Witness Record Issue Remark

1.Foundation
1.1 Diameter FC , CC Yes W

1.2 . Level FC , CC Yes W


1.3Center height FC , CC Yes W
1.4Orientation &mark FC,MC , CC Yes W

2.Material
2.1. Type FC , MC No SW
2.3. Dimension FC , MC Yes SW
2.3. Appearance FC , MC No SW
3.Welding
3.1. WPS&PQR approval FC,MC,CC Yes W
3.2. Welder qulifcation FC ,CC No W
4. Bottom plate (include annular plate )
4.1. Orientation FC No SW
4.2. Visual Weld FC,MC,CC Yes W

4.3. Visul check for the jig traces FC No W

4.4.Vacuum test FC,MC,CC Yes W

4.5 NDT Test FC,MC,CC Yes

5. Shell plate
5. 1. Fit up check FC,MC Yes W

5.2. Chek for level FC,MC,CC Yes SW


5.2. Plumness check FC,MC,CC Yes SW
5.3. Peaking &Banding FC,MC,CC Yes SW
5.4. Radiographic text FC,MC,CC Yes SW/Teejoints:RR

5.5. Visual check for the jig tracs FC No W

5.7. Roundness check FC,MC,CC Yes W

5.8. Oil test on weld of shell to bottom FC,MC,CC Yes W

6. Penumetic Test FC,MC,CC Yes W

7. HydroTest FC,MC,CC Yes W

8. Painting FC,MC,CC Yes W


9. Finl certificate FC,MC,CC Yes W

SHAFAB CO. MAPNA CO. GHODS NIROO CO.

NAME :B.BAGHERIAN NAME : NAME :

SIGN : SIGN : SIGN :

DATE : DATE : DATE :