Monthly Report of Maintenance Department

September 2017

I. Chart :

- Electrical engineer : Yazeed Saad Al Mousa

II. Electrical activities:

1. Site works:
- 02/12/2018
- Startup of DG for weekly check and checked transformer oil & winding
temp.
- By: Dexter,Manab.
- 03/12/2018
- Extended cable for basing pump for cooling water.
- Cleaned extension cables.
- Checked 20-p-001A pump, trip cannot be rest DUE room is close cannot
be open.
- Air blown compressor a technical combart next.
- By: Manab.
- 04/12/2018
- Changed cable trat at waste water treatment plant
- Monitored switchgear room & area.
- By: Dexter,Manab.
- 05/12/2018
- Staerted DC for PRE-heating &checking.
- By: Dexter,Manab.
- 06/12/2018
- Installed 2 floors & 4th at process area facing residue its charge as
temp.Light at night (tube lamp still not purchased request already sent )
- By: Dexter,Manab.
- 09/12/2018
- Started DG & checked transformer for weekly check list.
- Checked lamp ballast at Filipino cabin.
- Change lamps at inside area .
- By: Dexter,Manab.
- 10/12/2018
- Checked submersible pump at lifting tank (send to store for repair)
- Checked the 3Ph submersible pump in lifting tank area.
- By: Dexter,Manab.
- 11/12/2018
- Fixed 2 flood light at LMU & GMU plant ( 1lamp changed)
- Prepared extension cable for welding works at residue pump shelter.
- By: Dexter,Manab.
- 12/12/2018
- Layed extension cable for welding works in LMU & GMU plant.
- Checked current of 13-p500 A & B during starting with load.
- By: Dexter,Manab.
- 13/12/2018
- Installed 3Ph (small) submersible pump at LMU & GMU plant with
control.
- By: Dexter,Manab.
- 16/12/2018
- Started & checked DG & transformers.
- Checked florescent lamp at process tower.
- By: Dexter,Manab.
- 16/12/2018
- Started & checked DG & transformer (ok).
- Checked fluorescent lamp at process tower.
- By: Dexter,Manab.
- 17/12/2018
- Removed extension cable at LMU &GMU plant & brought to process
tower area.
- Monitored switchgear &field area.
- By: Dexter,Manab.
- 20/12/2018
- Test haydrojet (newly prepared) IR test 7.6 G ohm phase –earth(ok)
- No hose (hose lest in the repair shop)
- By: Dexter,Manab.
- 23/12/2018
- Started & checked DG & transformer
- By: Dexter,Manab.
- 24/12/2018
- Removed submersible motor control & cable at LMU & GMU plant.
- Checked power supply for civil works in area 13.
- By: Dexter,Manab.
- 25/12/2018
- Checked AC filter screens in switchgear room.
- Installed breaker for puel pump at boiler panel.
- By: Dexter,Manab.
- 26/12/2018
- Checked air blowing at DG panel & sync room & transformer area (Mv &
Lv)
- By: Dexter,Manab.
- 27/12/2018
- Cleaned Ac filter screen at control room.
- By: Dexter,Manab.
- /
III. Power consumption: