Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VARIATION SUMM
CBEME
VO NO REV PACKAGE REF TYPE OF VO DESCRIPTION OF VARIATION AFFECTED TONNAGE
ref
002 01 L037 & L068 Complexity Large 3D Built-up Frames - 20 Te. (Plate Girder as main members) 117.686
003 01 L039 & L068 Complexity Large 3D Built-up Frames - 32 Te. (Plate Girder as main members) 288.258
004 01 L042 & L068 Complexity Chequer plate welded to Frames 515.803
006 0 L044 Complexity Extra over for fabrication of built-up base frames
TA-008,TA -011,TA-
022,TA-023,TA-024
019 0 L058 Refebrication request from client
TA-026,TA-028
020 0 L059 TA-010 Stair stringer slotted holes requirement based on RFI-084/ RFI-083
410992899.xlsx 1 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VARIATION SUMM
CBEME
VO NO REV PACKAGE REF TYPE OF VO DESCRIPTION OF VARIATION AFFECTED TONNAGE
ref
026 01 L-086 Complexity Large 3D Built-up Frames - 32 Te. (Plate Girder as main members) 40.366
TA-031
TA-041
31 0 L-089 TA-044 Refebrication request from client
TA-045
410992899.xlsx 2 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VARIATION SUMM
CBEME
VO NO REV PACKAGE REF TYPE OF VO DESCRIPTION OF VARIATION AFFECTED TONNAGE
ref
120BC-S02
46 0 L-110 EMAIL DTD TA-052 Refabrication of missing plates for package 120BC-S02
08/08/2017
210AC-S02
47 0 L-110 EMAIL DTD TA-055 Fabrication of new plates due to design changes for package 210AC-S01
22/08/17
410992899.xlsx 3 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VARIATION SUMM
CBEME
VO NO REV PACKAGE REF TYPE OF VO DESCRIPTION OF VARIATION AFFECTED TONNAGE
ref
350AC-S02
48 0 L-110 EMAIL DTD TA-053 Abortive works of delivered items to site for package 350AC-02
15/08/17
000AD-S01,
52 0 L-110 TA-051 Supply and fixing of M12 nuts to light mount columns
000AE-S01RFI
350AC-S01
53 0 L-110 TA-042 Engineering abortive works due cancellation of intial rev 0 drawings for package 350AC-01
TRANS. 449517
611AF-S01
55 0 L-114 EMAIL DTD TA-034 Modification of assembly no, 611AF-S01-Y0042
04/04/17
220AD-S02
56 0 L-114 TRANS NO 438932 TA-037 Revised fabrication drawings recd.
115AC-S03
57 0 L-114 N/A Purlin price variance as per letter issued
purlin & girts
451AG-S02
61 0 L-113 TA-038 Revised fabrication drawings recd.
TRANS NO 440510
410992899.xlsx 4 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VARIATION SUMM
CBEME
VO NO REV PACKAGE REF TYPE OF VO DESCRIPTION OF VARIATION AFFECTED TONNAGE
ref
210AC-S01
62 0 L-115 TA-043 Revised fabrication drawings recd.
TRANS 456776
220BD-S01 &
220BD-S02
64 0 L-115 TA -029 Revised fabrication drawings recd.
TRN. 393176,
393318
220AD-S03
65 0 L-115 EMAIL DTD TA-036 Fabrication hold
12/04/17
220AE-S01
66 0 L-115 TRANS NO 423663 TA-039 Revised fabrication drawings recd.
470AD-S01
67 0 L-116 TRANS NO 421895 TA-040 Revised fabrication drawings recd.
350AG-S01
70 0 L-116 TA-049 Holes plugged
RFI-141 REPLY
410992899.xlsx 5 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VARIATION SUMM
CBEME
VO NO REV PACKAGE REF TYPE OF VO DESCRIPTION OF VARIATION AFFECTED TONNAGE
ref
210AC-S01
71 0 L-116 EMAIL DTD TA-054 Bracing length to be reduced modification to be done at shop
20/08/17
210AC-S01
72 0 L-116 EMAIL DTD TA-058 Abortive material due to receipt of revised drawing 350AC-S02
20/08/17
SUB TOTAL
CANCEELLED VO'S
007 0 L046 Complexity Type 1 Frames One Column with multiple channels 81.183
008 0 L047 Complexity Type 2 Frames Two Columns with multiple channels 233.440
009 0 L048 Complexity Type 3 Frames Three Columns with multiple channels 93.679
010 0 L049 Complexity Type 4 Frames Two Columns between channels 15.994
SUB TOTAL
410992899.xlsx 6 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VARIATION SUMM
CBEME
VO NO REV PACKAGE REF TYPE OF VO DESCRIPTION OF VARIATION AFFECTED TONNAGE
ref
N/A 01 L-040 - Material Extra over for procurement of Raw material from local stockists 4430.000
N/A 01 L-060 - Material Extra over for procurement of Open Sections and plates from local stockists-Premium Costs 596.426
Extra over for procurement of Raw material from local stockists ,remaining Tonnage purchased from Dec 2016 to
N/A 00 L-067 - Material 738.028
March 2017.
Extra over for procurement of Raw material from local stockists ,remaining Tonnage purchased from April and May
N/A 00 L-085 - Material 413.079
2017
Extra over for procurement of Raw material from local stockists ,remaining Tonnage purchased from April and May
N/A 00 L-090 - Material 88.763
2017
Total 6,266.30
EXTRA SCOPE
CBEME CBEME
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION AFFECTED TONNAGE
ref ref
Email Email
011 0 Complexity Mismatch between pay category and Description 761.888
13th April 2017 13th April 2017
Email Email
012 0 Complexity Discrepancy between item description and drawings 1021.157
13th April 2017 13th April 2017
Email-13th April Email-13th April
013 0 Complexity Discrepancy between unit weight and Pay category 17.773
2017 2017
Email-13th April Email-13th April
014 0 Complexity Built-up I sections in drawing instead of Rolled sections 231.25
2017 2017
Email-14th june Email-14th june
27 0 Complexity Mismatch between pay category and Description 182.72
2017 2017
Email-14th june Email-14th june
28 0 Complexity Discrepancy between item description and drawings 292.281
2017 2017
Email-14th june Email-14th june
29 0 Complexity Discrepancy between unit weight and Pay category 12.287
2017 2017
Email-14th june Email-14th june
30 0 Complexity Built-up I sections in drawing instead of Rolled sections 78.356
2017 2017
410992899.xlsx 7 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VARIATION SUMM
CBEME
VO NO REV PACKAGE REF TYPE OF VO DESCRIPTION OF VARIATION AFFECTED TONNAGE
ref
Email-26th Email-26th
58 September 2017 Complexity Mismatch between pay category and Description
September 2017
Email-26th Email-26th
59 September 2017 Complexity Discrepancy between item description and drawings
September 2017
Email-26th Email-26th
60 September 2017 Complexity Discrepancy between unit weight and Pay category
September 2017
SUB TOTAL
N/A 0 L061 &L071 L061 &L071 Additional Scope Rolling of Monorail 4.729
N/A 0 L064 L064 Additional Scope Extra over expenditure for painting of galvanized purlins and Eave beams
SUB TOTAL
410992899.xlsx 8 03/04/2019
VARIATION SUMMARY
EGA
Status as per the
VARIATION SUBMISSION EGA AGR Remaining amount as Meeting with Mr. Neal Status as per the Meeting with Buyer
COST AGREED per Considered pay Remarks
DATE EED dated on the 9 th dated on the 30th March 2017.
AED AMOUNT categories
DAT May2017.
E
1,088,660.82 31-Oct-16 Agreed in principle,Rates to be evaluated
Forwarded the
52,652.00 27-Mar-17 VO to Mr.Neal for review Agreed in principle, Neal to review and revert
71,904.00 27-Mar-17 Agreed by Mr. Neal Agreed in principle, Neal to review and revert
5,450.40 27-Mar-17 Agreed by Mr. Neal Agreed in principle, Neal to review and revert
410992899.xlsx 9 03/04/2019
VARIATION SUMMARY
EGA
Status as per the
VARIATION SUBMISSION EGA AGR Remaining amount as Meeting with Mr. Neal Status as per the Meeting with Buyer
COST AGREED per Considered pay Remarks
DATE EED dated on the 9 th dated on the 30th March 2017.
AED AMOUNT categories
DAT May2017.
E
67,542.00 27-Mar-17 Agreed by Mr. Neal Agreed in principle, Neal to review and revert
5,782.80 24-Jul-17
3,816.00 24-Jul-17
5,637.60 24-Jul-17
3,657.60 24-Jul-17
1,861.20 24-Jul-17
2,321.60 24-Jul-17
3,217.20 24-Jul-17
6,789.60 24-Jul-17
3,315.20 24-Jul-17
559,124.20 13-Aug-17
1,886,811.00 29-Aug-17
410992899.xlsx 10 03/04/2019
VARIATION SUMMARY
EGA
Status as per the
VARIATION SUBMISSION EGA AGR Remaining amount as Meeting with Mr. Neal Status as per the Meeting with Buyer
COST AGREED per Considered pay Remarks
DATE EED dated on the 9 th dated on the 30th March 2017.
AED AMOUNT categories
DAT May2017.
E
46,788.00 30-Aug-17
4,756.88 14-Sep-17
5,639.58 14-Sep-17
1,019.13 14-Sep-17
410992899.xlsx 11 03/04/2019
VARIATION SUMMARY
EGA
Status as per the
VARIATION SUBMISSION EGA AGR Remaining amount as Meeting with Mr. Neal Status as per the Meeting with Buyer
COST AGREED per Considered pay Remarks
DATE EED dated on the 9 th dated on the 30th March 2017.
AED AMOUNT categories
DAT May2017.
E
10,436.57 14-Sep-17
1,930.08 14-Sep-17
1,080.48 14-Sep-17
1,113.89 14-Sep-17
28,992.60 14-Sep-17
2,455.44 14-Sep-17
2,083.20 26-Sep-17
1,964.40 26-Sep-17
3,015.60 26-Sep-17
48,890.55 26-Sep-17
6,270.00 26-Sep-17
410992899.xlsx 12 03/04/2019
VARIATION SUMMARY
EGA
Status as per the
VARIATION SUBMISSION EGA AGR Remaining amount as Meeting with Mr. Neal Status as per the Meeting with Buyer
COST AGREED per Considered pay Remarks
DATE EED dated on the 9 th dated on the 30th March 2017.
AED AMOUNT categories
DAT May2017.
E
26,944.80 1-Oct-17
6,349.20 1-Oct-17
5,082.00 1-Oct-17
36,491.41 1-Oct-17
3,411.60 1-Oct-17
3,609.60 3-Oct-17
4,880.40 3-Oct-17
5,144.00 3-Oct-17
3,055.20 3-Oct-17
410992899.xlsx 13 03/04/2019
VARIATION SUMMARY
EGA
Status as per the
VARIATION SUBMISSION EGA AGR Remaining amount as Meeting with Mr. Neal Status as per the Meeting with Buyer
COST AGREED per Considered pay Remarks
DATE EED dated on the 9 th dated on the 30th March 2017.
AED AMOUNT categories
DAT May2017.
E
1,053.60 3-Oct-17
3,288.89 3-Oct-17
2,454.53 3-Oct-17
19,308.07
7,369,210.90 4,117,217.04
1,183,843.00
410992899.xlsx 14 03/04/2019
VARIATION SUMMARY
EGA
Status as per the
VARIATION SUBMISSION EGA AGR Remaining amount as Meeting with Mr. Neal Status as per the Meeting with Buyer
COST AGREED per Considered pay Remarks
DATE EED dated on the 9 th dated on the 30th March 2017.
AED AMOUNT categories
DAT May2017.
E
3,343,090.39
EGA
VARIATION SUBMISSION EGA AGR
COST AGREED REMARKS REMARKS
DATE EED
AED AMOUNT DAT
E Submitted invoice 17 L-075 dated 04th Agreed by Mr. Neal
1,347,499.45 27-Feb-17 Agreed in principle,Rates to be checked
May 2017
Submitted invoice 17 L-075 dated 04th Agreed by Mr. Neal Neal to review and revert.
1,350,451.24 13-Apr-17 May 2017 VO Summary forwarded to Tanya with SQ
Submitted invoice 17 L-075 dated 04th Agreed by Mr. Neal
23,012.13 27-Feb-17 VO Summary forwarded to Tanya with SQ
May 2017
Submitted invoice 17 L-075 dated 04th Agreed by Mr. Neal
48,932.32 27-Feb-17 VO Summary forwarded to Tanya with SQ
May 2017
310,553.49 14-Jun-17
385,033.21 14-Jun-17
14,471.72 14-Jun-17
23,933.29 14-Jun-17
410992899.xlsx 15 03/04/2019
VARIATION SUMMARY
EGA
Status as per the
VARIATION SUBMISSION EGA AGR Remaining amount as Meeting with Mr. Neal Status as per the Meeting with Buyer
COST AGREED per Considered pay Remarks
DATE EED dated on the 9 th dated on the 30th March 2017.
AED AMOUNT categories
DAT May2017.
E
44,909.00 26-Sep-17
2,296.40 26-Sep-17
16,359.98 26-Sep-17
3,567,452.23
165,922.00 OVOR004
342,798.00
AED 20,131,837.55
410992899.xlsx 16 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VA
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
001 01 L050 Complexity Beams with multiple Web stiffeners 262.485 1,088,660.82
004 01 L042 & L068 Complexity Chequer plate welded to Frames 515.803 1,935,305.00
005 0 L043 Complexity Extra over for fabrication of Sump Pits 73,524.00
006 0 L044 Complexity Extra over for fabrication of built-up base frames 86,592.00
Type 1 Frames
007 0 L046 Complexity 81.183 238,788.00
One Column with multiple channels
Type 2 Frames
008 0 L047 Complexity 233.440 631,800.00
Two Columns with multiple channels
Type 3 Frames
009 0 L048 Complexity 93.679 242,162.00
Three Columns with multiple channels
410992899.xlsx 17 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VA
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
Type 4 Frames
010 0 L049 Complexity 15.994 71,093.00
Two Columns between channels
021 0 L062 TA-009 Chequered plate drawing revised due to RFI-083 3,831.00
410992899.xlsx 18 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VA
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
022 00 L076 TA-013 330AE-S01-Existing stifener to cut as per RFI-087 AED 20,112.00
025 00 L-081 Complexity Chequer plate welded to Frames 103.015 AED 750,170.75
410992899.xlsx 19 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VA
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
TA-031
TA-041
31 0 L-089 TA-044 Refebrication request from client 67,542.00
TA-045
410992899.xlsx 20 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VA
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
410992899.xlsx 21 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VA
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
TA-025 HOLD
410992899.xlsx 22 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VA
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
TA-031 REFABRICATION
TA-041 REFABRICATION
410992899.xlsx 23 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VA
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
TA-044 REFABRICATION
TA-045 REFABRICATION
410992899.xlsx 24 03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
6228_VA
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
EXTRA SCOPE
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
Email
011 0 Complexity Mismatch between pay category and Description 761.888 1,347,499.45
13th April 2017
Email
012 0 Complexity Discrepancy between item description and drawings 1021.157 1,350,451.24
13th April 2017
Email-13th April
013 0 Complexity Discrepancy between unit weight and Pay category 17.773 23,012.13
2017
Email-13th April
014 0 Complexity Built-up I sections in drawing instead of Rolled sections 231.25 48,932.32
2017
Email-14th june
27 0 Complexity Mismatch between pay category and Description 182.72 310,553.49
2017
Email-14th june
28 0 Complexity Discrepancy between item description and drawings 292.281 385,033.21
2017
Email-14th june
29 0 Complexity Discrepancy between unit weight and Pay category 12.287 14,471.72
2017
30 0 Email-14th june Complexity Built-up I sections in drawing instead of Rolled sections 78.356 23,933.29
2017
SUB TOTAL 3,503,886.85
6228_VA
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
N/A 0 L065&L066&L070 Additional Scope Additional supply of Light Mount post 165,922.00
Amount on Extra Scope due to Pay category / drawing Discrepancies AED 3,503,886.85
Amount on Extra Scope due to Pay category / drawing Discrepancies AED 551,024.00
410992899.xlsx 26 03/04/2019
6228_VARIATION SUMMARY
Remaining Status as per the
EGA EGA
SUBMISSION amount as per Meeting with Mr. Neal
AGREED AGREED Remarks
DATE Considered pay dated on the 9 th
AMOUNT DATE categories May2017.
31-Oct-16
13-Apr-17 Submitted invoice 20 L-083 dated 31st May 2017 Agreed by Mr. Neal
31-Jan-17
2-Feb-17
14-Feb-17
14-Feb-17
14-Feb-17
410992899.xlsx 27 03/04/2019
6228_VARIATION SUMMARY
Remaining Status as per the
EGA EGA
SUBMISSION amount as per Meeting with Mr. Neal
AGREED AGREED Remarks
DATE Considered pay dated on the 9 th
AMOUNT DATE categories May2017.
14-Feb-17
21-Mar-17
20-Mar-17
Forwarded the
27-Mar-17 VO to Mr.Neal for review
9-Apr-17 Submitted invoice 21 L-084 dated 31st May 2017 Agreed by Mr. Neal
13-Apr-17 Submitted invoice 21 L-084 dated 31st May 2017 Agreed by Mr. Neal
410992899.xlsx 28 03/04/2019
6228_VARIATION SUMMARY
Remaining Status as per the
EGA EGA
SUBMISSION amount as per Meeting with Mr. Neal
AGREED AGREED Remarks
DATE Considered pay dated on the 9 th
AMOUNT DATE categories May2017.
4-May-17
4-May-17
4-May-17
31-May-17 745,606.53
12-Jun-17 137,842.51
410992899.xlsx 29 03/04/2019
6228_VARIATION SUMMARY
Remaining Status as per the
EGA EGA
SUBMISSION amount as per Meeting with Mr. Neal
AGREED AGREED Remarks
DATE Considered pay dated on the 9 th
AMOUNT DATE categories May2017.
24-Jul-17
24-Jul-17
24-Jul-17
24-Jul-17
24-Jul-17
24-Jul-17
24-Jul-17
24-Jul-17
24-Jul-17
410992899.xlsx 30 03/04/2019
6228_VARIATION SUMMARY
Remaining Status as per the
EGA EGA
SUBMISSION amount as per Meeting with Mr. Neal
AGREED AGREED Remarks
DATE Considered pay dated on the 9 th
AMOUNT DATE categories May2017.
410992899.xlsx 31 03/04/2019
6228_VARIATION SUMMARY
Remaining Status as per the
EGA EGA
SUBMISSION amount as per Meeting with Mr. Neal
AGREED AGREED Remarks
DATE Considered pay dated on the 9 th
AMOUNT DATE categories May2017.
410992899.xlsx 32 03/04/2019
6228_VARIATION SUMMARY
Remaining Status as per the
EGA EGA
SUBMISSION amount as per Meeting with Mr. Neal
AGREED AGREED Remarks
DATE Considered pay dated on the 9 th
AMOUNT DATE categories May2017.
410992899.xlsx 33 03/04/2019
6228_VARIATION SUMMARY
Remaining Status as per the
EGA EGA
SUBMISSION amount as per Meeting with Mr. Neal
AGREED AGREED Remarks
DATE Considered pay dated on the 9 th
AMOUNT DATE categories May2017.
4,033,673.04
410992899.xlsx 34 03/04/2019
6228_VARIATION SUMMARY
Remaining Status as per the
EGA EGA
SUBMISSION amount as per Meeting with Mr. Neal
AGREED AGREED Remarks
DATE Considered pay dated on the 9 th
AMOUNT DATE categories May2017.
EGA EGA
SUBMISSION AGREED AGREED REMARKS
DATE AMOUNT DATE
27-Feb-17 Submitted invoice 17 L-075 dated 04th May 2017 Agreed by Mr. Neal
13-Apr-17 Submitted invoice 17 L-075 dated 04th May 2017 Agreed by Mr. Neal
27-Feb-17 Submitted invoice 17 L-075 dated 04th May 2017 Agreed by Mr. Neal
27-Feb-17 Submitted invoice 17 L-075 dated 04th May 2017 Agreed by Mr. Neal
14-Jun-17
14-Jun-17
14-Jun-17
14-Jun-17
410992899.xlsx 35 03/04/2019
6228_VARIATION SUMMARY
Remaining Status as per the
EGA EGA
SUBMISSION amount as per Meeting with Mr. Neal
AGREED AGREED Remarks
DATE Considered pay dated on the 9 th
AMOUNT DATE categories May2017.
410992899.xlsx 36 03/04/2019
Status as per the Meeting with Buyer
dated on the 30th March 2017.
Informations on PO to be submitted
410992899.xlsx 37 03/04/2019
Status as per the Meeting with Buyer
dated on the 30th March 2017.
410992899.xlsx 38 03/04/2019
Status as per the Meeting with Buyer
dated on the 30th March 2017.
410992899.xlsx 39 03/04/2019
Status as per the Meeting with Buyer
dated on the 30th March 2017.
410992899.xlsx 40 03/04/2019
Status as per the Meeting with Buyer
dated on the 30th March 2017.
410992899.xlsx 41 03/04/2019
Status as per the Meeting with Buyer
dated on the 30th March 2017.
410992899.xlsx 42 03/04/2019
Status as per the Meeting with Buyer
dated on the 30th March 2017.
410992899.xlsx 43 03/04/2019
Status as per the Meeting with Buyer
dated on the 30th March 2017.
410992899.xlsx 44 03/04/2019
Status as per the Meeting with Buyer
dated on the 30th March 2017.
REMARKS
410992899.xlsx 45 03/04/2019
Status as per the Meeting with Buyer
dated on the 30th March 2017.
410992899.xlsx 46 03/04/2019
6228_ACCEPTED VARIATION COST SUMMARY ( APROX)
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST EXPECTED AMOUNT % considered
ref TONNAGE AED
001 01 L050 Complexity Beams with multiple Web stiffeners 262.485 1,088,660.82 272,165.21 25
004 01 L042 & L068 Complexity Chequer plate welded to Frames 515.803 1,935,305.00 290,295.75 15
005 0 L043 Complexity Extra over for fabrication of Sump Pits 73,524.00 29,409.60 40
006 0 L044 Complexity Extra over for fabrication of built-up base frames 86,592.00 34,636.80 40
015 0 L051 Complexity Built-up Frames with stiffeners 3.744 25,254.56 10,101.82 40
016 0 L055 Complexity Beam have haunch connections 205.800 31,258.71 12,503.48 40
018 0 L057 Client Temporary PFC Support to the frame 52,652.00 31,591.20 60
TA-008,TA -011,TA-
022,TA-023,TA-024
019 0 L058 Refebrication request from client 71,904.00 71,904.00 100
TA-026,TA-028
022 00 L076 TA-013 330AE-S01-Existing stifener to cut as per RFI-087 AED 20,112.00 AED 16,089.60 80
6228_ACCEPTED VARIATION COST SUMMARY ( APROX)
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST EXPECTED AMOUNT % considered
ref TONNAGE AED
023 00 L077 TA-019 560BB-S01-Revised fabrication drawings received AED 1,134.00 AED 907.20 80
025 00 L-081 Complexity Chequer plate welded to Frames 103.015 AED 750,170.75 15
CANCELLED VO'S
Type 1 Frames
007 0 L046 Complexity 81.183 238,788.00 0
One Column with multiple channels
Type 2 Frames
008 0 L047 Complexity 233.440 631,800.00 0
Two Columns with multiple channels
Type 3 Frames
009 0 L048 Complexity 93.679 242,162.00 0
Three Columns with multiple channels
Type 4 Frames
010 0 L049 Complexity 15.994 71,093.00 0
Two Columns between channels
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST EXPECTED AMOUNT % considered
ref TONNAGE AED
EXTRA SCOPE
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
ref TONNAGE AED
Email
011 0 Complexity Mismatch between pay category and Description 761.888 1,347,499.45 AED 1,347,499.45 100
13th April 2017
Email
012 0 Complexity Discrepancy between item description and drawings 1021.157 1,350,451.24 AED 1,080,360.99 80
13th April 2017
Email-13th April
013 0 Complexity Discrepancy between unit weight and Pay category 17.773 23,012.13 AED 23,012.13 100
2017
Email-13th April
014 0 Complexity Built-up I sections in drawing instead of Rolled sections 231.25 48,932.32 AED 48,932.32 100
2017
027 0 Complexity Mismatch between pay category and Description 182.72 310,553.49 AED 310,553.49 100
6228_ACCEPTED VARIATION COST SUMMARY ( APROX)
VARIATION
CBEME AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST EXPECTED AMOUNT % considered
ref TONNAGE AED
028 0 Complexity Discrepancy between item description and drawings 292.281 385,033.21 AED 308,026.57 80
029 0 Complexity Discrepancy between unit weight and Pay category 12.287 14,471.72 AED 14,471.72 100
030 0 Complexity Built-up I sections in drawing instead of Rolled sections 78.356 23,933.29 AED 23,933.29 100
N/A 0 L065&L066&L070 Additional Scope Additional supply of Light Mount post 165,922.00 165,922.00
N/A 0 L061 &L071 Additional Scope Rolling of Monorail 4.729 42,304.00 42,304.00
Extra over expenditure for painting of galvanized
N/A 0 L064 Additional Scope 342,798.00
purlins and Eave beams
SUBMITTED EXPECTED
Amount on Variation order Submitted AED 13,023,362.57 AED 8,389,241.35
Amount on Extra Scope due to Pay category / drawing Discrepancies AED 3,503,886.85 AED 3,156,789.96
Amount on Extra Scope due to Pay category / drawing Discrepancies AED 551,024.00 AED 208,226.00
441,419.00 Submitted invoice 16 L-074 dated 04th May Agreed with paycategory
2017
984,877.00 Submitted invoice 16 L-074 dated 04th May Agreed with paycategory
2017
1,723,928.00 Submitted invoice 16 L-074 dated 04th May Agreed with paycategory
2017
Forwarded the
VO to Mr.Neal for review Agreed in principle, Neal to review and revert
745,606.53 To invoice
137,842.51 To invoice
4,033,673.04
0.00
Y ( APROX)
REMARKS REMARKS
only additional
TA-014 68 d 260AD-S01 ADDITIONAL WELDING
welding .
45 TA-050
46 TA-052
47 TA-055
48 TA-053
49 TA-056
50 TA-057
51 TA-059
52 TA-051
53 TA-042 13,057,564.05
54 TA-005
55 TA-034
Page 55 of 72 03/04/2019
RIATION REGISTER
Submitted Status CBE remarks
Page 56 of 72 03/04/2019
PVO No AREA CLIENT'S DRG REF
560-AS-S01-C0025,C0051 & 452AH-S01-
TA-006 560AS-S01, 452AH-S01
C0014
TA-012 560AS-S01 560AS-S01
MODIFICATION
VARIATION SUMMARY
VARIATION Worst Cas
AFFECTED SUBMISSION
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
TONNAGE DATE
AED %
001 0 Complexity Beams with multiple Web stiffeners 262.485 1,088,660.82 31-Oct-16 70%
002 0 Complexity Large 3D Built-up Frames - 20 Te. 117.686 411,431.30 12-Jan-17 65%
003 0 Complexity Large 3D Built-up Frames - 32 Te. 288.258 910,318.13 17-Jan-17 66%
004 0 Complexity Chequer plate welded to Frames 515.803 2,086,563.08 25-Jan-17 21%
005 0 Complexity Extra over for fabrication of Sump Pits 73,524.00 31-Jan-17 70%
006 0 Complexity Extra over for fabrication of built-up base frames 86,592.00 2-Feb-17 70%
Type 1 Frames
007 0 Complexity 81.183 238,788.00 14-Feb-17 70%
One Column with multiple channels
Type 2 Frames
008 0 Complexity 233.440 631,800.00 14-Feb-17 70%
Two Columns with multiple channels
Type 3 Frames
009 0 Complexity 93.679 242,162.00 14-Feb-17 70%
Three Columns with multiple channels
Type 4 Frames
010 0 Complexity 15.994 71,093.00 14-Feb-17 70%
Two Columns between channels
03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
VARIATION SUMMARY
VARIATION Worst Cas
AFFECTED SUBMISSION
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
TONNAGE DATE
011 0 Complexity Mismatch between pay category and Description 761.888 AED
1,280,365.31 27-Feb-17 90%
012 0 Complexity Discrepancy between item description and drawings 1,705.534 2,004,137.93 28-Feb-17 50%
013 0 Complexity Discrepancy between unit weight and Pay category 17.773 23,012.13 27-Feb-17 90%
014 0 Complexity Built-up I sections in drawing instead of Rolled sections 231.25 48,932.32 27-Feb-17 90%
015 0 Complexity Built-up Frames with stiffeners 3.744 25,254.56 28-Feb-17 70%
03/04/2019
TION SUMMARY
Worst Case Expected REMARKS
Amount % Amount
03/04/2019
TION SUMMARY
Worst Case Expected REMARKS
5,241,635.47 7,945,453.06
03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
VARIATION SUMMARY
VARIATION SUBMISSION
AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
TONNAGE DATE
AED
001 01 Complexity Beams with multiple Web stiffeners 262.485 1,088,660.82 31-Oct-16
005 0 Complexity Extra over for fabrication of Sump Pits 73,524.00 31-Jan-17
006 0 Complexity Extra over for fabrication of built-up base frames 86,592.00 2-Feb-17
Type 1 Frames
007 0 Complexity 81.183 238,788.00 14-Feb-17
One Column with multiple channels
Type 2 Frames
008 0 Complexity 233.440 631,800.00 14-Feb-17
Two Columns with multiple channels
Type 3 Frames
009 0 Complexity 93.679 242,162.00 14-Feb-17
Three Columns with multiple channels
Type 4 Frames
010 0 Complexity 15.994 71,093.00 14-Feb-17
Two Columns between channels
03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
VARIATION SUMMARY
VARIATION SUBMISSION
AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
TONNAGE DATE
AED
011 0 Complexity Mismatch between pay category and Description 761.888 1,280,365.31 27-Feb-17
012 0 Complexity Discrepancy between item description and drawings 1021.157 1,350,451.24 28-Feb-17
013 0 Complexity Discrepancy between unit weight and Pay category 17.773 23,012.13 27-Feb-17
014 0 Complexity Built-up I sections in drawing instead of Rolled sections 231.25 48,932.32 27-Feb-17
021 0 TA-009 Chequered plate drawing revised due to RFI-083 3,831.00 27-Mar-17
03/04/2019
Project : AL TAWEELAH ALUMINA
Contract : 6228
PO Number : 25875-000-POB-SS00-00001 Rev. 0
PO Description : Structural steel Fabrication
VARIATION SUMMARY
VARIATION SUBMISSION
AFFECTED
VO NO REV TYPE OF VO DESCRIPTION OF VARIATION COST
TONNAGE DATE
AED
03/04/2019
RIATION SUMMARY
EGA EGA
AGREED AGREED REMARKS
AMOUNT DATE
03/04/2019
RIATION SUMMARY
EGA EGA
AGREED AGREED REMARKS
AMOUNT DATE
revised
03/04/2019
RIATION SUMMARY
EGA EGA
AGREED AGREED REMARKS
AMOUNT DATE
03/04/2019
1,088,660.82
90,290.00
193,801.00
2,116,166.70
1,935,305.00
73,524.00
86,592.00
238,788.00
631,800.00
242,162.00
71,093.00
1,280,365.31 1104 15080
1,350,451.24 1.04 1256.667
23,012.13
48,932.32
25,254.56
31,258.71
8,042.80
52,652.00
60,307.53
5,450.40
3,831.00
1102.91
1470
2300
1000
5872.91
4873.7
1630
3243.7
84000 97560
2352 12710
196
1400
1596 64135
70560
6425
2.552216
500