Sei sulla pagina 1di 1

THE UNIVERSITY OF ADELAIDE

ENERGY INITIATIVES CASE STUDY


POWER FACTOR CORRECTION
Straining Infrastructure This increases the infrastructure requirement on
a building basis, meaning that cables and
South Australian electricity infrastructure switchboards need to be larger and more
struggles to cope during periods of peak powerful. It can also mean that new or
demand when hot weather dictates in modern additional equipment can not be supported by
times the maximum operation of air the electrical infrastructure.
conditioning systems throughout the
community. The double penalty is that ETSA Utilities now
have the right to penalise customers, including
Domestic customers now pay more for their the University, showing poor power factor at
electrical energy usage during these periods of their point of electricity supply.
expected high demand.
Conversely, tariff bonuses are offered to
Whilst this happens, the Community is also customers able to comply with strict power
becoming frustrated with the increasing rate of factor criteria.
infrastructure failures that affect their homes
and working environments. University of Adelaide Implements a Solution

Whilst the major cause of these issues is The North Terrace Campus has some 13
undoubtedly increased electrical load, within separate electricity supply connections to the
the load increase is another hidden culprit network. Each supply has a specific capacity,
accounting for at least some of the strain on which is affected by the power factor of items
infrastructure – the phenomenon of power connected.
factor.
The University has begun implementation of a
Technicalities Power Factor Correction project for those
supplies that have been found to be operating
Most modern electrical equipment is based on with a poor power factor. Power Factor
the physics of electro-magnetism. For correction involves the installation of monitored
example, the work-horse of modern industry, capacitor banks located at main switchboards
the alternating current motor relies on or major items of equipment.
magnetism and until recently, fluorescent
lighting systems operating in office buildings It is anticipated that over 10% of the present
used magnetic iron-cored internals within every University supply capacity will be freed up for
fitting. other requirements of the Campus, or will be
returned to the Community to reinforce existing
The requirement for magnetism means an electricity supply infrastructure.
‘inductive load’, which in summary pushes the
current out of synchronism with the voltage. Project Facts
The science of this means that to produce the
power that the equipment needs, the current - First Power Factor Correction units installed
increases by a ratio known as the power factor. – Napier Building 2005, Plaza, 2006.
A ‘poor’ power factor requires a larger current, - Completion date for Power Factor
causing increased demand on electrical Correction project – North Terrace -
infrastructure. February 2007.
- Infrastructure Capacity improvement
The solution is to install additional devices that anticipated – greater than 10%, or around
create better synchronisation between voltage 1.5 MVA. In terms of augmentation, this
and current. In this manner the poor power has a simplified value of almost $190,000.
factor can be ‘corrected’. - Project Implementation cost at North
Terrace - $150,000, giving a simple
Double Jeopardy payback period of less than 12 months.

The University operates large amounts of


electrical equipment in most buildings and
facilities. Much of the equipment causes a
poor power factor.

Potrebbero piacerti anche