Sei sulla pagina 1di 8

PT.

PANCA INTIKARYA MANDIRI


GENERAL CONTRACTORS AND SERVICES
Jl. Raya Bantar - Gebang, Grand Regency C1. No. 09Jawa Barat 17422

QUOTATION
To /Kepada : PT.Beiersdorf Indonesia From /Dari : PT. Panca Intikarya Mandiri
Address/ Alamat : Malang Date/ Tanggal : 3 1 October 2018
Attn/ up. : Bpk . Pangki Subject/Perihal : Media MBBR XLB
Telp : - Reff No : Q-014/BDF/JZ/X/18
Mobile Phone : 0813-8983-3252
E-mail :
Inq No / RFQ : 01 Email : darrell.justine@gmail.com

We are please to quote the following as per your request .


DESCRIPTION PACKING PRICE/M3 QUANITTY AMOUNT

1 Media MBBR (m3)


Type XLB (PE03)
18 Rp. 345,780,000.-
Size : Ф10*7 0,1 m3/Bag Rp. 19.210.000.-
( diameter 10 mm, height 7 mm)

Hole number : 5
Density : 0,96-0,98 g/cm3
Weight : 140 kg/m3

Said : Total Rp Rp. 345,780,000.-


Three Hundred Forty Five Million Seven
Hundreds Eighty Thousand Rupiahs.

Grand Total Rp. 345,780,000.-


Terms and Conditions for the above quote :
1 Currency / Mata Uang : All Price are in IDR ( exclude PPN 10%)
2 Price Basis / Harga Loco : Malang- Indonesia.
3 Term of Payment/Cara Pembayaran : * Term 1 - Down Payment 50% After received PO
* * Term 2 – Balance-Before Shipment 50%
4 Time Schedule / Durasi Pekerjaan : indent ± 6 weeks
5 Validity / Masa Berlaku : 10 Days from date of quotation.

Noted: - please be confirmed before purchase


‘- Our offers accordingly to the form MBBR received (attached)
Yours faithfully,
We hereby accept and confirm the order as per Above.

Darrell Justine Date : ................/....................../..............................


Customer Signature & Company Stamp
PT. PANCA INTIKARYA MANDIRI
GENERAL CONTRACTORS AND SERVICES
Jl. Raya Bantar - Gebang, Grand Regency C1. No. 09Jawa Barat 17422

Calculation Basic Design

CLIENT : PT. BEIERSDORF INDONESIA


PROJECT : WWTP, CAPACITY 85 M3/DAY
LOACTION : MALANG-JAWA TIMUR

Data : Flow, Q 85 m3/day


COD in 1200 mg/L
BOD in 720 mg/L
COD out 100 mg/L
BOD out 30 mg/L
NH3 in 2.8 mg/L
NH3 out 10 mg/L

Calculation:
a. BOD removal

- BOD Balance 690 mg/L


- BOD loading 58650 g.BOD/day
-
- Surface Area MBBR 800 m2/m3
- flux MBBR 5 g.BOD/m2.day
-
- Area Required 11730 m2
- Volume Media Required 15 m3 media
- clogging% 20%
- Volume media Required 18 m3 media
- Fill media 40% Rate : 15%-67%
- Volume Aeration 44 m3
- HRT 12 hour

b. NH4 Removal
- NH4 balance -7.2 mg/L
- NH4 Loading -612 g.NH4/day
- NH4 loading - g.NH4/m3.day
- Flux MBRR 0.5 g NH4/m2.day (pit in range NH3 loading)
-
- Volume media Required - m3 media
- clogging % 20%
- Volume media required - m3 media
- Fill media 50% Rate : 15%-70%
- Volume aeration - m3
- HRT - hour
PT. PANCA INTIKARYA MANDIRI
GENERAL CONTRACTORS AND SERVICES
Jl. Raya Bantar - Gebang, Grand Regency C1. No. 09Jawa Barat 17422

c. Eksekutif Summary

I. Total Media Required for BOD&NH4


Removal 18 m3 of media

II. Total Volume Aeration required for


BOD&NH4 Removal 44 m3 tank

III. HRT total 12 hour

 Please take noted that any changes parameters coming from source stream will affect into the quality
of effluent.

MBBR Media Type


PT. PANCA INTIKARYA MANDIRI
GENERAL CONTRACTORS AND SERVICES
Jl. Raya Bantar - Gebang, Grand Regency C1. No. 09Jawa Barat 17422

Spesification Media MBBR


Client: PT. BEIERSDORF
Project:
gggy Beiersdorf Magma Phase 2 & 3

MOVING BED BIO REACTOR


PROCESS DATA SHEET

PT ARCHETYPE INDONESIA
Menara 165, 12th Floor
Jl. TB Simatupang Kav. 1
Cilandak Timur
Jakarta Selatan 12560
Indonesia

Author: Veronica Manalu


- Telephone: +62 21 29 40 68 40
- E-mail: veronica.manalu@archetype-group.com
16th October 2018
Project number: C-TID-EXT-18-016-B00
Document number: DS-BD-PR-SI-1002-01
Revision: 1

Shaping Tomorrow
PT Archetype Indonesia
MBBR Process Data Sheet
Project number: C-TID-EXT-18-016-B00
Document number: DS-BD-PR-SI-1002-01
Revision: 1
16th October 2018

1 16/10/2018 First Issued VM CM


Rev. Date Description Author Checked by Approved by
Shaping Tomorrow

© Copyright Archetype

All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means
without permission of the publisher.
MOVING BED BIO REACTOR
Spec./Data sheet for:

Cost Acc. Code: Vendor: Item no.:

Project Name: Beiersdorf Magma Phase 2 & 3


Industry Category: Cosmetic
End-user Name: PT BEIERSDORF INDONESIA
Representative (if applicable): -
Design Engineer (if applicable): -
Tel: Fax: Email:
Project Location (City, State, Country) Malang, East Java - Indonesia
Existing System (describe if applicable) : Conventional Activated Sludge (CAS)
System required (check one): MBBR YES IFAS NO
Objective (check one): BOD Reduction > 90% Nitrification > 85% Total Nitrogen Removal > 85%

Wastewater Characterization Profile / Design Parameters

Parameter Minimum Average Maximum Effluent Discharge Limitation


Flow (gpd or m3/day 85
Temp °(degrees) 30
BOD (mg/L) 588
COD (mg/L) 1200 100
TSS (mg/L)
FOG (mg/L) -
TKN (mg/L) -
TN (mg/L) -
Ammonia-N (mg/L) -
Phosphorus (mg/L -
Alkalinity (mg/L) -
TDS (mg/L) -
pH (S.U.) 7 6-7

Project : Beiersdorf Magma Phase 2 & 3 Plant Location : MALANG


Client : PT. BEIRSDORF INDONESIA
Rev. Date Description / Issued For Prep'd Ck'd App'd
1 16-Oct-18 First Issued VM CM

Office : Jakarta Document No : DS-BD-PR-SI-1002 Sheet : 1 of 2


Physical Design / Space Considerations

Designated Area Tanks for Retrofit


Space (LxWxH) (9.4 * 3.2 * 2.8) m Dimensions -
Utilities
Electrical Supply - Covered No (open aeration)
Potable Water - Available Fittings -
Compressed Air - Other Usable Equipment
Current Surcharges Lift Stations No
BOD 40 Blowers Yes, 20 kW
TSS 30 Clarifiers / DAFs Yes, Clarifier
NH4 - Sludge Handling Equipment Yes, Clarifier

Existing Treatment System Performance (if applicable)

Unit Type Quantity Volume / Capacity Dimensions


Aeration basin CAS 1 85 m3 ( 9.4 * 3.2 * 2.8 ) m
Clarifier Rectangular 1 25 m3 ( 3 * 3 * 2.8 ) m
Aeration Fine Diffuser 26 90 ft3 /minute -

Additional Information:

Proposal Requirements
Budgeting ( 26 -10 - 2018 ) Purchase ( xx - xx- 2018 )
(Check one)

Project Timing: Submittal ( xx - xx- 2018 ) PO Placement ( xx - xx- 2018 ) Kick-Off ( xx - xx- 2018 )

Target Installation Period: Engineering ( xx - xx- 2018 ) Equipment ( xx - xx- 2018 ) Completion ( xx - xx- 2018 )

Target Operational Date: ( xx - xx - 2018 )

Discharge To: River

Regulatory Agency: Meet the standard discharge permen LH No.51 tahun 1995

Project : Beiersdorf Magma Phase 2 & 3 Plant Location : MALANG


Client : PT BEIERSDORF INDONESIA
Rev. Date Description / Issued For Prep'd Ck'd App'd
A 16-Oct-18 First Issued VM CM

Office : Jakarta Document No : DS-BD-PR-SI-1002 Sheet : 2 of 2

Potrebbero piacerti anche