SEMESTER 1 2018/2019
QUIZ 5_ONLINE
4th DECEMBER 2018
The development of an innovative material failure detection system has been underway by HiTech
Engineering. The following workflow has been identified by the project manager.
Task Description Duration (Day) Predecessor (s)
A Requirement Analysis 5 -
B System design 15 A
C Programming 25 B
D Circuits and control 15 B
E Hardware installation 30 B
F System integration 10 C,D
G Commissioning and testing 10 E,F
H Training/support 5 G
I Handover and Go-live 5 H
iii) Identify the critical path and the duration of the project.
Critical Path: A B D F G H I
Critical Duration: 75 Days
iv) Draw the Gantt chart.
Activity/Days 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
A
B
C
F
G
H
I