China Harbour Engineering Co.L.L.C.

CHECK LIST FOR CONCRETE REPAIRS


SUBCONTRACTOR : HUNAN general contracting L.L.C CONTRACTOR: CHEC

SECTION OF WORK : CIVIL LACATION : RAS AL KHAMAIH

LEVEL :

CHECKED BY DATE
STATGE ITEM
S/C CHEC DORSCH
Concrete Repair Materials Approved
1.Preliminary
check Method Statement, QCP, ITP & RA approved

All concrete surfaces defects/honeycombs identified


and marked at site.

Check defective concrete/honey Combs are


removed

Check edges of all repairs should be cut vertically to


minimum depth of 10mm
2.backfilling &
Check all repairs areas shall be cleaned, sound and
compaction
free from all dust, loose material and oil/grease
marks.

Check repair mortar mixing for consistency.

Check thickness of application exceeds 50mm


thickness and shall be applied in layers , each layer
not exceeding 40mm thick.

FOR S/C QA/QC : FOR CONTRACTOR QA/QC : FOR DORSCH REP :

Name: Name: Name:

Sign: Sign: Sign:

Date : Date : Date :