Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
The proposed specification requires a also usually available from quality test-
two-hour curing time when non- Accommodating Absorption ing records that the aggregate source
absorptive aggregate is used in the or the State DOT maintains.
mix. The specification does not pro- It must be remembered that the basic
vide a definition of non-absorptive purpose of the curing process is to These water absorption values can be
aggregate nor does it spell out what allow for an amount of asphalt absorp- used to make a distinction between a
cure time should be used when a tion during mix design that is equiva- non-absorptive and an absorptive
highly absorptive aggregate is used. lent to the asphalt absorption that will aggregate. When a coarse aggregate
Since a significant amount of HMA is occur during typical production prac- has a water absorption of less than
produced using aggregates that have tices. The best way to evaluate the 2.5%, it should be considered a non-
relatively high absorptions, these absorptive characteristics of an aggre- absorptive (or low absorption)
questions must be addressed. gate is to look at the water absorption. aggregate.
Suggestions on these issues are
included in this article. Water absorption is determined as A good rule of thumb is that a two-
part of the aggregate specific gravity hour curing time is adequate where
testing. Typical water absorption val- low absorption coarse aggregate is
ues for a given coarse aggregate are being used. When water absorption
Figure 1.
2.440 Curing Time
2.420
2.410
Laboratory Curing
exceeds 2.5% in the coarse aggregate, absorption may not be completed SUMMARY
the curing time should be increased to prior to paving and the sampling /
approximately four hours. testing process. 1. It is essential to evaluate the volu-
metric properties (including VMA) of
Failure to increase the curing time In these circumstances, problems can plant produced HMA to ensure a
when using these highly absorptive be encountered in both mixture con- quality product.
aggregates, will result in incomplete struction and QC testing. The mixture
absorption of the asphalt into the may react as being over-asphalted dur-
2. It is important to allow for the total
aggregate and, ultimately, erroneous ing placement and compaction, and
amount of asphalt absorption that will
mix specific gravities and volumetric have low VMA and air voids and high
properties. VFA (voids filled with asphalt) when occur during production when
tested. This is because the aggregate absorptive aggregates are used.
As a general rule, the higher the water has not been given sufficient time to During mix design, when coarse
absorption, the more asphalt absorp- complete its absorption of the asphalt. aggregates with high water absorption
tion that will take place. However, (> 2.5%) are used, curing time should
there is no precise relationship The best way to avoid these problems be increased from the standard two
between the amount of water and is make sure that the produced mix is hours to four hours to approximate
asphalt absorption on aggregates. adequately cured prior to testing and asphalt absorption that may occur
The amount of asphalt absorption can to ensure that the production, storage during production.
vary greatly in a general range of 50 – and haul process allows for enough
80 % of water absorption. Many fac- time for asphalt absorption to be com-
3.When a four-hour cure time is used
tors can affect the percentage of pleted prior to laydown.
during the mix design phase (due to
asphalt to water absorption including
the use of high absorption coarse
the grade (viscosity) of asphalt cement To ensure that asphalt absorption has
used, aggregate type and pore size and been completed prior to testing plant- aggregate), plant-produced HMA
a number of construction variables. produced mixture in which high should be oven cured for two hours
absorption aggregates are used, it is prior to volumetric testing.
good practice to oven cure the mix-
ture prior to testing for volumetric
Field Curing
properties. When a four-hour oven
cure is used during the design Bob Horan is the Asphalt Institute’s
Two of the construction variables that
process, a two-hour oven cure should District Engineer for Maryland,
can have the most dramatic impact on
be performed on the plant–produced North Carolina, South Carolina,
the amount of asphalt absorption are
mixture. This will result in more accu- Virginia, and West Virginia.
initial mixing temperature and the
rate air void and VMA determinations
length of time that the mixture is held
to be made.
at an elevated temperature after mix-
ing. The length of time that the mix is
kept at an elevated temperature (at or The first steps in the volumetric analy-
near mixing temperature) would start sis of plant produced HMA is accom-
immediately after the mix is produced plished by obtaining a representative
and would include any storage time of sample. Proper curing of the mix is
the mix and also the time that the mix the essential second step that should
is being transported to the project lay- be accomplished prior to testing to
down site. determine the asphalt content of the
mix, performing the maximum specif-
When highly absorptive aggregates are ic gravity (AASHTO T-209) test on the
being used in situations where storage loose mix and determining bulk spe-
time is limited to less than two hours cific gravities of the compacted mix.▲
and haul distances are short, asphalt