Module 3 Quiz

SCORE: 100%
PASSED

Question 1
Correct
What are the Project Integration Management processes?
Your answer: Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Monitor & Control Project Work Perform
Integrated Change Control Close Project or Phase

Question 2
Correct
The processes associated with Integration management are which of the following?
Your answer: Develop Project Charter. Develop Project Management Plan, Direct and Manage Project Work, Monitor and Control Project Work, Perform
Integrated Change Control. Close Project or Phase

Question 3
Correct
What is the purpose of a Work Authorization System?
Your answer: Both A and B

Question 4
Correct
The charter for your commercial construction project has been signed off. In the charter it is stated that the height regulation in the neighborhood in
which the building is being built is 4 stories. What is this an example of?
Your answer: Constraint

Question 5
Correct
Your software development project has completed the planning processes and appropriate parties (sponsor, steering committee, and senior
management, etc.) have agreed to move the project into the executing phase. What do you have developed from which you can measure success?
Your answer: Project baselines

Question 6
Correct
If you are taking inputs of the project management plan, work performance reports and change requests, on which process are you working?
Your answer: Perform integrated change control

Question 7
Correct
Which of the following are not a part of the project management plan?
Your answer: Budget management plan

Question 8
Correct
If you are unable to get signoff on the final delivered product due to unclear standards or undocumented acceptance criteria, you have failed at which
area?
Your answer: Quality management

Question 9
Correct
"You are asked to give an opinion on which of 4 projects should be the highest priority next quarter. The project are: 
Project 1: NPV = $67,000 
Project 2: NPV = $50,000 
Project 3: NPV = $30,000 
Project 4: NPV = $20,000 
What is your recommendation?"
Your answer: Project 1

Question 10
Correct
You are on a project selection committee and you are developing a tool to help in the selection. The committee has decided on what 6 factors are
relevant to the selection and have determined the factors' relative value. What type of tool are you developing?
Your answer: Weighted Scoring model

Question 11
Correct
What is the purpose of a Change Control Board?
Your answer: To evaluate proposed project changes and determine whether to move forward with them.
Question 12
Correct
When the final product or service of a project is delivered or made available to the customer or sponsor, this marks an outputs for which process?
Your answer: Closing Project

Question 13
Correct
You are beginning a product development project with the objective to create a new mobile app for smart phones. The best time to begin capturing
lessons learned is _____.
Your answer: As soon as any stakeholder identifies something that would be improved in the future.

Question 14
Correct
A Business Case justifies the creation of what?
Your answer: A project

Question 15
Correct
All of the following are components of the project management plan except which of the following?
Your answer: Risk Register

Question 16
Correct
As the project manager of a house construction project, you are regularly visiting the job site to determine if the construction crew is on time with their
work and to check the quality of that work. While there you discuss any issues that the crew is having with the construction site or working conditions.
What process are you working on?
Your answer: Monitor and control project work

Question 17
Correct
All of the following are examples of project documents except _______.
Your answer: WBS

Question 18
Correct
Rebalancing the resource load after getting a new contractor onboard is an example of which of the following?
Your answer: Corrective action

Question 19
Correct
You recut the frame for a custom portrait because the first frame was cut 1/2 inch too small. This is an example of which of the following?
Your answer: Defect repair

Question 20
Correct
Configuration control is a subset of which of the following?
Your answer: Change control