DRAFT FINAL REPORT Masterplan PT. Tirta Remu Sorong
Summary
General
PT. Tirta Remu was founded in early of 2002 is a joint venture company between
Indowater, BV and Perusahaan Daerah Air Minum (PDAM) Kota Sorong/Water Supply
Company of Sorong City. The location of PT. Tirta Remu is in Sorong city. Concession
area of PT. Tirta Remu is whole area of Sorong City.
The average number of persons per household in Sorong City is 5 (five) persons and
base on data from Statistical Department.
The total number of employees of PT. Tirta Remu is 57 persons, divided into 2 (two)
divisions: General and Technical. At this moment PT. Tirta Remu use 5 water sources for
fulfill water demand consisting of 2 rivers and 3 springs. The quality of water sources is
below standard quality of clean water especially turbidity is high and which happens in wet
season. The capacity of water sources will decrease significant in the dry season. The
availability of new water sources for water supply for PT. Tirta Remu in the future is
limited, based on consultant investigation the possible water source to be used for PT.
Tirta Remu water supply development is making deep wells, but to make deep wells,
requires further investigation and study..
At this moment PT. Tirta Remu has 1 (one) water production facility, which located in
HBM pumping station. The capacity of this WTP is 150 l/s and the elevation is + 61m MSL
and supplies to 10,441 connections in Sorong City. At this moment for distribution water to
customers, PT. Tirta Remu uses 12 (twelve) reservoirs distribution. The reservoirs are
located in HBM, Remu, Klademak, Kampung Baru, Rufei and Malanu area. At this
moment only 8 (eight) reservoir are in operation. The transmission and distribution
network have a total length of 223,252 m’, which consists of various pipe materials and
diameters. The years of installation the transmission and distribution system is from 1993
to 2008. PT. Tirta Remu distribution zones are based on the area; there are 13 delivery
zones. 34.9% of the people in concession area have connection from PT. Tirta Remu.
Water tariff applied in PT. Tirta Remu still the water tariff of PDAM and need to be revised.
Development Plan
The existing water consumption in PT. Tirta Remu is estimated at 87 liter/capita/day, which
will increase to 120 liter/capita/day over a period of 15 years. This is based on the average
water consumption in other similar cities in Indonesia (98 ‐ 130 liter/capita/day). Based on
the water demand prognosis, the coverage of water supply services in Sorong will increase
from 34.9% in 2008 to 79% in 2020 and total non‐revenue water will decrease from 55 % in
2008 to 17 % in 2020.The development period of this master plan is set on a 12-years
basis. The implementation schedule of PT. Tirta Remu water supply infrastructure
development is divided into 3 phases:
Each phase is divided into yearly implementation stages, which means the system, will be
gradually improved, and rehabilitated every year simultaneously. The scope of work for
infrastructure development is divided into 4 groups:
a. Water sources; The capacity of water sources at this moment can fulfill water demand
until the end of development period. But for alternative water sources in Sorong, deep
well is one of solution for potential water sources. This has still to be confirm by
investigation and study.
b. Production plants and storages; the existing production unit in PT. Tirta Remu still
can coverage water demand but need some rehabilitation in filter, pump and piping
system. The capacity of reservoir is not enough for covering water demand. Because of
that in year 2020 a new reservoir distribution will be constructed with capacity 500 m3
and as alternative the existing Slow Sand Filter in Klademak may be used as a
reservoir.
The total investment cost are estimated at Rp. 45,520 billions, or Euro 3,035 millions for
alternative 1 and for alternative the total cost estimation is Rp. 31,930 billions, or Euro
2,129. This value includes the 21,914 new house connections. This means the average
price per new house connection will be approximately Rp. 2,217 million, which is ca. Euro
147 for alternative 1 and for alternative 2 Rp. 1,555 million, which is ca. Euro 103,‐
Appendix.
Appendix. A Map of Irian Jaya Barat Province
Appendix. B Map of Project Area
Appendix. C Map of Geological Condition
Appendix. D Map of Hydro geological Condition
Appendix. E Map of Hydrology Condition
Appendix. F Organizational Structure of PT. Tirta Remu
Appendix G Photograph Documentation
Appendix. H Map of Transmission and Distribution
Appendix. I Water Demand Prognosis
Appendix. J Existing Schematic of PT. Tirta Remu
Appendix. K Future Schematic System of PT. Tirta Remu Phase 1 (2010)
Appendix. L Future Schematic System of PT. Tirta Remu Phase 2 (2015)
Appendix. M Future Schematic System of PT. Tirta Remu Phase 3 (2020)
Appendix. N Estimate Quantity of Alternative 1
Appendix. O Cost Estimation of Alternative 1
Appendix. P Estimate Quantity of Alternative 2
Appendix. Q Cost Estimation of Alternative 2
1. INTRODUCTION
1.1 Background
1.2 Objectives
In geographic view, Sorong city is located between 131o 15' East Longitude - 0o 45' North
Longitude. Geographical location of Sorong is as following borders:
The map of Irian Jaya Barat Province is shown in Figure 2.1 below and for detail is shown
in Appendix A.
Sorong City
The project boundaries within which the WMD will work are equal to the PT. Tirta Remu
concession area. PT. Tirta Remu concession area is located in the Sorong City area.
Sorong City area covers 5 districts: Sorong Barat, Sorong Timur, Sorong, Sorong
Kepulauan and Sorong Utara with a total area of 1.105 Km2. The map of the PT. Tirta
Remu concession area is shown in Figure 2.2 below. The detail of administrative map of
Sorong is shown in Appendix B.
2.2.1 Topography
In general the topographic condition in Sorong City is separated in two areas a flat and a
hilly area. Seventy procent of the houses in Sorong are located in flat area.
The average slope in Sorong is between 10% and 20%. The lowerst area in Sorong City
has a level of + 2m MSL and the highest area has level + 66m MSL.
2.2.3 Geology
The Sorong Fault Zone is a major left-lateral fault system separating Australia from the
Philippine Sea Plate and the Molucca Sea Plate. The fault zone juxtaposes Mesozoic-
Tertiary continental and arc/ophiolitic rocks. Continental crust was derived from the
Australian margin. Crust of Philippine Sea Plate origin has a basement of ophiolitic and/or
arc origin.
Sorong has more than 10 unit lithology formation. There is Kemun Formation that consist
of metamorphic rocks, Faumai formation that consist of calcarenite etc., Volcanic Rocks of
Dore Mts in the Miocene age and consist of lava andesite until basalt, breccia etc.,
Sagewin Formation that predominantly consist of calccrenite families, Klasafet Formation
that consist of napal and mud-rocks, Klasaman Formation, Sorong Granite, Breccia
Yefman, Ultamafic rocks, Klasilutit, undifferentiated, Sele conglomerates, and alluvium
deposit and litoral. For geological condition in Sorong is shown in Appendix. C
2.2.4 Hydrogeology
Based on hydrogeology conditions, Sorong area can be divided into 4 classifications i.e.
• High groundwater potential is covered at the east lowland and west highland. Water
table is 0.5 – 2.5 m below ground level. Water quality is brackish.
• Moderate groundwater potential covers water table 1 – 5 m below ground surface.
Water quality is bad, except in the fissures system.
• Small groundwater potential covers hilly and mountains slope at the northern, eastern,
and southern area of the Sorong city. Water table is 2.5 – 7 m below ground surface.
Water quality is good and this area is dominated by breccia, andesite, basalt,
limestone, and sandstone.
• Area without groundwater potential includes the tops of hills and mountains.
2.2.5 Hydrology
In PT. Tirta Remu concession area, there are 5 (five) rivers, see Table 2.2. Generally
most of the rivers have a big fluctuation in the yield especially in the dry season, the yield
of some rivers completely drops to zero. The water quality of this river is already affected
by human activities because especially on Sundays people living in the neighbourhood
use this river for washing, and bathing activities.
End 2008, the population of Sorong was 163,483, figure resulting from population census.
Compared to the population of 2004, this results in an average growth rate of 1.7 % per
year. In 2009 the population of Sorong City is concentrated in the town centre of the
Sorong district and 33% from the total population of Sorong. In the future development of
houses in Sorong City will be concentrated in Sorong Timur area because in this area the
possibilities build houses is favourable and this area has a lot of supporting facilities for
new houses. The number of population in Sorong in 2008 is shown in Table 2.3.
For population development per year from year 2006 until 2008 is shown in Table 2.4
below.
2.4.1 General
The Socio economy data for Sorong City is not available because there’s no socio
economic survey in Sorong City to know the figure about household income and
expenditure, willingness to pay, affordability to pay for water bill and monthly water
consumption. In this Master Plan is only show about Gross Regional Domestic Product
(GRDP) for a figure socio economic condition in Sorong City. To get the real condition for
affordability to pay for water bill, it is need a survey about that.
According to statistical data of 2007, the Sorong city GRDP in 2007 is 1.869 billion rupiahs
and in 2006 1.636 billion rupiahs, it’s shown increasing 14.25 % in one year. The
manufacturing industries sector contributed 25,96 % to GPRD and 16,58 % is contributed
from trade, hotel and restaurant sector. The Sorong city economic growth rate in year
2006 and 2007 each are 15.47 % and 14.25 %. With that growth rate, Sorong City per
capita GPRD are 7.225 billion rupiah in year 2006 and 7.310 billion rupiah in year 2007 or
increased 1,21 %.The figure of main sector of financial activity is shown in Figure 2.3.
There’s no available data for household income and expenditure figure in Sorong City, it is
need survey for detail
For Household category, willingness to pay for monthly water consumption of the
respondents is distributed in a range of Rp. 3,000 to Rp. 5,000, where 97.25% of them are
willing to pay.
The total numbers of employees of PT. Tirta Remu are 131 persons, who are divided into
two departments and one internal bureau. The department levels are General and
Technical departments. PT. Tirta Remu is headed by a Managing director. The duties of
the departments are respectively:
For organizational structure of PT. Tirta Remu is shown in Appendix. E and for
photograph documentation is shown in Appendix. F.
1. Malanu Spring 1
Malanu spring is located in Malanu Village with an elevation of + 101m MSL. The safe
yield of this spring is 5 l/sec based on information from PT. Tirta Remu. This yield was
however measured in the rainy season. The capacity of this spring in the dry season will
decrease considerably. Besides that, Malanu Spring also has a quality problem, because
in the wet season the turbidity from this spring increases significantly. The Malanu spring
is equipped with a spring captation. Because this spring capture is uncovered often many
debris like wood and stone enters the capture.
2. Malanu Spring 2
The Malanu 2 Spring is close to the Malanu 1 Spring and located in Malanu village. The
elevation of Malanu 2 spring is + 93m MSL. The safe yield of the spring is 4 l/sec. The
spring is equipped with a spring capitation. The water quality of the spring is good. The
turbidity is low and is directly supplied to the customers, but the problem is that the
Malanu 2 Spring and Malanu 1 Spring are connected with each other by a pipe and during
the wet season when turbidity in Malanu 1 Spring increases, these worsen the quality of
the Malanu 2 Spring.
3. Rufei Spring
Rufei spring is a small spring owned by PT. Tirta Remu. Rufei Spring is located in Rufei
village with an elevation of +21m MSL. The yield of the spring is 3 l/sec and in the dry
season, the yield drop completely to zero. This spring is during the dry season not
operated. The water quality of the spring is good and is directly supplied to the customers.
1. Remu River
The Remu River is the main river in the PT. Tirta Remu concession area. The river is used
as main water source. The safe yield is 300 l/s. The intake is constructed from concrete at
level of + 20m MSL. The turbidity in the rainy season is high. An important threat to the
quality of the source are the washing, swimming and bathing activities of the local
population mainly on Sundays.
2. Rufei River
Rufei River is located in Rufei village with an elevation of +113m MSL. This river is the
second river used by PT. Tirta Remu as a water source. The safe yield is 10 l/s. The
turbidity of the river is high especially in the wet season. This situation is caused by
serious illegal logging in the catchment area. From this river the water is direct supplied to
the customers without treatment. In the dry season is this not a problem because the
turbidity is very low but in the wet season it becomes a problem because the turbidity is
high. For that reason, the intake of water from this source is stopped during the rainy
season.
The capacity of PT. Tirta Remu water sources is summarized in Table 3.1.
Beside springs and rivers, PT. Tirta Remu also has a deep well but is since 2005 not
operated anymore because when the deep well is operated this disturbs other private
wells near the location of the well.
PT. Tirta Remu have 3 (three) units system for fulfill water demand in Sorong City. In the
following paragraph will be explained about all unit system in PT. Tirta Remu.
Unit system HBM is the main unit system PT. Tirta Remu has. This unit are equip with
intake in Remu River and production plant in HBM. Intake Remu was constructing with
concrete structure and equip with transport pump and generator set for supply electricity.
From intake, raw water will be transport to HBM production unit by GIP pipe with diameter
300 mm as long as 300 m’. The equipment in Intake Remu is shown in Table 3.2 below.
The HBM WTP is located at an elevation of + 61m MSL in Sorong City. Remu River
provides raw water for HBM treatment plant using a compacted system with a capacity
300 l/s. The production units is constructed using reinforced concrete and stone masonry.
It consists of a capture unit and a clear-water reservoir with a volume of 1,400 m3. The
clear water reservoir is equipped with piping inlet, over flow, outlet, chlorine injection unit,
and pumping stations. In production plant, raw water will be treatment with slow sand filter
if the number of turbidity is low and with Rapid Sand Filter if the number is high. The water
treatment processes are describes step by step as follows:
• The raw water is pumped from the water intake into the discharge line and then it flows
to coagulation and flocculation units.
• Flash mixing of coagulant with raw water occurs in the pipe inlet and inlet of
coagulation chamber. Coagulant is injected into raw water flow and the system is
integrated with up-flow and down-flow flocculation units.
WTP HBM also equips by distribution pump and other pump for treatment water and also
equip by generator set for supply electricity. The specification of equipment in WTP HBM
is shown in Table 3.3.
The water sources was supply for this system are consist two sources Malanu 1 and
Malanu 2 Spring. The springs are equipping with spring capture and construct from
concrete. The elevation of the springs are + 101m MSL for Malanu 1 and + 93m MSL for
Malanu 2. Because the quality of the springs is good, the water directly supply to the
customers by pipe GIP ND 150 mm without pass water treatment. The problem of the
system is in Malanu 1 because the spring capture in this spring is uncovered because of
that in the wet season; sediment from around the spring is entered to the spring capture.
Unit System Rufei consists of two water sources Rufei River and Rufei Spring. The
location of water sources are in elevation +21m MSL for Rufei Spring and +115m MSL for
intake Rufei River. The water sources are equipped by Intake in Rufei River and Spring
Capture for Rufei Spring. The construction of both is from concrete structure. The
condition of the building still good and for Intake Rufei is need rehabilitation in Bar Screen
because the hole is big and stone or wood can enter to the intake. Beside that the
transmission pipe from intake o reservoir also need rehabilitation because at this moment
the transmission pipe in several segment located above the ground without supporting
pipe.
The existing reservoirs have two types of filling systems, by gravity from spring capture
and by pumping from production plant. At this moment for the distribution of water to the
customers, PT. Tirta Remu uses 12 (twelve) distribution reservoirs. The reservoirs are
located in Remu, Klademak, Kampung Baru and the Remu Selatan area. The problems
from all reservoirs are:
a. All reservoirs are not equipped with floating valve to control the inlet flow.
b. Some reservoirs are not equip with disinfectant
c. Measuring device is not equipped in the reservoir.
d. In some area, the condition of reservoir is not operated it is need rehabilitation.
The water supply connections are divided into different customers’ categories. The overall
division of connections in PT. Tirta Remu it is presented in Table 3.7. In general
connections are divided in active and non active customers. The active customers are
customers who are paying the water bill in every month, and including the customers who
are not using water but still pay for billing administration. The total number of these
connections in PT. Tirta Remu is 10,441.
Total population of Sorong City in the year 2008 is about 163,483 inhabitants. By
assuming 1 house connection (HC) service 5 people and 1 public tap (PT) service for 50
persons, the total population served is 53,350 persons or 41% coverage. The existing
service coverage is shown in Table 3.8.
PT. Tirta Remu still uses the old PDAM Kota Sorong water tariffs. This system is based on
a progressive tariff, which means that the price per m3/month/customer increases
proportionally to the water consumption. The tariff system per customer category is
presented in Table 3.9. The tariff of PT. Tirta Remu will be change but the draft of tariff is
still in discussing.
Based on water demand prognosis the number of connection in PT. Tirta Remu will
increase from 10.441 units in 2007 to 30.957 unit in 2020. The summary of connection
development in PT. Tirta Remu is shown in Figure 4.2 below.
To calculate the water demand over a period of 15 years, three criteria are taken into
account: coverage, water consumption, and non-revenue water (NRW). These are
summarized in Table 4.3 and explained in more detail below.
Based on water demand prognosis, the total non-revenue water in PT. Tirta Remu will
decrease from 56 % in 2008 to 17 % in 2020. The non-revenue water reduction plan is
shown in Table 4.6.
Water Demand Prognosis PT. Tirta Remu
350
300
250
200
l/s
Water Demand
150
Distribution
Production
100 Raw Water
NRW
50
‐
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Water Demand 67 94 147 184 198 213 218 222 227 232 237 241 247
Distribution 100 138 213 258 268 277 272 267 261 264 267 270 272
Production 107 148 228 276 284 294 288 283 277 280 281 284 280
Raw Water 114 158 244 295 301 311 306 300 293 297 295 298 294
NRW 40 54 81 92 85 81 71 60 50 48 44 42 33
Years
The water demand in figure 4.1 is calculated from the connection prognosis and the
standard water demand in Indonesia. The leakage percentage is based on consultant
prognosis and planning for 2023. The production is calculated from water demand and
leakage
A water demand prognosis has been made in accordance with the population
development. Water demand prognosis is used as a basic design for development of
water supply system e.g. for intake or WTP development.
The detailed calculations of the water demand prognosis are included in Appendix. H
Calculations on the actual water balance of the system follow the subsequent
assumptions:
• Area of service zone system is based on topographic condition of the service network
system;
• Actual production capacity of each source related to each service zone;
• Water sold (billing) according to the related number of connections per connected
area.
The existing production capacity requirements related to the sources is shown in Table
5.1 below.
Table 5.1 Existing demand vs. production capacity in PT. Tirta Remu
Water Demand (l/s)
Zone Total
HBM Malanu 1 Malanu 2 Rufei River Rufei Spring
Production Capacity 140 5 4 10 3 162
Additional production
Total Production 162
Water Demand 67
Idle Capacity 95
Source: Consultant Analyses, 2008
Based on Table 5.1, in 2009 PT Tirta Remu has idle capacity. The additional water
production is needed if the capacity of water production is less than the customer water
demand. There is idle capacity when the capacity of water production is more than the
customer water demand. The existing schematic of water balance system in PT. Tirta
Remu is shown in Appendix. I.
Figure 5.1 Existing schematic of water balance system in PT. Tirta Remu
To calculate the actual non-revenue water of the system, the following steps are taken:
• Calculate the total actual production capacity based on data from PT. Tirta Remu
• Calculate the total actual water sold based on water billing data from PT. Tirta Remu
• Calculate the total non-revenue by dividing water sold by actual production.
5.3 Conclusion
Increasing population growth and consumption level of water in Sorong will be affected to
the demand of water. Considering the high water leakage in distribution and limited
operational time of distribution pumps, it is required to increase water supply from
production unit to each part of the service areas.
Water sources
Another way to cope high water demand is to increase the production capacity in the
system. Therefore, sources at Malanu 1 and 2 need rehabilitation and spring capture
maintenance and then sources of Rufei 1 and 2 need rehabilitation and intake
maintenance to fulfill water demand in the future deep well can be one of the solutions for
additional water sources.
Another way to fulfill the increasing water demand is improving the water supply system
by NRW reduction program. Concerning the NRW for water reduction program, it is
strongly recommended to rehabilitate and re-arrange the scheme. The existing leakage
does not only occur in the distribution system but in the production plant as well.
The main program of NRW reduction is divided into four groups as follows:
• Rehabilitation at the production plant;
• Rehabilitation at the transmission and distribution pipe;
• Rehabilitation at the valves, fittings and pipe accessories;
• Rehabilitation at the reticulation pipe and the costumer connections;
At present PT. Tirta Remu is already implementing a NRW reduction program. The
program proposes to reduce the NRW below 10%.
Concerning NRW reduction, the following activities are recommended at the initial stage:
• Mapping pressure gauge in main pipe all system;
• General calibration in all of the pipe systems using hydraulic simulation software;
• Investigation of physical leakages;
• Identification of leakage locations and damage causes;
• Materials preparation and implementation of the rehabilitation;
• Calibrating all water meter costumers (replacement if necessary);
• Operating the improvement result integrated with the existing system;
• Identification night flow in the area.
Water losses in the system have a major negative effect on water production and
distribution and therefore need to be reduced in order to satisfy water demand.
6.1 General
For the rehabilitation and development of the water supply infrastructure, many factors
must be considered i.e. economic, technical, operational, and sources. For the main
network an information system integrated with leak detection programs to easi the
implementation of system rehabilitation to be developed. In 2009 and 2010 PT. Tirta
Remu will install additional 15,000 new HC. The proposed infrastructure development
should be supported by detailed information including measured data, topographical
measured data, and a detailed engineering design that is needed for all facilities
constructed during the first years.
Development priorities
First priority:
Second priority:
The development period of this master plan is set on a 12-year basis. The implementation
schedule of PT. Tirta Remu water supply infrastructure development is divided into 3
phases:
Each phase is divided into yearly implementation phasing, which means the system will
be gradually improved and rehabilitated every year simultaneously. Extension of the
system will be done parallel to the NRW reduction and the coverage increase.
Based on the field investigation, the following activities should be implemented at the
existing water sources, as high priority as follows:
1. Install a measuring equipment device for all water sources to determine the real
capacity of the water sources.
2. Protection intake Remu, because the existing location of Remu intake always used by
local people for washing, bathing etc and it will be influence the water quality in a bad
way.
3. Install screen in all outlets of broncaptering and intake to prevent material such a wood
or stone enters into the transmission pipe.
4. Rehabilitation Broncaptation of Malanu and Rufei
5. Made study for construct new deep well in such geoelectical study or pilot project.
The existing production unit in PT. Tirta Remu still can cover water demand until years
2010, but in years 2011 it is need additional production unit. Development of new
According to the water demand prognosis, to satisfy the increased water demand and
have sufficient pressure in each service zone, production capacity should be added by
constructing new production units. Development of production units from 2009 till 2020 is
divided in three phases as described in the Table 6.1, 6.2 and 6.3 below.
Table 6.1 Balancing Demand vs Production PT. Tirta Remu Phase 1 in 2009 – 2010
Water Demand (l/s)
Zone Total
HBM Malanu 1 Malanu 2 Rufei River Rufei Spring
Production Capacity 140 5 4 10 3 162
Additional production
Total Production 162
Water Demand 147
Idle Capacity 15
Sources: Consultant Analyses, 2008
Table 6.2 Balancing Demand vs Production PT. Tirta Remu Phase 1 in 2011 – 2015
Water Demand (l/s)
Zone Total
HBM Malanu 1 Malanu 2 Rufei River Rufei Spring
Production Capacity 140 5 4 10 3 262
Additional production 100
Total Production 262
Water Demand 222
Idle Capacity 40
Sources: Consultant Analyses, 2008
Table 6.3 Balancing Demand vs Production PT. Tirta Remu Phase 1 in 2016 – 2020
Water Demand (l/s)
Zone Total
HBM Malanu 1 Malanu 2 Rufei River Rufei Spring
Production Capacity 240 5 4 10 3 262
Additional production
Total Production 262
Water Demand 247
Idle Capacity 15
Sources: Consultant Analyses, 2008
1. Install floating valve in inlet of reservoir to control the inlet flow in the reservoir
especially in Malanu and Rufei reservoir because the location of reservoir is far away
from city in it is hard to control every day.
2. Rehabillitation all broken reservoir
3. Installation of measure instruments for reservoir in the water inflow and outflow.
4. Install screen in the outflow
5. Regularly drain and maintenance of ground reservoir.
6. Installation of water disinfection by chlorine dosing equipment.
The existing reservoir in PT. Tirta Remu is still can cover water demand, but in the years
2020, PT. Tirta Remu need additional reservoir for covering water demand. Based on
water demand calculation, the capacity of new reservoir is 500 m3 and for additional
reservoir, there are alternatives for development a storage system.
• Construct new reservoir in Klademak area.
• Used the existing Slow Sand Filter (SSF) in Klademak as reservoir, because at this
moment the SSF in Klademak is not operated. For this alternative rehabilitation SSF
is needed because SSF do not equip with roof and measuring device in outlet and
inlet.
The water storage as distribution buffer capacity will anticipate the demand fluctuation in
supply zone, especially at times of minimum flow, water will be saving in storage. At peak
hours water will be supplied into the network. Storage facilities related to zone district
locations for all three phases are presented in Tables 6.4, 6.5 and 6.6 below
Table 6.4 Storage for PT. Tirta Remu Phase I (2009 - 2010)
Reservoir Capacity
Zone
HBM Klademak Kampung Baru Remu Rufei Malanu
Reservoir Capacity 1.400 1.050 1.050 820 50 50
Additional reservoir
Total reservoir
4.420
capacity
Reservoir needed 2.544
Idle Capacity 1.876
Source: Consultant Analyses, 2008
Table 6.5 Storage for PT. Tirta Remu Phase II (2011 - 2015)
Reservoir Capacity
Zone
HBM Klademak Kampung Baru Remu Rufei Malanu
Reservoir Capacity 1.400 1.050 1.050 820 50 50
Additional reservoir
Total reservoir
4.420
capacity
Reservoir needed 3.841
Idle Capacity 579
Table 6.6 Storage for PT. Tirta Remu Phase III (2016 - 2020)
Reservoir Capacity
Zone
HBM Klademak Kampung Baru Remu Rufei Malanu
Reservoir Capacity 1.400 1.050 1.050 820 50 50
Additional reservoir 500
Total reservoir
4.920
capacity
Reservoir needed 4.268
Idle Capacity 652
Source: Consultant Analyses, 2008
Bad and damage transmission and distribution pipes is one factor which is related to
leakage rehabilitation. Damaging pipes can happen because the age of the pipes
sociological reason. Sometimes pipe are demaged on purpose by inhabitants for various
reasons.
The first step is to make a plan for the rehabilitation of the existing transmission and
distribution network, which can be done through the following activities:
In this report, development options for transmission and distribution infrastructure are
based on connection growth, water production, and water demand projection.
Considering the network development, a new network should be in accordance with city
planning and existing network facilities. A new pipe should be added parallel to the main
• Rehabilitation main distribution pipe in Neraka Street area, because at this moment all
main distribution pipes are located under constructed houses. The length of the pipes
to be rehabilitated is about 1,400 m’ with various diameters.
• Rehabilitation pipes in Kampung Baru area. Same situation with Neraka Street, all
distribution pipe in that area are located under constructed houses and the length of
pipefor which rehabilitation is required is 5.000 m’ with various diameters.
And for development activities for network extension required for additional house
connection are:
1. Arranging the billing system by district approach; it will be easy to control the
consumption through connection bills and district meter;
2. Performing step and night flow tests in the related district when the bills do not match
the district meter;
3. Domestic water meter replacement.
4. Continuing Block Renovation Program (BRP)
5. Regular customers monitoring by check every month the condition of house
connection.
Development HC PT. Tirta Remu
30000
25000
20000
15000
HC
New connections
10000 Connections begin
5000
0
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Years
• 15.014 units in the first five years, this activity is including 15,000 HC in RNE program.
• 2.500 units in the second five years
• 2.600 units in the third five years
The future schematic system of PT. Tirta Remu is shown in Appendix. J, K and L and for
design of house connection in PT. Tirta Remu is shown in Figure 6.7 below.
7.1 General
From this study, and the projections calculated, a water supply development scheme is
drawn. This scheme includes necessary implementation of production and distribution
facilities in the concerned areas.
The cost estimate is set up with a bill of quantities and basic unit prices. It is not known in
what way the cost estimate will be influenced by future changes of unit prices and re- or
devaluation of the Indonesian Rupiah.
The estimated quantity and the cost estimation for alternative 1 are shown in Appendix.
M and N and alternative 2 are shown in Appendix. O and P.
The calculated estimation of costs for PT. Tirta Remu water supply development project
is shown in the description below. This engineering estimate is based on cost only. The
inflation rate and interest rate is not included in this calculation. The summary of cost
estimation is shown in Table 7.1 and Table 7.2 below.
Concerning the investment costs, the cost estimate is set up from unit cost parameters; a
preliminary Bill of Quantity has been elaborated for project development. It uses the
February 2009 price level as reference.
According to the project staging, necessary adjustment and expansion of the total water
supply system, including raw water resources, the cost per stage are estimated.
Table 7.1: Summary of PT. Tirta Remu investment cost estimation (alternative 1)
x million
Additional cost (35%) including: - VAT, engineering, supervision, insurance, contingencies and risk
Euro : 15.000
USD : 11.000
The total costs are estimated at a sum of Rp. 45,520 million, or Euro 3,0 millions. This
value includes the 21.914 new house connections. This means the average price per new
house connection will be approximately Rp. 2.117 millions, which is ca. Euro 141,-
And for second alternative of investment cost plan in PT. Tirta Remu Sorong is shown
Table 7.2 below.
Table 7.2: Summary of PT. Tirta Remu investment cost estimation (alternative 2)
x million
Additional cost (35%) including: - VAT, engineering, supervision, insurance, contingencies and risk
Euro : 15.000
USD : 11.000
The total costs are estimated at a sum of Rp. 31,930 million, or Euro 2.1 millions. This
value includes the 21.914 new house connections. This means the average price per new
house connection will be approximately Rp. 1,514 millions, which is ca. Euro 100,-
8.1 Conclusion
• At present, production unit in PT. Tirta Remu can fulfill water demand and still have
idle capacity.
• Not all production and distribution units have measurement devices.
• Malanu 1 Spring needs rehabilitation especially in the broncaptering.
• Existing reservoirs can fulfill water the demand until 2020, but actual some reservoirs
cannot operate because some reservoirs have a leaking.
• New reservoir will construct in 2020 for covering water demand and as an alternative is
use existing Slow Sand Filter in Klademak as a reservoir.
• Rehabilitation of the distribution system is necessary because at this moment the
distribution system is partly located below houses.
8.2 Recommendation
• It’s recommended to establish groundwater protection area’s of recharge area of
groundwater to ensure sustainability of spring and deep well flow rates for the future.
For this purpose water company institutions have to cooperate with Forestry Agency to
implement re forestry programs.
• The local government must control land use tightly to prevent settlement in the
recharge area of ground water protection zone.
• Saline water conversion is one of possible source for further development (beyond the
year of 2023) if all other possibilities for additional sources is not feasible.
• It’s recommended to increase human resource skill by training or course.
• Detailed data collection by detailed measuring program surveys to achieve more
accurate source data, actual production, and water distribution capacity.
• Detailed field surveys to find all potential sources and all data concerning service
areas, infrastructure conditions and others water supply facilities.
• To recondition existing production capacity, the consultant recommends a
rehabilitation and reparation of the old existing water production units. Implement
pumping systems with high efficiency to safe electricity consumption and to be cost
effective. The existing pumping has to be rearranged and improved according to the
new operational scheme.
• It is suggested to calibrate domestic water meters periodically and make sure that
meters still work accurately. Normally, meters will work accurately with a good water
quality and suitable pressure, otherwise they will easily damage.
• At the main feeder of the network, it is necessary to implement a bulk water meter.
This flow meter can control the distributed water and can be useful in calibration
system with network simulation. At the main branch line/service pipe, it is suggested to
implement a district meter to control a capacity of customers.
• Detailed engineering design (DED) of all projects has to be prepared before physical
implementation.