Sei sulla pagina 1di 12

1

Your customer's MySQL application is being overloaded. You determine that


more memory will alleviate the problem and decide to add more RAM to the
computer. The system currently has two sockets for memory, both of which are
occupied with 512MB DIMMs. Which of the following steps are necessary to
ensure a suitable memory upgrade?
532773 Text

1. Determine whether the memory is ECC or non-ECC.

2. Replace both current DIMMS with 1GB modules - doubling capacity.

3. Determine the speed of the motherboard and purchase DIMMS with the same rating.

4. Use memory from the same vendor as that currently installed in the server.

1, 2, 4
1, 2, 3, 4
2, 3, 4
1, 4

2
As a consultant for a new Internet based home shopping company, you are being
tasked with designing the server infrastructure to support their online systems.
Fault tolerance is critical. You want to ensure that the database is always
accessible from the web servers, and that the system can support server failures
and still provide the same throughput. Which of the following technologies would
you implement to support the server side requests to ensure both consistent
performance and high reliability?
532774 Text

Network Load Balancing


Adapter Teaming
Active/Active Clustering
Active/ Passive Clustering

3
You are advising a client on the best system to implement in terms of backup.
The customer proposes using a tape system, and intends to use GFS rotation,
with full normal backups occurring on every Friday and the last day of the
month. All other backups are incremental. No backups are performed at the
weekends. The system goes live on 1st December 2005, and runs smoothly for
several months. However, a telephone call to your offices on February 6th alerts
you to the fact that data has been lost - and the customer needs to perform a
restore. The customer tells you that the backup on the Friday preceding the
crash failed. Which of the following solutions would recover the most data?
532775 Text

Restoring the data from the 31st January tape, followed by the tape from Feb 2nd.
Restoring the data from the 27th January tape, followed by the tape from Feb 2nd.
Restoring the data from the 31st January tape, followed by the tape from Feb 1st
and Feb 2nd.
None of the above restore operations are valid

4
You are considering installing a new departmental server in your remote sales
office in Slough. The 10 sales people there do not make great demands on their
current server, but as the other regional office in Swindon is set to close, causing
an expansion at Slough, you decide that server capacity and throughout will
become more relevant. You also plan to implement a fault tolerant RAID
configuration. Which of the following might be a suitable storage choice?
532776 Text

IDE based hard disks (ATA1)


SCSI based hard disks (SAS)
IDE based hard disks (ATA133)
SCSI based hard disks (SCSI-1)

5
You need to install a UPS with the following equipment will be connected. What
VA rating is needed for the UPS?
532777 Text

Drive array - 150 watts


Monitor - 100 watts
System Unit - 450 watts
Tape drive - 100 watts

1000
1500
800
450

6
Your customer is planning to allow their sales team to gain remote access to the
sales reporting data, which resides on the customer's intranet. They are
concerned about unauthorised access to this data, and need some advice about
making the data available in a secure manner. The sales team will access the data
from the Internet, using a browser based application which will connect to a
front-end web server. Secure Sockets will be used from the client to the front-end
server. Which of the following will provide a viable solution for your customer?
532778 Text

Install a certificate on the client to enable SSL. Sit the server behind a firewall and
enable port 443 over TCP through the firewall. Block all other ports.
Install a certificate on the front end server to enable SSL. Sit the server behind a
firewall and enable port 443 over TCP through the firewall. Block all other ports.
Install a certificate on the front end server to enable SSL. Sit the server behind a
firewall and enable port 80 over TCP through the firewall. Block all other ports.
Install a certificate on the client to enable SSL. Sit the server behind a firewall and
enable port 80 over TCP through the firewall. Block all other ports
7
Over the last few days, you've been monitoring the performance and
responsiveness of your DNS servers. On examining the results, you notice that
one server is performing considerably less well, leading to client connection slow
downs. You decide to investigate its configuration. It becomes apparent that the
server has an older network card and that the bottleneck in the server's
performance is the network interface. Which of the following would improve the
throughput of this server?
532779 Text

Update the NIC driver.


Add another NIC and configure network load balancing.
Add another NIC and configure adapter teaming.
Reconfigure virtual memory.

8
Your customer uses a SQL Server database system to process the thousands of
online transactions per hour that they receive from Internet customers. The
backup solution must provide recovery to the point of failure. You propose a mix
of online file based backups and tape archives to be performed daily. Given that
the quantity of data to be backed up daily is 75GB. Which of the following tape
standards provides an uncompressed capacity that could hold this data on a
single tape?
532780 Text

AIT-4
QIC
Travan TR5
DAT-72

9
The sales office in Slough has implemented a new database which will be
installed on a dedicated file server based on a SCSI drive array provided by Dell.
The array comes with 10 disks, connected via an external cable to the server unit.
You want to provide a high degree of fault tolerance. Which of the following
RAID standards will you implement?
532781 Text

RAID 1
RAID 5
RAID 50
RAID10

10
Your customer's MySQL application is being overloaded. You determine that
more memory will alleviate the problem, and decide to add RAM to the
computer. The system currently has two sockets for memory, both of which are
occupied with 512MB DIMMs. Which of the following steps are necessary to
ensure a suitable memory upgrade?
532782 Text

1. Replace both current DIMMS with 1GB modules - doubling capacity.

2. Determine whether the memory is ECG or non-ECG.

3. Determine the speed of the motherboard and purchase DIMMs with the same rating.

4. Use memory from the same vendor as that currently installed in the server.

1, 3, 4
1, 2, 4
2, 3, 4
2, 4

11
You have been asked to advise a client on the appropriate form factor for their
new web server farm. They need to support tens of thousands of concurrent
online connections with their front end servers, whilst the back end servers will
be processing many thousands of transactions, 24 hours a day, 365 days a year.
Downtime is NOT an option, and redundancy must be built in to the solution.
Cost is always a factor, but high availability is more important. Which of the
following form factors would best suit their needs?
532783 Text

Mini tower servers


Blade servers
Rack-mounted servers
Desktop servers

12
Your database application runs on SQL Server, and requires a hefty processor
platform to support the connected users. You have chosen to deploy an AMD
Opteron based server platform, utilising the maximum supported number of
processors. Which edition of Windows will support this configuration?
532784 Text

1. Windows 2000 Server

2. Windows 2000 Advanced Server

3. Windows Server 2003

4. Windows Server 2003 Enterprise Edition

5. Windows Server 2003 DataCenter Edition

1, 3, 4, 5
2, 4, 5
1, 2, 3
1, 4, 5

13
You need to choose a server form factor which will allow for hot swappable
servers. Which of the following form factors supports this feature?
532724 Text

Rack-mounted servers
Desktop servers
Blade Servers
Mini tower servers

14
When installing SUSE Linux, which key do you need to hit to choose additional
drivers?
532725 Text

F1
F6
DEL
F12

15
Which of the following components is responsible for name resolution in a
network?
532726 Text

1. DHCP

2. Host Integration Server

3. WINS

4. ISA Server

5. DNS

3, 5
2, 3
1, 4, 5
1, 3

16
Which program is used to monitor connected users in NetWare?
532727 Text

NWADMIN
NETADMIN
MONITOR
Computer Management

17
Which program is used under Windows to view the TCP/IP configuration?
532728 Text

IPCONFIG
IFCONFIG
TCPCONFIG
CONFIG

18
Which of the following are valid clock speeds for PCI-X?
532729 Text

1. 512 MHz

2. 533 MHz

3. 266 MHz

4. 1024 MHz
1, 3
2, 3
3, 4
1, 4

19
You need to enable remote management of your NetWare servers. You propose
to use Remote Manager and connect across the company's private routed
network, through the head office firewall, to the NetWare servers. Which port(s)
need to be open to support this through the firewall?
532766 Text

80 and 993
8009
8008 and 8009
993
80 and 8008

20
Which of the following is NOT true of Network Attached Storage?
532767 Text

They are usually IP based units.


Clients attach directly to them.
You need to attach your NAS box to a file server.
They provide high performance file level storage.

21
You need to determine whether your SQL based database will be able to scale
properly as your users' needs grow. You decide to implement Microsoft SQL
Server 2005 on Windows Server 2003. Which of the following platforms will
NOT support your configuration?
532768 Text

1. Windows Server 2003

2. Windows XP-SP2

3. Windows DataCenter Edition

4. Linux

2, 4
1, 4
1, 2
2, 3

22
To configure NLB in a Windows system, which of the following steps is NOT
required?
532769 Text

1. Install a second network adapter.

2. Login as administrator.

3. Install the NLB network service via Control Panel   > Add/Remove Windows Components.

4. Install the NLB network service via the Network Connection property sheet.

5. Enter an IP address for the NLB object.

6. Enter a name for the NLB object.

1, 3
2, 4, 5
1, 2, 6
4, 6
23
Your customer intends to provide a high end, file level storage system attached
directly to the network. Which of the following would meet these needs?
532770 Text

iSCSI
NAS
RAID50
SNA

24
You need to install a UPS with the following equipment connected. What VA
rating is needed for the UPS?
532771 Text

Drive array - 50 watts


Monitor - 50 watts
System Unit - 350 watts
Tape drive - 50 watts

1000
1500
800
450

25
Your DHCP server is servicing more clients since you added 1000 new machines
at the head office. The service is becoming slower. What configuration change
could you make to improve service throughput?
532772 Text

Configure Adapter Teaming


Configure Network Load Balancing
Configure Clustering
Previous
Next

Submit