Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1
Guidelines for preparing Detailed project Report
2
Table Of Contents Page Number
Salient Features
Executive Summary
1 Introduction
2 Project Definition, Concept and Scope
3 Project Background
4 Project Details
5 Objective And Scope Of The Work
3
19 Statutory Clearances
20 Quality Management Plan
22 Annexure
4
SALIENT FEATURES
2. Department
4. Implementing agency/SPV
5. DPR prepared by
6. Project outlay
7. Budget provision
9. Administrative sanction
5
iv. Details of cross drainage works
v. Other details
6
EXECUTIVE SUMMARY:
This section shall contain brief of all relevant details discussed in the following
chapters.
7
1. INTRODUCTION
The proposed project has to be clearly demarcated in terms of all its sub-
components/elements including quantum of land required, whether any
acquisition is needed, the design, detailed engineering and drawings of each
physical infrastructure sub components, environmental compliance,/protection
measures/improvement measures .
3. PROJECT BACKGROUND
A brief description of the existing bridge, if any, in the project area, its present
condition and need for the present project..
4. PROJECT DETAILS
Description of the location and geographic features of the area and adjoining
land.
A brief description of the geometry of the approach roads, description of
whether there are temples, schools, mosques along the alignment, existing
cross drainage structures, existing utilities like electric & telephone poles and
water lines along the proposed bridge.
8
5. OBJECTIVE AND SCOPE OF THE WORK
A brief note about the necessity of the works proposed under the project and
the main works to be carried out to fulfill the objective.
Description of any feasibility study conducted earlier and their outcome shall
be discussed in this section.
8. FUNCTIONAL DESIGN
9
acquisition and avoiding problematic soils, too many cross-drainage works,
landslide susceptible slopes etc.
The proposed alignment should achieve the least overall cost on
transportation, having regard to the costs of initial construction of the road
facility, its maintenance, and road user cost, while at the same time, satisfying
the social and environmental requirements.
Where the project involves improvements to an existing road, every effort
should be directed towards the inherent deficiencies with respect to: plan and
profile, sight distance/visibility in horizontal as well vertical plan, carriageway,
shoulder and roadway width, cross-drainage structures, road side drainage
provisions as well as area drainage consideration and safety features.
The field study shall include traffic surveys and documentation which may be
done as per the latest revisions and amendments of the relevant guidelines of
MoRTH, publications of Indian Roads Congress (IRC) and Bureau of Indian
Standards (BIS).
Information about traffic is indispensable for any road project since it would
form the basis for the design of the pavement, fixing the number of traffic
lanes, design of intersections etc. Traffic surveys required to be conducted in
connection with the preparation of road project are: Classified Traffic Volume
Counts, Origin-Destination Surveys, Speed and delay studies, Traffic Surveys
for the Design of Road Junction, Axle Load Surveys, and Accident Records
etc.
10
i. Soil investigation report including CBR details
ii. Borrow area and quarry details ensuring the quality and quantity of
materials, construction water sources
iii. Soil sample collection and Testing
Traffic Survey
BBD survey, if the project demands
11
Existing ROW details:
ix. Existing sub grade condition with position of water table, HFL(High
Flood Level) etc if the project demands
This section should focus on the cost estimates, budget for the project, means
of financing and phasing of expenditure.
12
Cost estimates have to be worked out on the basis of detailed bill of quantities
(with detailed measurements of length, breadth, and depth / height for each
item), using the current Schedule of Rates of the State Government (PRICE)
or relevant SOR as applicable.
Applicable taxes, contingencies, investigation charges including any O&M cost
for a specific period shall be clearly specified.
Lump sum provisions for land acquisition etc. shall be explained in detail.
Cost Benefit Analysis (CBA) is a technique whereby the costs of and benefits
from a scheme are quantified over a selected time horizon and evaluated by a
common yardstick.
Cost Benefit Ratio (CBR - benefit to cost ratio), EIRR (Economic Internal Rate
of Return) etc. shall be worked out in detail with all supporting primary and
secondary data conforming to the guidelines of IRC: SP 30 - 2009.
The project cash flow projections for the life cycle along with underlying
assumptions have to be presented.
13
Environmental impact assessment study if mandatory and measures identified
to mitigate the adverse impact, if any shall be conducted and documented in
detail.
Issues relating to land acquisition, diversion of forest land, wildlife clearances,
rehabilitation and resettlement should be addressed in this section.
Inclusion of international best practices in sustainable infrastructure
management including potential low carbon emission, low energy, zero
pollution etc. is desirable.
For those projects which involve large capital outlay and various issues
relating to land acquisition, environmental aspects, a detailed and systematic
risk analysis may be resorted.
Identification and assessment of implementations risks which can lead to time
overrun, cost escalation, scope reduction etc. is the primary stage in risk
assessment.
Risk analysis could include legal/contractual risks, environmental risks,
revenue risks, project management risks, regulatory risks etc.
The mitigation plans including risk avoidance, risk transfer, and risk elimination
are to be well analysed and documented.
For complex projects with multiple risk profiles, numerical modeling and
simulation may be adopted.
14
17. CONTRACT MANAGEMENT STRATEGY
The time bound work schedule is an important part of every project because it
helps in better handling of projects in planning, implementation etc.
This section should indicate the propose zero date of commencement and
also provide a Bar chart / Project Schedule, wherever relevant.
Phasing of project activities, proposed contract packages and schedule of
implementation for each phase.
Identify critical dependencies in the project and expected timelines for
completion of key milestones and associated process indicators for the same.
The DPR should provide a time-bound action plan including tendering,
appointment of contractors, construction schedule,, quality assurance & quality
control and post-construction activities, including project delivery
This section should elaborate the statutory clearances to be obtained from the
various authorities.
Statutory approvals as per bye laws, master plan, fire safety norms,
environmental clearance etc. as applicable for the project are to be taken.
15
20. QUALITY MANAGEMENT PLAN
ANNEXURES
16
IX. PROPOSED CULVERT DRAWINGS
X. ROAD SAFETY STRIP PLAN
17