Sei sulla pagina 1di 6

IN-SERVICE PARTIAL DISCHARGE TESTING OF GENERATOR INSULATION

M. Kurtz and G. C. Stone, Ontario Hydro, Research Division


Toronto, Canada
IEEE Trans. Electr. Insul, Vol EI-14 No 2, April 1979
ABSTRACT are observed, together with a power-frequency trigger signal
Progressive degradation of high-voltage generator insulation, taken from one of the filter inputs, on an oscilloscope with
whether due directly to the erosive effects of internal or slot a four-channel display as shown in Figure 2. The discharge
discharge or to other debilitating factors such as heat and patterns in Figure 3 are typical of a new and an old winding.
vibration, may be detected and monitored as a function of Experience shows that as the magnitude of the highest partial
time by in-situ partial-discharge tests. This paper describes discharge pulse increases, damage to the stator insulation
new diagnostic test techniques for assessing the condition of also increases.
generator insulation with a minimum of service interruption.
An improved means of coupling or data acquisition is
described, as well as a versatile single-channel pulse height
analyzer with characteristics adequate for a field application
of this type. Some typical test data are given. These studies
were sponsored by the Canadian Electrical Association and
are presented with their permission.

INTRODUCTION
Generator insulation systems, however perfect their initial
state, inevitably degrade in service. Heat, thermal cycling,
bar forces, vibration, mechanical shock, shrinkage of support
structure such as wedges and spacers, and the presence of a
high electric stress, act and interact to impair the integrity of
the dielectric system. At some stage, partial discharges will Fig. 1: Cable-type portable partial-discharge coupling capacitors being connected
start or begin to increase, providing an additional erosive to the three phase-conductors of a. machine prior to test.
aging factor. This usually occurs at abraded outer shielding,
in cavities or delaminations, or in the end-turn structure.
The number, magnitude and distribution of the partial
discharge pulses can conceivably identify predominant aging
mechanisms. Changes in these quantities, as a function of
machine age, become a measure of cumulative insulation
deterioration.

“CONVENTIONAL” DIAGNOSTIC TEST


A relatively inexpensive technique for the detection and
display of partial-discharge pulses in generators has been
developed and used by Ontario Hydro for over 20 years for
the assessment of stator insulation condition [1]. In its present
form, portable discharge-free coupling units, fabricated from
Fig. 2: Typical display showing the partial discharges from three phases of a
approximately 2.5 m looped lengths of single conductor machine and one power-frequency reference signal.
27.6 kV concentric-neutral power cable are used, one for Tests are usually done with the machine (a) isolated from
each phase of the generator as shown in Figure 1. the system, (b) synchronized at no load and (c) a full load.
The core conductors of the cables are connected to In many cases, a skilled operator can distinguish between
the generator’s respective terminals at any conveniently pulses originating in the machine winding and external noise
accessible point on the machine side of the disconnecting entering from the power (?). Large differences between the
switch. The cable shields, the “low” sides of these high data for the (?) test modes may be caused by movement
voltage coupling capacitors, are respectively connected, via of bars in response to dynamic forces as the load changes.
lengths of shielded coaxial cable, to three five-stage RC high These movements result in a change in the contact resistance
pass filters with a cut-off at about 30 kHz. After the machine between the bar shielding paint and the iron in the (?).
is brought up to rated speed and voltage, the filter outputs causing discharges in the slot to change. Such (?) are subject
to abrasion, cumulative damage to shielding, increasing slot 3. Interruption to service is required. Though a Machine
discharge with further (?). more loosening, more movement need not necessarily be at standstill, it is desirable, from
and the beginning of a runaway condition to failure. safety considerations, to isolate the machine and open the
The major limitations of “conventional” partial-discharge field breaker before connecting or removing the portable
tests are: coupling capacitors.
1. Noise originating from external sources, whether from 4. The portable couplers must be maintained in a safe
other equipment in the station, or from the power system condition. Periodic high-voltage testing is required to
in the synchronized-mode tests, tends to mask the desired ensure that the couplers are discharge-free at 150% of
information. Such external noise can be as much as Maximum operating voltage.
an order of magnitude higher than the pulses related to
discharges in the machine. The phase position and the To overcome these limitations the Canadian Electrical
general shape of the “external noise” pulses may be the Association undertook the sponsorship of the development
same as the “internal noise” pulses. (The pulse shapes are of a more objective technique making use of recent advances
indeed largely a characteristic of the generator, and the in digital methods.
coupling and filtering equipment characteristics.)
2. The discharge pulses, with rise times in the nano-second PULSE HEIGHT ANALYZER
range, usually do not recur at the same phase position in Examination of the oscilloscope displays of discharge pulses
successive cycles of power frequency. Estimation of the from different machines, insulated with a variety of systems
highest pulse magnitude is difficult and test results tend subject to different kinds and degrees of damage, discloses
to be highly subjective, i.e., different operators report subtle differences not easily characterized by quantities such
different data. Capturing of the highest pulses with an as maximum pulse height and the like, and often not readily
oscilloscope camera, even with fast film, is uncertain and captured on film. There is clearly more information is the
undependable. pulse pattern than even a trained eye can realize. A method
of quantizing the data in the discharge pattern is required for
future correlation with Insulation condition.
A versatile dual-polarity single-channel pulse height
analyzer has been built to study the characteristics of discharge
pulses, particularly the uniqueness and repeatability of the
pulse height distributions. This Generator Corona Analyzer
(GCA) is designed specifically to accommodate the short
rise time and high repetition rate (multiple sites) of these
pulses and to be insensitive to “ringing”.
The GCA receives data from the high-pass filter Mentioned
above and counts the number of pulses during a one-second
interval which fall in the “window” between lower and upper
thresholds, manual 1’y variable from O.I to 1.4 V in 0.1 V
steps, with a 0.1 V interval between the thresholds. (These
values were selected after some experience with the first
prototype circuit which permitted continuous independent
variation of these thresholds.) A manual scan with a threshold
selector switch permits a complete pulse height analysis in
about 2 minutes. A “phase window”, adjustable in width and
position relative to the power frequency cycle, allows pulse
counts to be made in any desired portion of the cycle.

Fig. 3: Partial discharge displays, one phase only, of asphaltic-mica insulated


windings. These are from two identical machines. The upper trace is from a 3
year old winding, the lower from a 24 year old winding.
of the output pulse from B Bust be set greater than the sum
of A’s output width and the signal rise time. This concept has
been used elsewhere [2].
A cross-inhibit feature between the above positive-pulse
channel and a similar negative-pulse channel, prevents either
channel from functioning for 3 us after the first channel has
been triggered, to avoid false counts due to opposite polarity
voltage swings in the partial discharge pulse. (Individual
partial discharge pulses are oscillatory, generally with a
duration of less than 1 us. Observation of partial discharges
on many different machines indicates that two consecutive
Fig. 4: Simplified schematic of analyzer. pulses are rarely less than 10µs apart.) In practice, the circuit
requires an overdrive of 20 mV for 25 ns to count a pulse,
and pulses separated by 5 us or more can be resolved.

Fig. 6: Typical GCA Pulse Height Distribution, Mountain Chute GS, Unit 2,
Blue Phase.
Fig. 5: Sequence of analyzer’s operation. Only pulses greater than the tower
threshold produce trigger signals. It is interesting to note that the magnitudes of pulses in the 10
The circuit uses two types of high-speed TTL 1C logic to 15 counts per second region correspond to the maximum
devices: fast comparators and “non-retriggerable, edge- pulse magnitudes observed in the “conventional” test.
triggered” monostables which can also be inhibited by an
appropriate logic signal. NOISE CORRECTION
The operation of the magnitude window for the positive- From basic considerations, partial discharges occurring
positive-pulse channel may be explained with reference during the rising portion of the applied high voltage wave,
to Figure 4. Monostables A and B are only triggered by a are detected as negative pulses, and vice versa. The GCA
positive pulse. C is triggered only when both the inhibit phase window may be adjusted so that in a sequence of
signal is removed and a negative wave front appears at the pulse counts, one may record the distribution of positive
trigger input. and negative pulses in the rising and falling portions of the
The sequence of operations for a pulse with a peak power frequency cycle, respectively. On the assumption that
magnitude falling within the window is shown in Figure unwanted noise is more or less uniformly distributed in both
5(a). The pulse triggers an output from comparator A only, half cycles, a net distribution may be derived which ore truly
while the inverted output from mono-stable B remains high represents the discharge situation in the insulation system.
since it was not triggered, thus failing to inhibit C. When A Typical data obtained in this way are shown in Figures 6
returns to the low level, monostable C is triggered by the and 7. A calibration procedure to be described later, permits
negative front, its output activating a pulse counter. Until conversion from a mV to a pC base.
non-retriggerable monostable A returns to the low level, it Correction for transient noise occurring at the time of
cannot perceive input signals, thus ignoring ringing for a measurement is achieved by a simultaneous display, renewed
preselected time, in this case, 3µs. every second, of the count of a selected pulse polarity in both
When the input pulse exceeds the upper threshold, as the rising and falling portions of the power frequency cycle,
shown in Figure 5(b), both A and B are triggered. Since B’s both counted in the same one second interval.
output is now low, C is inhibited from triggering when A’s This noise correction technique may be only partially
output drops; hence the counter is not activated. The width effective because the external noise (discharges on the
incoming transmission lines, transformers, bus work) tends COUPLER CONSTRUCTION
to be phase-oriented in exactly the same way as the generator Essentially high-voltage power cable splice materials and
insulation discharge pulses. Yet one invariably finds that techniques are employed. A sufficient thickness of self-
the count in the “expected” polarity far exceeds the other. amalgamating insulating tape to insulate for 4 kV (about 2
A more effective approach to noise elimination is described mm) is applied first over the jumper insulation for a length
below. limited only by the local geometry (typically 20 cm). Over
this insulation, a semi-conductive, self-amalgamating tape
and tinned copper braid sandwich provides a discharge-free
capacitor electrode. The capacitance of the coupler is adjusted
to match symmetrical pairs to within about 2%. Depending
on the jumper length, a typical coupler capacitance will be
in the 70 to 90 pF range. The centre conductor of a co-
axial cable (RGS8C/U) is soldered to the braid and securely
fastened in place, as shown in Figure 9. The shield is
removed to a point beyond the braid and left open at this end.
Insulating tape is applied overall for mechanical security and
a final finish layer similar to that normally used over jumpers
may be used.

Fig. 7: GCA Pulse Height Distribution, Barrett Chute GS, Unit 4, Red Phase.

PERMANENT COUPLING CAPACITORS


Permanent capacitive coupling devices may be installed in the
winding itself, on the circuit ring bus, or on suitable jumpers
between coils or coil groups. Such couplers permit observation
of the discharge condition in a machine in the presence of
external noise, and with no interruptions to service, though
some load variation during tests my be advantageous to
search for loose bars. These may be fabricated quite simply,
at least on hydraulic units, by applying a conductive layer Fig. 8: Schematic of permanent couplers in machine splits.
over the bus or jumper insulation in a convenient location
and providing for connection to detection equipment. The co-axial cables from all installed couplers are trained and
If the permanent couplers are placed at corresponding secured to a common junction box, external to the machine,
points in a pair of parallels or “splits”, equidistant from the where each cable is terminated with a 50-ohm resistor and
machine terminal, “differential” noise rejection is possible. connected to a BNC connector. This resistor eliminates
(In cases where the circuit ring bus lengths are unequal, the reflections and keeps the 60 Hz potential on the coupler and
difference may be compensated by suitable delay lines to the cable down to less than a volt. It is important to note that the
differential amplifiers.) A differential amplifier as shown in cables from symmetrical coupler pairs must be matched in
Figure S will eliminate not only external or common-mode length to better than 1 m.
noise, but also the power frequency and its harmonics, so
that a filter with its associated signal distortion is no longer PERMANENT COUPLER EVALUATION
required. Tests on generators with permanent couplers demonstrated
It may be noted that pulses from a third split, entering that pulses applied at the machine terminal were rejected in
via the circuit ring bus, may be rejected like common-mode the differential mode and could not be detected. However,
noise. Thus in order to survey a machine winding completely, pulses injected near one of the couplers in a pair could be
every split must be equipped with a permanent coupler. observed directly on an oscilloscope, chiefly because the
Couplers were installed initially on the six splits in one difference in arrival time (50 ns) at the two couplers, and
phase of a 13.8 kV hydraulic machine. These were placed on hence at the differential amplifier inputs, resulted in a net
coil group jumpers half way down the winding between line signal. Note that the polarity of an observed pulse depends
and neutral where the jumper conductor operates at about 4 on the source split as well as its phase relative to power
kV to ground at 60 Hz frequency.
Effective noise rejection and correlation with conventional
techniques were demonstrated with permanent couplers GCA. Some 60 machines have been tested with this technique
installed on four machines. to date, though the opportunity has not yet arisen to make
Inherent in the Use of the permanent couplers on all splits measurements on a machine before and after maintenance,
is the capability, by observing pulse polarities, of identifying such as re-wedging or the like. Good correspondence has
the location of the source of anomalously high pulses to been noted between the new and the “conventional” test
within possibly a few coils at the line end of a single split. data.
The “conventional” test, using portable couplers and the
oscilloscope display, has correctly identified windings in
the process of deterioration. Test data have ranged from 10
to 20 mV on machines considered to be in good running
condition, to 50 mV to 500 mV (2000 to 5000 pC, depending
on individual machine Vibrations) for machines in trouble.
One large hydraulic generator suffering from severe ground
wall erosion failed within a few months of the 50 mV
measurement.

Fig. 9: Unfinished permanent coupler installed on jumper in generator winding.


Kote the co-axial cable attachment.

CALIBRATION
The conversion of test data in terms of millivolts of
deflection on an oscilloscope screen, into apparent charge in
picocoulombs is of paramount importance for rendering the
data “independent” of the detection equipment parameters, Fig. 10: Calibration of pulse voltage magnitudes into picocoulombs. The lower
machine size and the loading effects of connected bus, etc. trace shows the front of a negative square wave which is applied through a 50 pF
ideating capacitor. The response through the filter is shown in the upper trace.
For this purpose, it is necessary to inject a known charge
The injected charge, about 200 pC, yields a calibration in this case, of 20 pC/mV.
at the machine terminals and to note the response on the
For several machines, maximum pulse height has been
detection equipment.
decreased by an order of magnitude following treatment such
A simple means of injecting such a pulse is achieved by
as slot wedge tightening, re-finishing of semi-conductive
isolating about 15 cm at one end of the shield on a portable
slot paint, injection of semi-conductive silicone rubber in
discharge coupler by separating the concentric neutral
slot sides, etc. [4].
conductors and cutting a I mm gap in the extruded shield
of the cable. This provides a 30-pF high-voltage coupling
CONCLUSIONS AND FUTURE WORK
capacitance through which a suitable square wave may be
The goal of a more objective and reliable test method with
supplied via a length of co-axial cable, for calibration [3].
reduced system cost and independence from the interfering
A 50-Q terminating resistor, connected to the co-axial cable
effects of external noise has been achieved. Further
at the coupling capacitor, limits the 60 Hz rise in potential
refinement and time reduction for the test is possible using
of the HV cable shield to the order of 4 mV for a 13.8 kV
a multichannel analyzer. A commercial analyzer has been
generator winding, and eliminates reflections.
modified to accept pulses at intervals down to about 10
A typical input square wave and output response is shown
us, yielding test curves identical to those obtained with the
in Figure 10. A 200 ns rise time was selected since faster
single-channel Generator Corona Analyzer, but in a much
fronts produced unacceptable, ringing in the response.
shorter time.
Typical calibrations obtained to date range from 10 to 35 pC
A prototype system has been demonstrated using a
per mV, depending on the machine size. A pulse generator at
programmable calculator and a fast digitally controllable
a repetition frequency of 5 kHz, capable of driving 50 Ω to
counter for the permanent installation and continuous
20 V, has been built into the GCA and may also be used to
pre-programmed periodic monitoring of discharge pulse
check its operation.
distribution as a function of load and time.
Now that data may be obtained in a consistent and
TEST RESULTS
repeatable manner, the enormous task remains of collecting
Pulse height distribution data is being collected using the
data from the field and establishing correlations with
observed insulation damage in service as a function
probably of the type of insulation system in question. When
such correlations are confirmed, early warning of incipient
problems will hopefully be obtainable so that suitable repair
and maintenance work may be scheduled.

REFERENCES
[1] M. Kurtz, “A Partial Discharge Test for Generator
Insulation,” Ontario Hydro Research Quarterly, Vol. 23, No
4, 1973, pp 1-4.
[2] H. A. Cole, “A Differential Pulse Height Discriminator,”
Nuclear Instrumentation and Methods, Nov. 1976, p 551.
[3] “Detection and Measurement of Discharge (Corona)
Pulses in Evaluation of Insulation Systems, ASTM 0 1868,
Part 39.
[4] M. Kurtz and J. F. Lyies “Generator Insulation Diagnostic
Testing”, IEEE Paper So. F7918S-0, PES “Winter Meeting,
New York, N. Y., Feb. 1979.

This paper was presented at the 1978 International


Symposium on Electrical Insulation, Philadelphia, June
1978.

Manuscript was received 11 August 1378, in revised form 30


November 1978.

Potrebbero piacerti anche