Item
Description of works No. Length Breadth Height Quantity Unit
No.
(m) (m) (m)

1 Earthwork in excavation in foundation


Abutment Wall 2 5.10 2.70 1.50 41.31 cu.m.
Wing Walls 4 2.98 1.65 1.50 29.50 cu.m.
Bedding in between Abutments 1 5.10 0.20 1.50 1.53 cu.m.
U/S & D/S Apron 2 2.10 2.67 0.50 5.61 cu.m.
Cut off Walls (U/S & D/S) 2 4.17 0.50 1.00 4.17 cu.m.
Total = 82.12 cu.m.

2 P.C.C work in 1:2:4 in foundation bed & floors :


Abutments 2 5.10 2.60 0.20 5.30 cu.m
Wing Walls 4 2.88 1.55 0.10 1.79 cu.m
Total = 7.09 cu.m.

3 Gabion work
Bed Block 1 5.10 1.66 0.50 4.23 cu.m
Apron 2 2.00 2.67 0.50 5.34 cu.m.
Cut off Walls (U/S & D/S) 2 4.17 1.00 1.00 8.34 cu.m.
Total = 17.91 cu.m.

4 Stone masonry work in 1:4 c/s mortar


Abutments 2 5.10 0.890 2.00 18.16 cu.m
Abutment First Footing 2 5.10 2.20 0.50 11.22 cu.m
Abutment Second Footing 2 5.10 1.70 0.50 8.67 cu.m
Wing Walls 4 2.83 0.93 2.70 28.42 cu.m
Total = 66.47 cu.m.

5 PCC work for RCC in 1:1.5:3


Deck Slab 1 2.65 5.10 0.29 3.92
Kerb 2 2.65 area= 0.13 0.69
Abutment cap 2 5.10 0.625 0.30 1.91
Dirt wall 2 5.10 0.250 0.29 0.74
Total = 7.26 cu.m.

6 Reinforcement Work Area Wt


Slab along Span bottom 1 2.55 0.006 120.11 Kg
Slab along Span top 1 2.55 0.002 34.21 Kg
Slab across Span bottom 1 5.00 0.0017 66.73 Kg
Slab across Span top 1 5.00 0.00085 33.36 Kg
Abutment Cap Longitudinal bars (top+bottom) 2 5.00 0.001 78.50 Kg
Abutment Cap Stirrups 2 1.550 0.004 97.34 Kg
Dirt wall Longitudinal bars 2 5.00 0.00020 15.70 Kg
Dirt wall Stirrups 2 1.38 0.004 86.66 Kg
Kerb Longitudinal Bars 2 6.75 0.0005 49.94 Kg
Rural Reconstruction & Rehabilitation Sector Development Programme - 2
District Project Office, Chitwan

DETAILED QUANTITY ESTIMATE

Name of Works: 2 m Slab Culvert

Item
Description of works No. Length Breadth Height Quantity Unit
No.
(m) (m) (m)

Kerb Stirrups 2 2.21 0.00267 92.86 Kg


25mm dia Dowel Bars in abutments 2 1.07 0.00147 24.66 Kg
Total = 700.07 Kg

7 Formwork
Slab Bottom 1 1.90 5.100 9.69 sq.m
Slab Edge 2 2.65 0.25 1.33 sq.m
Kerb Outer side 2 2.65 0.5 2.65 sq.m
Kerb inner side inclined portion 2 2.65 0.29 1.55 sq.m
Kerb inner side vertical portion 2 2.65 0.25 1.33 sq.m
Abutment Cap outer side 2 5.10 0.59 6.02 sq.m
Abutment Cap inner side 2 5.10 0.59 6.02 sq.m
Abutment Cap side Horizontal 4 0.30 0.3 0.36 sq.m
Abutment Cap side vertical 4 0.25 0.29 0.29 sq.m
Total = 29.22 sq.m

8 100mm Dia. HDPE Pipe Weep Holes Nos.


Abutments 2 0.89 9.000 16.02 rm.
Wing walls 4 0.75 9.000 24.00 rm.
Total = 40.02 rm.

9 Bearing (Tar Paper) 2 5.10 0.325 3.32 sq.m.


Unit Total
Number Quantity

Culvert Details
Clear Span 6
Overall Depth 0.5
Overall Length 6.85
H 1.5
width of Culvert 5.1
Apron length 1
0

120.105

spacing dia(m)
0.12 0.02

12mm bar 12 nos.


2 LS 8mm dia @150mm C/C
8mm dia. Bar @ 150mm C/C
2 LS 12mm dia @150mm C/C
Unit Total
Number Quantity

Culvert Details

150

1 0.750
0.666667