2. Confirm flange faces cleaned and This tag indicates the
free from defects prior to joint being flange requires repair. completed. Sign: 3. Installed gaskets are of the correct material and rating. Sign: QC Inspector 4. Installed studbolts, size and material comply with specification. Name:……………………. Sign:
5. Specified bolt tightening sequence
Signed:…………………… has been used. Sign: Date:……………………… 6. Confirm bolts tightened to correct torque values. Sign:
7. Confirm approximately 2 threads of
bolt protrude through nut. Sign: This is tag can only be 8. Joint alignment is parallel and within removed by the QC tolerance: 0.25 mm / 100 mm diameter Inspector and only after Sign: the flange has been 9. Supervisor/QC approved. repaired and accepted. Sign: Flange No:
WHITE
QA / QC Inspector
Name:…………………………….
Signed:……………………………
Date:………………………………
This tag indicates the flange
is ready for service.
This tag is to be removed by
the operator once the equipment is on-line and leak free and is to be placed in the work pack.