Sei sulla pagina 1di 1

REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


H
OFFICE OF THE BUILDING OFFICIAL
MANDAUE CITY
ISSUANCE RECOMMENDED

H
GENERAL STRUCTURAL/CONSTRUCTION NOTES AND SPECIFICATIONS

H
CRITICAL SECTION
(INTERIOR FACE OF HEAD STRUCTURAL DATE
SUPPORT)
(A) GENERAL REQUIREMENTS SECTION
ISSUED BY:
1. ALL STRUCTURAL MATERIALS AND WORK SHALL CONFORM TO THE REQUIREMENTS 6. MAINTAIN MINIMUM CONCRETE COVER FOR REINFORCING STEEL AS FOLLOWS:
OF THE LATEST EDITION OF THE NATIONAL STRUCTURAL CODE OF THE PHILIPPINES
FOOTINGS (CAST AGAINST & EXPOSED TO EARTH) . . . . . 75MM (3")
(NSCP 2010).
WHERE CONCRETE IS EXPOSED TO BUILDING OFFICIAL DATE
2. VERIFY ALL DIMENSIONS, ELEVATIONS AND SITE CONDITIONS BEFORE STARTING
EARTH BUT POURED AGAINST FORMS . . . . . . . . . . . . . . . . 50MM (2") WHERE:
WORK. NOTIFY THE ENGINEER IMMEDIATELY OF ANY DISCREPANCIES. Ldh = DEVELOPMENT LENGTH FOR
40MM ( 1 1/2") STANDARD HOOK NOTE:
SLAB ON GRADE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3. NOTES AND DETAILS ON THE DRAWINGS TAKE PRECEDENCE OVER THE GENERAL H H = EXTENSION
This drawing is property of Archiglobal, Inc. whether the object for which they are
NOTES AND TYPICAL DETAILS IN CASE OF CONFLICT. COLUMN TIES OR SPIRALS AND BEAM STIRRUPS . . . . . . . 40MM ( 1 1/2") Ldh
r = INSIDE RADIUS OF BEND
made is executed or not. Do not reproduce and disclose this drawing to any
*ONLY WHEN USED AS COMPRESSION MEMBER IN FOOTING, unauthorized person without the written consent of Archiglobal, Inc.
4. WHERE CONSTRUCTION DETAILS ARE NOT SHOWN OR NOTED FOR ANY PART OF THE SUSPENDED SLABS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20MM ( 3/4") SPLICED WITH DOWELS OR WHEN LAP SPLICED
WITH SMALLER BAR.
WORK, SUCH DETAILS SHALL BE THE SAME AS FOR SIMILAR WORK SHOWN ON THE Do not scale this drawing. All dimensions have to be verified on site. All
DRAWINGS. 7. SPLICES SHALL BE SECURELY WIRED TOGETHER AND SHALL LAP AT LEAST 40 TIMES STANDARD HOOKS discrepancies have to be clarified with the Project Architect.
DIAMETER OR 600MM WHICHEVER IS GREATER. STAGGER BOTTOM AT LEAST 1.50M STIRRUPS AND TIE HOOKS
All dimensions are in millimeters unless otherwise specified.
5. PIPES, DUCTS, SLEEVES, CHASES, ETC. SHALL NOT BE PLACED IN SLABS, BEAMS, OR FROM SPLICES IN OTHER BOTTOM REINFORCEMENT. STAGGER SPLICES FOR TOP
WALLS UNLESS SPECIFICALLY SHOWN OR NOTED NOR SHALL ANY STRUCTURAL
MEMBER BE CUT FOR PIPES, DUCTS, ETC. UNLESS SPECIFICALLY SHOWN. OBTAIN
REINFORCEMENT SIMILARLY. TABLE OF LAP SPLICE All levels indicated are finish floor levels in meters unless otherwise specified.

PRIOR WRITTEN APPROVAL FROM THE ENGINEER FOR INSTALLATION OF ANY 8. ALL ANCHOR BOLTS, DOWELS, AND OTHER INSERTS SHALL BE PROPERLY
ADDITIONAL PIPES, DUCTS, ETC. POSITION AND SECURED IN PLACE PRIOR TO PLACING OF CONCRETE. PARAMETERS
LOCATE AND PROTECT UNDERGROUND OR CONCEALED CONDUIT, PLUMBING OR 9. ALL CONCRETE SHALL BE KEPT MOIST FOR A MINIMUM OF 7 CONSECUTIVE DAYS MATERIAL psi MPa ACI 318-05
OTHER UTILITIES WHERE NEW WORK IS BEING PERFORMED. IMMEDIATELY AFTER POURING BY THE USE OF CURING COMPOUNDS, OR OTHER f'c 5000 34.5 DEV'T & SPLICE LENGTH
6. LOCATE AND PROTECT UNDERGROUND OR CONCEALED CONDUIT, PLUMBING OR APPROVED METHODS.
fy 60000 414 16mm & HIGHER
OTHER UTILITIES WHERE NEW WORK IS BEING PERFORMED. 10. STRIPPING OF FORMS AND SHORES: fyh 40000 276 12mm & LOWER
7. TAKE NECESSARY PRECAUTIONS TO MAINTAIN AND INSURE THE INTEGRITY OF THE FOUNDATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 HRS. tie Ø 10 stirrup Ø 10
STRUCTURE DURING CONSTRUCTION. NEITHER THE OWNER NOR SUSPENDED SLAB EXCEPT WHEN fyt 40000 fyt 40000
ARCHITECT/ENGINEER WILL ENFORCE SAFETY MEASURES OR REGULATIONS. IT ADDITIONAL LOADS ARE IMPOSED . . . . . . . . . . . . . . . . . . . . . . . . 8 DAYS
SHALL BE THE CONTRACTORS RESPONSIBILITY TO PROVIDE ADEQUATE SHORING WALLS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 HRS STANDARD HOOK (mm) TENSION LAP SPLICE (mm)
BARØ ANCHORAGE BEAM COMP.
AND BRACING OF THE STRUCTURE FOR ALL THE LOADS THAT MAYBE IMPOSED BEAMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 DAYS (mm) LENGTH (mm)
Ldh(mm)
SPLICE (mm)
UNIT WT.
BEAM COLUMN (kg/m)
DURING CONSTRUCTION. FURTHER, THE CONTRACTOR SHALL DESIGN, CONSTRUCT (E) CAMBER REQUIREMENTS 90° 180° 135°-90° LAP CLASS
TOP BAR BOTTOM BAR TIED SPIRAL
AND MAINTAIN ALL SAFETY DEVICES AND SHALL BE SOLELY RESPONSIBLE FOR
A 300 300
CONFORMING TO ALL SAFETY AND HEALTH STANDARDS, LAWS AND REGULATIONS. 1. UNLESS OTHERWISE NOTED ON THE PLANS OR SPECIFICATIONS CAMBER ALL RC 10 600 150 160 110 120~120 300 300 300 0.616
B 390 390
BEAMS AT LEAST 10mm FOR EVERY 4000mm OF CLEAR SPAN EXCEPT CANTILEVERS
8. OBTAIN PRIOR WRITTEN APPROVAL FROM THE ENGINEER IN CASE OF CHANGES TO A 530 410
WHICH WHICH SHALL BE 50mm FOR EVERY 3000mm OF CLEAR SPAN. 12 600 200 200 120 130~130 350 410 410 0.888
THE WORKING DRAWINGS. B 690 530
A 700 540
2. UNLESS OTHERWISE NOTED ON THE PLANS OR SPECIFICATIONS CAMBER ALL SLABS 16 740 270 260 130 160~160 460 540 540 1.579
B 910 700
(B) DESIGN CRITERIA 8mm PER 3000mm OF SHORTER SPAN AND 14mm FOR EVERY 2000mm OF SLABS
A 880 680
CANTILEVER SPAN. 20 920 340 320 160 200~320 580 680 680 2.466
B 1140 880
- - - REFER TO STRUCTURAL COMPUTATIONS
A 1370 1060
25 1150 430 400 200 250~400 720 1060 1060 3.854
(F) MASONRY AND CONCRETE BLOCKS B 1780 1380
(C) FOUNDATION A 1540 1180
1. CONCRETE HOLLOW BLOCKS, UNLESS OTHERWISE SPECIFIED SHALL BE 150MM 28 1300 480 480 260 810 1180 1180 4.833
B 2000 1530
1. FOOTINGS SHALL BEAR ON SOLID UNDISTURBED EARTH (CONTROLLED, COMPACTED THICK. LOAD BEARING BLOCKS SHALL HAVE A MINIMUM COMPRESSIVE STRENGTH OF A 1760 1350
STRUCTURAL FILL OR BOTH) AT LEAST 600MM BELOW LOWEST ADJACENT FINISHED 750 PSI (5.175 MPa) WHILE NON-LOAD BEARING SHALL HAVE A MINIMUM 32 1700 540 550 290 930 1350 1350 6.313
B 2290 1760
GRADE. COMPRESSIVE STRENGTH OF 400 PSI (2.76 MPa). A 1980 1520
2. FOUNDATION DESIGN IS BASED ON THE SOIL EXPLORATION AND GEOTECHNICAL 36 2150 610 650 360 1040 1520 1520 7.991
2. PROVIDE 1-16MMØ VERTICAL BARS AT CORNERS, INTERSECTIONS, END OF WALLS, B 2570 1980
EVALUATION PREPARED BY INDUSTRIAL INSPECTION (INT'L) INC. DATED JANUARY
EACH SIDE OF OPENINGS. NOTES:
07-19, 2013
3. SUB-GRADE PREPARATION INCLUDING DRAINAGE, EXCAVATION, COMPACTION, 3. LINTEL BEAMS SHALL BEAR AT LEAST 200MM (8") ON EACH SIDE OF MASONRY WALL 1. DEVELOPMENT LENGTH OF INDIVIDUAL BARS WITHIN A BUNDLE, IN TENSION OR COMPRESSION, SHALL BE THAT FOR INDIVIDUAL BARS,
INCREASED 20% FOR THREE-BUNDLED AND 33% FOR FOUR-BUNDLED BARS.
AND FILLING REQUIREMENTS, SHALL CONFORM STRICTLY WITH THE OPENING. 2. FOR COLUMNS AT ANY LEVEL, NO MORE THAN ALTERNATE BARS SHOULD BE SPLICED, NOTMORE THAN 33% OF THE BARS SHALL BE SPLICED WITHIN
RECOMMENDATIONS GIVEN IN THE SOILS REPORT OR AS DIRECTED BY THE SOILS THE REQUIRED LAP LENGTH, MINIMUM DISTANCE BETWEEN TWO ADJACENT SPLICED SHALL BE 600mm.
ENGINEER. 4. WALL REINFORCEMENTS SHALL BE AS FOLLOWS: 3. TOP BARS ARE HORIZONTAL BARS WITH MORE THAN 300mm DEPTH OF CONCRETE CAST BELOW REINFORCEMENT.
WALL THICKNESS VERTICAL BARS HORIZONTAL BARS 4. LAP SPLICE SHALL BE "CLASS B" TENSION LAP SPLICE IF MORE THAN ONE HALF OF THE BARS WERE SPLICED AT ANY SECTION, WHILE "CLASS A"
4. THE CONTRACTOR SHALL NOTIFY THE ENGINEER AFTER FOOTING EXCAVATION TENSION LAP SPLICE IF HALF OR FEWER THAN HALF OF BARS WERE SPLICED.
HAVE BEEN COMPLETED AND PRIOR TO CONCRETING TO CONFIRM THE DESIGN 8 IN. (200 mm) . . . . . . . . . . 12MMØ @ 400 mm 10MMØ @ 600 mm 5. TOP BARS SPLICE FOR BEAMS, SHOULD BE "BEAM COMPRESSIVE SPLICE x1.3"
SOIL BEARING CAPACITY. 6 IN (150 mm) . . . . . . . . . . . 10MMØ @ 400 mm 10MMØ @ 600 mm
4 IN. (100 mm) . . . . . . . . . . 10MMØ @ 400 mm 10MMØ @ 600 mm
5. ROOF AND AREA DRAINAGE SHALL BE DIRECTED AWAY FROM THE FOUNDATIONS. PARAMETERS
5. BLOCK WALL REINFORCING BARS SHALL BE LAPPED OF 30 BAR DIAMETERS WHERE
6. EXCAVATIONS SHALL BE PROPERLY BACKFILLED. BACKFILL FOR WALLS SHALL BE MATERIAL psi MPa ACI 318-05
SPLICED, HORIZONTAL/VERTICAL DOWELS FROM FOOTINGS, COLUMNS/WALLS OR
PERVIOUS MATERIAL ACCEPTABLE TO THE GEOTECHNICAL ENGINEER. DO NOT PLACE f'c 3000 20.7 DEV'T & SPLICE LENGTH
SLABS SHALL EXTEND INTO THE BLOCK WALL A MINIMUM OF 30 BAR DIAMETERS OR A
BACKFILL BEHIND WALLS BEFORE THEY HAVE ATTAINED THEIR DESIGN STRENGTH.
MINIMUM OF 400MM WHICHEVER IS LONGER AND DOWELS TO MATCH VERTICAL fy 60000 414 16mm & HIGHER
SHORE AND PROTECT WALLS FROM LATERAL LOADS UNTIL THE SUPPORTING
REINFORCEMENTS OF WALL. fyh 40000 276 12mm & LOWER
MEMBERS ARE IN PLACE AND HAVE DEVELOPED SPECIFIED STRENGTHS.
tie Ø 10 stirrup Ø 10
(G) STRUCTURAL STEEL
fyt 40000 fyt 40000
(D) REINFORCED CONCRETE
1. ALL STRUCTURAL STEELS SUCH AS ANGLES, WIDE FLANGE SECTIONS, PIPES, STANDARD HOOK (mm) TENSION LAP SPLICE (mm)
1. CONCRETE SHALL BE MIXED, PROPORTIONED, CONVEYED AND PLACED IN STIFFENER PLATES, BASE PLATES, ETC. SHALL CONFORM TO ASTM A-36. BARØ ANCHORAGE
Ldh(mm)
BEAM COMP.
UNIT WT.
ACCORDANCE WITH THE PROVISIONS SET BY THE NSCP 2010. (mm) LENGTH (mm) SPLICE (mm) BEAM COLUMN
90° 180° 135°-90° LAP CLASS (kg/m)
2. ALL STRUCTURAL STEEL SHALL BE DETAILED, FABRICATED AND ERECTED BASED ON TOP BAR BOTTOM BAR TIED SPIRAL
2. ALL CONCRETE SHALL DEVELOP A MINIMUM COMPRESSIVE STRENGTH AT 28 DAYS THE SPECIFICATION FOR DESIGN, FABRICATION, AND ERECTION OF STRUCTURAL A 380 300
STEEL GIVEN BY THE NATIONAL STRUCTURAL CODE OF THE PHILIPPINES (NSCP). 10 600 150 160 110 120~120 300 300 300 0.616
WITH CORRESPONDING MAXIMUM SLUMP AND MAXIMUM SIZE AGGREGATE AS B 490 390
FOLLOWS: 3. CONNECTION BOLTS (34 ROUND, UNLESS SHOWN OTHERWISE) SHALL CONFORM TO A 680 520
12 710 260 200 120 130~130 350 520 520 0.888
ASTM A-325. ANCHOR BOLTS (EMBEDDED IN MASONRY OR CONCRETE) SHALL B 880 680
STRUCTURAL MEMBER 28 DAY STRENGTH MAX. SLUMP MAX. SIZE AGG. A 910 700
CONFORM TO ASTM A307 UNLESS NOTED OTHERWISE ON THE DRAWINGS. 16 950 350 260 130 160~160 460 700 700 1.579
A. SLAB ON GRADE 21 MPa (3,000 PSI) 100MM (4") 25MM (1") B 1180 910
B. FOOTINGS & RETAINING WALLS 35 MPa (5,000 PSI) 100MM (4") 19MM (3/4") 4. ALL STRUCTURAL STEEL SHALL BE CLEAN, RUST FREE AND SHOP COATED WITH THE A 1140 870
APPROPRIATE PAINT. STRUCTURAL STEEL AND ANCHOR BOLTS SHALL BE MINIMUM 20 1180 440 320 160 200~320 580 870 870 2.466
C. COLUMNS / SHEARWALLS 35 MPa (5,000 PSI) 100MM (4") 19MM (3/4") B 1480 1130
D. BEAMS & SLABS 35 MPa (5,000 PSI) 100MM (4") 19MM (3/4") ASTM A-36 DOMESTIC, LATEST REVISION. A 1780 1370
25 1900 550 400 200 250~400 720 1370 1370 3.854
5. NON - SHRINK GROUT - PRE-MIXED, NON-METALLIC, CEMENT-BASED GROUT, MEETING B 2310 1780
3. ALL REINFORCING STEEL BARS SHALL CONFORM TO ASTM A615 GRADE 40 FOR THE REQUIREMENT OF ASTM C827, ASTM C109 & CRD-C621, WITH A MINIMUM A 1990 1530
28 2190 620 480 260 810 1530 1530 4.833
12MMØ AND SMALLER BARS WHILE BARS 16MMM Ø AND LARGER SHALL BE GRADE 60. COMPRESSIVE STRENGTH OF 7000psi AT 28 DAYS. B 2590 1990
A 2270 1750
6. PROVIDE MISCELLANEOUS PLATES, ANGLES AND ANCHORS AS SHOWN OR NOTED ON 32 2590 700 550 290 930 1750 1750 6.313
4. ALL FABRICATION, DETAILING AND PLACING SHALL CONFORM TO THE PROVISIONS DRAWINGS. B 2950 2280
SET BY THE NSCP 2010 EDITION. A 2560 1970
7. ALL CUTTING AND BLOCKING OF STEEL SHALL BE SHOWN ON SHOP DRAWINGS AND 36 2990 790 650 360 1040 1970 1970 7.991
B 3330 2560
5. CLEAR DISTANCE SPACING BETWEEN PARALLED BARS IN A LAYER SHALL NOT BE PERFORMED IN SHOP.
LESS THAN 1.50 TIMES THE NOMINAL DIAMETER OF THE BAR, OR 1.33 TIMES MAXIMUM NOTES:
8. PROVIDE TEMPORARY BRACING AS REQUIRED FOR A SAFE STRUCTURE UNTIL ALL
1 1. DEVELOPMENT LENGTH OF INDIVIDUAL BARS WITHIN A BUNDLE, IN TENSION OR COMPRESSION, SHALL BE THAT FOR INDIVIDUAL BARS,
SIZE AGGREGATE, NOR LESS THAN 38MM (1 2"). FINAL CONNECTIONS ARE MADE.
INCREASED 20% FOR THREE-BUNDLED AND 33% FOR FOUR-BUNDLED BARS.
2. FOR COLUMNS AT ANY LEVEL, NO MORE THAN ALTERNATE BARS SHOULD BE SPLICED, NOTMORE THAN 33% OF THE BARS SHALL BE SPLICED WITHIN
THE REQUIRED LAP LENGTH, MINIMUM DISTANCE BETWEEN TWO ADJACENT SPLICED SHALL BE 600mm.
3. TOP BARS ARE HORIZONTAL BARS WITH MORE THAN 300mm DEPTH OF CONCRETE CAST BELOW REINFORCEMENT.
4. LAP SPLICE SHALL BE "CLASS B" TENSION LAP SPLICE IF MORE THAN ONE HALF OF THE BARS WERE SPLICED AT ANY SECTION, WHILE "CLASS A"

FOR CONSTRUCTION PURPOSES TENSION LAP SPLICE IF HALF OR FEWER THAN HALF OF BARS WERE SPLICED.
5. TOP BARS SPLICE FOR BEAMS, SHOULD BE "BEAM COMPRESSIVE SPLICE x1.3"
- - -
DATE ISSUED: 03-19-2018 BY: GGSE
REV. DATE DESCRIPTION
R.A.9266 Section 33 ARCHITECTURAL: STRUCTURAL:
SEAL ARCHIGLOBAL, INC. GITAMONDOC-GOPAOCO
PROJECT TITLE: APPROVED BY: DRAWING TITLE: SCALE: DATE: 3/21/2018 SHEET NUMBER: REVISION:
Drawing and specifications and other
contract documents signed, stamped or PROJECT IN CHARGE:
GITAMONDOC-GOPAOCO RAMON M. GITAMONDOC sealed, as instruments of service, are the ELECTRICAL: ELECTRONICS:
OAKRIDGE REALITY BUILDING 2 N
S-100.0 R00
intellectual property and documents of the JONATHAN A. VILLAFLOR VICTOR C. NAVARRO 1 : 150 A1 JOHN
STRUCTURAL ENGINEERING COMPANY
www.ggstructural.com
STRUCTURAL ENGINEER
architect, whether the object for which
they are made is executed or not, it shall MECHANICAL:
be unlawful for any person to duplicate or L.M PARAGSA DESIGN &
FIRE PROTECTION:
L.M PARAGSA DESIGN &
A PROPOSED MIXED-USE DEVELOPMENT DEVELOPMENT CORPORATION GENERAL STRUCTURAL AND
REG. NO.: 92466 DATE : 01/15/2002
WOOLBRIGHT DRIVE, LAHUG, CEBU CITY,
to make copies of said documents for use
in the repetition of and for other projects CONSULTANCY CONSULTANCY OWNER CONSTRUCTION NOTES DRAFTED BY:
PTR NO. : 6632275 DATE : 01/08/2016 of building, whether executed partly in PLUMBING: SITE DEVELOPMENT: -
PHILIPPINES whole, without the written consent of JOHN
TIN : 135-446-443 architect or author of said documents. J.M SALERA CONSTRUCTION LOCATION: 880 - A.S FORTUNA STREET, BANILAD, MANDAUE CITY, CEBU ADDRESS: 880 - A.S FORTUNA STREET, BANILAD, MANDAUE CITY, CEBU PROJECT CODE: P11_C0M_126

Potrebbero piacerti anche