil, phone:
Proc. III Symposium of Specialists in Electric Operational and +55 21 31141214, fax: +55 21 31141232, e-mail:
Expansion Planning, 1992, Belo Horizonte, Brazil. prada@ele.puc-rio.br
[4] R. B. Prada, E. G. C. Palomino, J. O. R. dos Santos, A. Bianco, and L. A.
S. Pilotto, "Voltage stability assessment for real time operation", Proc. Luis F. Ferreira was born in 1980, obtained
IEE Generation, Transmission and Distribution, Vol. 149, No. 2, Diploma in Electrical Engineering (2003) from
pp.175-180, March 2002. Federal University of São João Del Rei, Minas
[5] C. W. Taylor, “Power system voltage stability”, McGraw Hill, 1994. Gerais, MG, Brazil. He is currently working toward
[6] W. R. Lachs, "Voltage collapse in EHV power systems", presented at his MSc degree in voltage stability analysis at the
IEEE PES Winter Power Meeting, January 1978, paper A 78 057-2. Catholic University of Rio de Janeiro, Rio de
[7] C. Barbier and J. P. Barret, "An analysis of phenomena of voltage Janeiro, RJ, Brazil. Now he is an engineer with ICF
collapse on a transmission system", Rev. Générale Electricité, Tome International, Av. das Américas, 700 - bl. 06, sl.
89, No. 10, pp. 672-690, October 1980,. 250, Rio de Janeiro, RJ Brazil, phone: +55 21
[8] A. Tiranuchit and R. J. Thomas, "A posturing strategy against voltage 21172569, fax: +55 21 21327354, e-mail:
instabilities in electric power systems", IEEE Transactions on Power nando@ele.puc-rio.br
Systems, Vol. 3, No. 1, pp. 87-93, February 1988.
[9] R. B. Prada, L. J. Souza and L.A.P. Sousa, “The need for a new constraint
Luiz Cláudio Araujo Ferreira was born in
on voltage / reactive power studies to ensure proper voltage control”, Int.
Rio de Janeiro, where he took his BSc degree at
J. of Electrical Power & Energy Systems, Vol. 24, No. 7, pp. 535-540,
Federal Centre of Technological Education of Rio
September 2002.
de Janeiro (CEFET-RJ). His MSc degree was
[10] IEEE Power System Stability Committee, Special Report, Voltage
obtained at the Federal University at Itajubá in
stability assessment: procedures and guides, Chapter 6, On-line VSA
1999. He is currently working toward his PhD in
functional requirements, January 2001.
voltage stability analysis. Since 1998, he is a
senior engineer for the ONS - the Operator of the
Brazilian Power System, Rua Real Grandeza, 219,
503-E, Rio de Janeiro, RJ, Brazil, phone: +55 21
25283788, fax: +55 21 25283794, e-mail:
lclaudio@ons.org.br.

Potrebbero piacerti anche