A B C D E F G H I J K

1
2 Provincial Government

3 Ministry of Physical Infrastructure Development


4 Province -2 Janakpurdham

5 Detail Estimate
6
7 Name of work: Repair and Maintenance of Roof Slab of APF Building.
8 Name of office :
9 Location :
10
11 Description of work No Length Breadth height Quantity Remarks
12 1 Dismantaling of existing plasster
13 Roof of APF Building
14 1.00 15.80 11.40 180.12
15 1.00 15.90 11.40 181.26
16 total 361.38 m2
R.C.C work in all P.C.C (1:1.5:3) work on the existing
17 2 slab including supply of materials all complete.
18 Slab1 top 1 15.80 11.40 0.07 12.608
19 Slab2 top 1 15.90 11.40 0.07 12.688
20 Water tank base slab 2 1.20 1.20 0.10 0.288
21 Staicase base 1 1.20 1.20 0.10 0.144
22 total 25.728 m3
23 3 1st class brick work in 1:6 c/s mortar :
24 Tank support walls 4 1.20 0.25 0.60 0.72 m3
25 total 0.720 m3
26 4 12.5mm thick plaster in 1:4 c/s mortar :
27 slab top 1 15.80 11.40 180.12
28 1 15.90 11.40 181.26
29 support walls 8 1.20 0.60 5.76
30 8 0.30 0.60 1.44
31 total 368.58 m2
32 5 Formwork :
33 Slab sides total =86.20m 1 86.2 0.07 6.034
34 water tank base 2 1.20 0.70 1.68
35 sides 2 4.80 0.10 0.96
36 Total 8.674 m2
Supplying and laying reinforcement steel for RCC
37 6 work :
38 slab 8 mmdia. Steel @ 15cm c/c, Main b 76 15.75 1197.00
39 76 15.85 1204.60
40 slab 8 mmdia. Steel @ 15cm c/cdistribution bars 105 11.35 1191.75
41 106 11.35 1203.10
42 water tank slabs, Main bars 8mm dia @10 cm c/c 24 1.15 29.90
43 distribution bars 8mm dia @ 10 cm c/c 16 1.15 20.70
44 Staircase base , main bar 8mm dia @10cm c/c 24 1.15 14.95
45 distribution bar @10 cm c/c 24 1.15 14.95
46 total 4876.95 m
47 total 1923.39 kg
48 7 3mm cement sand punning in 1:1 c/s mortar :
49 Slab top 1 15.80 11.40 180.12
50 1 15.90 11.40 181.26
51 total 361.38 m2
52 8 Railing work:
Supplying & fixing work of 38 mm Ø stainless steel pipe post @
2.0 mtr , 38 mm Ø stainless steel pipe hand rail with two rows 25
53 mm Ø stainless steel pipe in between ground & hand rail. 1 54.50 0.9 49.05 sqm
54 total 49.05
9 Supplying,fitting & Erection of steel Spiral
55 Staircase as per specifications. 1 3.00 3.00 m
56
A B C D E F G H I J K
57
58
59
60 Provincial Government
61 Ministry of Physical Infrastructure Development
62 Province -2 Janakpurdham
63 Detail Estimate
64
65
66 Name of Work : Construction of Waiting Room
67 S.N. Description of work no Length Breadth Height Quantity Remarks
1 Earthwork Excavation for Foundation in
68 Ordinary soils
69 For Post 6 0.40 0.40 0.60 0.58
70 wall 6 2.25 0.35 0.44 2.08
71 Stair 1 0.90 1.50 0.14 0.19
72 total 2.85 m3
73 2 Back filling
74 Wating Room 1 Area= 18.24 0.45 8.21 m3
75 4 Brick soling work
76 For Post 6 0.50 0.50 1.50
77 wall 6 2.25 0.35 4.73
78 Stair 1 0.90 1.50 1.35
79 Wating Room 1 Area= 18.24 18.24 m3
80 total 25.820 m3
81 5 PCC work in 1:2:4
82 Post 6 0.30 0.30 0.95 0.51
83 post Footing 6 0.50 0.50 0.15 0.23
84 wall 6 2.25 0.35 0.08 0.38
85 Stair 1 0.90 1.50 0.08 0.11
86 Wating Room 1 Area= 18.24 0.08 1.46 m3
87 total 2.690 m3
88 Formwork
89 For Post 6 0.30 0.95 1.71
90 total 5.970 m3
91 6 1st class brick work in 1:6 c/s mortar
92 wall 6 2.25 0.23 0.75 2.33
93 Stair 1 0.60 1.50 0.45 0.41
94 total 2.740 m3
7 12.5mm thick cement plaster in 1:4 c/s
95 mortar
96 wall outside 6 2.25 0.45 6.08
97 Stair 1 1.05 1.50 1.58
98 Wating Room 1 Area= 18.24 18.24 m3
99 total 25.900 m2
100 8 3mm thick cement punning in 1:1 c/s mortar
101 Wating Room 1 Area= 18.24 18.24 m3
102 total 18.24 m2
13 Supplying & fixing of rafter,purlin & post for
supporting of trusses including all other nuts
& bolts & prefabrication of pipes required all
103 complete
104 Waiting room shade
105 90 mm black pipe vertical post 1 3.6 6.35 22.86
106 65 mm vertical post 6 2.90 4.19 72.9
107 65mm rafter 6 3.1 4.19 77.93
108 38*38*2.9 mm square pipe purlin1 1 15.9 3.03 48.17
109 38*38*2.9 mm square pipe purlin2 1 9.9 3.03 29.99
110 38*38*2.9 mm square pipe purlin3 1 3.66 3.03 11.08
111 Total 262.930 Kg
A B C D E F G H I J K
10 24 Gauge CGI Sheet Roofing with all
necessary fittings, hooks and nut bolts all
112 complete.
113 Wating Room 1 Area= 26.50 26.50 m3
Supply and laying 24gauge plane sheet at
114 11 ridge joints 6 3.1 18.6
115 total 18.60 Rm
116
117
118 Construction of Watch tower (Centry Post)
119 s.n. Details of work No Length Breath Height Quantity Remarks
Siteclearance work by removing bush and
16.00
120 1 levelling . 1 4 4
121 Sub Total 16.00 m2
122 For 7NOS 112.00
123 2 Earthwork excation in ordinary soils.
124 Foundation of post 4 1.00 1.00 1.00 4.00
125 Sub Total 4.00 m2
126 For 7NOS 28.00
127 3 Brick Soling work in foundation. 4 1.00 1.00 4.00
128 Sub Total 4.00 m2
129 For 7NOS 28.00
Brick masonry work in 1:4 Cement sand
130 4 mortar
131 wall 4 2.40 0.23 0.24 0.53
132 Sub Total 0.53 m2
133 For 7NOS 3.71
134 5 PCC WORK in 1:2:4
135 post 4 1.00 1.00 0.08 0.32
136 Sub Total 0.32 m2
137 For 7NOS 2.24
138 6 PCC WORK for RCC in 1:1.5:3
139 For Footing
140 for rectangular part 4 1 1 0.2 0.80 -
141 for trapezoidal part 4 1 0.25 0.2 0.47 -
142 For Column
143 4 0.35 0.35 0.47 0.23
144 For Plinth Beam 4 1.85 0.23 0.23 0.39
145 Sub Total 1.89 m2
146 For 7NOS 13.23
Tor /TMT Reinforcement work for R.C.C work including supply,
straighting, cutting, bending, binding and laying of different
7
diameter steel rod in all types of R.C.C work as per design
147 ,drawing ,specification and instruction all complete work
148 1.7% of PCC 281.89 kg
149 Sub Total 281.89 m2
150 For 7NOS 1973.23
151 8 Formwork
152 For Footing
153 for rectangular part 16 1 0.2 3.20 -
154 For Column
155 16 0.35 0.47 2.63
156 For Plinth Beam 8 1.85 0.23 3.40
157 Sub Total 9.23 m2
158 For 7NOS 64.61
9 Making Centry post by black Iron
Pipe(medium) vertical 100 mm
dia.member,50mmdia cross,25mm dia
roofing member,Iron staircase with railing,
159 24gauge G.I.Sheet roofing all complete.
160 a) 80mm dia vertical post 4 8.00 8.48 271.36
161 horizontal upper frame 8 2.10 8.48 142.46
162 b)50mm dia across 24 2.60 5.90 368.16
163 horizontal bar 24 2.10 5.90 297.36
164 staircase hand railing 1 12.00 5.90 70.80
A B C D E F G H I J K
165 staircase frame 1 26.00 5.90 153.40
166 c)25mm dia vertical bar 48 0.90 2.75 118.80
167 60 0.90 2.75 148.50
168 roof member 4 1.90 2.75 20.90
169 4 1.60 2.75 17.60
170 4 1.50 2.75 16.50
171 Sub Total 1625.84 m2
172 For 7NOS 11380.88
10 Providing & laying 24 gause G.I.sheet
roofing with all necessary fittings all
173 complete.
174 4 1.80 1.90 13.68
175 Sub Total 13.68 m2
176 For 7NOS 95.76
11 Providing & laying 24 gause G.I.sheet at
177 ridge with all necessary fittings all complete.
178 4 3.00 12.00
179 Sub Total 12.00 m2
180 For 7NOS 84.00
181
182 ELECTRICAL WORKS
183 1 a)8-22 wattC.F.L.Lightwork all complete. 2x7 14.00 nos
b)300/500 watt Hologen light wipro/GE or
184 equivalent all complete. 1x7 7.00 no
185 c)3/22 copper wire Nepal,NS equivalent. 1x7 10.00 70.00 no
d)7/22 PVC Copper wire Nepal, NS
186 equivalent. 1x7 40.00 280.00 rm
e) 2 gangone way switch CPL/Anchor,S etc all
187 complete. 1x7 7.00 no
188 f) 4 way SPN DB Double Cover. 7x1 7.00 no
189 g) 6-32 Amps SP MCB 7x2 14.00 nos
190
191
192
193
194
195 Barbed wire Fencing Work
196 Ja. Chu. Ka. Ltd Compound
197
198 S.N. Description of work No Length Breath Height Quantity Remarks
1 Site clearance work by removing bush and
199 levelling .
200 2 1800.00 2.00 7200.00
201 total 7200.00 m2
202 2 dismantaling of brick masonry work:
203 900 0.30 0.25 0.30 20.25
204 total 27.47 m3
3 Supplying & fixing work of 50 mm Ø MS black pipe @ 2.0 mtr
with 10 S.W.G.G. I. Chain Link 2"x2" mesh size fixing in
4x20x20 mm & 4x25x25 mm ms angle frame & top 3x20 mm
205 MS grill 15 cm height .

206 500 0.6 300.00


207 total 300.00 sqm
3 Fabricating, supplying & fixing of different size M.S. angle of
208 25*25*4 mm and 2'6'' length at spacing of 2m

209 650 weight= 1.064 691.60


210 total 691.60 kg
3 Supplying and fixing of Barbed wire 12 gauge including hooks,
211 nails etc

212 6500 6500.00


213 total 6500.00 rm
214 5 PCC 1:2:4 mix to fix the angels in posion.
215 900 0.30 0.25 0.3 20.25
A B C D E F G H I J K
216 total 20.25 cum
217 6 Formwork :
218 1800 0.3 0.3 162.00
219 total 162.00 m2
7 Plastering in 1:4 cement mortar to Repair at
220 different sections
221 1800 0.3 0.3 162.00
222 total 162.00 m2
8 2 coats weather proof painting work over
primer coat of approaved colour and shade
including cleaning scaffolding with supply of
223 materials all complete.
224 inner and outer face 2 1800.00 1.80 6480.00
225 total 6480.00 m2
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
A B C D E F G H I J K
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
L M N
1
2

5
6
7
8
9
10
11
12
13
14
15
16

17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36

37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52

53
54

55
56
L M N
57
58
59
60
61
62
63
64
65
66
67

68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94

95
96
97
98
99
100
101
102

103
104
105 6.37
106
107
108
109
110 18.40
111
L M N

112
113

114
115
116
117
118
119

120
121
122
123
124
125
126
127
128
129

130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146

147
148
149
150
151
152
153
154
155
156
157
158

159
160
161
162
163
164

Potrebbero piacerti anche