Item No. Description Unit Quantity Rate Amount

Excavations including maintaining and supporting sides


and keeping free from water, mud and fallen material

A Excavate for foundations not exceeding 1.00 metre, starting from


ground level CM 210 550.00 115,500.00

Disposal

B Return, fill and ram selected excavated material around foundations. CM 150 250.00 37,500.00

C Load, wheel and deposit surplus excavated material from site CM 60 450.00 27,000.00

Plain concrete class 15 in:

D 50mm thick blinding under foundations SM 210 750.00 157,500.00

Reinforced concrete class (20) as described, in:-

E Ground floor slab SM 210 1,275.00 267,750.00

Mesh fabric reinforcement to B.S 4483 and setting in concrete with


300mm side and end laps (measured nett-allow for laps).

F Fabric ref. A142 in surface SM 210 450.00 94,500.00

Hardcore fill

G 300mm thick well compacted hardcore filling blinded with 50mm thick
quarry dust layer to receive surface bed SM 210 500 105,000.00

Murram fill

H Provide, place, water process and compact in accordance


with the specification natural gravel material n.e. 300mm thick SM 210 550 115,500.00

Sawn formwork, as described, to:-

I Vertical sides of floor slab n.e. 150mm high LM 75 150.00 11,250.00

Floor finish

Cement and sand (1:4 )backings etc

J 12mm backing finished to receive ceramic wall tiles (ms) SM 210 400.00 84,000.00

K Supply of ceramic floor tiles, fix on prepared bed (m.s) with


proprietary adhesive; jointed and pointed in matching SM 210 1,250.00 262,500.00
coloured proprietary grouting

TOTAL AMOUNT TO FORM OF TENDER 1,278,000.00