Sei sulla pagina 1di 16

Shell U.K.

Limited

21st July 2009 Report : EP200907328245


Filing key :

HAZID AND RISK ASSESSMENT


REPORT FOR THE USE OF ALLOY
SCAFFOLDING ON OFFSHORE
FACILITIES
FINAL REPORT
First Issue

Keywords:

This document is the property of Shell U.K. Limited, and the copyright therein is vested in
Shell U.K. Limited. All rights reserved. Neither the whole nor any part of this document may
be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form
by any means (electronic, mechanical, reprographic recording or otherwise) without prior
written consent of the copyright owner.
HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON
OFFSHORE FACILITIES Page i

Distribution List
Name Reference

EP200907328245 July 2009


Page ii HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING
ON OFFSHORE FACILITIES

Authorised For Issue


Prepared by; Accepted by;

Signed : Signed :

Chris Grant (EPE-P-FP) Chris Wilson (EPE-P-ED)

Field Productivity Team Safety Engineering Team Leader

Reviewed by;

Alan Sherriff (EPE-P-ED)

Philip Brunton (EPE-S-HU)

July 2009 EP200907328245


HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON
OFFSHORE FACILITIES Page iii

Contents

BACKGROUND............................................................................................................. 4

PURPOSE OF HAZID AND RISK ASSESSMENT ....................................................... 5

KEY FINDINGS AND CONCLUSIONS ......................................................................... 5

ACTION CLOSE-OUT ................................................................................................... 5

ATTACHMENTS............................................................................................................ 6

APPENDIX 1 WORKSHEETS

EP200907328245 July 2009


Page 4 HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING
ON OFFSHORE FACILITIES

BACKGROUND
A Lean/Kaizen event was held on Brent Charlie during September 2008 which
established a number of improvement opportunites to improve HSE risk exposure
and efficiency of platform scaffolding operations. In summary these opportunities
included better planning, reduced manual handling and transportation wastes due to
more strategic storage of materials and also the use of alloy scaffold materials.

Brent Charlie had previously been testing an alloy system scaffold however the
Kaizen event established this was not fot for purpose due to its fixed dimensions and
as a result the use alloy scaffold tube was identified and developed as an opportunity.

Susequent performance tracking and analysis has demonstrated the improvements


on Brent Charlie have reduce carrying of materials by 50% and the overall task time
per m3 of scaffold has reduced by 32%.

July 2009 EP200907328245


HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON
OFFSHORE FACILITIES Page 5

PURPOSE OF HAZID AND RISK ASSESSMENT


st
A hazard identification (HAZID) exercise and risk assessment was completed on 1
July 2009 at Tullos, Aberdeen. The purpose of this HAZID/risk assessment was to
determine what hazards there are associated with using aluminium alloy scaffolding
systems offshore compared to the current practice of using steel scaffolding
systems.

A brainstorming session was used to prompt discussion of potential hazards. The


potential consequences and effects of these hazards were considered along with
the controls in place to manage them and a qualitative assessment was made of the
residual risks with these controls in place

The following personnel attended the HAZID:

Name Role
Chris Wilson Safety Engineering Team Leader
Chris Grant Field Productivity Team
Scott Fraser Brent Operations Support
Andy Fairnie SORT4 Delivery Manager (Brent)
Roger Esson SORT4 Delivery Manager (CNNS)
Hamid Iravani Corrosion Engineer
Keith Greenwood Sort 4 SHEQC Advisor

KEY FINDINGS AND CONCLUSIONS


A number of safety concerns about the use of aluminium alloy scaffolding in an
offshore environment were addressed during the HAZID and risk assessement. The
worksheets recording the discussion from the HAZID and risk assessment are
included as Appendix 1. A presentation prepared by SORT4 addressing some of
the safety concerns raised is attached to the document.

It was concluded from the risk assessment that there are no safety reasons why
aluminium alloy scaffolding should not be used on offshore facilities provided the
controls identified in the worksheets are adhered to. This primarily concerns the use
of scaffolding systems in Zone 1 hazardous areas and areas where it could be
exposed to mecury contamination.

ACTION CLOSE-OUT
The following actions were raised during the HAZID and risk assessment session.

Responsibility for the close-out of the actions rests with Roger Esson, SORT4
Delivery Manager with Chris Grant, Field Productivity Team acting as close-out co-
ordinator. Unless otherwise agreed with the co-ordinator, all actions should be
st
targeted for completion by 1 September 2009.

EP200907328245 July 2009


Page 6 HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING
ON OFFSHORE FACILITIES

ATTACHMENTS
Presentation prepared by SORT4 addressing concerns raised about the use of
aluminuium alloy scaffolding systems in an offshore environment.

Scaffold Alum
Alloy.ppt (Compr...

July 2009 EP200907328245


HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON
OFFSHORE FACILITIES Page 7

APPENDIX 1

HAZARD IDENTIFICATION WORKSHEETS

EP200907328245 July 2009


Page 8 HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON OFFSHORE FACILITIES

HAZARD POTENTIAL CONTROLS RISK ASSESSMENT ACTION


CONSEQUENCES

Incendive sparking Ignition risk in As per rcommended guidance in Based on the controls outlined ACTION 1 Communicate
flammable gas Hazardous Are Code IP15 the risk of incendive spark requirement for Cat 2 Hot
environment “Standards for electrical and non- igniting flammable gas cloud on Work WCC for alloy
electrical equipment for use in our facilities is considered to be scaffold use in Zone 1
Incendive sparking is hazardous areas place very low and is acceptable. areas.
initiated by an exothermic restrictions on the use of light
reduction of iron oxide (in the metals on the outside of
Ignition of other Allloy scaffolding is already Risk assessment for use
form of rust) by aluminium equipment to prevent this risk. For
flammable materials being used in other areas of the of alloy in zone 1 areas to
particles. Three basic the same reason, the use of
e.g. oily rags. offshore industry e.g. Norway be built in to ISSOW
mechanisms produce the aluminium ladders or scaffolding and there is no evidence that system.
pre-requisite conditions for may create an ignition source, incendive sparking is a source
incendive sparking. The first and this should be considered of ignition of hydrocarbon C. Grant to action with
is single impact sparking and before they are used in a Zone 1 releases. Production Services
requires relatively high area.” ISSOW owners.
energy (minimum 300
To manage this risk it is The main risk associated with
Joules). Subsequent impact
recommended that Cat 2 hot work incendive sparking is associated
sparking may occur from
Work Control Certificate (WCC) is with erection and dismantling of
striking a previously
used for alloy scaffold in zone 1 alloy scaffolding rather during
deposited aluminium smear
areas. it’s use for work activities. This
resulting from an earlier
is covered by the Cat 2 Hot
impact of an aluminium
Alloy scaffold should not be used Work WCC within Zone 1 areas
object on a rusted steel
in Zone 0 classified ares unless for erection and dismantle only.
surface. This mechanism is
the plant has been shutdown and Once scaffold is built/in place
the most probable as it
hydrocarbon free, risk is negligible.
requires much lower impact
energies (1-5 Joules) to Any other flammable materials
initiate the spark. The third e.g. oily rags should be identified
mechanism is friction and removed prior to scaffold
sparking. This type of erection/dismantling.
sparking is most unlikely to
occur as the temperature
caused by sparking are

July 2009 EP200907328245


HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON OFFSHORE FACILITIES Page 9

HAZARD POTENTIAL CONTROLS RISK ASSESSMENT ACTION


CONSEQUENCES
much too low to cause
ignition.

Corrosion due to salty Degradation of The oxide coating formed on Any degredation of the alloy will Incorporate guidance in to
environment material leading failure Aluminium and its alloys makes be a slow process. Any signs of SORT4 procedures on
which could lead to them resistant to corrosion. corrosion will be picked up by how to identify corroded
possible collapse of Surface damage to the oxide routine inspections before it alloy tubes that need to be
scaffolding coating is self repairing. becomes critical. taken out of service.
Visual inspections of erected Alloy corrosion rates are
structures are carried out weekly. ACTION Roger Esson
significantly smaller than those
for steel tube in an offshore
Materials are inspected at time of
environment. E.g. 7g/m2 alloy
build and dismantle.
versus 933g/m2 steel over an 8
Damaged materials are year period.
quarantined. Inspection carried
out by competent person.
Erected structures have a
maximum 2 year build life.
Tube conforms to European
standards for temporary
structures.

Users conform to scaff tag and


erected scaffold register systems.

Poor Scaffold Integrity due to Failure of scaffold Steel tube and Aluminium tube With adequate training, the Incorporate guidance in to
mixture of tube materials structure with potential shall not be mixed during Scaffold obvious weight difference SORT4 procedures to
(Variation in dynamic injury to personnel construction. between steel and alloy tubes ensure tube materials are
properties of steel and alloy and damage to and inspection of the build not mixed
In a designed scaffold where
should ensure the risk is very

EP200907328245 July 2009


Page 10 HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON OFFSHORE FACILITIES

HAZARD POTENTIAL CONTROLS RISK ASSESSMENT ACTION


CONSEQUENCES
tubing) equipment ladder beams are used, Scaffold low.
ACTION Roger Esson
Design Engineer sign off is
required. This applies to scaffold
structures used as lifting frames.
Scaff tag system should identify
any build issues.

Corrosion due to dissimilar Failure of scaffold Scaffold is a temporary structure Historical use of alloy lifting Confirm Alloy/Steel
metals, alloy tube and steel structure with potential and Company procedures specify beams and alloy lifting beams corrosion is not an issue
fitting fittings injury to personnel and that the erection time should not and system scaffold on Brent with the controls in place
damage to equipment exceed two years. Charlie has not identified any via Draugen experience.
corrosion problems if the
Visual inspections of erected scaffold is dismantled within
structures are carried out weekly. ACTION Andy Fairnie
this timeframe.
Materials are inspected at time of Incorporate guidance in to
build and dismantle. Introducing a sampled
SORT4 procedures to
inspection of fittings, as part of
monitor any corrosion at
Damaged materials are the weekly scaff tag
tube/fitting interface as
quarantined. Inspection carried recertification process, should
part of inspections. This
out by competent person. ensure the risk is managed.
should continue until we
can assure ourselves this
is not an issue.

ACTION Roger Esson

Human Factors –An erected Personnel feel unsafe Communication, familiarisation Genuine concern which needs Incorprate in to SORT4
alloy structure feels different to or uncomfortable and understanding of the new to be address through staff Q&A engagement pack
steel structure to walk on system. engagement
ACTION Roger Esson

Manual handling issues due to Unfamiliar with build Scaffold structures constructed in Brent Charlie pilot use analysis Review locations of
perceived additional material requirements and use line with contractor procedures – shows material carry time has scaffold storage racks to
requirements of alloy tubing alloy bay sizes are the same as been reduced by 50% and ensure proximity to

July 2009 EP200907328245


HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON OFFSHORE FACILITIES Page 11

HAZARD POTENTIAL CONTROLS RISK ASSESSMENT ACTION


CONSEQUENCES
steel scaffold bays. This means overall task time reduced by worksite.
the number of materials is the 30% through the use of alloy
same, therefore no extra manual tube and strategic storage Incorporate alloy bay size
handling. locations. guidance in to SORT4
procedures and
Alloy tube 30% of steel weight. commincate requiremts
with offshore scaffolder
staff

ACTION Roger Esson

Manual handling issues due to Injury to personnel The use of Aluminium tube With adequate training and Incorporate in to training &
an increased number of alloy caused by carrying too reduces the Manual Handling supervision the risk is very low. awareness session to
tubes being carried many tubes (which are impacts, as the Aluminium tube is provide guidance on
much lighter than approximately one third the number of tubes to be
steel) density of steel. carried.
Tubes may be slippery Introducing guidance/caps on
when wet ACTION Roger Esson
number of tubes to be carried.

Site supervision to ensure rules


are adhered to.

Envrionmental conditions should


be assessed as part of worksite
task risk assessment.

Non slip gloves such as Showa


310 or 377 should be used
accoding to wearther conditions.

Alloy tube corrosion while in Failure of scaffold The occurrence of salts, Any degredation of the alloy will Incorporate guidance in to
storage structure with potential especially chlorides marginally be a slow process. Any signs of SORT4 procedures on
injury to personnel reduces durability but Aluminium corrosion will be picked up by how to identify corroded

EP200907328245 July 2009


Page 12 HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON OFFSHORE FACILITIES

HAZARD POTENTIAL CONTROLS RISK ASSESSMENT ACTION


CONSEQUENCES
and damage to is generally better than Carbon routine inspections before it alloy tubes that need to be
equipment Steel becomes critical taken out of service.
See above corrosion mitigation. ACTION Roger Esson

Degradation of Alloy scaffold Failure of scaffold N2 spreads bunded as per Very low likelihood of liquid None required.
tube due to exposure to liquid structure with potential procedures nitrogen coming in to contact
nitrogen injury to personnel and with alloy scaffold due to bund
damage to equipment N2 spread bund is non load design.
bearing

Degradation of Alloy scaffold Failure of scaffold Hydrorcarbon systems are Based on the controls outlined Incorporate guidance in to
tube due to exposure to structure with potential flushed and purged prior to any the risk of significant mercury SORT4 procedures on
mercury injury to personnel and breaching. exposue on our facilities is how to identify corroded
damage to equipment considered to be very low and is alloy tubes that need to be
Mercury test are carried out prior
acceptable. taken out of service.
to any vessel entry activities.
Any alloy tube exposed to Allloy scaffolding is already SORT4 to verify impact of
hydrocarbon spills should be being used in other areas of the Mercury impact on alloy
removed and inspected. offshore industry e.g. Norway tubing based on exposure
and there is no evidence that levels on Shell
Link to ISSOW controls. Mercury exposure is an issue. installations by end of
August 2009.

In the interim, special


precautions should be
taken to ensure no
mercury spills occur.

ACTION Roger Esson

Erosion of Alloy scaffold tube Failure of scaffold Control measures in place for Task risk assessment and site None required.
due to exposure to blasting structure with potential blasting to prevent damage contols ensure scaffold
activities injury to personnel caused by inadvertent blasting of structures are not exposed to

July 2009 EP200907328245


HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON OFFSHORE FACILITIES Page 13

HAZARD POTENTIAL CONTROLS RISK ASSESSMENT ACTION


CONSEQUENCES
and damage to the scaffold tubes blasting.
equipment
If any tube is blasted the job
should be stopped and structure
inspected.

Visual inspections of erected


structures are carried out weekly.
Damaged materials are
quarantined. Inspection carried
out by competent person.

EP200907328245 July 2009


Page 14 HAZID AND RISK ASSESSMENT REPORT FOR THE USE OF ALLOY SCAFFOLDING ON OFFSHORE FACILITIES

July 2009 EP200907328245

Potrebbero piacerti anche