Rencana Anggaran Biaya (RAB)

Proyek : Rumah 1 Unit


Lokasi : Indonesia

SATUAN VOLUME HARGA SAT. JUMLAH HARGA


NO. URAIAN PEKERJAAN
[SAT.] [VOL.] [Rp.] [Rp.]
A PEKERJAAN PENDAHULUAN
1 Pek. Pengukuran / Pas. Bouwplank m1 18.00 91,760 1,651,680
2 Pek. Penyediaan Air Kerja Ls 1.00 5,000,000 5,000,000
3 Penyediaan Gudang / Direksi Keet / Pagar Proyek Ls 1.00 20,000,000 20,000,000
SUB-TOTAL [Rp.] 26,651,680
B PEKERJAAN PONDASI
1 Pek. Galian Pondasi Setempat (PS) M3 50.70 46,200 2,342,340
2 Pek. Galian Sloof S1 20/40 M3 16.72 46,200 772,464
3 Pek. Urugan Pasir dibawah PS M3 1.95 128,700 250,965
4 Pek. Cor Tapak Pondasi 30x120x130 M3 11.70 3,671,350 42,954,795
5 Pek. Stik Kolom 20/40 M3 2.00 3,671,350 7,342,700
SUB-TOTAL [Rp.] 53,663,264
C PEKERJAAN STRUKTUR
1 Pek. Sloof S1 20/40 M3 16.72 dst… dst…
2 Pek. Kolom K1 15/40 M3 6.00 dst… dst…
3 Pek. Kolom Praktis K2 15/15 M3 2.88 dst… dst…
4 Pek. Balok Gantung Pintu Depan 15/25 M3 0.23 dst… dst…
5 Pek. Plat Beton Pintu Depan, tebal 10cm M3 0.74 dst… dst…
6 Pek. Cor Rabat Lantai M3 16.80 dst… dst…
SUB-TOTAL [Rp.] dst…
D PEKERJAAN DINDING BATA
1 Pek. Pas. Dinding 1/2 Bata Camp. 1:4 M2 706.67 dst… dst…
2 Pek. Plesteran dan Aci 1:4 M2 1,413.34 dst… dst…
SUB-TOTAL [Rp.] dst…
E PEK. KUSEN, PINTU, JENDELA, DAN AKSESORIS
1 Pek. Kusen & Pintu Utama (Pintu 2 Daun) Unit 4.00 dst… dst…
2 Pek. Kusen & Pintu Belakang (Pakai Jalusi Kayu) Unit 4.00 dst… dst…
3 Pek. Kusen & Pintu K.Tidur Unit 8.00 dst… dst…
4 Pek. Pintu Fiber Sisir KM [tanpa kozen] Unit 4.00 dst… dst…
5 Pek. Kusen & Daun Jendela Kaca Depan Unit 4.00 dst… dst…
6 Pek. Kusen & Jendela Kaca Nako Belakang (Pakai Jalusi Kayu) Unit 4.00 dst… dst…
SUB-TOTAL [Rp.] dst…
F PEKERJAAN INSTALASI LISTRIK
1 Pek. Instalasi Titik Lampu & Stop Kontak Ttk 64.00 dst… dst…
2 Pek. Pas. Saklar Bh 36.00 dst… dst…
3 Pek. Pas. Stop Kontak Set 28.00 dst… dst…
4 Pek. Panel box Unt 4.00 dst… dst…
SUB-TOTAL [Rp.] dst…
G PEKERJAAN SANITAIR
1 Pek. Instalasi Air Bersih [Pipa PVC 3/4" dan 1/2"] M' 104.00 dst… dst…
2 Pek. Instalasi Air Kotor K.Mandi, Dapur, Air Hujan [Pipa PVC Ø3"] M' 154.00 dst… dst…
3 Pek. Instalasi Air Buangan Closet [Pipa PVC Ø4"] M' 48.00 dst… dst…
4 Pek. Septick tank Unt 4.00 dst… dst…
SUB-TOTAL [Rp.] dst…
H PEKERJAAN ATAP BETON
1 Pek. Balok Gantung 25/50 M3 10.00 dst… dst…
2 Pek. Balok Duduk 20/40 M3 6.00 dst… dst…
3 Pek. Cor Plat Beton (tbl. 10 cm) M3 24.00 dst… dst…
4 Pek. Kolom Praktis K2 15/15 (Pagar Keliling Atap) M3 0.56 dst… dst…
5 Pek. Pas. Dinding 1/2 Bata Camp. 1:4 M2 85.60 dst… dst…
6 Pek. Plesteran dan Aci Bata 1:4 M2 214.00 dst… dst…
7 Pek. Plesteran dan Aci Lantai Atap 1:4 M2 240.00 dst… dst…
8 Pek. Floor Drain M2 12.00 dst… dst…
SUB-TOTAL [Rp.] dst…
I PEKERJAAN FINISHING
1 Pek. Keramik Lantai (Keramik 40x40) M2 240.00 dst… dst…
2 Pek. Keramik K.Mandi Unit 4.00 dst… dst…
3 Pek. Meja Dapur dan Pas. Keramik Unit 4.00 dst… dst…
4 Pek. Plafon M2 240.00 dst… dst…
5 Pek. Finishing Plesteran Motif Tpk. Depan Unit 4.00 dst… dst…
6 Pek. Cat Dinding Luar M2 500.60 dst… dst…
7 Pek. Cat Dinding Dalam dan Plafon M2 1147.20 dst… dst…
8 Pek. Cat Kusen, Daun Pintu, dan Daun Jendela Unit 28.00 dst… dst…
SUB-TOTAL [Rp.] dst…
TOTAL [Rp.] 80,314,944
Indonesia, 7 Juli 2014
Dibuat Oleh:

proyeksipil.blogspot.com
BOBOT
[%]

0.00
Juli 2014

ogspot.com
Daftar Harga Bahan dan Upah
Proyek : Rumah 1 Unit
Lokasi : Indonesia

A. Harga Bahan (Material)


No. Nama Bahan (Material) Satuan Harga Satuan (Rp.)
1 Kayu gergajian kelas III, papan m3 4,800,000
2 Kayu gergajian kelas III, balok m3 4,800,000
3 Paku berbagai ukuran (2" - 5") kg 13,000
4 Pasir urug / timbun m3 90,000
5 Minyak bekisting ltr 5,000
6 Besi beton kg 8,500
7 Kawat beton kg 18,000
8 Semen PC @ 50 kg kg 1,200
9 Pasir ayak untuk beton m3 100,000
10 Batu pecah 2 - 3 (cm) m3 265,000

B. Harga Upah
No. Uraian Satuan Harga Satuan (Rp.)
1 Mandor m3 120,000
2 Kepala tukang m3 100,000
3 Tukang batu kg 90,000
4 Tukang kayu m3 90,000
5 Tukang besi / tukang las ltr 90,000
6 Pekerja tak terlatih kg 65,000
Analisa Harga Satuan Bahan dan Upah
Proyek : Rumah 1 Unit
Lokasi : Indonesia

Kode Harga Satuan (Rp.)


Uraian Pekerjaan
Analisa Bahan Upah
A.4 1 m' Pengukuran dan pemasangan bouwplank, papan 2/10
0.0035 m³ Kayu gergajian kelas III, papan 4,800,000.00
0.0120 m³ Kayu gergajian kelas III, balok 4,800,000.00
0.0200 kg Paku berbagai ukuran (2" - 5") 13,000.00
0.1000 Oh Pekerja tak terlatih 65,000.00
0.1000 Oh Tukang kayu 90,000.00
0.0100 Oh Kepala tukang 100,000.00
0.0050 Oh Mandor 120,000.00
Jumlah (Rp.)

B.1 1 m³ Galian Tanah biasa Sedalam 1 m (dengan tenaga)


0.6000 Oh Pekerja tak terlatih 65,000.00
0.0600 Oh Mandor 120,000.00
Jumlah (Rp.)

B.11 1 m³ Urugan Pasir (dengan tenaga)


1.2000 m³ Pasir urug / timbun 90,000.00
0.3000 Oh Pekerja tak terlatih 65,000.00
0.0100 Oh Mandor 120,000.00
Jumlah (Rp.)

G.29 1 m³ Membuat pondasi beton bertulang (150 kg besi + bekisting)


0.2000 m³ Kayu gergajian kelas IV, papan 4,800,000.00
1.5000 kg Paku berbagai ukuran (2" - 5") 13,000.00
0.4000 ltr Minyak bekisting 5,000.00
157.5000 kg Besi beton 8,500.00
2.2500 kg Kawat beton 18,000.00
336.0000 kg Semen PC @ 50 kg 1,200.00
0.5400 m³ Pasir ayak untuk beton 100,000.00
0.8100 m³ Batu pecah 2 - 3 (cm) 265,000.00
5.3000 Oh Pekerja tak terlatih 65,000.00
0.2750 Oh Tukang batu 90,000.00
1.3000 Oh Tukang kayu 90,000.00
1.0500 Oh Tukang besi / tukang las 90,000.00
0.2620 Oh Kepala tukang 100,000.00
0.2650 Oh Mandor 120,000.00
Jumlah (Rp.)
Harga Analisa (Rp.) Harga Analisa
Bahan Upah Bahan dan Upah (Rp.)

16,800.00
57,600.00
260.00
6,500.00
9,000.00
1,000.00
600.00
74,660.00 17,100.00 91,760.00

39,000.00
7,200.00
- 46,200.00 46,200.00

108,000.00
19,500.00
1,200.00
108,000.00 20,700.00 128,700.00

960,000.00
19,500.00
2,000.00
1,338,750.00
40,500.00
403,200.00
54,000.00
214,650.00
344,500.00
24,750.00
117,000.00
94,500.00
26,200.00
31,800.00
3,032,600.00 638,750.00 3,671,350.00
``
No. Uraian Pekerjaan Jumlah Harga [Rp.]

A PEKERJAAN PENDAHULUAN Rp. 26,651,680.00


B PEKERJAAN PONDASI Rp. 53,663,264.00
C PEKERJAAN STRUKTUR Rp. 100,000,000.00
D PEKERJAAN DINDING BATA Rp. 40,000,000.00
E PEK. KUSEN, PINTU, JENDELA, DAN AKSESORIS Rp. 30,000,000.00
F PEKERJAAN INSTALASI LISTRIK Rp. 15,000,000.00
G PEKERJAAN SANITAIR Rp. 15,000,000.00
H PEKERJAAN ATAP BETON Rp. 55,000,000.00
I PEKERJAAN FINISHING Rp. 20,000,000.00

TOTAL Rp. 355,314,944.00


DIBULATKAN Rp. 355,314,000.00

Terbilang : Delapan Puluh Juta Tiga Ratus Empat Belas Ribu Rupiah

Indonesia, 7 Juli 2014


Dibuat Oleh:

proyeksipil.blogspot.com
WAKTU PELAKSANAAN (TIME SCHEDULE)
PROYEK PEMBANGUNAN ………

JUMLAH
BOBOT
NO URAIAN PEKERJAAN HARGA
(RP.) (%)
A PEKERJAAN PENDAHULUAN 26,651,680.00 7.50
B PEKERJAAN PONDASI 53,663,264.00 15.10
C PEKERJAAN STRUKTUR 100,000,000.00 28.14
D PEKERJAAN DINDING BATA 40,000,000.00 11.26
E PEK. KUSEN, PINTU, JENDELA, DAN AKSESORIS 30,000,000.00 8.44
F PEKERJAAN INSTALASI LISTRIK 15,000,000.00 4.22
G PEKERJAAN SANITAIR 15,000,000.00 4.22
H PEKERJAAN ATAP BETON 55,000,000.00 15.48
I PEKERJAAN FINISHING 20,000,000.00 5.63
JUMLAH = 355,314,944.00 100.00

Indonesia, 22 Februari 2017


Dibuat Oleh:

proyeksipil.blogspot.co.id
WAKTU PELAKSANAAN (TIME SCHEDULE)
PROYEK PEMBANGUNAN ………

JUMLAH WAKTU
BOBOT
NO URAIAN PEKERJAAN HARGA MARET 2017
(RP.) (%) 1 2 3
A PEKERJAAN PENDAHULUAN 26,651,680.00 7.50
IN
B PEKERJAAN PONDASI 53,663,264.00 15.10
SE
C PEKERJAAN STRUKTUR 100,000,000.00 28.14 RT
D PEKERJAAN DINDING BATA 40,000,000.00 11.26 -
8.44
IN
E PEK. KUSEN, PINTU, JENDELA, DAN AKSESORIS 30,000,000.00
SE
F PEKERJAAN INSTALASI LISTRIK 15,000,000.00 4.22
RT
G PEKERJAAN SANITAIR 15,000,000.00 4.22 S
H PEKERJAAN ATAP BETON 55,000,000.00 15.48 H
5.63
EE
I PEKERJAAN FINISHING 20,000,000.00
T
JUMLAH = 355,314,944.00 100.00 R
O
W
WAKTU PELAKSANAAN PEKERJAAN = 4 BULAN
ARET 2017 APRIL 2017 MEI 2017 JUNI 2017 KET.
4 1 2 3 4 1 2 3 4 1 2 3 4

Indonesia, 22 Februari 2017


Dibuat Oleh:

proyeksipil.blogspot.co.id
WAKTU PELAKSANAAN (TIME SCHEDULE)
PROYEK PEMBANGUNAN ………

JUMLAH WAKTU
BOBOT
NO URAIAN PEKERJAAN HARGA MARET 2017
(RP.) (%) 1 2 3
A PEKERJAAN PENDAHULUAN 26,651,680.00 7.50 3.75 3.75

B PEKERJAAN PONDASI 53,663,264.00 15.10 5.03

C PEKERJAAN STRUKTUR 100,000,000.00 28.14

D PEKERJAAN DINDING BATA 40,000,000.00 11.26

E PEK. KUSEN, PINTU, JENDELA, DAN AKSESORIS 30,000,000.00 8.44

F PEKERJAAN INSTALASI LISTRIK 15,000,000.00 4.22 BAR-CHART


G PEKERJAAN SANITAIR 15,000,000.00 4.22

H PEKERJAAN ATAP BETON 55,000,000.00 15.48

I PEKERJAAN FINISHING 20,000,000.00 5.63

JUMLAH = 355,314,944.00 100.00


RENCANA PROGRESS MINGGUAN (%) = 0.00 3.75 3.75 5.03
RENCANA PROGRESS KOMULATIF (%) = 0.00 3.75 7.50 12.54
WAKTU PELAKSANAAN PEKERJAAN = 4 BULAN
ARET 2017 APRIL 2017 MEI 2017 JUNI 2017 KET.
4 1 2 3 4 1 2 3 4 1 2 3 4

5.03 5.03

7.04 7.04 7.04 7.04

2.81 2.81 2.81 2.81

1.41 1.41 1.41 1.41 1.41 1.41

R-CHART 0.60 0.60 0.60 0.60 0.60 0.60 0.60

0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53

3.10 3.10 3.10 3.10 3.10

1.13 1.13 1.13 1.13 1.13

5.03 12.07 11.26 11.26 12.39 8.45 5.63 5.63 5.35 5.35 2.26 1.65 1.13
17.57 29.64 40.90 52.16 64.54 72.99 78.63 84.26 89.61 94.96 97.22 98.87 100.0

Indonesia, 22 Februari 2017


Dibuat Oleh:

proyeksipil.blogspot.co.id
WAKTU PELAKSANAAN (TIME SCHEDULE)
PROYEK PEMBANGUNAN ………

JUMLAH WAKTU
BOBOT
NO URAIAN PEKERJAAN HARGA MARET 2017
(RP.) (%) 1 2 3
A PEKERJAAN PENDAHULUAN 26,651,680.00 7.50 3.75 3.75

B PEKERJAAN PONDASI 53,663,264.00 15.10 5.03

C PEKERJAAN STRUKTUR 100,000,000.00 28.14

D PEKERJAAN DINDING BATA 40,000,000.00 11.26

E PEK. KUSEN, PINTU, JENDELA, DAN AKSESORIS 30,000,000.00 8.44

F PEKERJAAN INSTALASI LISTRIK 15,000,000.00 4.22 KURVA-S


G PEKERJAAN SANITAIR 15,000,000.00 4.22

H PEKERJAAN ATAP BETON 55,000,000.00 15.48

I PEKERJAAN FINISHING 20,000,000.00 5.63

JUMLAH = 355,314,944.00 100.00


RENCANA PROGRESS MINGGUAN (%) = 0.00 3.75 3.75 5.03
RENCANA PROGRESS KOMULATIF (%) = 0.00 3.75 7.50 12.54

REALISASI PROGRESS MINGGUAN (%) = 0.00


REALISASI PROGRESS KOMULATIF (%) = 0.00

SELISIH (DEVIASI) MINGGUAN (%) = 0.00


SELISIH (DEVIASI) KOMULATIF (%) = 0.00

https://proyeksipil.blogspot.com/2017/02/cara-buat-time-schedule-bar-chart.html
WAKTU PELAKSANAAN PEKERJAAN = 4 BULAN
ARET 2017 APRIL 2017 MEI 2017 JUNI 2017 KET.
4 1 2 3 4 1 2 3 4 1 2 3 4
100

5.03 5.03
80
7.04 7.04 7.04 7.04

2.81 2.81 2.81 2.81


60
1.41 1.41 1.41 1.41 1.41 1.41

KURVA-S 0.60 0.60 0.60 0.60 0.60 0.60 0.60 40

0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53

3.10 3.10 3.10 3.10 3.10 20

1.13 1.13 1.13 1.13 1.13


0

5.03 12.07 11.26 11.26 12.39 8.45 5.63 5.63 5.35 5.35 2.26 1.65 1.13
17.57 29.64 40.90 52.16 64.54 72.99 78.63 84.26 89.61 94.96 97.22 98.87 100.0