Sei sulla pagina 1di 6

Estimating reinforcing bars

How the bid price is determined

BY WILLIAM C. BLACK
CHIEF ENGINEER
REINFORCING BARS, PILING AND CONSTRUCTION
SPECIALTY SALES
BETHLEHEM STEEL CORPORATION

uppliers of reinforcing bars usually provide cer-

S tain added services in addition to furnishing


fabricated reinforcing bars to the job site. One
important function is estimating. This is per-
formed by estimator specialists who study a set of con-
tract drawings and specifications and, from their
FABRICATED DEFORMED CONCRETE
REINFORCING BARS

Area
SIZE EXTRAS

Weight Extra per


knowledge of construction and reinforcing bars, are Bar size sq. in. lb per ft 100 lb
able to develop a list of quantities of material which #18 4.00 13.600 $ 2.00
they believe or “estimate” are required to build the #14 2.25 7.650 2.00
structure under consideration. From this information #11 1.56 5.313 1.00
the necessary pricing is developed so that a bid can be
#10 1.27 4.303 1.00
submitted to the general contractor. In a few metropol-
#9 1.00 3.400 1.00
itan areas this estimating service is provided by esti-
#8 0.79 2.670 1.00
mating bureaus which contract with a number of rein-
forcing bar supplier clients and prorate the cost of the #7 0.60 2.044 1.00
service among the various users. #6 0.44 1.502 1.25
It is important that the contract drawings and specifi- #5 0.31 1.043 1.50
cations give complete detailed information about the re- #4 0.20 0.668 2.00
inforcing bars. The estimate is a line-by-line takeoff and #3 0.11 0.376 6.00
complete details will usually insure a more accurate es- # 2* 0.05 0.167 15.00
timate. When the estimator has to guess and make as-
sumptions, the quality of the estimate may be impaired. QUANTITY EXTRAS
A prudent estimator will tend to figure quantities on the
Extra per
safe side when there is a question of what is actually re- Quantity 100 lb
quired. This, of course, can increase the amount of the
material quotation. The estimator’s other alternative is Over 300 tons None
to contact the architect or engineer and attempt to clar- 100-300 tons $0.25
ify that which is not clear. This can be a very frustrating 50-99 tons 0.50
experience as answers are not always forthcoming. The 20-49 tons 0.75
estimator usually works under a tight deadline and must Under 20 tons** 1.25
move forward and complete the estimate. Of course the
bid can be qualified and limited to the assumptions
made, but this can lead to having the bid rejected as be- the current published size extras for fabricated bars
ing nonresponsive. from a major rebar fabricator. Note that the size extra for
#3 bars is $4.00 per hundred pounds or $80 per ton more
EXTRAS ADDED TO BASE PRICE than for #4 bars. This shows that it is generally more eco-
One aspect of preparing quantity estimates for fabri- nomical to specify #4 rather than #3 bars for approxi-
cated reinforcing bars is the way in which charges for ex- mately equal areas of steel. Similar comparisons could
tras (per hundredweight of material) may be added to be made for other sizes.
the base price. The principal extras are for size, grade, Quantity: Extra charges may be incurred depending
bending and quantity. on the total weight of steel ordered. The table also shows
Si ze : Extras for size may vary; therefore it is necessary the current quantity extras for fabricated re i n f o rc i n g
for the estimator to segregate by size. The table shows bars from the same fabricator whose size extras are giv-
en. This shows that there may be a job size penalty in 23 jobs—showed class of splice, per
breaking down smaller structures at bidding time for ACI 318.
separate acceptance.
Grade: Some grades of bars have an extra, making it 24 jobs—gave a table of splice lengths
necessary for the estimator to segregate by grade as well (inches), generally conform-
as size. ing to ACI 318, but not
Bending: Extra charges are applied for all shop bend- always.
ing. The estimator must segregate the total quantity of
bending into three classes as follows, based on current 10 jobs—merely referenced ACI 318 or
industry definitions: CRSI Manual of Standard
Practice (or silent).
• LIGHT BENDING—All #3 bars, all stirrups and ties, and
all bars #4 through #18 which are bent at more than six 14 jobs—had miscellaneous other
points in one plane, or bars which are bent in more combinations.
than one plane (unless “special bending”). Also includ-
ed are all one-plane radius bending with more than One of our conclusions is that some of the odd com-
one radius in any bar (three maximum), and any com- binations are due to different designers working on the
bination of radius and other type bending in one plane same contract.
(radius bending being defined as all bends having a ra-
dius of 12 inches or more to inside of bar).
* Standard tolerances are given in the Manual of Standard Practice published
• HEAVY BENDING—Bar sizes #4 through #18, which are by Concrete Reinforcing Steel Institute, 180 N. LaSalle Street, Chicago, Illi-
bent at not more than six points in one plane (unless nois 60601.

classified as light bending or special bending) and sin-


gle-radius bending.

• SPECIAL BENDING—All bending to tolerances more


restrictive than those shown in industry standards, all
radius bending in more than one plane, all multiple
plane bending containing one or more radius bends,
and all bending for precast units.*

Typical extra charges may be of the order of $4.00 per


hundred pounds for light bending and $1.75 per hun-
dred pounds for heavy bending. Since light bending
costs $2.25 per hundred pounds ($45.00 per ton) more
than heavy bending, it is more economical to specify,
for example, #4 bent bars rather than #3 where total re-
quired areas are approximately equal. Multiple bends
such as continuous truss bars in bridge deck slabs are
more costly per hundred pounds since they usually have
more than six bends per bar and come under the “light
bending” extra. Figure 1. Using contract drawing information (top) the
estimator visualizes how the detailer would handle the bars
LAP SPLICES (bottom) before he can estimate quantities. See Figure 2
for a much better way for the designer to treat this corner.
Ideally, the length and location of all lap splices should
be shown in the contract documents. Unfortunately, this
is seldom the case in the real world. Recently we sur-
veyed 139 jobs currently being serviced around the con-
tinental United States. The results indicated that splice Figure 2. Preferred
way of showing wall
information was given in the following ways:
corner in Figure 1.
Overall cost of
46 jobs—indicated splice lengths in horizontal wall
bar diameters, generally 24, reinforcement is
36 or 40. reduced because only
the bent corner bar is
22 jobs—provided splice dimensions charged the heavy
on plans, sections, or details. bending extra.
Splice location problem if the contract documents do not indicate
The estimator must first determine the location of all whether horizontal wall bars are top bars or not. The de-
splices so as to calculate the total quantity required. This signer should state explicitly if he has provided for top
is fairly straightforward for columns where the typical bar effect and which splices are affected, including hor-
detail may show a splice at each floor level. It is not so izontal wall bars. If the contract documents are silent on
obvious for elements such as walls with long runs of hor- this, the estimator would usually assume that no top bar
izontal bars. The estimator has a double problem here: effect is required for walls, and splices would be figured
(1) he needs to determine the quantity of splices re- as “other.”
quired in each run of bars; and (2) he also must make a Probably the most frustrating experience for an esti-
judgement decision as to how many feet of the run will mator or a detailer is to have the contract documents
be estimated as bent and how many as straight. spell out splices “in accordance with ACI 318” and be
An example is shown in Figure l. The contract draw- otherwise silent. This is of absolutely no help to the esti-
ings show a wall cross section and indicate “#5 at 12 hor- mator; he is in no position to determine conditions of
izontal both faces.” The outside face bars are bent tension or compression, class of splice, top bar effect,
around each corner and extended 2 feet 2 inches. The in- confinement, and the like. He must then contact the ar-
side face bars extend in straight. The estimator must vi- chitect or engineer to determine what is required. All too
sualize how the detailer would actually handle it. In this often the response is “You fellows are the experts; work
example the estimator has assumed three bars per run in out the solution yourself,” or “What do you recom-
30-foot stock lengths, plus a bent bar at each end for the mend?”
outside bars. This approach minimizes the weight of
bent bar required, and therefore the quoted price of the BUTT SPLICES
material, without adding extra splices. A far better and Butt splices, which are less frequently encountered,
more economical solution would be for the designer to may be either mechanical or arc welded. The majority
show separate corner bars 2 feet 2 inches on a side (Fig- of butt splices used today are mechanical. There are nu-
ure 2). The estimator would then figure the inside and merous proprietary types, including the following:
outside horizontal bars in an identical manner, as
straight bars. The only bars that would require the heavy • metal filled sleeve
bending extra would be the bent corner bars, thereby re-
ducing the overall cost of the horizontal wall reinforce- • hot forged sleeve
ment. The inside face bars would probably be figured as
• cold forged sleeve
a run of four bars, each approximately 30 feet long, with
three splices. It is important to recognize that the stan- • forged sleeve with threaded stud
dard industry method of pricing bending is on a hun-
dredweight basis. Placing a bend at the end of a longer • taper threaded sleeve
bar causes the bending extra to be applied to the entire
weight of the bar. • thread deformed rebar with matching sleeve
Fabrication, transportation and construction limita-
tions should have been considered by the designer when • cement mortar filled sleeve
determining permissible splice locations (or prohibition
of splices). The estimator is not in a position to make • end bearing sleeve
these decisions.
Detailed descriptions are given in the Concrete Rein-
forcing Steel Institute’s publication, “Reinforcement An-
Length of lap chorages and Splices.”
Once the estimator has determined where the splice It is the job of the architect-engineer to indicate where
is, he must determine its length. If the splice lengths are butt splices are required and to further define whether
specified as a certain number of bar diameters for all they are to be end bearing (compression only), metal
splices (33 percent of jobs in survey) or clearly dimen- filled sleeves (compression only), or tension splices. For
sioned on the plans and sections (16 percent) there is
no problem. If the splice is specified as Class A, B or C ac-
* “Building Code Requirements for Reinforced Concrete (ACI 318-77)” is spe-
cording to ACI 318 (17 percent) the estimator must cal- cific regarding “top reinforcement” requiring a multiplier of 1.4 and defining
culate this length or have look-up tables such as those top reinforcement as horizontal reinforcement so placed that more than 12
in the ACI Detailing Manual—1980. Even then there are inches of concrete is cast in the member below the reinforcement. However,
the commentary to the code states that “Recent research studying other mat-
questions, as spacing and edge cover are variable, and a ters has seemed to reflect a lessening of this effect when the horizontal ‘top’
reduction can be made when spirals are involved. An bar is in a wall or wall-like beam with multiple runs of other horizontal bars
estimator would normally apply the “top bar” factor re- plus vertical bars and/or ties and stirrups. This suggests that some water and
air may be entrapped by other reinforcement and not be free to reach the
quired by the code* to all splices with more than 12 inch- ‘top’ bars.” However, judgment regarding interpretation of these provisions
es of concrete under the bars. Howe ve r, he may have a should be made by the designer, not the estimator.
tension splices, the engineer decides whether they must
develop 125 percent of minimum specified yield
strength (per ACI 318) or the minimum ultimate tensile
strength (per ACI 359 and others). If splices must be stag-
gered, the designer must also indicate this as well as the
amount of stagger.
The estimator must know which kinds of splices are
permitted as this affects his estimate. The firm for which
he is doing the estimating may include the splice sleeve

Figure 4. Extra column ties may be required at the location


of bends in column steel which is offset bent, as shown in
this detail reproduced from the ACI Detailing Manual.

Figure 3. Anchorage for dowels in Drawing A would probably


be estimated exactly as shown, whereas for the deep
footing (B) a check of the required anchorage length might
be made by the estimator. This makes it all the more important that the designer
should indicate his wants clearly and concisely.
If a straight bar length of anchorage or embedment is
itself in the bid or may only include special end prepa- shown and the contract drawings are not specific as to
ration of the bars, if required. If the sleeve is included, amount, the estimator figures either all the way to the
the estimator obviously must figure the quantity of bottom of the footing (the usual way) or assumes ten-
splices required for each bar size and must follow rea- sion bar anchorage. He is never in a position to assume
soning similar to that for lapped splices. Even if others compression anchorage.
are furnishing the splice sleeve, the estimator must de-
termine any end preparation necessary and the quanti-
ty of ends involved for each bar size. COLUMN TIES
The estimator must determine the size, length and
ANCHORAGES quantity of column ties. Where the contract documents
Anchorages are usually not a problem for the estima- are complete with schedules and typical column details,
tor since he generally is able to follow the contract doc- this is fairly straightforward. Howe ve r, where no typical
uments. When hooked anchorages are specified they sections are shown, the estimator does have decisions to
probably would be estimated without regard to whether make. He either must contact the architect-engineer for
the minimum code anchorage lengths have been pro- clarification or assume an arrangement such as shown
vided. Usually the hooks are on beam or slab bars shown in Figure 4 for multiple story heights, which has been
anchored fully into the support. Column dowels are taken from the ACI Detailing Manual. These details as-
sometimes a problem. Figure 3A shows a dowel appar- sume that at least some of the vertical column bars are
ently extending down to the footing mat reinforcement, offset bent and that extra ties are required at the bend lo-
with a standard 90-degree hook. In this case, the esti- cation. This is true of the majority of building designs. If
mator would probably figure it just that way, regardless butt splices are involved, the estimator has to make an-
of whether the anchorage length exceeded or even met other decision: whether to add extra column ties adja-
code requirements. However, if the footing or mat depth, cent to the butt splice, as shown in Figure 5. The extra
as illustrated in Figure 3B is very large, the estimator ties are presumably required to replace ties eliminated at
might check the required anchorage length per CRSI Re- the splice. This is a judgment call and depends on the
inforcement Anchorages and Splices or the ACI Design tie spacing and the length of the splice sleeve. Ne ve rt h e-
Handbook (SP 17) to determine if he should use it. Inci- less, it is possible that tie spacing is large enough so that
dentally, these two documents are not in agreement. no ties would be eliminated by the splice. This becomes
Figure 5. Extra ties may also
be required in the region of
butt splices in column bars,
presumably to replace ties
which may have been
displaced by the splice
location.

more complicated if the splices are staggered. It is espe-


cially important that the estimator be accurate with ties,
as all ties (and stirrups) are subject to the light bending
extra and affect the quoted price out of proportion to Figure 6. Supports for bars in foundation mats and slabs on
their weight. ground include individual high chairs with sand plates for
soil bearing (HCP) and continuous high chairs for upper bar
BAR SUPPORTS support (CHCU). Standees—reinforcing bars fabricated to
order with bent legs resting on lower mat of bars—are also
Suppliers of reinforcing bars frequently include as part
used. Dowel blocks are common in western areas of the
of their service a quantity survey for bar supports. Bar United States. Drawing from CRSI Manual of Standard
supports may consist of concrete, metal or other ap- Practice.
proved materials. Standard specifications for wire bar
supports are included in the CRSI Manual of Standard
Practice, which is revised periodically to reflect latest
practice. The contract documents should indicate types survey for one-way supported slabs, if not otherwise de-
of bar supports permitted and for wire supports, the fined in the contract documents. When estimating the
class of protection. Most widely used are standard i ze d bar supports for the top reinforcement, he could figure
factory-made wire bar supports and reinforcing bars. continuous high chairs or individual high chairs with #4
After identifying the types of bar supports permitted support bars. Economy usually determines his decision.
and the class of protection required, the estimator must Where it is feasible to use a temperature bar as a sup-
make a quantity survey. He will base his quantities on re- port bar, individual high chairs will almost always be
quirements shown in the contract documents or as cov- more economical for building slabs. In certain areas of
ered in the CRSI Manual of Standard Practice. This in- the country continuous high chairs, with runners, are
volves first determining the number of rows of supports specified for bridge decks to support the top mat from
required. In continuous elements such as slab bolsters the bottom mat of rebars, where an all-straight-bar de-
or rebar support bars the number of rows must be con- sign is involved. The estimator would figure on the con-
verted into lineal feet. For individual elements such as tinuous chairs in this instance as a contract requirement.
high chairs or rebar “standees,” the number of pieces per Furnishing of spacers against vertical or sloping forms
row must also be determined. to maintain prescribed side cover and cross position of
Unless otherwise shown in the contract documents, reinforcing bars has not been standardized within the
the estimator would figure bar supports for slabs on reinforcement industry. Estimating or detailing such
grade for support of top bars only. For foundation mats spacers with the reinforcement is not a normal industry
more than 4 feet thick, supports are not normally practice, and the CRSI manual indicates that they are to
provided for top bars. The estimator would usually take be furnished by the general contractor (see related arti-
off individual standees spaced at 4 feet in each direction cle on page 825).
and assume that bars in the top mat in one direction
(approximately every 4 feet) would be lowered two SUMMARY
bar diameters to be used as a continuous horizontal An attempt has been made to give some insight into
bar support. the business of making a quantity survey (estimating) of
The estimator has a choice, when making a quantity reinforcing bars. Only a few of the many variables have
been briefly touched on. It has been said many times their office at 180 North LaSalle Street, Chicago, Illinois
that an estimator’s quantity survey may determine (1) 60601.
whether the rebar fabricator is successful in securing a ACI Detailing Manual—1980 is available from Concrete Con-
certain contract and (2) whether it turns out to be a prof- struction Publications, 426 S. Westgate, Addison, Illinois
60101 for $39.95 postpaid; check should accompany order.
itable contract or not. In other words, the rebar estima- ACI members may wish to order directly from ACI to obtain
tor is a very important cog in the reinforced concrete member discount.
construction wheel.

Editor’s note: PUBLICATION#C810793


Publications of the Concrete Reinforcing Steel Institute cited Copyright © 1981, The Aberdeen Group
in this article are for sale by CRSI. Address all inquiries to All rights reserved

Potrebbero piacerti anche