ID Task Name Duration Start Finish July August September October November December January

6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30
1 PENGADAAN 2 (DUA) UNIT 180 days Mon 7/2/18 Fri 12/28/18
MPFM UNTUK
SUMUR-SUMUR PRODUKSI
DU FIELD TAMBUN
2 Kontrak/Purchasing Order 1 day Mon 7/2/18 Mon 7/2/18

3 ENGINEERING 14 days Tue 7/3/18 Mon 7/16/18

4 Design Engineering 14 days Tue 7/3/18 Mon 7/16/18

5 PROCUREMENT 152 days Tue 7/10/18 Sat 12/8/18

6 Truck 6x4 PS minimum 145 days Tue 7/10/18 Sat 12/1/18


220 PS dilengkapi spark
arrestor, APAR 3 kg,
Segitiga pengaman, alat
pemecah kaca, kotak P3K
(isi sesuai permenaker),
lampu rotary dan ban
cadangan

7 Multi Phase Flow Meter 152 days Tue 7/10/18 Sat 12/8/18
(MPFM) & Assesories

8 Purchasing Orde PPS 1 day Tue 7/10/18 Tue 7/10/18


ke Vendor
9 Fabrikasi/Manufacture 146 days Wed 7/11/18 Mon 12/3/18

10 Testing 3 days Tue 12/4/18 Thu 12/6/18

11 Pengiriman ke Site 2 days Fri 12/7/18 Sat 12/8/18

12 Material Utility 140 days Tue 7/17/18 Mon 12/3/18

13 Diesel Engine Genset 140 days Tue 7/17/18 Mon 12/3/18


Silent Type
14 Air Compressor 140 days Tue 7/17/18 Mon 12/3/18

15 Lampu Sorot Portable 120 days Tue 7/17/18 Tue 11/13/18


LED 100W Class 1 Div
1, Explotion proof,
height 2 -2,5 Meter

16 Lampu sorot pada truck 120 days Tue 7/17/18 Tue 11/13/18
LED 100W, Class 1 Div
1, explotion proof

17 KONSTRUKSI & INSTALASI 43 days Tue 10/30/18 Tue 12/11/18

18 Mobilsasi peralatan & 2 days Tue 10/30/18 Wed 10/31/18


manpower
19 mini control room c/w Air 30 days Thu 11/1/18 Fri 11/30/18
Conditioner 3/4 PK
20 Instalasi & Integrasi Prime 3 days Sun 12/9/18 Tue 12/11/18
mover truck
21 Instalasi Utility 7 days Tue 12/4/18 Mon 12/10/18

22 TESTING & 5 days Wed 12/12/18 Sun 12/16/18


COMMISSIONING
23 Site Integrated Acceptance 2 days Wed 12/12/18 Thu 12/13/18
(SAT)
24 Commissioning 3 days Fri 12/14/18 Sun 12/16/18

25 PEKERJAAN AKHIR 15 days Fri 12/14/18 Fri 12/28/18


PROJECT
26 Persetujuan Layak Operasi 14 days Fri 12/14/18 Thu 12/27/18
(PLO) & Sertifikasi Dinas
Metrologi

27 Serah Terima Pekerjaan 1 day Fri 12/28/18 Fri 12/28/18

Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Project: Project1
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: Mon 5/21/18
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

Page 1