JOB HAZARD
ANALYSIS PERFORMED BY: VERIFIED BY: TITLE OF EMPLOYEE DOING
JOB:
NEW
PERSONAL PROTECTIVE EQUIPMENT USED: Hard Hat, Safety Shoes, Hand Gloves, Safety Harness.
REVISED
EXISTING AND POTENTIAL
SEQUENCE OF BASIC JOB STEPS RECOMMENDED CORRECTIVE MEASURES
HAZARDS
Ensure the emergency equipment will not be
Location of Emergency Equipment near
blocked or damaged due to scaffolding
the proposed Scaffolding
erection.
Pre – Work Refer SSI Safety Program
Non-compliance of SSI Safety Program Obtain hot work permit
Conduct Tool Box Talk
Unauthorized erection of scaffolding Obtain the Cold Work Permit.
Take extreme care during removal and override
Damage to onsite detectors or switches
it if needed.
Take proper care while dismantling the scaffold
to prevent fall of scaffold parts.
Hand tools to be tied with permanent structure
Fall of objects / Tools. or person.
Use proper PPE during removal of scaffold.
If required barricade the area during dismantle
work.
Dismantling of Scaffold The Scaffolder must use Safety Harness to
Accidental Fall of Person
prevent accidental fall .
Inspect the scaffold for its stability & support
Unstable Scaffold
before removing in sequence.
Remove safely the load / equipment / plant from
Loaded Scaffolding
the scaffold before dismantling the scaffold.
The scaffolding is to be inspected for any
damage before dismantling.
Damaged Scaffold
Take extreme care while removing a loose part
/attachment from the scaffold.
Arrange the dismantled parts of the scaffold
and stack properly.
Scattered Materials
Segregate different parts of scaffold and store it
Housekeeping
separately.
Remove and discard the defective parts /
Defective Part
attachment from the scaffold storage.