NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
REVISION HISTORY
Rev. CONTRACTOR-CCECC Status of
Date Prepared Reviewed Approved Revision History ENGINEER
No. Approval
First Submission
0 25/03/2017 following award of
Contract
CONTENTS
Contract Name: Contractor:
NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
2.0 Definitions
3.0 References
4.0 Subcontractors
5.0 Materials
7.0 Safety
9.0 Procedure
10.0 Responsibilities
11.0 Attachments
Contract Name: Contractor:
NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
SCOPE:
This Method Statement defines the procedures to be followed in installation of Low
voltage cables.
PURPOSE
The Purpose of this method statement is to ensure that correct cables are
installed and agreed procedures are implemented during execution of the
previously described work.
REFERENCES
Project Specification
IEC 60228, BS 6360.
BS 5467.
Project Drawing
DEFINITION
LV – Low Voltage
RESPONSIBILITES
Contract Name: Contractor:
NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
METHOD OF WORK
Material
Power Cables (LV)
ELV Cables
Equipment/ Tools
Manual Crimping Tools
Cable Rollers
Cable Spindle and Jacks
Cable Drum Trolleys
Scaffolding Step Ladder
Pulling Wires Rope, Lubricant (Soap based, wax based)
Hand Tools-gloves, Cable cutter, measuring tape, pliers, screw drivers,
puncher, cutting saw, spanner and etc.
Personal Protective Equipment
Testing Equipment
LV Insulation resistance tester
Multi-meter
Current & Voltage meter
Material Handling and Storage
Store materials in protected dry location off-ground in accordance with
manufacturer’s instructions and to protect from mechanical damage or
weather effects, etc. Extreme care will be taken while handling the subject
materials.
Lay down area at site to be coordinated with main contractor and
arrangements to be made for unloading and/ or mobilization of materials.
Contract Name: Contractor:
NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
Once the conduit is not blocked the wires shall be pulled using the draw
wires while ensuring no damage occurs while pulling.
Pulling compound or lubricant shall be used for pulling wires where required.
Use soap-based pulling compound for the runs greater than 20 Meters for
semi conductive insulated wires.
While pulling the wires, care will be taken to not insert the pull tension
greater than manufacturer’s allowed limits.
Wiring Installation for Small Power and Lighting & Low Current Services
Materials will be checked against project specifications.
Low current service wirings / cables are to be laid in trunkings separate from
power wirings / cables.
Prepare mock up installations where applicable; seek its approval prior to
commence of the next other typical works.
Required conduit sizes will be used. Conduit’s sharp internal surfaces will be
removed and bends will be limited following standard practice. Sharp conduit
bends will not be permitted. Placing of conduits will be embedded during the
concrete casting and in block wall. Conduits can be run fixed at the soffit or to
be laid on the concrete screed. Conduit laying will be as per approved
drawings and specifications.
After ensuring that conduits are in placed a guide wire or fish line will be
inserted in preparation for wire pulling. Whenever a bunch of wires are to be
pulled a rope and basket weave wire will be required in order to hold the
conductors to be pulled together.
Wires or conductors will be pulled simultaneously and pulling lubricant will
be used when necessary. Wires or cables will have sufficient slack at both
ends for convenience in connections and maintenance.
Cables, wires and connectors, utility, junction boxes, pull boxes will be as per
specified type or class. As soon as the conductors reaches the panels, boxes,
raceways it will be tagged. Wires and cables will have identifications, labels or
tags at both ends.
Manufacturer’s recommendations will be followed during work execution.
Wires or cables will have sufficient slack at both ends for convenience in
connections and maintenance.
Pulling of wires, cables will not exceed manufacturer’s recommended
tension.
Any damaged conduits during the construction stages will be reported to
proper authority and the same will be repaired immediately.
Electrical Fittings will be inspected and ensured they are securely fixed as
per the installation detailed drawings.
Contract Name: Contractor:
NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
The location, level and alignment of fittings shall be checked, fixtures will be
installed only after the approval of wiring installation or during testing only.
Stability of fittings and fixtures assembly will always be considered.
After the installation, the required tests (type, sample & routine) are to be
carried out as stated in this Specification
Low Current System Wiring Test
Applicable test will be conducted for low current system wirings to ensure
continuity and no shorts and grounded wires exist prior to terminations to all
devices / equipment.
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
Cables will be capped and sealed on both ends after installation until
termination is due.
Termination shall be done by using the approved termination materials that
include glands, lugs and other accessories part of termination kit by using
proper crimping tools. Matching color gland sheaths shall be provided.
All termination will be provided with tight fit covering sleeves.
All work to be done under the attendance of safety officer/s.
Cables Identification
Install the tags/labels as per project specifications and as per approved
material submittals.
When completely erected, each cable and wire shall have permanently
attached to it at each end and at intermediate positions.
Non-corrodible metal plates upon, which the identification number of the
cable, voltage rating, conductor size and make shall be engraved or stamped.
For cables at feeders, identification will be done as per specification and
approved materials.
Safey
All appropriate safety personal protective equipment shall be worn by
workmen such as Helmet, cover all clothing, safety shoes, goggles and gloves
whenever required.
Only approved scaffoldings & safety belts can be used on high level works.
Fire extinguisher shall be positioned in the event where energized cable
is/are present on work place.
1. Scope:
1.1 This Method Statement covers the installation and laying of pipes.
2. Definitions:
2.5 UG Underground
Contract Name: Contractor:
NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
3. References:
4. Subcontractors:
4.1 None
5. Products:
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
6.2 Excavators
6.14 Ladders
7. Safety
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
b)-Excavation Collapse:
d)-Crane Accidents:
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
Check excavations and pipes for snakes and scorpions before entry.
8. Prior Activities:
8.3 Check all pipes free of cracks and chips or damage to linear
9. Procedure:
All activities carried out will comply with the JV Inspection Test Plan which reflects the testing requirements
of the Contract documents.
9.1 Prepare the Construction Drawings and submit to the Consultant to get his approval prior
to starting any excavation works.
Note: Only the drawings marked as approved “Issued for Construction” are allowed to be
used by the Site Staff.
Contract Name: Contractor:
NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
Note: The Engineer’s Inspector will be notified if any areas are over excavated or
unsuitable materials are encountered, in which case replacement material will be
used.
9.5 The formation level will be to the required lines and grades as detailed in the approved
Shop Drawings.
9.6 The trench formation shall be compacted to 98% MDD or to the soil bearing value.
Note: Formation compaction is a Hold Point and will be confirmed by the Engineer’s
Inspector before proceeding with the bedding.
Note: The pipe installation is a hold point and lines and levels must be checked and
approved by the Consultant’s Inspector before other work proceeds. Any
adjustment in the line and grade shall be made by scrapping away or filling and
tampering in under the barrel of the pipe.
9.7 Trailer with hoist crane shall be used for shifting pipes from yard to the site.
9.8 End lifting hooks for lifting the pipes shall be insulated with rubber sleeve to prevent
damage to cement lining and other coating.
9.9 Stacking of pipes along the trench side opposite to the excavated material heap with the
sockets pointing the direction of laying. Transportation, storage and handling of pipes will
be according to the manufacturer’s instructions.
9.10 A single wide flat sling shall be used to lift the pipe at its center of gravity and in order to
lower the pipe into the trench.
9.12 All open ends to be plugged when pipe laying is not in progress
9.13 The socket of the pipes shall be carefully cleaned to eliminate all soil and sand.
9.14 Check the gasket condition and place it in its seat, looping it into the shape of a heart for
insertion.
9.15 Apply the lubricant paste to the exposed surface of the gasket and the pipe spigot.
9.16 Insert the spigot, checking the alignment of the assembled components, until the jointing
mark on the spigot is in line with the socket face.
Contract Name: Contractor:
NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
9.17 Clamps and chains shall be used for jointing pipe and straight fittings.
9.18 In order to avoid damage to the coating of the pipes, it is essential to use rubber paid at the
points of contact between chains and pipe.
9.19 Any joint deflection required shall be made only after the completion of the joint.
9.20 Flanged joint is to be made using flat gasket and bolt shall be inserted and must be turned
to fingers tightness. Thereafter the final tightening of the nuts to be completed by the toggle
spanners in such sequence that diametrically opposite must be tightened together.
All valves and fittings to be installed as per the approved shop drawing.
All pipes, fittings, valves etc. will be carefully lowered in the trench with suitable
equipment in a manner that will prevent damage and all foreign materials shall be
removed from inside the pipes and fittings before being lowered into position.
Valves, fittings, adapter, meters, fire hydrant, etc which are housed in concrete
chambers shall be protected to avoid damage to the factory applied coating. Pipe
ports and fittings inside the chambers with bituminous coating to be protected with
approved paint.
Backfilling:
Pressure test.
01. The hydrostatic pressure testing of pipeline shall be carried out on section of completed
pipelines as approved by the engineer.
02. Complete construction of pipeline with all thrust blocks and valve chambers for a
particular section to be tested in accordance with the approved Construction drawing.
03. Before commencement of pressure testing of a particular section, all the line valves will
be opened to prevent pressure being applied against closed valves.
04. Install test heads with provision of bleeding air vent at the highest point.
Contract Name: Contractor:
NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
05. Install test heads with provision of filling water at the lowest point of the pipeline.
06. Calibrated pressure gauges will be installed at both ends of the pipeline.
07. With approval from Engineer, the water from pressure testing shall be taken from
existing fire hydrant, washout or air release valve, whichever is nearer to the filling point.
08. Subsequent to obtaining approval from the client, the filling of water and testing shall
commence.
09. During the water filling all air in the pipeline shall be expelled through the air bleeding
nozzles installed at the highest.
10. The pressure in the pipeline shall be raised steadily by a small capacity high-pressure
positive displacement pump until normal operating pressure of 6 bars is reached.
11. The pipeline shall be maintained at 6 bars pressure for a minimum of 24 hours soaking
period during which a record of the water added to maintain the 6.00 bar pressure shall
be kept.
12. In case of any visible leaks during inspection, the particular section shall be repaired to
the satisfaction of the Engineer after which the 24 hours soaking period shall be
repeated at 6 bars pressure.
13. Upon satisfactory completion of 24-hour soaking period the pipeline shall be brought to
the test pressure of 9 bars and maintained at this pressure, by pumping if necessary.
14. Subsequently, the pump shall be disconnected and further water allowed to enter the
pipeline for a period of 1 hour and at the end of this period the pressure will be recorded.
15. The pump will be reconnected, if a pressure drop is noted and the original pressure (9
bar) will be restored in the pipeline. The water pumped into the pipeline to rebuild the
pressure will be collected in a calibrated tank. The volume of the water used to rebuild
the pressure to 9 bars shall not exceed (0.1litre/mm of diameter/KM of
length/24hours/30metres of head)
Note. IN case leakage exceeds permissible allowance, the leakage spot shall be detected and
remedial work shall be carried out and the pressure test shall be repeated until
satisfactory pressure test is achieved.
10. Responsibilities:
10.1 It is the Construction Manager’s duty to ensure that all necessary safety and protective
equipment are provided along with properly trained and qualified personnel.
10.2 It is the Site Supervisor’s/Agent duty to organize the work in a safe manner to ensure
that safety and protective equipment are being properly utilized. He must also assure
the method statement procedure is followed and must observe the Hold-points and
Contract Name: Contractor:
NEW WATER SUPPLY NETWORKS FOR MISUNGWI, MAGU AND LAMADI M/S. CHINA CIVIL ENGINEERING
CONSTRUCTION CORPORATTON
(CCECC)
Project Engineer: EGIS EAU/IA/ICE
Project No.: AE/042/2015-2016/W/02
Document Category:
Agreement No.:
Method Statement
Project Title: LAKE VICTORIA WATER AND SANITATION PROJECT (WATER SUPPLY, Procedure No.:
WASTE WATER AND SANITATION) FOR MWANZA CITY, MISUNGWI, MAGU AND LAMADI
10.3 It is the worker’s duty to properly wear the protective equipment provided and obey all
safety rules. He must also perform the work as described in the method statement
procedure.
10.4 The Site Engineer will ensure that the site preparation activities are conducted
according to the approved method statement.
10.5 The Material Engineer will ensure that the materials being used are in accordance to
the project specifications and the approved method statement.
11. Attachments: