RATE ANALYSIS FOR SHUTTERING OF FLOOR BEAM /SLAB.

Sr. No. Description Qty. Unit Rate Total cost cost per sq.m Repeatations

Shuttering Area 180 Sqmt

1 Vertical cuplock support length


-2.00 m 196.00 No. 623 122108 678.38 90
2 Vertical Cuplock support
Length-1.00 m 96.00 No. 323 31008 172.27 90
3 Adj Stirrup Head 32mm dia 600
mm long 196.00 No. 361 70756 393.09 90
4 Ledger pipe length - 1.20 M 354.00 No. 277 98058 544.77 90
5 Ledger Pipe length -1.50 m 438.00 No. 337 147606 820.03 90
6 Wooden Chavi4" x 3" size 198.45 Cf 300 59535 330.75 10
7 Wooden Chavi 4" x 1" size 92.61 Cf 300 27783 154.35 10
8 Nails 12.00 Kg 40 480 2.67 1
9 Ply Wood 180.00 Sqmt 480 86400 480.00 8
10 Shuttering Oil 13.00 lt. 50 650 3.61 1
11 Tie Rod 0.9 Mt 60.00 No. 90 5400 30.00 50
12 hollow Section Size
49.5*49.5*3.6 mm 1.60 MT 37000 59200 328.89 90
13 Forman 5.00 No. 250 1250 6.94 1
14 Carpenter 22.00 No. 250 5500 30.56 1
15 Helper 33.00 No. 150 4950 27.50 1
Total
Contractors profit @15%

Rate per sq.m


Rate per Sqmt

7.54

1.91

4.37
6.05
9.11
33.08
15.44
2.67
60.00
3.61
0.60

3.65
6.94
30.56
27.50
213.03
31.95
244.98

244.98

Potrebbero piacerti anche