PT. CITRA MODIFIKAS PIPA 8 INCHI PT.

PRATIWI PUTRI SULUNG


ID Task Name Duration Start Finish March April May June July August
22/02 29/02 07/03 14/03 21/03 28/03 04/04 11/04 18/04 25/04 02/05 09/05 16/05 23/05 30/05 06/06 13/06 20/06 27/06 04/07 11/07 18/07 25/07 01/08
1 RELOKASI PIPA 104 days Mon 07/03/16 Sat 18/06/16

2 Purchasing Order / Contract 1 day Mon 07/03/16 Mon 07/03/16 Purchasing Order / Contract
3 ENGINEERING 30 days Tue 08/03/16 Wed 06/04/16

4 Site Survey 1 day Tue 08/03/16 Tue 08/03/16

5 Detail Design 30 days Tue 08/03/16 Wed 06/04/16

6 PROCUREMENT 45 days Fri 11/03/16 Sun 24/04/16

7 Pipa 45 days Fri 11/03/16 Sun 24/04/16

8 Fitting 30 days Tue 15/03/16 Wed 13/04/16

9 Material Katodik 30 days Sun 13/03/16 Mon 11/04/16

10 KONSTRUKSI 102 days Wed 09/03/16 Sat 18/06/16

11 PERSIAPAN KONSTRNUKSI 42 days Wed 09/03/16 Tue 19/04/16

12 Test Pit 3 days Wed 09/03/16 Fri 11/03/16

13 Penggalian pipa lama 21 days Wed 09/03/16 Tue 29/03/16

14 Purging Pipa Lama 21 days Wed 30/03/16 Tue 19/04/16

15 Pipe Stringing 7 days Mon 25/04/16 Sun 01/05/16

16 Trenching (galian pipa baru) 10 days Mon 25/04/16 Wed 04/05/16

17 Pekerjaan Crossing 10 days Mon 02/05/16 Wed 11/05/16

18 HDD 10 days Mon 02/05/16 Wed 11/05/16

19 Pekerjaan welding 21 days Wed 27/04/16 Tue 17/05/16

20 Non Destructive Test 20 days Fri 29/04/16 Wed 18/05/16

21 Field Joint Coating 5 days Thu 19/05/16 Mon 23/05/16

22 Golden Joint 5 days Thu 19/05/16 Mon 23/05/16

23 Holiday Test 5 days Tue 24/05/16 Sat 28/05/16

24 Lowering 7 days Tue 24/05/16 Mon 30/05/16

25 Hydrotest for new pipeline 7 days Tue 31/05/16 Mon 06/06/16

26 Backfilling & Compaction 5 days Tue 07/06/16 Sat 11/06/16

27 Swabbing & Flushing (for new pipeline) 3 days Sun 12/06/16 Tue 14/06/16

28 Re-instatement/ Pekerjaan pengembalian ke keadaan 1 day Sat 18/06/16 Sat 18/06/16 Re-instatement/ Pekerjaan pengembalian ke keadaan
semula
29 Pemasangan Marker Permanen 1 day Sat 18/06/16 Sat 18/06/16 Pemasangan Marker Permanen
30 Commissioning 3 days Wed 15/06/16 Fri 17/06/16 Commissioning

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Jadwal Pelaksanaan Citra Split External Tasks Inactive Summary Manual Summary Progress
Date: Sat 19/03/16 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1