Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
0mØ )
Vertical Shafts on a South African Colliery
G r e g Tr i v e t t ,
S e n i o r P r o j e c t E n g i n e e r, P r o j e c t s a n d Te c h n o l o g y S e r v i c e s ,
Sasol Mining,
SYNOPSIS
A requirement was identified at Sasol Mining to harness the cost,
safety and time advantages associated with raise-boring as a shaft
sinking method with the ever increasing requirements for ventilation
volume.
Previously a maximum diameter of 6.1 meters had been raise bore
reamed; this allowed for a maximum air volume of a little over
560 m3/s for a single raise bored upcast shaft. Sasol Mining required
upcast ventilation installations on two of its Collieries, which
could each deliver in the region of 760 m3/s.
Simply put, the solution for this requirement was to either raise
bore two shafts, execute a blasting operation or move the boundary
for raise boring diameter to at least 7.0m.
Sasol Mining (Pty) Ltd and Rucbor (Pty) Ltd have successfully
concluded the raise boring of three shafts at >7. 1meters diameter
as part of a sequence of nine new shafts on Sasol Mining's Secunda
Collieries.
This paper discusses the planning and execution of these three
large diameter shafts, particular reference is made to the prevailing
local geological conditions and to the risk mitigation methods
e m p l o y e d t o e n s u r e t h a t t h i s t e c h n o l o g y, - s t r e t c h i n g p r o j e c t w a s
c o m p l e t e d s u c c e s s f u l l y.
"Risks exists, and the successful mining engineer is the one who
never accepts a solution at face value, he strives continuously
t o l e a r n f r o m t h e p a s t a n d t h e p re s e n t a n d h e i s a l w a y s p r e p a re d
to sow his knowledge into the future".
373
INTRODUCTION
374
• Syferfontein Colliery: 1 off 5.1m ∅ upcast shaft,
111 m d e e p
1 off 4.1m ∅ downcast
shaft, 105m deep
Piek Mining (Pty) Ltd were awarded the contract to bolt, mesh
and shot-crete line the remainder of the shafts.
375
LARGE HOLE RAISE BORING - A TECHNOLOGY
I N S I G H T.
T h e r a i s e b o r i n g t e c h n o l o g y, e q u i p m e n t a n d o p e r a t i o n a l m e t h o d s
to be used have to be understood in order to carry out the mining
design and assessment of risk.
The technology for the smaller diameter (up to the 6.1m ∅ required
a t Tw i s t d r a a i ) r a i s e b o r i n g o p e r a t i o n s w a s o p e r a t i o n a l l y p r o v e n
and standard reaming tools were available. A diameter of 6.1m
was however insufficient for the ventilation requirements at Middlebult
and Bosjesspruit Colliers.
GEOLOGICAL CONDITIONS
General geology
376
The Karoo supergroup sediments in the Highveld Coal field are
represented from the base upward by the Dwyka formation, the
P i e t e r m a r i t z b u r g f o r m a t i o n , t h e Vr y h e i d f o r m a t i o n a n d p a r t i a l l y
t h e Vo l k s r u s t f o r m a t i o n o f t h e E c c a G r o u p .
S p e c i f i c g e o l o g y : M i d d l e b u l t a n d B o s j e s s p r u i t ( 7 . 1 m Ø) s h a f t s
377
The B8, although very hard by karoo sequence standards was well
below the hardness of >450 Mpa UCS material frequently encountered
during raise-boring operations on South Africa's platinum mines.
In addition, this strata has been successfully piloted and reamed
several times at Secunda.
378
E X E C U T I O N R I S K I D E N T I F I C AT I O N A N D M I T I G AT I O N
ACTIONS.
Ta b l e d b e l o w a r e t h e m a j o r e x e c u t i o n r i s k s i d e n t i f i e d a n d t h e
mitgation actions undertaken.
I n c re a s e d s h a f t d i a m e t e r ( M e c h a n i c a l r i s k
379
Challenging geologicl conditions (Mining Risk)
Figure 3
Figure 3
380
T E C H N I C A L S O L U T I O N S TO R I S K M I T I G AT I O N
REQUIREMENTS.
The result was a reamer head, which would enable the excavation
of the required 7.1m∅ shafts through the strata overlying the
shaft positions at the Middelbult and Bosjesspruit ventilation
shafts.
A c t i o n s p r i o r t o r a i s e b o r i n g ( P re - m i n i n g g ro u n d s t a b i l i s a t i o n )
St a b i l i s a t i o n o f c e n t r e c o r e f o r p i l o t h o l e d r i l l i n g
(Risk 2)
The first requirement was to replace the upper ten metres of weathered
material in the shaft centre to a diameter that would safely accommodate
the 381 mm Ø pilot hole. This was achieved by drilling a 600mm
ø and back filling with 30 Mpa mass concrete prior to the establishment
o f t h e r a i s e - b o r i n g c o n t r a c t o r.
Va r i o u s d r i l l i n g o p t i o n s a r e a v a i l a b l e , i n c l u d e d t h e C h a m b e r o f
Mines rescue drill and piling auger rigs. Due to time, safety and
logistical constraints at the time of execution, a button bit reamer
on a percussion drill rig was used to widen a 203mm hole, foam
was added to the drill liquid to ensure adequate flushing of the
drill chips with the increased annulus of the hole. (Figure 4)
381
The second requirement was to minimise the amount of pilot hole
erosion in the middle zone of the B4 dolerite. Extending the 600mm
ø hole to a depth of ±50m was unacceptably costly; the selected
solution was to apply a bentonite mud additive to the flushing
water during pilot hole drilling.
St a b i l i s a t i o n o f re a m i n g f a c e ( R i s k 3 )
The reamer face support system has the following design drivers:
M a s s = Vo l u m e S . G
= 1.4m X 1.4m x 1.0m X 2.7m tons/m3
= 5.3 tons
382
Three test dowels were made up and failure tested at CSIR Mining
Te k w i t h t h e f o l l o w i n g r e s u l t s :
• A r r e s t a n y o v e r m i n i n g t h a t m a y o c c u r.
Note 1
What the modelling showed was that a single ring of spiles was
sufficient; this resulted in a considerable cost saving from estimates
during the design phase.
For the same reasons as noted above, removal of the reamer and
raise boring equipment from the shaft should take place within
24hrs of holing. Once the reamer had holed to surface this was
achieved by using a 550-ton crane to first lift the 85t raise bore
machine and then the 105-ton reamer head. (Figures 5a. & 5b.)
384
Rapid sealing of B4 dolerite (Risk 6)
Now that the shaft was clear of raise boring equipment a layer
of shot-Crete was applied to the shaft sidewall. The requirements
were as follows:
B 8 D O L E R I T E A N O M A LY
The B8 dolerite has never been the cause of any failure or non-
conformance at previous shaft sinking operations at Secunda. Although
the material, at 250-350 Mpa is hard by Karoo sequence standards,
the net result of this hardness in a raise boring operation is usually
l i m i t e d t o a s l o w e r a d v a n c e r a t e a n d i n c r e a s e d c u t t e r w e a r.
CONCLUSION
386
It is a strongly held belief that having detailed information on
the prevailing geological and mining conditions, and being able
to successfully synthesise this knowledge with the operation to
be undertaken is a requirement for successful project planning
and implementation. The more complete the technical input information,
the greater the success of the risk mitigation actions and the lower
the risk of non-conformance.
"Risk exists, and the successful mining engineer is the one who
never accepts a solution at face value, he strives continuously
t o l e a r n f r o m t h e p a s t a n d t h e p re s e n t a n d h e i s a l w a y s p r e p a re d
to sow his knowledge into the future".
REFERENCES
387
The raise boring of large diameter (>7.0m ø) vertical shafts on
a S o u t h A f r i c a n C o l l i e r y, P r e s e n t a t i o n t o S A C M A , G. Tr i v e t t ,
August 2000.
ACKNOWLEDGEMENTS
To K o o s D e b e e r a n d B a r n e y B e s t e r f o r t h e i r p a s t e x p e r i e n c e s i n
r a i s e b o r i n g a t S e c u n d a , D a w i d P o s t m a a n d B r i a n Vo r s t e r f o r t h e i r
rock engineering contributions and to John Sparrow for his geological
insights.
F o r t h e i r p a r t n e r s h i p ro l e s :
388
Figure 1:
9 0 0 Ve r t i c a l j o i n t i n g o f B 4 D o l e r i t e
389
390
Figure 2:
Serpentinised zone in B4 Dolerite
• A l l t h e l i g h t e r, s e r p e n t i n e b a n d s i n t h i s c o r e d i s a p p e a r e d
within two weeks of exposure to air resulting in a total unravelling
of this 12m thick zone
• Notice also the vertical fracturing present
Figure 3:
Shaft collar ready for Raise bore machine
391
Figure 4:
600mm Ø percussion drill reamer for centre core removal
392
Figure 5a:
S i n g l e l i f t ( 8 5 t o n s ) o f Wi r t h R a i s e b o r e m a c h i n e f r o m s h a f t
within 6 hrs of holing
393
394
Figure 5b:
Single lift (106 tons) of 7.1mø raise bore reamer from shaft within 12 hrs of holing.
Figure 6:
Birds-eye view of 7.1mø raise bored shaft after removal of raise
bore equipment
395
Addendum 1
396
Addendum 2
397
Addendum 3
398