your name : Ali Said Ali Al kindi

student ID: 1623666

Unit Co-ordinator : Dr Nasrullah K. Khilji

Unit Name: Operations and Project Management

Unit Code: SHR039-6

Title of Coursework: ERP Training Program for Procurement


Managers
Case Study Analysis of Al Buraimi
hospital, Oman

signature and date: 3/5/2018

1
ERP Training Program for
Procurement Managers

Case Study Analysis of Al Buraimi


hospital, Oman

2
Contents
1. Introduction ............................................................................................................................. 4

1.1. Project Objective .............................................................................................................. 4

2. Work Break Down Structure ................................................................................................... 5

3. Gantt chart ............................................................................................................................... 6

4. Network Diagram and Critical Path ........................................................................................ 7

5. Budget ...................................................................................................................................... 8

6. Risk Registers .......................................................................................................................... 9

7. Quality Plan ........................................................................................................................... 10

7.1. Quality Register.............................................................................................................. 11

Conclusion .................................................................................................................................... 12

References ..................................................................................................................................... 13

3
1. Introduction
The present study is revolving around the development of suitable project plan by
including the appropriate tools and techniques of the project management. For the purpose of
developing the study and collecting all the required information, the organization that has been
selected here is Al Buraimi hospital in the Sultanate of Oman. The company is the best health
care service provider in the Sultanate of Oman. In addition to this, the company has also lead
towards the digitalization across the society, providing the people with new and innovative ways
of performing the business related activities and the company is making all the adequate efforts
for making the entertainment and all the information available at just the fingertips (Moh, 2018).

Furthermore, in the study, the work break down structure also explained that is required for
the completion of project related activities in an appropriate manner along with the estimation of
the required budget for the implementation of the ERP training program especially designed for
the project managers of the company ( Al Buraimi hospital) so that the smooth tendering can be
ensured along with the process of procurement and the other operational functions that are
performed manually. The study also includes the information regarding the risk registers so that
all the risks that may be in the project can be assessed and also the quality plan so that the
adequate quality of project can be maintained.

1.1. Project Objective


The present study includes the project plan that has been described so that the steps that are
involved in the project plan can be executed in an appropriate manner and the achievement of the
objectives can be ensured in a successful manner. In this regard, the project objectives of the
present study have been stated below:

 It is very important to first analyze that the ERP training program is going to online or
offline so that the activities can be designed accordingly.
 It is also required that few important information of the project managers that are to be
involved in the ERP training program and these information include; the educational
qualification, details of experience of domain, career goals and so on.
 The information is also required to be collected about the domain of the project
managers as for the performance of different activities different forms of ERP are

4
needed. For instance; for the process of procurement, the appropriate ERP is ERP
material management.
 Communicating all the required information with the participants of the ERP training
program along with the advantages so that they get motivated and willingly attend the
training program so that the desired result out of the training can be achieved.
 It is also required to select the best trainers with high proficiency so that all the required
skills and knowledge can be transferred to the trainees in an appropriate manner.
 Along with the educational qualification, it is also important to assess the technical
proficiency of the project managers so that the training program can be designed in the
most suitable manner.
1.1. For the purpose of the ERP training program, from the organization ( Al Buraimi
hospital), the number of project managers that have selected for undergoing the training
program is 15 and the number of trainers that have been hired is 5. It is so because for the
purpose of different needs, different ERP tool is needed and thus, different trainers are
required to be hired. Furthermore, on the basis of the skills, experience, educational
qualification and expertise, the trainees have been divided among different groups.
1.2. The stages that are to be involved in the ERP training program along with the key
variables have been stated below:
 Selecting the location for the training program along with the arrangement of all
the resources required
 Identifying the trainers and trainees to be involved in the training program
 Developing and implementing the training program
 Setting the benchmark for analyzing the effectiveness of training program
 The budget for the training program is decided
 The outcome of the training program is decided

5
2. Work Break down Structure
Task WBS ID Task Details Days
ID
1 1. ERP training program for project managers 120
days
2 1.1 Development of training program 50
3 1.1.1 The clear purpose of training is developed 5
4 1.1.2 Needs of the employees are identified 5
5 1.1.3 Plan is developed as per the need 10
6 1.1.4 Efficient trainers are selected 10
7 1.1.5 Interest and commitment of project managers for training 5
8 1.1.6 Effectiveness of designed training program is analyzed 15
9 1.2 Suitable location for training is identified 70
10 1.2.1 Required resources for training are procured 5
11 1.2.2 Suitable tools of ERP are selected for training 3
12 1.2.3 Suitable method of training is decided 3
13 1.2.4 Development of online resources for trainees (project 5
managers)
14 1.2.5 Actual training 54

3. Gantt chart FOR Project Time Management


In order to develop the gnat chart for the project of Al Buraimi hospital ERP training program
integration of the MS Project by which allocation of the determined time period as well as the
development of the time plan will be managed in effective way (Li & Lu, 2016). By the
assistance of this every task will be executed in step by step way to complete it in determined
time. The gnat chart for the ERP training program in Al Buraimi hospital are as stated:

6
The above diagram is the gnat chart of the project which is useful to complete step by step way.
In the presented gnat chart it is noticed that all the activity which is need to complete in the
project. In order to complete the project it requires 120days to complete and this determine time
is distributed in the each activity which is required to complete in the task

4. Network Diagram and Critical Path-


Building up the network diagram is very important to determine the accurate path by which the
all the task of the project will be completed in time (Meher & Park, 2014). The main objective
associated to this project is to provide the relevant ERP training by completing each project
activity. With aid of the network diagram this will positively done in the task in step by step
manner. With the aid of this assessment in regards of the critical path also be done.

In order to make the assessment of critical path selection of the path take place under which
each project activity will be covered in longest period of path under which all project tasks will
be completed. In this way project manager can manage effective ERP training process for the
Employees of Al Buraimi hospital. Assessment of the critical path for this project are as follows:

5 + 5 + 10 + 10 + 5 + 15 + 5 + 3 + 3 + 5 + 54 = 120 days

7
5. Budget
This is the section where the budgeting has been done for providing ERP training to the
project managers of Al Buraimi hospital so that effectiveness and efficiencies of the activities
can be enhanced. In this below is the estimated cost required for the whole training program.

Activity Fixed Fixed Total Baseline Variance Actual Remaining


need to be Cost Cost Cost
done (OMR) Accrual
Human 700 Allocated 1400 0.00 1400 0.00 1400
Resource
Cost of 500 Allocated 1000 0.00 1000 0.00 1000
location for
training
Cost of 300 Allocated 300 0.00 300 0.00 300
procuring
required
resources
Cost of 500 Allocated 500 0.00 500 0.00 500
hiring
trainers
Cost of ERP 100 Allocated 100 0.00 100 0.00 100
tools
Cost of 700 Allocated 700 0.00 700 700
developing
online
resources
Total cost 21000

8
The total cost that has been estimated for conducting the ERP training program for the
project managers is 2100 OMR.

6. Risk Registers
This particular section is for the risk register that is established for identifying all the
potential risks that may be during the course of training program. Along with this, the section
also identifies the appropriate manner in which all the identified risks can be mitigated and the
duration that is required for overcoming the risks and completes the training program within the
decided time period.

Risk Risk Risk Probabilit Effect Risk Risk Risk Risk Dur
ID Descriptio Type y of Severity Owner Statu Typ mitigation atio
n occurrence s e n

R1 The Critical High High Manage Open Neg Every aspect 10


trainers ment ative need to be days
have not made clear
been made before
clear about initiating
the training
requiremen
ts
R2 The Critical High High Trainers Open Neg The selection 20
trainers are ative to be done days
not capable appropriately
of
providing
the
required
information
regarding

9
all the
aspects

R3 Ineffective Critical Medium High Manage Open Neg Enough time 5


communica ment of ative should be days
tion among Al provided to
the trainers Buraimi both the
and hospital trainers and
trainees trainees for
developing a
comfortable
environment

7. Quality Plan
The quality is considered as one of the most important factors that can result in the suitable
accomplishment of the demands from the employees and the clients as well. In the present study,
the quality plan has been developed so that the training program can meet with the highest
quality standards and the suitable environment for training can be developed. Furthermore, when
the training is provided by maintaining the utmost quality, the skills and knowledge can be
imparted in an improved manner and the use of ERP for performing the project related activities
can be done by the project managers. Moreover, there are various factors that can lead to the
involvement of appropriate quality in the training program and these are; the trainer needs to be
highly qualified and knowledgeable in not just the skills related to speaking but also needs to be
confident enough, ability of inspiring others need to be there and so on (Kerzner, 2018).

The trainer cannot be considered to be effective if solely the technical knowledge is given
importance. It is also important that the training program is appropriate according to the
identified needs for the training. Furthermore, the quality in the training can also be ensured by
finding the answers to various questions before designing and implementing the training program
10
such as; the results expected out of the training, identification of behavior of trainees required for
achievement of those results and so on (Kulkarni, 2013).In the same manner, the next aspect is
related to the selection of the location for training and it should be that where the effectiveness of
cost can be ensured and appropriate environment of learning can be developed (Gollenia, 2016).
Moreover, the quality in training program is also in terms of the contents that are provided to the
trainees for getting the insights of the topics and engaging them in the training program.

7.1. Quality Register


Qua Product Quality Quality Quality Qualit Qualit Target Actual
lity Method Producer Review y y Approv Approval
ID er Appro Result al date date
val
1 Resource Inspecti Authorities Review Board Pass Nil Nil
s on at Al team set up
required Buraimi for
in hospital project
training
2 ERP Examin Manageme Review Board Pass Nil Nil
tools ation nt at Al team of
Buraimi project
hospital
3 Location Review Authority Inspecti Board Pass Nil Nil
of at Al on team of
training Buraimi project
hospital
4 Online Review Manageme Review Board Pass nil nil
resources nt team team of
project

11
Conclusion
The present study has been developed with the purpose of developing the suitable ERP
training program for the project managers at Al Buraimi hospital in the Sultanate of Oman so
that the various project related activities such as tendering, procurement and so on can be made
efficient. In this regard, in the study, the work break down structure has been developed and
various risks have been identified that can be associated with the training program such as; the
inefficiency of trainers, ineffective communication and so on. The study also includes the
manner in which the risks can be mitigated along with the quality plan.

12
References
Gollenia, L.A., 2016. Business transformation management methodology. Routledge.

Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley
& Sons.

Kulkarni, P.P., 2013. A literature review on training & development and quality of work
life. Researchers World, 4(2), p.136.

Al Buraimi hospital. 2018. About Us. [Online]. Available at: https://www. Al Buraimi

hospital.om/wps/portal/ Al Buraimi hospital/About%20us [Accessed on: 18 April, 2018]

Li, D., & Lu, M. (2016). Automated generation of work breakdown structure and project
network model for earthworks project planning: a flow network-based optimization
approach. Journal of Construction Engineering and Management, 143(1), 04016086.

Meher, P., & Park, S. (2014). Critical-path analysis and low-complexity implementation of the
LMS adaptive algorithm. IEEE Transactions on Circuits and Systems I: Regular Papers,
61(3), 778-788.