Schedule of Material Approval

Expected
date of Approval Date Of
Sr. No. Ref Material Description Make Rev Delivery Status
Submission required Order Date
1 MAS-AC-01A pre Insulated Ducting PAL/Ezee, Bahrain 0 26-Sep 3-Oct 6-Oct 15-Oct
2 MAS-AC-01B GI Sheets Jindal, India 0 26-Sep 3-Oct 6-Oct 25-Oct

3 MAS-AC-02 Duct insulation( Inside building) Kimmco, Kuwait 0 26-Sep 3-Oct 6-Oct 25-Oct
Duct insulation( exposed and
4 MAS-AC-03 shafts) Kimmco, Kuwait 0 26-Sep 3-Oct 6-Oct 25-Oct
5 MAS-AC-04 Acoustic insulation Kimmco, Kuwait 0 26-Sep 3-Oct 6-Oct 25-Oct
6 MAS-AC-05 Protective coating Fosters 0 26-Sep 3-Oct 6-Oct 25-Oct
7 MAS-AC-06 Refrigerant Pipes Maksal 0 26-Sep 3-Oct 6-Oct 25-Oct
8 MAS-AC-07 Refrigerant Pipe insulation Gulf-o-Flex 0 26-Sep 3-Oct 6-Oct 25-Oct
9 MAS-AC-08 Pipes and duct supports Weicco, Diamond 0 26-Sep 3-Oct 6-Oct 25-Oct
10 MAS-AC-09 Grilles and Diffusers Tecnalco 0 26-Sep 3-Oct 6-Oct 30-Oct
11 MAS-AC-10 Sand Trap Louvers Tecnalco 0 26-Sep 3-Oct 6-Oct 30-Oct
12 MAS-AC-11 Door transfer Grilles Tecnalco 0 26-Sep 3-Oct 6-Oct 30-Oct
13 MAS-AC-12 extract Louvers Tecnalco 0 26-Sep 3-Oct 6-Oct 30-Oct
14 MAS-AC-13 Volume Control damper Tecnalco 0 26-Sep 3-Oct 6-Oct 30-Oct
15 MAS-AC-14 Fire Damper Tecnalco 0 26-Sep 3-Oct 6-Oct 30-Oct
16 MAS-AC-15 Extract Fans Dynair/Flaktwood 0 26-Sep 3-Oct 6-Oct 24-Nov
Universal, Awal
17 MAS-AC-16 Fan Coil Units Gulf. Bahrain 0 29-Sep 3-Oct 6-Oct 24-Nov
Universal, Awal
18 MAS-AC-17 Air Handling Units Gulf. Bahrain 0 29-Sep 3-Oct 6-Oct 24-Nov
19 MAS-AC-18 Tray for refrigerant Pipes KEI 0 26-Sep 3-Oct 6-Oct 30-Oct

A-Approved, AWC - Approved with Comments, R - Revise and resubmitt, NA - Not Approved