RIF: J-30435754-0
OBRA: CONSTRUCCION DE HOTEL EL VELERO
Contratante: SERVICIOS INTEGRALES MOCA
PART
DESCRIPCION UND CANT CONVERSION
No
ml 12ml
1 E351200250
SUMINISTRO, PREPARACION Y COLOCACION DE MALLA SOLDADA DE
kgf 4,323.84
ACERO TIPO TRUCKSON ( 4x4") PARA SUPERESTRUCTURA
2 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE ESTRUCTURA METALICA
CON PERFILES CONDUVEN 300x100 MM, INCLUYE EL TRANSPORTE kgf 28,821.07 0 0
HASTA 50 KM.
3 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE ESTRUCTURA METALICA
(CORREAS) CON PERFILES CONDUVEN 180x65 MM, INCLUYE EL kgf 38,904.17 104.18 10
TRANSPORTE HASTA 50 KM.
4 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE ANGULO METALICO
100X100X10 , INCLUYE EL TRANSPORTE HASTA 50 KM. kgf 22,260.42 189.00 17
5 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE ESTRUCTURA METALICA
CON PERFILES CONDUVEN 350x170 MM, INCLUYE EL TRANSPORTE kgf 12,760.90 0.00 0
HASTA 50 KM.
6 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE ESTRUCTURA METALICA
CON PERFILES CONDUVEN 220x220 MM( COLUMNA), INCLUYE EL kgf 17,370.36 0.00 0
TRANSPORTE HASTA 50 KM.
7 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE ESTRUCTURA METALICA
CON PERFILES CONDUVEN 155x155 MM( COLUMNA), INCLUYE EL kgf 535.34 0.00 0
TRANSPORTE HASTA 50 KM.
8 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE ESTRUCTURA METALICA
CON PERFILES CONDUVEN 320x120 MM, INCLUYE EL TRANSPORTE kgf 1,865.18 0.00 0
HASTA 50 KM.
9 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE ANGULO METALICO
50X50X7 (DETALLE 01). INCLUYE EL TRANSPORTE HASTA 50 KM. kgf 692.59 134.48 12
10 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE ANGULO METALICO
75X75X8 (DETALLE 04). INCLUYE EL TRANSPORTE HASTA 50 KM. kgf 938.67 103.95 10
11 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE CORREAS SIMPLE CON
PERFILES CONDUVEN 220x90 MM. ( DETALLE 01 VIGA EXPUESTA).
kgf 1,385.19 67.24 7
INCLUYE TRANSPORTE DE LOS ELEMENTOS HASTA 50 KM.
12 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE CORREAS SIMPLE CON
PERFILES CONDUVEN 220x90 MM. ( DETALLE 05 / SV220). INCLUYE kgf 3,836.30 186.23 17
TRANSPORTE DE LOS ELEMENTOS HASTA 50 KM.
13 ES/C.
SERVICIOS INTEGRALES MOCA C.A.
RIF: J-30435754-0
OBRA: CONSTRUCCION DE HOTEL EL VELERO
Contratante: SERVICIOS INTEGRALES MOCA
PART
DESCRIPCION UND CANT CONVERSION
No
SUMINISTRO, TRANSPORTE Y COLOCACION DE VIGA UPN 260. PARA
EL REFORZAMIENTO DE VIGA 300x100. ( DETALLE SV-300) kgf
INCLUYE EL TRANSPORTE HASTA 50 KM.
14 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE VIGAS UPN 180. PARA
EL REFORZAMIENTO DE VIGA 220X90. ( DETALLE SV-220). INCLUYE kgf 10,428.77 372.46
TRANSPORTE DE LOS ELEMENTOS HASTA 50 KM.
15 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE PLANCHAS 200 cms.
E=10mm. PARA EL REFORZAMIENTO DE VIGA 220X90 mm.
( DETALLE SV-220). INCLUYE TRANSPORTE DE LOS ELEMENTOS kgf 0.00
HASTA 50 KM.
16 ES/C.
SUMINISTRO, TRANSPORTE Y COLOCACION DE PLANCHA
300X9MM_x000D_. (DETALLE 05) kgf 7,892.34 372.46 32
_x000D_
.
MODULO 02
TOTAL
CONVERSION TUBOS BS
12 ML 1
ml 12 ml
701.24 59 59
179.55 16 33
187.11 17 17
384.30 33 33
0.00 0 0
41.27 4 4
0.00 0 12
0.00 0 10
0.00 1 8
0.00 1 18
MODULO 02
TOTAL
CONVERSION TUBOS BS
12 ML 1
0.00 0
VIGA UPN 180 mm ( DETALLE SV-220). F=28,0 kgs/Ml
UBICACIÓN ALTURA VIGAS ML
MODULO 1
SUMATORIA 177.36
UPN 2 354.72
5% DESP 17.74
TOTAL 372.46
5% DESP 4.056
TOTAL 85.18
57
57
60
66
63
63
SUMATORIA 366
5% DESP 18.3
TOTAL 384.3
FACTOR Kgrs/Ml 45.2
TOTAL Kgrs 17,370.36
TOTAL Ton 17.37
COLUMNAS 155X155 / E= 4.5mm / f= 20,60 Kgs/Ml. (h=1,65 Mts)
UBICACIÓN NIVEL ALTURA 260/220 220X220 155X155 (SC)
TOTAL COL H.COL
N° COL N° COL N° COL
MODULO 02 PB 0.00 0 0 0 0
PISO 01 3.00 0 0 0 0
PISO 02 6.00 0 0 0 0
SALON MULT PISO 3 9.00 0 0 15 15 1.65
SUMATORIA
FACTOR Kgrs/Ml
h=1,65 Mts)
ML
0
0
0
24.75
SUMATORIA 24.75
5% DESP 1.24
TOTAL 25.99
FACTOR Kgrs/Ml 20.60
TOTAL Kgrs 535.34
TOTAL Ton 0.54
ANGULO 75X75X8 (DETALLE 04) / F= 9,03 Kgs/Ml. (h=1,65 Mts)
UBICACIÓN NIVEL ALTURA 260/220 220X220 155X155 (SC)
TOTAL COL H.COL
N° COL N° COL N° COL
MODULO 02 PB 0.00 0 0 0 0
PISO 01 3.00 0 0 0 0
PISO 02 6.00 0 0 0 0
SALON MULT PISO 3 9.00 0 0 15 15 1.65
SUMATORIA
5% DESP
TOTAL
LADOS 4
FACTOR Kgrs/Ml
TOTAL Kgrs
TOTAL Ton
s)
ML
0
0
0
24.75
24.75
1.24
25.99
103.95
9.03
938.67
0.94
99
ANGULO 100X100X10 EN COL 220X220. f= 15,10 Kgs/ML.
UBICACIÓN NIVEL ALTURA 260/220 220X220 220X220 (SC)
TOTAL COL H.COL
N° COL N° COL N° COL
MODULO 02 PB 0.00 12 12 3
PISO 01 3.00 12 12 3
NO
PISO 02 6.00 13 13 3
REQUIERE
PISO 03 9.00 7 7 14 3
REFORZA
PISO 04 12.00 2 1 3 3
PISO 05 15.00 2 1 3 3
SUMATORIA
5% DESP
TOTAL
FACTOR Kgrs/Ml
TOTAL Kgrs
TOTAL Ton
0
UBICACIÓN NIVEL ALTURA 260/220 220X220 220X220 (SC) TOTAL COL H.COL
MODULO 01 PB 0.00 NO NO 15 15 3
PISO 01 3.00 NO NO 15 15 3
PISO 02 6.00 NO NO 15 15 3
PISO 03 9.00 NO NO 15 15 3
SUMATORIA
5% DESP
TOTAL
FACTOR Kgrs/Ml
TOTAL Kgrs
TOTAL Ton
36
36
39
42
9
9
171
8.55
179.55
15.1
2,711.21
2.71
ML
45
45
45
45
180
9
189
15.1
2,853.90
2.85
solo modulo 01
CORREAS 180X65 CORREAS 180X
UBICACIÓN ALTURA VIGAS ML UBICACIÓN
MODULO 2 3.00 PISO 01 345.95 MODULO 2
6.00 PISO 02 345.95
NOTA. 17
NOTA. 17
9.00 PISO 03 345.95 CORREAS X
CORREAS X PISO
PISO
12.00 PISO 04 345.95
15.00 PISO 05 345.95
TECHO 18.00 PISO 06 345.95 TECHO
CORREA 3 (D7) TODOS PISOS 122.1 CORREA 3 (D7)
EJS 5-6/A-C TODOS PISOS 294.00 EJS 5-6/A-C
MODULO 1 PISO 1 ( h=3,00) CORREA 3 (D7) 46.87 MODULO 1
PISO 2 ( h=6,00) CORREA 3 (D7) 26.15 PISO 2 ( h=6,00)
PISO 3 ( h=9,00) CORREA 3 (D7) 13.10 PISO 3 ( h=9,00)
TECHO ( h=13,65) CORREA 3 (D7) 13.10 TECHO ( h=13,65)
SUMATORIA
2,591.02
TOTAL
5% DESP 129.551
TOTAL 2,720.57
FACTOR Kgrs/Ml 14.3
TOTAL Kgrs 38,904.17
TOTAL Ton 38.90
solo modulo 02
CORREAS 180X65
UBICACIÓN ALTURA VIGAS ML
MODULO 2 3.00 PISO 01 345.95
6.00 PISO 02 345.95
NOTA. 17
9.00 PISO 03 345.95
CORREAS X PISO
9.00 PISO 03 0
12.00 PISO 04 0
15.00 PISO 05 0
18.00 PISO 06 0
CORREA 3 (D7) TODOS PISOS 0
TODOS PISOS 0
PISO 1 ( h=3,00)
CORREA 3 (D7) 46.87
PISO 2 ( h=6,00)
CORREA 3 (D7) 26.15
PISO 3 ( h=9,00)
CORREA 3 (D7) 13.10
TECHO ( h=13,65)
CORREA 3 (D7) 13.10
SUMATORI
99.22
A TOTAL
5% DESP 4.961
TOTAL 104.18
FACTOR
14.3
Kgrs/Ml
TOTAL Kgrs 1,489.79
TOTAL Ton 1.49
DETALLE 02 (VIGAS 260X90). F= 28,30 Kgs/Ml
UBICACIÓN ALTURA VIGAS ML
MODULO 1 PISO 1 ( h=3,00) 260X90 36.52
PISO 2 ( h=6,00) CORREA 3 (D7) 44.60
SUMATORIA TOTAL 81.12
5% DESP 4.056
TOTAL 85.18
FACTOR Kgrs/Ml 28.3
TOTAL Kgrs 2,410.48
TOTAL Ton 2.41
VIGAS 320X120
UBICACIÓN ALTURA VIGAS ML
MODULO 2 3.00 PISO 01 13.1
6.00 PISO 02 13.1
9.00 PISO 03 13.1
12.00 PISO 04 0
15.00 PISO 05 0
TECHO 18.00 PISO 06 0
0
0
SUMATORIA 39.3
5% DESP 1.965
TOTAL 41.265
FACTOR Kgrs/Ml 45.2
TOTAL Kgrs 1,865.18
TOTAL Ton 1.87
VIGAS 300X100
UBICACIÓN ALTURA VIGAS ML
MODULO 2 3.00 PISO 01 94.2
6.00 PISO 02 94.2
9.00 PISO 03 94.2
12.00 PISO 04 107.3
15.00 PISO 05 94.2
TECHO 18.00 PISO 06 94.2
VOLADOS TODOS LOS PISOS 42.3
EJS 5-6(A-C) TODOS LOS PISOS 47.25
SUMATORIA 667.85
5% DESP 33.3925
TOTAL 701.2425
FACTOR Kgrs/Ml 41.1
TOTAL Kgrs 28,821.07
TOTAL Ton 28.82
VIGAS 350X170
UBICACIÓN ALTURA VIGAS ML
MODULO 2 3.00 PISO 01 29.7
6.00 PISO 02 29.7
9.00 PISO 03 29.7
12.00 PISO 04 29.7
15.00 PISO 05 29.7
TECHO 18.00 PISO 06 29.7
VOLADOS TODOS LOS PISOS 0
EJS 5-6(A-C) TODOS LOS PISOS 0
SUMATORIA 178.2
5% DESP 8.91
TOTAL 187.11
FACTOR Kgrs/Ml 68.2
TOTAL Kgrs 12,760.90
TOTAL Ton 12.76