ID Task Task Name Duration StartJuly 2017 Finish Predecessors August 2017

Mode 20 22 24 26 28 30 01 03 05 07 09 11 13
1 MY PROJECT 65 days Tue 25/07/17 Mon 23/10/17
2 Railway Planning 24 days Tue 25/07/17 Fri 25/08/17
3 Project Profile 2 days Tue 25/07/17 Wed 26/07/17
4 Socio Economic Study 2 days Thu 27/07/17 Fri 28/07/17 3
5 Ridership Study 3 days Mon 31/07/17 Wed 02/08/17 4
6 Alignment / Right of Way 3 days Thu 03/08/17 Mon 07/08/17 5
Acquisition
7 Technical Aspect of the 3 days Tue 08/08/17 Thu 10/08/17 6
Project
8 Project Estimated Cost 2 days Fri 11/08/17 Mon 14/08/17 7
9 Project Financing Scheme 1 day Tue 15/08/17 Tue 15/08/17 8
10 Environmental Studies 3 days Wed 16/08/17 Fri 18/08/17 9
11 Financial/Economic 3 days Mon 21/08/17 Wed 23/08/17 10
viability of the study
12 Institutional Framework 1 day Thu 24/08/17 Thu 24/08/17 11
13 Implementation Schedule 1 day Fri 25/08/17 Fri 25/08/17 12
14 Railway Construction 13 days Mon 28/08/17 Wed 13/09/17
15 Railway Viaduct 2 days Mon 28/08/17 Tue 29/08/17 13
16 Railway Structure 2 days Wed 30/08/17 Thu 31/08/17 15
17 Track Geometry 2 days Fri 01/09/17 Mon 04/09/17 16
18 Minimum required curves 2 days Tue 05/09/17 Wed 06/09/17 17
in railway

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: RTE-AYTONA, MELODY
Summary Manual Summary Rollup Progress
Date: Sat 29/07/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration StartJuly 2017 Finish Predecessors August 2017
Mode 20 22 24 26 28 30 01 03 05 07 09 11 13
19 Railway Switces and 2 days Thu 07/09/17 Fri 08/09/17 18
Crossover
20 Tracks Installation 3 days Mon 11/09/17 Wed 13/09/17 19
21 Railway Operation 10 days Thu 14/09/17 Wed 27/09/17
22 Train Schedule 1 day Thu 14/09/17 Thu 14/09/17 20
23 Train Headway 1 day Fri 15/09/17 Fri 15/09/17 22
24 Cycle Time Computation 2 days Mon 18/09/17 Tue 19/09/17 23
25 Passenger Per Hour Per 1 day Wed 20/09/17 Wed 20/09/17 24
Direcction Computation
26 Number of required fleet 1 day Thu 21/09/17 Thu 21/09/17 25
per hour
27 Signaling System and Train 2 days Fri 22/09/17 Mon 25/09/17 26
Control
28 Operations Control Center 2 days Tue 26/09/17 Wed 27/09/17 27
(OCC)
29 Railway System Maintenance18 days Thu 28/09/17 Mon 23/10/17
30 Rolling Stock 4 days Thu 28/09/17 Tue 03/10/17
31 Preventive Maintenance 2 days Thu 28/09/17 Fri 29/09/17 28
32 Annual Maintenance 1 day Mon 02/10/17 Mon 02/10/17 31
33 Emergency Repair 1 day Tue 03/10/17 Tue 03/10/17 32
Maintenance
34 Buildings and Facilities 4 days Wed 04/10/17 Mon 09/10/17
35 Preventive Maintenance 2 days Wed 04/10/17 Thu 05/10/17 33

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: RTE-AYTONA, MELODY
Summary Manual Summary Rollup Progress
Date: Sat 29/07/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration StartJuly 2017 Finish Predecessors August 2017
Mode 20 22 24 26 28 30 01 03 05 07 09 11 13
36 Annual Maintenance 1 day Fri 06/10/17 Fri 06/10/17 35
37 Emergency Repair 1 day Mon 09/10/17 Mon 09/10/17 36
Maintenance
38 Tracks and Permanent Ways4 days Tue 10/10/17 Fri 13/10/17
39 Preventive Maintenance 2 days Tue 10/10/17 Wed 11/10/17 37
40 Annual Maintenance 1 day Thu 12/10/17 Thu 12/10/17 39
41 Emergency Repair 1 day Fri 13/10/17 Fri 13/10/17 40
Maintenance
42 Signalling 4 days Mon 16/10/17 Thu 19/10/17
43 Preventive Maintenance 2 days Mon 16/10/17 Tue 17/10/17 41
44 Annual Maintenance 1 day Wed 18/10/17 Wed 18/10/17 43
45 Emergency Repair 1 day Thu 19/10/17 Thu 19/10/17 44
Maintenance
46 Power Supply 2 days Fri 20/10/17 Mon 23/10/17
47 TPSS 1 day Fri 20/10/17 Fri 20/10/17 45
48 SS 1 day Mon 23/10/17 Mon 23/10/17 47

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: RTE-AYTONA, MELODY
Summary Manual Summary Rollup Progress
Date: Sat 29/07/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
September 2017 October 2017
13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: RTE-AYTONA, MELODY
Summary Manual Summary Rollup Progress
Date: Sat 29/07/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
September 2017 October 2017
13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: RTE-AYTONA, MELODY
Summary Manual Summary Rollup Progress
Date: Sat 29/07/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
September 2017 October 2017
13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: RTE-AYTONA, MELODY
Summary Manual Summary Rollup Progress
Date: Sat 29/07/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only