Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
2 Purchasing Order / Contract 1 day Mon 07/03/16 Mon 07/03/16 Purchasing Order / Contract
3 ENGINEERING 30 days Tue 08/03/16 Wed 06/04/16
27 Swabbing & Flushing (for new pipeline) 3 days Sun 12/06/16 Tue 14/06/16
28 Re-instatement/ Pekerjaan pengembalian ke keadaan 1 day Sat 18/06/16 Sat 18/06/16 Re-instatement/ Pekerjaan pengembalian ke keadaan
semula
29 Pemasangan Marker Permanen 1 day Sat 18/06/16 Sat 18/06/16 Pemasangan Marker Permanen
30 Commissioning 3 days Wed 15/06/16 Fri 17/06/16 Commissioning
Project: Jadwal Pelaksanaan Citra Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 19/03/16 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only
Page 1