Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
D72048GC10
Edition 1.0
February 2011
1
Introduction to Portfolios
Objectives
Projects Manual
in EPS Portfolio
Project
Project
Project
Project
Project
Project Project
Project
Filtered Portfolios
Projects
in EPS Filtered
Project Portfolio
Project
Project
Project
Project
Project Project
2
Viewing Portfolio Information
Objectives
Return
Investment
Gantt Chart
Project
WBS
Gantt Chart
Project
WBS
3
Earned Value Analysis and Portfolio Performance
Objectives
Project Plan:
10-day project to build 10 desks for $1,000
● $1,000 total value
● 1 desk per day
● $100 per desk
10 days 10 desks $1,000 (1 desk/day) ($100/desk)
Planned Value (PV)
In our example:
$300 (EV) – $500 (PV) = – $200 (SV)
In our example:
$300 (EV) – $600 (AC) = – $300 (CV)
In our example:
300/500 = .6
In our example:
300/600 = .5
A number less than 1.0 indicates that the project is over budget.
For every project dollar spent, only $.50 in physical work was
accomplished.
Earned Value Graph
Key
SV Schedule Variance
Actual Cost CV Cost Variance
ETC Estimate to Complete
BAC Budget at Completion
Planned Value EAC Estimate at Completion
VAC Variance at Completion
Earned Value
4
Analyzing Portfolios
Objectives
Bubble size
Y axis
X axis
Waterline Analysis
Project 1
projects that collectively
Project 2 meet constraint limit
constraint limit
Project 3
sorting order other projects
Project 4
Project 5
Scenario
regular view
updates with latest
data
scenario frozen
with January 2018
data
Capacity Planning Chart
available
capacity
limit
labor units
required
units
time
5
Dashboards and Portfolios
Objectives