Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
mohammadreza.habibi@mavs.uta.edu
2
Assistant Professor, Dept. of Civil Engineering, Univ. of Texas at Arlington, 425
Nedderman Hall, 416 Yates St., P.O. Box 19308, Arlington, TX 76019
(corresponding author). E-mail: sharareh.kermanshachi@uta.edu
3
Ph.D. Student, Dept. of Civil Engineering, Univ. of Texas at Arlington, 425
Nedderman Hall, 416 Yates St., Arlington, TX 76019. E-mail:
elnaz.safapour@uta.edu
Abstract
Construction projects have been rarely completed at the estimated cost and
time as it is forecasted approximately more than 50% of projects face significant
delay and major cost escalation. Hence, it is of importance to investigate the main
schedule and cost performance indicators of engineering, procurement, and
construction (EPC) projects and address these challenging issue. In spite of the fact
that a vast range of studies conducted to identify the leading performance indicators
(LPIs), lack of consistency between these indicators has been a matter of debate
among construction practitioners and scholars. Furthermore, since construction phase
activities consume the largest portion of the project budget and time, most of the
previous studies concentrated solely on the performance of construction phase. As a
result, the performance of engineering and procurement phases has received the least
attention. Therefore, this study will review numerous existing research documents to
collect the identified leading time/cost performance indicators and then prioritize
them based on their frequency of occurrence in the literature. To accomplish this
objective, over 200 peer-reviewed papers from different parts of the world have been
studied and a vast range of LPIs in each EPC phase was identified. This study
concludes that the principal common cause of delay and cost overrun in both
engineering and construction phases is “design change.” Moreover, the schedule and
cost performance of procurement phase can be highly affected by “resource shortage”
and “price fluctuation” respectively. Although, it is proven that any delay in the
project causes cost overrun, the other root causes of cost escalation lie in “poor
economic condition,” “poor communication between different stakeholders” and
“severe weather condition.” The findings of this review assist construction
practitioners to provide required resources properly and help academic researchers to
conduct their future studies by presenting an extensive phase-based review of
time/cost performance.
INTRODUCTION
Construction process can be examined in three main phases namely (1)
Engineering phase (2) Procurement phase (3) Construction phase known as EPC
© ASCE
METHODOLOGY
To fulfill the objectives of this study, more than two-hundred peer-reviewed
journal articles, conference papers, dissertations and research reports focusing on cost
overrun and delay were identified and collected. The identified academic sources
have been published in a period of 46 years, between 1971 and 2017. As a result of
this research, 115 journal articles have been found examining the LPIs in construction
industry. Since the number of identified related journals was adequate, the authors
decided to only focus on journal articles as their publications undergo a more rigorous
review process. It was observed that most of the highly cited studies concentrated on
the identification of the construction phase LPIs and were published in one of the
following journals: “International Journal of Project Management”, “Journal of
Construction Engineering and Management”, “Construction Management &
Economics”, “Journal of Management in Engineering”, “Engineering, Construction
© ASCE
and Architectural Management”, etc. According to our research, most of the studies
conducted their research methodology in two sequential steps to identify the LPIs. As
a first step, different methods of data collection were adopted to accumulate a list of
potential performance indicators including literature review, interview, case study,
and pilot survey. Often, an integration of several methods was employed to identify
these performance indicators. Almost all the papers designed a questionnaire to assess
the perception of active construction practitioners. Diverse data analysis techniques
Downloaded from ascelibrary.org by University of Texas at Arlington on 04/06/18. Copyright ASCE. For personal use only; all rights reserved.
were used to analyze and evaluate the results of the collected questionnaire responses.
Relative Important Index (RII), Severe Index (S.I), Important Index (I.I), Mean Score
(M.S), Frequency Index (F.I) are typical examples to illustrate some of these
techniques.
As Figure 1 illustrates, the trends of the utilized data analysis techniques in
published papers from 1990 to 2017 were studied and investigated. It should be noted
that since a few number of papers in our database was published prior to year 1990,
they were not considered in the trend analysis section of this study. Since this
research has been conducted in the middle of year 2017, the last time interval group
(2015-2020) has not been completed yet and therefore, its results have been combined
with the precedent group (2010-2015). As it is shown in this Figure, although the
utilization of RII remained constant during 2000 to 2005, however, it significantly
increased afterwards. This trend proves that RII data analysis technique has found
more popularity in the last decade.
© ASCE
Fig
gure 2. Perccentage of papers accorrding to the utilized datta analysis ttechniques
REESULTS
Eng gineering Phase
Ph Cost an nd Schedulee Performan nce
Engineeering is a proocess in whiich the owneer’s requiremments includding wishes,
dessires, and neeeds are ideentified and designed too be submittted to the ccontractors.
Num merous imp portant decisions are made durinng the pre-project plaanning and
enggineering phaase to appropriately allo ocate large ammount of funnds and otheer resources
to the
t project. AsA these deccisions highlly affect the successful ccompletion oof a project,
enggineering ph hase has the advantage of o having thhe highest leevel of influeence on the
proj
oject (Liao ett al. 2011). Although a number of rresearchers devoted theiir resources
to identify
i perfformance ind dicators in construction
c phase, enginneering phase has been
deddicated the leeast attention
n in construcction industrry (Yang andd Wei, 2010)).
Marzouuk et al. (20008) conducteed a questionnnaire to ideentify the keey causes off
enggineering-rellated delayss. To serve this purposse, the percception of cconsultants,
conntractors, andd employerss was targeteed. The mainn engineerinng- related ddelay causes
werre classified d into threee following main grouups: (1) dessign develoopment; (2)
worrkshop draw wings; and (3 3) project parrties’ changees delays.
Yang and
a Wei (20 010) conclu uded that cliients, plannners, and deesigners are
respponsible forr the most important delaysd happeening in thee planning and design
phaases. “Change in client’s requirem ments” is thhe main reaason that ddeviates the
sch
hedule perfo ormance off initial ph hase of coonstruction projects foollowed by
“coomplicated administratio
a on process of client”, and “insuffficient or illl-integrated
bassic project daata”.
Table 1 displays thhe Frequency y (F) and Raanking (R) oof top frequuent LPIs in
enggineering ph hase. It shou uld be noted d that the fr
frequency off LPIs in thhis phase is
signnificantly loower than th hat of otherr phases. T This is mainnly because of lack off
atteention to thhis significan nt phase by y the researrchers especcially in terrms of cost
perrformance. Based
B on thhe results off this studyy, “design cchange” is tthe primary
enggineering ph hase perform mance indicattor which h as been conncluded 13 ttimes as the
sch
hedule perfo ormance ind dicator and 7 times ass the cost pperformancee indicator.
“Slowness in making
m deciisions by ow wner” and ““delay in appproval stagee” both are
placced in the seecond positiion of the scchedule perfformance inddicators list.. These two
LPIIs were cateegorized into o the client-- related grooup and accoording to Suun & Meng
(20
009), design changes by client are also very com mmon duringg the engineeering phase.
Hen nce, we can nnot neglect the significcant role of the client iin time perfformance off
inittial phase.
© ASCE
© ASCE
causing cost overrun. These two LPIs are classified in “external group” meaning that
none of construction stakeholders (client, consultant, and contractor) have any control
or impact in this regard.
© ASCE
(2012) investigated the main corrective measures and Kermanshachi et al. (2016a,
2016b) identified management strategies which reduce design changes and eliminate
unnecessary delays and cost overruns. In this regard, Safapour et al. (2017)
investigated how implementation of change management process could significantly
prevent potential design changes.
Chan and Kumaraswamy, (1997) undertook a survey to gain perception of
clients, consultants and contractors about eliciting the significant delay indicators
Downloaded from ascelibrary.org by University of Texas at Arlington on 04/06/18. Copyright ASCE. For personal use only; all rights reserved.
during the construction phase. Based on the experience of the practitioner, “poor site
management and supervision”, “unforeseen ground conditions”, and “low speed of
decision making involving all project teams” are the most important indicators
harming the schedule of construction and causing delay in local building projects in
Hong Kong.
Since construction is too risky by nature, cost overrun is a very common
matter happened throughout history in construction industry. The main sources of
these risks can be divided into two groups; controllable and uncontrollable risks.
Often, there is no control or little control over the uncontrollable indicators by
contractors such as unforeseen conditions (Akinci & Fischer, 1998). A careful
analysis of 40 public infrastructure projects by Al-Hazim et al. (2017) indicates the
high importance of unforeseen conditions such as severe weather and terrain
condition on the construction phase cost and schedule performance.
Table 3 displays the distribution of top ranking LPIs in construction phase. It
should be noted that the frequency of LPIs in construction phase is higher compared
with that of other phases, as a vast range of authors focus on the performance of this
phase. Same as engineering phase, “design change” also seems to play a decisive role
in cost and schedule performance of construction phase. It is ranked first in both
schedule and cost performance groups with 28 and 14 citations respectively.
Regarding schedule performance, “poor site management and supervision”, “severe
weather condition”, and “financial issues by client” are other LPIs which can cause
delay in time performance of construction project. On the other hand, in addition to
“design change”, it is found that “severe weather condition”, “laws and regulations”,
and “inaccuracy and deficiencies in cost estimates” have also the most influence in
increasing the cost of construction phase.
© ASCE
DISCUSSION
Based on the information collected from over two-hundred papers, 121
indicators were identified and classified into thirteen groups including: change,
consultant, labor, client, contractor, material, equipment, external, project,
management, sub-contractor, planning-scheduling-estimating, and contract. We
examined each EPC phase from two main perspectives: schedule performance and
cost performance. The identified indicators are spread to the related schedule/cost
Downloaded from ascelibrary.org by University of Texas at Arlington on 04/06/18. Copyright ASCE. For personal use only; all rights reserved.
performance groups of each EPC phase based on the paper of origin. The frequency
of each indicator was also calculated to identify the LPIs.
Figure 3 demonstrates the distribution of top 10 LPIs in different groups
according to phase-based time/cost performance. As it is seen, External group has the
largest portion of indicators among all groups with 10 indicators in all EPC phases.
Most of the LPIs in “external group” are related to economic, governmental and
unforeseen conditions. “Price fluctuation”, “law and regulation”, and “severe weather
and terrain condition” are perceived to be the main LPIs in “external group”. Based
on the Figure 3, “management” and “consultant” groups occupy the subsequent
positions (after External) with 8 and 7 indicators respectively. It is notable that each
of these three groups includes LPIs at least from two different EPC phases. Other
groups either have a small number of indicators or they are related to only one EPC
phase. For instance, sub-contractor, planning-scheduling-estimating, and contract
groups do not have any LPIs among the top ten LPIs in all EPC phases.
© ASCE
research, a list of the most frequent LPIs, along with popular data collection and data
analysis methods in the literature were identified.
Based on this study, “design change” has been found to have the most
significant indicators affecting the schedule/cost performance of engineering and
construction phase. Besides, “resource shortages” and “price fluctuation” are two
most frequent indicators causing delay and cost overrun in procurement phase.
Furthermore, by dividing all performance indicators into thirteen groups, it has been
Downloaded from ascelibrary.org by University of Texas at Arlington on 04/06/18. Copyright ASCE. For personal use only; all rights reserved.
found that “external group” has the largest portion of time/cost performance
indicators among all groups in all EPC phases, followed by the “management”, and
“consultant” groups.
The finding of this paper creates the ground for construction professionals to
recognize the LPIs endangering the schedule/cost performance, and assists them to
allocate resources properly during the lifecycle of the construction projects.
Furthermore, identifying the LPIs helps practitioners to proactively prepare
themselves with the preventive strategies and corrective best practices before and
after facing schedule and cost overrun. It also provides a comprehensive
understanding of delay/cost overrun causes for academic researchers to undertake
their future related-studies in this field and guides them to examine all phase-based
indicators in more details based on various project sizes and project types. Under such
circumstances, they would be able to make a comparison between delay and cost-
overrun sources within different industries.
REFERENCE
Akinci, B., & Fischer, M. (1998). “Factors affecting contractors' risk of cost
overburden”. Journal of Management in Engineering, 14(1), 67-76.
Al-Hazim, N., Salem, Z. A., & Ahmad, H. (2017). “Delay and cost overrun in
infrastructure projects in Jordan”. Procedia Engineering, 182, 18-24.
Ameh, O. J., Soyingbe, A. A., & Odusami, K. T. (2010). “Significant factors causing
cost overruns in telecommunication projects in Nigeria”. Journal of
Construction in Developing Countries, 15(2), 49-67.
Chan, A. P., & Chan, A. P. (2004). “Key performance indicators for measuring
construction success”. Benchmarking: an international journal, 11(2), 203-
221
Chan, D. W., & Kumaraswamy, M. M. (1997). “A comparative study of causes of
time overruns in Hong Kong construction projects”. IPMA, 15(1), 55-63.
Dao, B., Kermanshachi, S., Shane. J., Anderson, S., and Hare, E. (2017). “Exploring
and Assessing Project Complexity,” ASCE Journal of Construction
Engineering and Management, 143(5) 04016126.
Faridi, S., & El‐Sayegh, M. (2006). “Significant factors causing delay in the UAE
construction industry”. Const. Mgmt. and Economics. 24(11), 1167-1176.
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003). Megaprojects and risk: An
anatomy of ambition. Cambridge University Press.
Kamalirad, S., Kermanshachi, S., Shane, J. and Anderson, S. (2017), “Assessment of
Construction Projects’ Impact on Internal Communication of Primary
Stakeholders in Complex Projects,” Proceedings for the 6th CSCE
International Construction Specialty Conference, Vancouver, Canada May
31-June 3.
© ASCE
Kermanshachi, S., Dao, B., Shane. J., and Anderson, S. (2017), “Uncertainty Analysis
of Procurement Phase Performance Indicators Using Extreme Bounds
Analysis (EBA),” Proceedings of the 6th CSCE International Construction
Specialty Conference, Vancouver, Canada May 31-June 3.
Kermanshachi, S., Dao, B., Shane, J., and Anderson, S. (2016). “An Empirical Study
into Identifying Project Complexity Management Strategies,” Elsevier
Journal of Procedia Engineering, 145, 603-610.
Kermanshachi, S., Dao, B., Shane, J., and Anderson, S. (2016). “Project Complexity
Indicators and Management Strategies–A Delphi Study,” Elsevier Journal of
Procedia Engineering, 145, 587-594.
Le-Hoai, L., Dai Lee, Y., & Lee, J. Y. (2008). “Delay and cost overruns in Vietnam
large construction projects: A comparison with other selected countries”.
KSCE journal of civil engineering, 12(6), 367-377.
Liao, P. C., O’Brien, W. J., Thomas, S. R., Dai, J., & Mulva, S. P. (2011). “Factors
affecting engineering productivity”. J. of Mgmt. in Eng., 27(4), 229-235.
Mahmoud-Jouini, S. B., Midler, C., & Garel, G. (2004). “Time-to-market vs. time-to-
delivery: Managing speed in Engineering, Procurement and Construction
projects”. International Journal of Project Management, 22(5), 359-367.
Mansfield, R., Ugwu, O., & Doran, T. (1994). “Causes of delay and cost overruns in
Nigerian construction projects”. Int. J. of Project Mgmt., 12(4), 254-260
Marzouk, M., El-Dokhmasey, A., & El-Said, M. (2008). “Assessing construction
engineering-related delays: Egyptian perspective”. Journal of Professional
Issues in Engineering Education and Practice, 134(3), 315-326.
Mohamad, M. I., Nekooie, M. A., Al-Harthy, A. B. S., & Amur, B. (2012). “Design
changes in residential reinforced concrete buildings”. J. of Construction in
Developing Countries, 17(2).
Mulholland, B., & Christian, J. (1999). “Risk assessment in construction
schedules”. J. of construction engineering and management, 125(1), 8-15.
NEDO. Building, E. D. C. (1987). “Achieving Quality on Building Sites”. London.
Nethery, S. K. (1989). “Model planning and controlling system for engineering,
procurement and construction of industrial projects”. In Project Controls:
Needs and Solutions (pp. 1-10). ASCE.
Pocock, J. B., Liu, L. Y., & Tang, W. H. (1997). “Prediction of project performance
based on degree of interaction”. J. of Mgmt. in Eng., 13(2), 63-76.
Safapour, E., Kermanshachi, S., Shane, J. and Anderson, S. (2017), “Exploring and
Assessing the Utilization of Best Practices for Achieving Excellence in
Construction Projects,” proceedings of the 6th CSCE International
Construction Specialty Conference, Vancouver, Canada May 31-June 3.
© ASCE
Said, H., & El-Rayes, K. (2010). “Optimizing material procurement and storage on
construction sites”. J. of Const. Eng. and Mgmt., 137(6), 421-431.
Sambasivan, M., & Soon, Y. W. (2007). “Causes and effects of delays in Malaysian
construction industry”. International Journal of project mgmt., 25(5), 517-
526.
Sanvido, V., Grobler, F., Parfitt, K., Guvenis, M., & Coyle, M. (1992). “Critical
success factors for construction projects”. J. of Cons. Eng. and Mgmt., 118(1),
Downloaded from ascelibrary.org by University of Texas at Arlington on 04/06/18. Copyright ASCE. For personal use only; all rights reserved.
94-111.
Shane, J. S., Molenaar, K. R., Anderson, S., & Schexnayder, C. (2009). Construction
project cost escalation factors. J. of Mgmt. in Eng., 25(4), 221-229.
Sun, M., & Meng, X. (2009). “Taxonomy for change causes and effects in
construction projects”. International Journal of Project Management, 27(6),
560-572.
Yang, J. B., & Wei, P. R. (2010). “Causes of delay in the planning and design phases
for construction projects”. Journal of Architectural Engineering, 16(2), 80-83.
Yeo, T., & Ning, H. (2006). “Managing uncertainty in major equipment procurement
in engineering projects”. European journal of operational research, 171(1),
123-134.
© ASCE