Client: SNPL, Simara, Bara, Nepal Inspection Test Plan (ITP) for Electri

PMC: TAEC Consult Pvt. Ltd., Nepal


Contractor: AirTech Industries Pvt. Ltd., Nepal Residential Apartments for Man

Procedure/
Matarials No. Activity Description Frequency Specification

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing
Receiving Inspection
Procedure

Installation Cable Tray, Approved Drawing


2 Ladder and Conduit 100% Vendor Drawing
Installation

Cables/ Trays/
Conduit
Excavation,
Backfilling(Civil), 100% installation Approved Drawing
3 Duct, Sand bed & Sand All route
fill
Cable Installation
- Installation and Visual Approved Vendor
4 check All Cable Drawing
-Instulation Resistance Approved Drawing
Check

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

MV/LV Switchgear
MV/LV Switchgear

MV/LV Switchgear Approved Vendor


-Installation & Visual Drawing
Check
2 -Busbar Conductivity Each Unit Approved Drawing
Check
-Insulation Resistace Technical
Test Specification

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection Each Delivery General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

Transformer
Transformer

Transformer Approved Vendor


-Installation and Visual Drawing
Check
2 -Insulation resistance Each Unit Approved Drawing
Check
-Oil level & dielectric Technical
Check Specification

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection Each Delivery General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

Inverter System

Approved Vendor
Drawing
Inverter System
2 -Installation and Visual Each Set Approved Drawing
Check
Technical
Specification
Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

Bus Duct

BUS DUCT Approved Vendor


-Installation & Visual Drawing
Check
2 -Busbar Conductivity Each Set Approved Drawing
Check
-Insullation Resistance Technical
Check Specification

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing
Receiving Inspection
Procedure
Distribution
Board(including
Inverter DB)

Approved Vendor
Drawing
Distribution Board
2 - Installation & Visual Each Unit Approved Drawing
Check
Technical
Specification
Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

Earthing and
Bonding

Earthing and Bonding Approved Vendor


-Earthing electrode/ Drawing
Cable Route/ Cable
connection Each Unit &
2 Approved Drawing
-Inspection earth pit Equipment
check Technical
-Electrical system Specification
earthing test

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

Lighting System
Lighting System

Approved Vendor
Lighting System Drawing
-Installation & Visual Each Unit &
2 Check Approved Drawing
Equipment
-Insulation resistance
Test Technical
Specification

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

Lighting Protection

Approved Vendor
Drawing
Lighting Protectiom Each Unit &
2 -Installation & Visual Approved Drawing
Equipment
Check
Technical
Specification

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

Receptacles,
Junction Box,
RCU(remote control
utility)
Receptacles,
Junction Box,
RCU(remote control
utility)

Approved Vendor
Receptacle & Junction Drawing
Box, RCU
-Installation & Visual Each Unit &
2 Approved Drawing
Check Equipment
-Insulation Resistance Technical
Test Specification

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

Cables/ Trays/
Conduit (Telecom)
Installation Cable Tray, Approved Drawing
2 Ladder and Conduit 100% Vendor Drawing
Cables/ Trays/ Installation
Conduit (Telecom)

Cable Installation Approved Vendor


- Installation and Visual Drawing
3 check All Cable
-Instulation Resistance Approved Drawing
Check

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure
PA System &
Telephone
PA System &
Telephone

Approved Vendor
Drawing
PA system and
Telephone installation
2 Each Unit Approved Drawing
-Installation and Visual
Check Technical
Specification

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

CCTV System

Approved Vendor
Drawing
CCTV Installation
2 -Installation and Visual Each Unit Approved Drawing
Check
Technical
Specification

Related POS/
Material
Specification
Material Verification
1 Receiving Inspection 100% General Ass'y
-Raw Material Drawing

Receiving Inspection
Procedure

Fire & Alarm system


Fire & Alarm System
Fire & Alarm system Installation
-Installation and Visual
check
-Sequence Operation Approved Vendor
Test Drawing
-Calibration Teat
-Internal Components Each Unit &
2 Approved Drawing
Inspection Equipment
-Alarm Circuit Test Technical
-Switching Device Test Specification
-Insulation Resistance
Test
-Battery Cycle Test
- Dielectric Strength
Test

* Legend: R(Review Point): To determine subject matter has achieved


M(Monitoring): Periodic and systematic check (does not imply any actio
W(Witness Point): Observation of an activitiy to ensure work is progressing a
H(Hold Point): A point beyond which an activity must not proceed without the approval of a designate
Inspection Test Plan (ITP) for Electrical Works
Inspection By
Residential Apartments for Managers Remarks

Inspection Method/ Acceptance Criteria


Contractor PMC Client

As Per Specified in Applicable Specification and


Drawing
1. No Damage, Corrosion & Deformation W W R
2. Shall be properly laid out on wooden supports clear
of the soil.

1. Check tag numbers are correct


2. Verify Cable tray and tray installed as per
construction drawing
3. Check allignment as overlapped of trays
4. Check bonding jumpers installed at tray joint and
tight
5.Check hold down clamp and brackets are installed
6. Check Cable ladder properly suppoerted
7.Check cover installed(to be installed after all the W W M
cables are tested and properly terminated)
8. Check Junction Box suppoerts within the specified
interval according to approved drawing
9. Check touch up for galvanizing performed(if
required)
10. No sharp edges
11.No obstructions
12.Check tray Labelling

1. Check using of clean sand without stone for sand


bedding and sand filling with appropriate depth
2. Check the Trench route maker and symbol (after W W M
cable testing and complete backfill
1. Check and confirm cable shall be meggered before
installation (on reel test/ Only Power Cable: If
required)
2. Verify Cable type and Configuration
3.Damaged Cables shall be replaced before Sandfilling
4.Check and confirm cable shall before and after
installation, record of testing shall be available
5. Check Proper arrangement, segregation and layer of
cable, bending radius as per vendor data, and W W M
allowable slack
6. Check the barrier between the HV/LV cable (if
required)
7.Check cable fix to cable tray and ladder properly
8. Check cable tags correct
9. Check cable caps for protection of cable ends (shall
be properly protected after installation)

As Per Specified in Applicable Specification and


Drawing
1. No Damage, Corrosion & Deformation
2. Shall be properly laid out on wooden supports clear W W R
of the soil.
3. Check Shock indicator (if applicable)
1.Check Installation method as per installation
drawing
2.Check doors and panels to ensure proper opening
and closure
3.Check paint damage, tag plate, warning label. Visual
damage etc.
4.Check fuse rating, main parts rating/type
5.CT/PT ratios shall be visually checked against
drawing.
6.Check operation of safety shutter
7.Check busbars are installed at correct locatiom W W W
8. Check busbars connection tightness and correct
phasing
9. Torque Check of busbar connection as per
manufacturer recomendation
10. Check busbars conductivity (end to end)
11. Check the condition of earthing bar and
connections, measure continuity of switchboard to
main earth.
12. Check Insulation resistance values of busbars.

As Per Specified in Applicable Specification and


Drawing
1. No Damage, Corrosion & Deformation
2. Shall be properly laid out on wooden supports clear W W R
of the soil.
3. Check Shock indicator or Shock record (if required)
1.Check installation method as per installation drawing
2. Check paint damage,tag plate, warning label, visual
damage etc.
3. Check insulation resistance for HV-earth/ LV -earth
4. Check explicit all porcelain & other bushings for
Damages on surface
5. Check no-load tap changer for proper movement
6.Check continuity on all tap position W W W/M
7. Check oil colour and smell
8.Check connection as approved drawing
9. Check neutral earthing connection
10. Measure neutral earthing, equipment earthing
continuity
11. Check oil level and pressure level

As Per Specified in Applicable Specification and


Drawing
1. No Damage, Corrosion & Deformation W W R
2. Shall be properly laid out on wooden supports clear
of the soil.

1. Check installation method as per installation


drawing
2. Check paint damage, tag plate, warning label, visual
damage etc.
3. Check installation of inter-connection cabling as per
approved drawing W W W
4. Check Main parts rating/ type as per relevant
drawing
5.Check isolation switch open/close
6. Check earthing for system cubicle
7. Check battery type
As Per Specified in Applicable Specification and
Drawing
1. No Damage, Corrosion & Deformation
2. Shall be properly laid out on wooden supports clear W W R
of the soil.
3. Check the group identification number of BUS
DUCT(if required)

1. Check the position of equipment to be connected


with regard to the layout drawing
2. Check assemble & install support as detail
3. Check paint damage, tag plate, warning label, visual
damage etc.
4. Torque check of busbar connection per vendor
Recommendation
5. Check the phase sequence of the connection W W W
6. Check the connection of switchboard bus duct
section
7. Check busbars are installed at correct location
8. Check busbar conductivity test
9. Check insulation resistance of busbar
10. Check the instrument air condition

As per specified in applicable specification and


drawing
- No Damage, Corrosion & Deformation W W R
-Shall be properly laid out on wooden supports clear
of the soil

1. Check installation method as per installation


drawing
2. Check assemble & install supports as drawing
3. Check Paint damage, tag plate, warning label visual
damage etc. W W W
4. Check MCB rating, main Parts rating/type
5. Check the condition of earthing bar and
connections, measure continuity of switchboards to
main earth
As Per Specified in Applicable Specification and
Drawing
1. No Damage, Corrosion & Deformation W W R
2. Shall be properly laid out on wooden supports clear
of the soil.

1.Verify the marking points for installation rod as per


the construction drawing
2. Check and verify the installation of earthing rod as
per the project specification
3. Verify the completed section of depth of the cable
as per the specification and construction
4. Verify cable kicker pipes or protection pipes are
adequate
5. Check cable size and connection
6. Check cable protection W W W
7. Compression type splice or thermo-weld
connection, wrapped with insulation tape
8. Check inspection earth pit according to the
construction drawing
9. Check individual electrode resistance value
10. Check group earth resistance value
11. Check earth connection between the electrode
and the supply and group earth loop continuity
12 Check connection of clean earth to group earth

As Per Specified in Applicable Specification and


Drawing
1. No Damage, Corrosion & Deformation W W R
2. Shall be properly laid out on wooden supports clear
of the soil.
1. Check Installation method as per the drawing
2. Check Paint damage, tag plate, warning label, visual
damage etc.
3. Check cable size and connection
4. Check lighting model and type with lamp type
5. Fixtures tag number
6. Check type of ex-protection W W W
7. Check spare hole/cover to seal and cover tightened
8.Check the earthing wire connection Properly
9. Verify continuity and insulation resistance
10. Check the light cable condition(rigid or flexible
conduits, cable glands)

As Per Specified in Applicable Specification and


Drawing
1. No Damage, Corrosion & Deformation W W R
2. Shall be properly laid out on wooden supports clear
of the soil.

1.Check Installation method as per installation


drawing
2. Check tah plate, visual damage etc.
3. Check cable size and connection
4. Check Lighting model and type W W W
5. Fixtures tag number
6. Check the earthing wire connection properly made
7. Verify continuity and insulaton resistance

As Per Specified in Applicable Specification and


Drawing
1. No Damage, Corrosion & Deformation W W R
2. Shall be properly laid out on wooden supports clear
of the soil.
1. Check installation method as per the installation
drawing
2. Check paint damage, name plate, warning label,
visual damage etc. incl(IP Protection class)
3. Check adequate protection for fittings and cable
against corrosion weather etc.
4. Check earth bonding correct
5. Check type of IP protection class & ex Protection
6. Check spare hole/cover to seal and cover tightened. W W W
7. Inspect wiring inside the junction boxes for correct
wiring method and wire splicing
8. Verify continuity and insulation resistance
9. Check zone applicable safety code.
10. Check that the appropriate cover is installed for
each type of receptacle
11. Verify the position of switch according to the
specification.

As Per Specified in Applicable Specification and


Drawing
1. No Damage, Corrosion & Deformation W W R
2. Shall be properly laid out on wooden supports clear
of the soil.
1. Check tag numbers are correct
2. Verify Cable tray and tray installed as per
construction drawing
3. Check allignment as overlapped of trays
4. Check bonding jumpers installed at tray joint and
tight
5.Check hold down clamp and brackets are installed
7. Check cable fix to cable tray and ladder Properly.
8. Check Cable ladder properly suppoerted
9.Check cover installed(to be installed after all the W W/M W/M
cables are tested and properly terminated)
10. Check Junction Box suppoerts within the specified
interval according to approved drawing
11. Check touch up for galvanizing performed(if
required)
12. No sharp edges
13.No obstructions
14.Check tray Labelling

Check the megger test on the reel (For the


construction: If required)
1. Verify Cable type and Configuration
2. Check and confirm cable shall before and after
installation, record of testing shall be available
3. Check Proper arrangement, segregation and layer of W W W/M
cable, bending radius as per vendor data, and
allowable slack
4. Check cable tags correct
5. Check cable caps for protection of cable ends (shall
be properly protected after installation)

As Per Specified in Applicable Specification and


Drawing W W W
1. No Damage, Corrosion & Deformation
1.Check name plate, tag no.
2.Check wiring as per construction drawing
3.Check the structured cabling cabinet are installed as
per drawing and orientation
4.Check the earthing and arresters for telecom W W R
cabinet(if applicable)
5.Check no damage
6.verify explosion proof telephone are installed.

As Per Specified in Applicable Specification and


Drawing W W R
1. No Damage, Corrosion & Deformation

1. Check name plate, Tag number


2. Check cameras are mounted at correct location as
per the drawings
3. Check the correct lighting is provided for the
camera
4. Check the power & signal cables are properly fixed W W W
with appropriate cable marking & the cable length is
ample for movement of camera
5. Check the accessibility and facilities maintenance.
6. Check no damage
7. Check earthing connection

As Per Specified in Applicable Specification and


Drawing W W W
1. No Damage, Corrosion & Deformation
1. Check name plate, Tag number
2. Check detectors are mounted at correct location as
per the drawings
4. Check the power & signal cables are properly fixed
with appropriate cable marking
5. Check the accessibility and facilities maintenance. W W/M M/W/R
6. Check no damage
7. Check earthing connection
8.Perform all tests
9.Test the degree of enclosure Protection

To determine subject matter has achieved objectives.


ystematic check (does not imply any action will be taken.
n activitiy to ensure work is progressing as per requiredments.
oceed without the approval of a designated organization or authority, SNPL's decision.